Department of Commerce, Community, and Economic Development
Alaska Oil and Gas Conservation Commission
Loading...
HomeMy WebLinkAbout224-151Alaska Oil and Gas
Conservation Commission
333 West Seventh Avenue
Anchorage, Alaska 99501-3572
Main: 907.279.1433
Fax: 907.276.7542
www.aogcc.alaska.gov
January 15, 2026
Greg Hobbs
Regulatory Engineer, Wells Team
ConocoPhillips Alaska, Inc.
P. O. Box 100360
Anchorage, AK 99510-0360
Re: Docket Number: OTH-25-050
Notice of Violation – Closeout
Late Log and Geologic Data Submittal
KRU 3S-714 (PTD 224-151), KRU 3T-616 (224-138), KRU 3T-731 (224-156), KRU 3S-
723 (225-016), KRU 3T-730 (225-010), KRU 3S-703 (225-035)
Dear Mr. Hobbs:
ConocoPhillips Alaska, Inc responded to the above referenced notice of violation by electronic
letter dated November 4, 2025. The missing data sets noted on the NOV were all submitted by
November 3, 2025.
The Alaska Oil and Gas Conservation Commission does not intend to pursue any further
enforcement action regarding the late log and geologic data submittal.
Sincerely,
Jessie L. Chmielowski Gregory C. Wilson
Commissioner Commissioner
cc: Phoebe Brooks
Jessie L.
Chmielowski
Digitally signed by Jessie
L. Chmielowski
Date: 2026.01.14
08:24:23 -09'00'
Gregory C Wilson Digitally signed by Gregory C Wilson
Date: 2026.01.15 08:21:30 -09'00'
November 4, 2025
Jessie Chmielowski
Commissioner
Alaska Oil and Gas Conservation Comm’n
333 West Seventh Avenue, Suite 100
Anchorage, Alaska 99501-3572
Gregory Wilson
Commissioner
Alaska Oil and Gas Conservation Comm’n
333 West Seventh Avenue, Suite 100
Anchorage, Alaska 99501-3572
VIA E-MAIL (samantha.coldiron@alaska.gov)
Re: Docket No. OTH-25-050
Notice of Violation – Late Log and Geologic Data Submittal
Commissioners Chmielowski and Wilson:
On October 23, 2025, the AOGCC sent a Notice of Violation (NOV) to ConocoPhillips Alaska, Inc.
(CPAI) regarding the late submission of logging and geologic data for six Kuparuk River Unit wells.
The NOV ordered CPAI to submit the missing data within 14 days.
As of November 3, 2025, all of these missing data have been submitted.
These submissions completed 1 full set and 5 partial sets of data owed to the AOGCC by CPAI.
The exercise reinforced the AOGCC requirements for image logs delivery formats, redefined
internal requirements of a complete package, and highlighted log provider delivery issues that
have been addressed by CPAI. Please find the acknowledged transmittals for the data attached.
If there are further questions or requests, do not hesitate to reach out.
Sincerely,
Greg Hobbs
Regulatory Engineer, Wells Team
ConocoPhillips Alaska, Inc.
Attachments
Greg Hobbs, P.E.
Regulatory Engineer, Wells Team
700 G Street, ATO 1504
Anchorage, AK 99501
(907) 263-4749 (office)
Greg.S.Hobbs@conocophillips.com
By Samantha Coldiron at 3:44 pm, Nov 04, 2025
Greg
Hobbs
Digitally signed by
Greg Hobbs
Date: 2025.11.04
15:06:07 -09'00'
T R A N S M I T T A LL
FROM:Anu Ambatipudi TO: Meredith Guhl ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3T-616 PB2 Pixstar
224-138
DATE: 10/10/2025
Transmitted:
3T-616 PB2 Pixstar Updated
Via SFTP
Transmittall instructions: please promptly sign, scan, and e-mail to
AKGGREDTSupport@ConocoPhillips.onmicrosoft.COM
CC: 3T-616 PB2 - e-transmittal well folder
Receipt: Date:
Alaska/IT-Data Services |ConocoPhillips Alaska |
224-138
T41019
Gavin Gluyas
Digitally signed by Gavin
Gluyas
Date: 2025.10.21 09:42:24
-08'00'
T R A N S M I T T A LL
FROM:Anu Ambatipudi TO: Meredith Guhl ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3T-616 Pixstar
224-138
DATE: 10/21/2025
Transmitted:
3T-616 Pixstar Updated
Via SFTP
Transmittall instructions: please promptly sign, scan, and e-mail to
AKGGREDTSupport@ConocoPhillips.onmicrosoft.COM
CC: 3T-616 - e-transmittal well folder
Receipt: Date:
Alaska/IT-Data Services |ConocoPhillips Alaska |
224-138
T41018
Gavin Gluyas
Digitally signed by Gavin
Gluyas
Date: 2025.10.21 09:38:53
-08'00'
T R A N S M I T T A LL
FROM:Anu Ambatipudi TO: Meredith Guhl ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3T-730
225-010
DATE:10/24/2025
Transmitted:
3T-730 EcoScope Image File
Via SFTP
Transmittall instructions: please promptly sign, scan, and e-mail to
AKGGREDTSupport@ConocoPhillips.onmicrosoft.COM
CC: 3T-730 - e-transmittal well folder
Receipt: Date: Alaska/IT-Data
Services |ConocoPhillips Alaska |
225-010
T41035
Gavin Gluyas
Digitally signed by Gavin
Gluyas
Date: 2025.10.27 08:24:59
-08'00'
T R A N S M I T T A LL
FROM:Anu Ambatipudi TO: Meredith Guhl ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3S-714 Mudlog Image File
DATE: 10/27/2025
Transmitted:
3S-714
Via SFTP
Transmittall instructions: please promptly sign, scan, and e-mail to
AKGGREDTSupport@ConocoPhillips.onmicrosoft.COM
CC: 3S-714 - e-transmittal well folder
Receipt: Date:
Alaska/IT-Data Services |ConocoPhillips Alaska |
224-151
T41037
Gavin Gluyas
Digitally signed by Gavin
Gluyas
Date: 2025.10.27 14:15:39
-08'00'
T R A N S M I T T A LL
FROM:Anu Ambatipudi TO: Meredith Guhl ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3T-731 Microscope Image File
DATE:10/27/2025
Transmitted:
3T-731
Via SFTP
Transmittall instructions: please promptly sign, scan, and e-mail to
AKGGREDTSupport@ConocoPhillips.onmicrosoft.COM
CC: 3T-731 - e-transmittal well folder
Receipt: Date:
Alaska/IT-Data Services |ConocoPhillips Alaska |
224-156
T41036
Gavin
Gluyas
Digitally signed by
Gavin Gluyas
Date: 2025.10.27
14:14:24 -08'00'
T R A N S M I T T A LL
FROM:Anu Ambatipudi TO: Meredith Guhl ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3S-703
DATE:11/03/2025
Transmitted:
3S-703
Via SFTP
Transmittall instructions: please promptly sign, scan, and e-mail to
AKGGREDTSupport@ConocoPhillips.onmicrosoft.COM
CC: 3S-703 - e-transmittal well folder
Receipt: Date:
Alaska/IT-Data Services |ConocoPhillips Alaska |
225-035
T41048
Gavin
Gluyas
Digitally signed by
Gavin Gluyas
Date: 2025.11.03
12:57:06 -09'00'
T R A N S M I T T A LL
FROM:Anu Ambatipudi TO: Meredith Guhl ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3S-723
DATE:11/03/2025
Transmitted:
3S-723 Pixstar Updated
Via SFTP
Transmittall instructions: please promptly sign, scan, and e-mail to
AKGGREDTSupport@ConocoPhillips.onmicrosoft.COM
CC: 3S-723 - e-transmittal well folder
Receipt: Date:
225-016
T40739
Gavin Gluyas
Digitally signed by Gavin
Gluyas
Date: 2025.11.03 13:00:48
-09'00'
Alaska/IT-Data Services |ConocoPhillips Alaska |
Alaska Oil and Gas
Conservation Commission
333 West Seventh Avenue
Anchorage, Alaska 99501-3572
Main: 907.279.1433
Fax: 907.276.7542
www.aogcc.alaska.gov
October 23, 2025
CERTIFIED MAIL –
RETURN RECEIPT
7018 0680 0002 2052 9846
Greg Hobbs
Regulatory Engineer, Wells Team
ConocoPhillips Alaska, Inc.
P. O. Box 100360
Anchorage, AK 99510-0360
Re: Docket Number: OTH-25-050
Notice of Violation (NOV) – Late Log and Geologic Data Submittal
KRU 3S-714 (PTD 224-151), KRU 3T-616 (224-138), KRU 3T-731 (224-156), KRU 3S-
723 (225-016), KRU 3T-730 (225-010), KRU 3S-703 (225-035)
Dear Mr. Hobbs:
Regulation 20 AAC 25.071 establishes the due date for logs and geologic data acquired during
well work, and the types of data to be submitted to the Alaska Oil and Gas Conservation
Commission (AOGCC). Per 20 AAC 25.071(b), data are due to the AOGCC within 90 days after
completion, suspension, or plugging of a well or well branch, or not later than 90 days after the
date of acquisition of the data, whichever occurs first. The following table lists wells with data that
has not been submitted to the AOGCC within the 90-day time frame:
PTD Well Name
Date Well
Completed
Date Data
Due Data Not Submitted
224-151 KRU 3S-714 2/24/2025 5/25/2025 mudlog image files, show reports
224-138 KRU 3T-616 3/9/2025 6/7/2025 PixStar image file
224-156 KRU 3T-731 4/11/2025 7/10/2025 MicroScope image files
225-016 KRU 3S-723 4/16/2025 7/15/2025 PixStar image file
225-010 KRU 3T-730 5/2/2025 7/31/2025 EcoScope image file
225-035 KRU 3S-703 6/2/2025 8/31/2025 PixStar all data
On October 9, 2025, the AOGCC requested that by October 20, 2025, ConocoPhillips provide a
firm timeline with actionable dates for when missing datasets would be provided for each well,
along with an accounting of which data were still not available. This request was unfulfilled. Two
earlier email requests from the AOGCC sent on August 11 and August 19, 2025, were also not
Docket Number: OTH-25-050
October 23, 2025
Page 2 of 2
responded to by either providing the missing data or acknowledging that the requested data was
still missing.
Data for KRU 3S-714 is almost 5 months late, and the partial mudlog data submitted on October
13, 2025, was not provided until the AOGCC noted it was missing in an email to ConocoPhillips
on October 9. The PixStar, MicroScope, and EcoScope image files are required by 20 AAC
25.071(b)(6), and the mudlog image files and show reports (if available) are required by 20 AAC
25.071(b)(1).
While late reporting of data may not implicate a threat to public safety or the environment, this
type of violation may demonstrate an overall inability to manage regulatory compliance.
Moreover, this violation impacts timely public access to data and requires an inordinate amount of
AOGCC staff time to rectify.
Within 14 days after receipt of this letter (next business day if the due date falls on a weekend
or holiday), ConocoPhillips Alaska is required to submit any outstanding data required by 20 AAC
25.071 for the six wells referenced in this notice. If the data are not yet available from vendors,
ConocoPhillips must submit a written response to Meredith Guhl outlining which specific items
are not yet available, a proposed date for submission of those items, and the contact information
for the ConocoPhillips employee who will be managing the submission of the data.
The information request is made pursuant to 20 AAC 25.300. Failure to comply with this request
will be an additional violation. The AOGCC reserves the right to pursue an enforcement action in
this matter according to 20 AAC 25.535. Questions regarding this letter should be directed to
Meredith Guhl at meredith.guhl@alaska.gov or 907-793-1235.
Sincerely,
Jessie L. Chmeilowski Gregory C. Wilson
Commissioner Commissioner
Jessie L.
Chmielowski
Digitally signed by
Jessie L. Chmielowski
Date: 2025.10.23
11:52:56 -08'00'
Gregory C Wilson Digitally signed by Gregory C Wilson
Date: 2025.10.23 13:33:07 -08'00'
From:Hobbs, Greg S
To:Guhl, Meredith D (OGC); Dodson, Kate
Cc:Dewhurst, Andrew D (OGC); Davies, Stephen F (OGC); Starns, Ted C (OGC); Coldiron, Samantha J (OGC)
Subject:RE: [EXTERNAL]Missing logs follow up
Date:Friday, October 10, 2025 11:03:05 AM
Hello Meredith,
We are still waiting on this data ourselves. It was noted in a 9.30.25 internal check on
data. My boss, Chris Brillon, is following up with Halliburton.
Have a great weekend!
Greg
From: Guhl, Meredith D (OGC) <meredith.guhl@alaska.gov>
Sent: Thursday, October 9, 2025 9:49 AM
To: Dodson, Kate <Kate.Dodson@conocophillips.com>; Hobbs, Greg S
<Greg.S.Hobbs@conocophillips.com>
Cc: Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>; Davies, Stephen F (OGC)
<steve.davies@alaska.gov>; Starns, Ted C (OGC) <ted.starns@alaska.gov>; Coldiron, Samantha J
(OGC) <samantha.coldiron@alaska.gov>
Subject: RE: [EXTERNAL]Missing logs follow up
Importance: High
Greg,
I’m attempting to complete the compliance review for KRU 3S-714, completed February 24,
2025. No mudlog data have been submitted. It is nearing 8 months after the well completion
date. The timeline and data required are clearly listed in Regulation 20 AAC 25.071, and
although some delays are allowable, an almost 5 month delay for submittal of the mudlog
dataset, a standard data type, is troubling.
By October 20, 2025, ConocoPhillips is required provide a firm timeline with actionable dates
for when datasets will be provided for each well, along with an accounting of which data are
still missing. If data for wells listed below have been submitted, the data type and date of
submittal should also be included. A response to my last email, below, is also required.
Meredith
Meredith Guhl (she/her)
Petroleum Geology Assistant
Alaska Oil and Gas Conservation Commission
333 W. 7th Ave, Anchorage, AK 99501
meredith.guhl@alaska.gov
Direct: (907) 793-1235
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska
Oil and Gas Conservation Commission (AOGCC), State of Alaska and is for the sole use of the intended recipient(s). It
may contain confidential and/or privileged information. The unauthorized review, use or disclosure of such
information may violate state or federal law. If you are an unintended recipient of this e-mail, please delete it, without
first saving or forwarding it, and, so that the AOGCC is aware of the mistake in sending it to you, contact Meredith Guhl
at 907-793-1235 or meredith.guhl@alaska.gov.
From: Guhl, Meredith D (OGC)
Sent: Tuesday, August 19, 2025 10:15 AM
To: Dodson, Kate <Kate.Dodson@conocophillips.com>
Cc: Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>; Davies, Stephen F (OGC)
<steve.davies@alaska.gov>; Hobbs, Greg S <Greg.S.Hobbs@conocophillips.com>; Starns, Ted C
(OGC) <ted.starns@alaska.gov>; Gluyas, Gavin R (OGC) <gavin.gluyas@alaska.gov>
Subject: RE: [EXTERNAL]Missing logs follow up
Kate,
Thank you for the update. However the data for KRU 3S-723 is not complete, as a PDF and/or
TIF image file is also required, per 20 AAC 25.071(b)(7) which states “an electronic image file in
formats acceptable to the commission of all open-hole logs and mud logs run, including
common derivative formats such as tadpole plots of dipmeter data and borehole images
produced from sonic or resistivity data,”.
Meredith
From: Dodson, Kate <Kate.Dodson@conocophillips.com>
Sent: Monday, August 18, 2025 10:10 AM
To: Guhl, Meredith D (OGC) <meredith.guhl@alaska.gov>
Cc: Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>; Davies, Stephen F (OGC)
<steve.davies@alaska.gov>; Hobbs, Greg S <Greg.S.Hobbs@conocophillips.com>; Starns, Ted C
(OGC) <ted.starns@alaska.gov>; Gluyas, Gavin R (OGC) <gavin.gluyas@alaska.gov>
Subject: RE: [EXTERNAL]Missing logs follow up
Meredith,
CPAI is working with one of our log vendors to better understand delivery timeline and their
responsiveness has been slow. Please see below for the latest data update. Thank you for
the flexibility as CPAI works to get data delivery streamlined.
3T-616 – Still working on all data submission requirements.
3T-731 – Data submission complete.
3T-730 – Still working on all data submission requirements.
3T-613 – Still working on all data submission requirements.
3T-605 – Still working on all data submission requirements.
3T-617 – Still working on all data submission requirements.
3S-714 – Still working on all data submission requirements.
3S-723 – Data submission complete.
3S-703 – Still working on all data submission requirements.
3S-721 – Data submission complete.
3S-719 – Still working on all data submission requirements.
Thanks,
Kate Dodson | Senior Drilling Engineer
ConocoPhillips Alaska | Alaska Wells
O: 907-265-6181 | M: 907-217-3655 | Kate.Dodson@conocophillips.com
From: Guhl, Meredith D (OGC) <meredith.guhl@alaska.gov>
Sent: Monday, August 11, 2025 8:23 AM
To: Dodson, Kate <Kate.Dodson@conocophillips.com>
Cc: Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>; Davies, Stephen F (OGC)
<steve.davies@alaska.gov>; Hobbs, Greg S <Greg.S.Hobbs@conocophillips.com>; Starns, Ted C
(OGC) <ted.starns@alaska.gov>; Gluyas, Gavin R (OGC) <gavin.gluyas@alaska.gov>
Subject: RE: [EXTERNAL]Missing logs follow up
Good Morning Kate,
Halliburton PixStar data was submitted for KRU 3T-616 and KRU 3S-723 last week, but only
DLIS data was supplied. A PDF and/or TIF image file of the log is also required, see bolded
portion of the regulation below.
Please advise on ETA for when the full complement of required data will be submitted for the
two wells noted above, and the status of the other wells on your list below.
Thank you,
Meredith
From: Dodson, Kate <Kate.Dodson@conocophillips.com>
Sent: Friday, July 18, 2025 8:43 AM
To: Guhl, Meredith D (OGC) <meredith.guhl@alaska.gov>
CAUTION: This email originated from outside the State of Alaska mail system. Do not
click links or open attachments unless you recognize the sender and know the content
is safe.
Cc: Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>; Davies, Stephen F (OGC)
<steve.davies@alaska.gov>; Hobbs, Greg S <Greg.S.Hobbs@conocophillips.com>
Subject: RE: [EXTERNAL]Missing logs follow up
Meredith,
CPAI Reviewed wells drilled in 2025 for missing data, the CD4 wells are not on the list, but
CPAI will review them for missing data. See below for the list of wells CPAI is working to
get submitted to AOGCC.
3T-616 – Still working on all data submission requirements.
3T-731 – Data submission complete.
3T-730 – Still working on all data submission requirements.
3T-613 – Still working on all data submission requirements.
3T-605 – Still working on all data submission requirements.
3T-617 – Still working on all data submission requirements.
3S-714 – Still working on all data submission requirements.
3S-723 – Data submission complete.
3S-703 – Still working on all data submission requirements.
3S-721 – Data submission complete.
3S-719 – Still working on all data submission requirements.
Thanks,
Kate Dodson | Senior Drilling Engineer
ConocoPhillips Alaska | Alaska Wells
O: 907-265-6181 | M: 907-217-3655 | Kate.Dodson@conocophillips.com
From: Guhl, Meredith D (OGC) <meredith.guhl@alaska.gov>
Sent: Thursday, July 17, 2025 2:51 PM
To: Dodson, Kate <Kate.Dodson@conocophillips.com>
Cc: Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>; Davies, Stephen F (OGC)
<steve.davies@alaska.gov>
Subject: [EXTERNAL]Missing logs follow up
CAUTION:This email originated from outside of the organization. Do not click links or open
attachments unless you recognize the sender and know the content is safe.
Hello Kate,
After a discussion with Andrew Dewhurst and Steve Davies, the AOGCC requests that
ConocoPhillips continues to use the branded tool name in box 22 when submitting 10-407s.
The reasons for this request include:
1. Easily identifiable for both COP and AOGCC staff when comparing Box 22 list of logs
with the submitted data file names, i.e.:
a. 09-52_BHGE_LTK_RLT_Composite_FE Drilling Data.las
b. CD4-539_MagniSphere_Services_Memory_Drilling_12038ft-22957f.las
c. OP14-S3 L1_LWD_PeriScope_Resistivity_RM_LAS_10100_21371.las
2. Matches tool names noted in daily drilling reports and listed in permit to drill
applications.
3. Using the tool name clearly delineates log type from the general log collection of
GR/RES/NEU/DEN.
I’m not sure which wells are on your list of missing logs, but if CD4-536, CD4-539, and CD4-
587 aren’t on it, please add them as all appear to be missing the GeoSphere logging data
based on file names in data submitted.
The AOGCC understands that the missing log data will be delivered separately from the
already delivered LWD data. That is permissible in this case, but going forward, all LWD logging
data should be submitted as a single data package within 90 days of well completion,
suspension, or abandonment, or within 90 days of log acquisition. Note that 20 AAC 25.071(b)
(7) states “an electronic image file in formats acceptable to the commission of all open-hole
logs and mud logs run, including common derivative formats such as tadpole plots of dipmeter
data and borehole images produced from sonic or resistivity data,” so an image file, in
addition to any DLIS or LAS files should be submitted if available.
Thank you,
Meredith
Meredith Guhl (she/her)
Petroleum Geology Assistant
Alaska Oil and Gas Conservation Commission
333 W. 7th Ave, Anchorage, AK 99501
meredith.guhl@alaska.gov
Direct: (907) 793-1235
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska
Oil and Gas Conservation Commission (AOGCC), State of Alaska and is for the sole use of the intended recipient(s). It
may contain confidential and/or privileged information. The unauthorized review, use or disclosure of such
information may violate state or federal law. If you are an unintended recipient of this e-mail, please delete it, without
first saving or forwarding it, and, so that the AOGCC is aware of the mistake in sending it to you, contact Meredith Guhl
at 907-793-1235 or meredith.guhl@alaska.gov.
From:Guhl, Meredith D (OGC)
To:Ambatipudi, Anu
Cc:kate.dodson@conocophillips.com; Dewhurst, Andrew D (OGC); Davies, Stephen F (OGC)
Subject:PTD 225-035: KRU 3S-703 BakerHughes data: AutoTrak and PixStar
Date:Wednesday, July 16, 2025 11:19:00 AM
Hello Anu,
I’m completing the initial loading of downhole data for KRU 3S-703. On the 10-407 form it is
noted that LithoTrak, AutoTrak, and PixStar were collected. However, reviewing the
BakerHughes data submitted to date, only the LithoTrak data is present in the dataset. Will the
AutoTrak and PixStar data be delivered separately?
Thank you,
Meredith
Meredith Guhl (she/her)
Petroleum Geology Assistant
Alaska Oil and Gas Conservation Commission
333 W. 7th Ave, Anchorage, AK 99501
meredith.guhl@alaska.gov
Direct: (907) 793-1235
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska
Oil and Gas Conservation Commission (AOGCC), State of Alaska and is for the sole use of the intended recipient(s). It
may contain confidential and/or privileged information. The unauthorized review, use or disclosure of such
information may violate state or federal law. If you are an unintended recipient of this e-mail, please delete it, without
first saving or forwarding it, and, so that the AOGCC is aware of the mistake in sending it to you, contact Meredith Guhl
at 907-793-1235 or meredith.guhl@alaska.gov.
DA
T
A
S
U
B
M
I
T
T
A
L
C
O
M
P
L
I
A
N
C
E
R
E
P
O
R
T
AP
I
N
o
.
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
0
0
We
l
l
N
a
m
e
/
N
o
.
K
U
P
A
R
U
K
R
I
V
U
N
I
T
3
S
-
7
1
4
Co
m
p
l
e
t
i
o
n
S
t
a
t
u
s
WA
G
I
N
Co
m
p
l
e
t
i
o
n
D
a
t
e
2/
2
4
/
2
0
2
5
Pe
r
m
i
t
t
o
D
r
i
l
l
22
4
1
5
1
0
Op
e
r
a
t
o
r
C
o
n
o
c
o
P
h
i
l
l
i
p
s
A
l
a
s
k
a
,
I
n
c
.
MD
16
3
9
2
TV
D
42
0
4
Cu
r
r
e
n
t
S
t
a
t
u
s
WA
G
I
N
11
/
1
7
/
2
0
2
5
UI
C
Ye
s
We
l
l
L
o
g
I
n
f
o
r
m
a
t
i
o
n
:
Di
g
i
t
a
l
Me
d
/
F
r
m
t
Re
c
e
i
v
e
d
St
a
r
t
S
t
o
p
OH
/
CH
Co
m
m
e
n
t
s
Lo
g
Me
d
i
a
Ru
n
No
El
e
c
t
r
Da
t
a
s
e
t
Nu
m
b
e
r
Na
m
e
In
t
e
r
v
a
l
Li
s
t
o
f
L
o
g
s
O
b
t
a
i
n
e
d
:
GR
,
R
E
S
,
D
E
N
,
D
I
R
,
N
E
U
,
P
O
R
,
S
O
N
I
C
,
C
A
L
I
P
E
R
,
M
U
D
,
U
l
t
r
a
s
o
n
i
c
I
m
a
g
i
n
g
No
No
Ye
s
Mu
d
L
o
g
S
a
m
p
l
e
s
D
i
r
e
c
t
i
o
n
a
l
S
u
r
v
e
y
RE
Q
U
I
R
E
D
I
N
F
O
R
M
A
T
I
O
N
(f
r
o
m
M
a
s
t
e
r
W
e
l
l
D
a
t
a
/
L
o
g
s
)
DA
T
A
I
N
F
O
R
M
A
T
I
O
N
Lo
g
/
Da
t
a
Ty
p
e
Lo
g
Sc
a
l
e
DF
3/
3
/
2
0
2
5
28
0
0
6
5
0
0
E
l
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
CP
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
7
1
4
_
T
O
C
.
l
a
s
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
CP
A
I
_
3
S
_
7
1
4
_
R
1
_
7
.
6
2
5
i
n
_
C
a
s
i
n
g
_
S
o
n
i
c
S
c
o
p
e
4
75
_
R
M
_
T
O
C
_
R
e
p
o
r
t
(
1
)
.
p
p
t
x
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
.
d
l
i
s
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
.
h
t
m
l
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
.
p
d
s
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
_
1
0
0
0
M
D
_
R
M
.
p
d
f
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
_
2
0
0
0
M
D
_
R
M
.
p
d
f
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
_
2
0
0
M
D
_
R
M
.
p
d
f
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
_
4
0
0
0
M
D
_
R
M
.
p
d
f
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
_
5
0
0
M
D
_
R
M
.
p
d
f
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
K
u
p
a
r
u
k
_
R
i
v
e
r
_
3
S
-
71
4
_
T
O
C
_
6
0
0
0
M
D
_
R
M
.
p
d
f
40
1
8
0
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
11
0
1
6
3
9
2
E
l
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
C
O
M
P
_
M
E
M
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
11
0
1
6
3
9
2
E
l
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
C
O
M
P
_
M
E
M
_
F
u
l
l
h
e
a
d
e
r
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
Mo
n
d
a
y
,
N
o
v
e
m
b
e
r
1
7
,
2
0
2
5
AO
G
C
C
Pa
g
e
1
o
f
5
Su
p
p
l
i
e
d
b
y
Op
Su
p
p
l
i
e
d
b
y
Op
CP
A
I
_
3
S
-
,
71
4
_
CO
MP
_
M
E
M
.
l
a
s
DA
T
A
S
U
B
M
I
T
T
A
L
C
O
M
P
L
I
A
N
C
E
R
E
P
O
R
T
AP
I
N
o
.
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
0
0
We
l
l
N
a
m
e
/
N
o
.
K
U
P
A
R
U
K
R
I
V
U
N
I
T
3
S
-
7
1
4
Co
m
p
l
e
t
i
o
n
S
t
a
t
u
s
WA
G
I
N
Co
m
p
l
e
t
i
o
n
D
a
t
e
2/
2
4
/
2
0
2
5
Pe
r
m
i
t
t
o
D
r
i
l
l
22
4
1
5
1
0
Op
e
r
a
t
o
r
C
o
n
o
c
o
P
h
i
l
l
i
p
s
A
l
a
s
k
a
,
I
n
c
.
MD
16
3
9
2
TV
D
42
0
4
Cu
r
r
e
n
t
S
t
a
t
u
s
WA
G
I
N
11
/
1
7
/
2
0
2
5
UI
C
Ye
s
DF
3/
2
6
/
2
0
2
5
###
#
#
#
#
####
#
#
#
#
#
El
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
A
P
-
T
I
M
E
_
M
E
M
_
R
u
n
1
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
###
#
#
#
#
####
#
#
#
#
#
El
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
A
P
-
T
I
M
E
_
M
E
M
_
R
u
n
2
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
###
#
#
#
#
####
#
#
#
#
#
El
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
A
P
-
T
I
M
E
_
M
E
M
_
R
u
n
3
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
11
0
1
6
3
9
2
E
l
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
V
S
S
-
D
E
P
T
H
_
M
E
M
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
###
#
#
#
#
####
#
#
#
#
#
El
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
V
S
S
-
T
I
M
E
_
M
E
M
_
R
u
n
1
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
###
#
#
#
#
####
#
#
#
#
#
El
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
V
S
S
-
T
I
M
E
_
M
E
M
_
R
u
n
2
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
###
#
#
#
#
####
#
#
#
#
#
El
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
C
P
A
I
_
3
S
-
71
4
_
V
S
S
-
T
I
M
E
_
M
E
M
_
R
u
n
3
.
l
a
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
A
P
-
TI
M
E
_
M
E
M
_
R
u
n
1
.
a
s
c
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
A
P
-
TI
M
E
_
M
E
M
_
R
u
n
2
.
a
s
c
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
A
P
-
TI
M
E
_
M
E
M
_
R
u
n
3
.
a
s
c
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
V
S
S
-
DE
P
T
H
_
M
E
M
.
a
s
c
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
V
S
S
-
TI
M
E
_
M
E
M
_
R
u
n
1
.
a
s
c
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
V
S
S
-
TI
M
E
_
M
E
M
_
R
u
n
2
.
a
s
c
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
V
S
S
-
TI
M
E
_
M
E
M
_
R
u
n
3
.
a
s
c
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
9
7
5
i
n
_
r
e
a
m
i
n
g
_
1
-
20
0
f
t
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
9
7
5
i
n
_
r
e
a
m
i
n
g
_
1
-
40
f
t
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
9
7
5
i
n
_
r
e
a
m
i
n
g
_
1
-
20
0
f
t
.
P
D
F
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
Mo
n
d
a
y
,
N
o
v
e
m
b
e
r
1
7
,
2
0
2
5
AO
G
C
C
Pa
g
e
2
o
f
5
DA
T
A
S
U
B
M
I
T
T
A
L
C
O
M
P
L
I
A
N
C
E
R
E
P
O
R
T
AP
I
N
o
.
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
0
0
We
l
l
N
a
m
e
/
N
o
.
K
U
P
A
R
U
K
R
I
V
U
N
I
T
3
S
-
7
1
4
Co
m
p
l
e
t
i
o
n
S
t
a
t
u
s
WA
G
I
N
Co
m
p
l
e
t
i
o
n
D
a
t
e
2/
2
4
/
2
0
2
5
Pe
r
m
i
t
t
o
D
r
i
l
l
22
4
1
5
1
0
Op
e
r
a
t
o
r
C
o
n
o
c
o
P
h
i
l
l
i
p
s
A
l
a
s
k
a
,
I
n
c
.
MD
16
3
9
2
TV
D
42
0
4
Cu
r
r
e
n
t
S
t
a
t
u
s
WA
G
I
N
11
/
1
7
/
2
0
2
5
UI
C
Ye
s
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
9
7
5
i
n
_
r
e
a
m
i
n
g
_
1
-
40
f
t
.
P
D
F
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
I
m
a
g
e
t
r
a
k
-
Pr
o
c
e
s
s
e
d
_
9
7
5
i
n
_
2
7
9
0
-
6
6
0
1
f
t
_
1
-
2
0
0
F
T
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
I
m
a
g
e
t
r
a
k
-
Pr
o
c
e
s
s
e
d
_
9
7
5
i
n
_
2
7
9
0
-
6
6
0
1
f
t
_
1
-
4
0
F
T
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
9
7
5
i
n
_
2
7
9
0
-
66
0
1
f
t
.
d
l
i
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
I
m
a
g
e
t
r
a
k
-
Pr
o
c
e
s
s
e
d
_
9
7
5
i
n
_
2
7
9
0
-
6
6
0
1
f
t
_
1
-
2
0
0
F
T
.
P
D
F
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
Co
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
_
7
1
4
_
L
W
D
_
I
m
a
g
e
t
r
a
k
-
Pr
o
c
e
s
s
e
d
_
9
7
5
i
n
_
2
7
9
0
-
6
6
0
1
f
t
_
1
-
4
0
F
T
.
P
D
F
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
o
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
-
71
4
_
P
R
O
C
E
S
S
E
D
_
L
T
K
.
d
l
i
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
o
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
-
71
4
_
P
R
O
C
E
S
S
E
D
_
L
T
K
_
I
M
A
G
E
_
1
_
2
4
0
_
R
U
N
2
.
c
gm
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
o
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
-
71
4
_
P
R
O
C
E
S
S
E
D
_
L
T
K
_
I
M
A
G
E
_
1
_
2
4
0
_
R
U
N
2
.
p
df
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
o
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
-
71
4
_
P
R
O
C
E
S
S
E
D
_
L
T
K
_
I
M
A
G
E
_
1
_
2
4
0
_
R
U
N
3
.
c
gm
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
o
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
-
71
4
_
P
R
O
C
E
S
S
E
D
_
L
T
K
_
I
M
A
G
E
_
1
_
2
4
0
_
R
U
N
3
.
d
li
s
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
o
n
o
c
o
P
h
i
l
l
i
p
s
_
3
S
-
71
4
_
P
R
O
C
E
S
S
E
D
_
L
T
K
_
I
M
A
G
E
_
1
_
2
4
0
_
R
U
N
3
.
p
df
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
71
4
_
2
M
D
_
C
O
M
P
_
M
E
M
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
71
4
_
2
T
V
D
_
C
O
M
P
_
M
E
M
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
Mo
n
d
a
y
,
N
o
v
e
m
b
e
r
1
7
,
2
0
2
5
AO
G
C
C
Pa
g
e
3
o
f
5
DA
T
A
S
U
B
M
I
T
T
A
L
C
O
M
P
L
I
A
N
C
E
R
E
P
O
R
T
AP
I
N
o
.
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
0
0
We
l
l
N
a
m
e
/
N
o
.
K
U
P
A
R
U
K
R
I
V
U
N
I
T
3
S
-
7
1
4
Co
m
p
l
e
t
i
o
n
S
t
a
t
u
s
WA
G
I
N
Co
m
p
l
e
t
i
o
n
D
a
t
e
2/
2
4
/
2
0
2
5
Pe
r
m
i
t
t
o
D
r
i
l
l
22
4
1
5
1
0
Op
e
r
a
t
o
r
C
o
n
o
c
o
P
h
i
l
l
i
p
s
A
l
a
s
k
a
,
I
n
c
.
MD
16
3
9
2
TV
D
42
0
4
Cu
r
r
e
n
t
S
t
a
t
u
s
WA
G
I
N
11
/
1
7
/
2
0
2
5
UI
C
Ye
s
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
71
4
_
5
M
D
_
C
O
M
P
_
M
E
M
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
71
4
_
5
T
V
D
_
C
O
M
P
_
M
E
M
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
A
P
-
TI
M
E
_
M
E
M
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
V
S
S
-
DE
P
T
H
_
M
E
M
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
V
S
S
-
TI
M
E
_
M
E
M
.
c
g
m
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
71
4
_
2
M
D
_
C
O
M
P
_
M
E
M
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
71
4
_
2
T
V
D
_
C
O
M
P
_
M
E
M
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
71
4
_
5
M
D
_
C
O
M
P
_
M
E
M
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
71
4
_
5
T
V
D
_
C
O
M
P
_
M
E
M
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
A
P
-
TI
M
E
_
M
E
M
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
V
S
S
-
DE
P
T
H
_
M
E
M
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
C
P
A
I
_
3
S
-
7
1
4
_
V
S
S
-
TI
M
E
_
M
E
M
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
3
S
-
7
1
4
D
e
f
i
n
i
t
i
v
e
S
u
r
v
e
y
s
NA
D
2
7
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
3
S
-
7
1
4
D
e
f
i
n
i
t
i
v
e
S
u
r
v
e
y
s
NA
D
2
7
.
t
x
t
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
3
S
-
7
1
4
D
e
f
i
n
i
t
i
v
e
S
u
r
v
e
y
s
NA
D
8
3
.
p
d
f
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
3/
2
6
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
3
S
-
7
1
4
D
e
f
i
n
i
t
i
v
e
S
u
r
v
e
y
s
NA
D
8
3
.
t
x
t
40
2
3
7
ED
Di
g
i
t
a
l
D
a
t
a
DF
10
/
1
3
/
2
0
2
5
66
5
0
1
6
3
9
1
E
l
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
00
_
3
S
-
7
1
4
_
F
i
n
a
l
M
u
d
l
o
g
L
A
S
_
1
6
3
9
2
_
f
t
_
M
D
.
l
a
s
40
9
8
9
ED
Di
g
i
t
a
l
D
a
t
a
DF
10
/
1
3
/
2
0
2
5
66
5
0
1
6
3
9
2
E
l
e
c
t
r
o
n
i
c
D
a
t
a
S
e
t
,
F
i
l
e
n
a
m
e
:
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
00
_
3
S
-
7
1
4
_
G
a
s
F
a
c
t
F
i
n
a
l
L
A
S
_
1
6
3
9
2
_
f
t
.
l
a
s
40
9
8
9
ED
Di
g
i
t
a
l
D
a
t
a
Mo
n
d
a
y
,
N
o
v
e
m
b
e
r
1
7
,
2
0
2
5
AO
G
C
C
Pa
g
e
4
o
f
5
50
-
1
0
3
-
2
0
9
0
3
-
0
0
-
,
00_
3
S-7
1
4
_
F
i
n
a
l
M
u
d
l
o
g L
A
S_1
6
3
9
2
_
ft_
M
D
.
l
a
s
DA
T
A
S
U
B
M
I
T
T
A
L
C
O
M
P
L
I
A
N
C
E
R
E
P
O
R
T
AP
I
N
o
.
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
0
0
We
l
l
N
a
m
e
/
N
o
.
K
U
P
A
R
U
K
R
I
V
U
N
I
T
3
S
-
7
1
4
Co
m
p
l
e
t
i
o
n
S
t
a
t
u
s
WA
G
I
N
Co
m
p
l
e
t
i
o
n
D
a
t
e
2/
2
4
/
2
0
2
5
Pe
r
m
i
t
t
o
D
r
i
l
l
22
4
1
5
1
0
Op
e
r
a
t
o
r
C
o
n
o
c
o
P
h
i
l
l
i
p
s
A
l
a
s
k
a
,
I
n
c
.
MD
16
3
9
2
TV
D
42
0
4
Cu
r
r
e
n
t
S
t
a
t
u
s
WA
G
I
N
11
/
1
7
/
2
0
2
5
UI
C
Ye
s
We
l
l
C
o
r
e
s
/
S
a
m
p
l
e
s
I
n
f
o
r
m
a
t
i
o
n
:
Re
c
e
i
v
e
d
St
a
r
t
S
t
o
p
C
o
m
m
e
n
t
s
To
t
a
l
Bo
x
e
s
Sa
m
p
l
e
Se
t
Nu
m
b
e
r
Na
m
e
In
t
e
r
v
a
l
IN
F
O
R
M
A
T
I
O
N
R
E
C
E
I
V
E
D
Co
m
p
l
e
t
i
o
n
R
e
p
o
r
t
Pr
o
d
u
c
t
i
o
n
T
e
s
t
I
n
f
o
r
m
a
t
i
o
n
Ge
o
l
o
g
i
c
M
a
r
k
e
r
s
/
T
o
p
s
Y Y
/
N
A
Y
Co
m
m
e
n
t
s
:
Co
m
p
l
i
a
n
c
e
R
e
v
i
e
w
e
d
B
y
:
Da
t
e
:
Mu
d
L
o
g
s
,
I
m
a
g
e
F
i
l
e
s
,
D
i
g
i
t
a
l
D
a
t
a
Co
m
p
o
s
i
t
e
L
o
g
s
,
I
m
a
g
e
,
D
a
t
a
F
i
l
e
s
Cu
t
t
i
n
g
s
S
a
m
p
l
e
s
Y
/
N
A
Y Y
/
N
A
Di
r
e
c
t
i
o
n
a
l
/
I
n
c
l
i
n
a
t
i
o
n
D
a
t
a
Me
c
h
a
n
i
c
a
l
I
n
t
e
g
r
i
t
y
T
e
s
t
I
n
f
o
r
m
a
t
i
o
n
Da
i
l
y
O
p
e
r
a
t
i
o
n
s
S
u
m
m
a
r
y
Y Y
/
N
A
Y
Co
r
e
C
h
i
p
s
Co
r
e
P
h
o
t
o
g
r
a
p
h
s
La
b
o
r
a
t
o
r
y
A
n
a
l
y
s
e
s
Y
/
N
A
Y
/
N
A
Y
/
N
A
CO
M
P
L
I
A
N
C
E
H
I
S
T
O
R
Y
Da
t
e
C
o
m
m
e
n
t
s
De
s
c
r
i
p
t
i
o
n
Co
m
p
l
e
t
i
o
n
D
a
t
e
:
2/
2
4
/
2
0
2
5
Re
l
e
a
s
e
D
a
t
e
:
1/
9
/
2
0
2
5
DF
10
/
1
3
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
0
0
_
3
S
-
71
4
_
L
i
t
h
o
l
o
g
y
D
o
w
n
l
o
a
d
_
1
6
3
9
2
_
f
t
.
t
x
t
40
9
8
9
ED
Di
g
i
t
a
l
D
a
t
a
DF
10
/
2
7
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
0
0
_
3
S
-
71
4
_
F
o
r
m
a
t
i
o
n
Ev
a
l
u
a
t
i
o
n
_
1
6
3
9
2
_
f
t
_
M
D
_
2
i
n
c
h
.
p
d
f
40
9
8
9
ED
Di
g
i
t
a
l
D
a
t
a
DF
10
/
2
7
/
2
0
2
5
E
l
e
c
t
r
o
n
i
c
F
i
l
e
:
5
0
-
1
0
3
-
2
0
9
0
3
-
0
0
-
0
0
_
3
S
-
71
4
_
F
o
r
m
a
t
i
o
n
Ev
a
l
u
a
t
i
o
n
_
1
6
3
9
2
_
f
t
_
M
D
_
5
i
n
c
h
.
p
d
f
40
9
8
9
ED
Di
g
i
t
a
l
D
a
t
a
2/
2
7
/
2
0
2
5
66
0
0
1
6
3
9
2
41
9
2
4
Cu
t
t
i
n
g
s
Mo
n
d
a
y
,
N
o
v
e
m
b
e
r
1
7
,
2
0
2
5
AO
G
C
C
Pa
g
e
5
o
f
5
11
/
2
5
/
2
0
2
5
M.
G
u
h
l
MEMORANDUM State of Alaska
Alaska Oil and Gas Conservation Commission
DATE:Wednesday, October 22, 2025
SUBJECT:Mechanical Integrity Tests
TO:
FROM:Kam StJohn
P.I. Supervisor
Petroleum Inspector
NON-CONFIDENTIAL
ConocoPhillips Alaska, Inc.
3S-714
KUPARUK RIV UNIT 3S-714
Jim Regg
InspectorSrc:
Reviewed By:
P.I. Suprv
Comm ________
JBR 10/22/2025
3S-714
50-103-20903-00-00
224-151-0
W
SPT
4098
2241510 1500
0 0 0 0
570 615 617 609
INITAL P
Kam StJohn
9/20/2025
Initial MIT-IA for new injector. This well is on a vac injecting +- 2000 bbls a day Temp and IA pressures have been stable
30 MinPretestInitial15 Min
Well Name
Type Test
Notes:
Interval P/F
Well
Permit Number:
Type Inj TVD
PTD Test psi
API Well Number Inspector Name:KUPARUK RIV UNIT 3S-714
Inspection Date:
Tubing
OA
Packer Depth
900 1800 1770 1770IA
45 Min 60 Min
Rel Insp Num:
Insp Num:mitKPS250920193356
BBL Pumped:0.8 BBL Returned:0.8
Wednesday, October 22, 2025 Page 1 of 1
T40989
T R A N S M I T T A LL
FROM:Anu Ambatipudi TO: Meredith Guhl ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3S-714 Mudlog Image File
DATE: 10/27/2025
Transmitted:
3S-714
Via SFTP
Transmittall instructions: please promptly sign, scan, and e-mail to
AKGGREDTSupport@ConocoPhillips.onmicrosoft.COM
CC: 3S-714 - e-transmittal well folder
Receipt: Date:
Alaska/IT-Data Services |ConocoPhillips Alaska |
224-151
T41037
Gavin Gluyas
Digitally signed by Gavin
Gluyas
Date: 2025.10.27 14:15:39
-08'00'
T R A N S M I T T A L
FROM:Anu Ambatipudi TO:Meredith Guhl
ConocoPhillips Alaska, Inc. AOGCC
700 G Street 333 W.7
th Ave., Suite 100
Anchorage AK 99501 Anchorage, Alaska
RE: 3S-714
224-151
DATE:10/13/2025
Transmitted:
3S-714
Via SFTP
Transmittal instructions: please promptly sign, scan, and e-mail to
CC: 3S-714- e-transmittal well folder
Receipt: Date:
||
CDW 07/31/2025
Corrected chemical disclosure showing ResMetrics tracers
included to www.fracfocus.org 7/31/2025. CDW
Corrected chemical disclosure showing ResMetrics tracers
included to www.fracfocus.org 7/31/2025. CDW
1a. Well Status:Oil SPLUG Other Abandoned Suspended
1b. Well Class:
20AAC 25.105 20AAC 25.110 Development Exploratory
GINJ WINJ WDSPL No. of Completions: __________________ Service Stratigraphic Test
2. Operator Name:6. Date Comp., Susp., or 14. Permit to Drill Number / Sundry:
Aband.:
3. Address:7. Date Spudded: 15. API Number:
4a. Location of Well (Governmental Section):8. Date TD Reached: 16. Well Name and Number:
Surface:
Top of Productive Interval:2571' FNL, 4008' FEL S18 T12N R8E, UM 9. Ref Elevations: KB: 17. Field / Pool(s):
GL: 24.0 BF:
Total Depth:10. Plug Back Depth MD/TVD: 18. Property Designation:
4b. Location of Well (State Base Plane Coordinates, NAD 27):11. Total Depth MD/TVD: 19. DNR Approval Number:
Surface: x- y- Zone- 4
TPI:x- y- Zone- 4 12. SSSV Depth MD/TVD: 20. Thickness of Permafrost MD/TVD:
Total Depth:x- y- Zone- 4
5. Directional or Inclination Survey: Yes (attached) No 13. Water Depth, if Offshore: 21. Re-drill/Lateral Top Window MD/TVD:
Submit electronic information per 20 AAC 25.050 N/A (ft MSL)
22. Logs Obtained:
23.
BOTTOM
20"X65 120'
10 3/4"L-80 2520'
7-5/8"L-80 4139'
4 1/2"P110S 4204'
24. Open to production or injection? Yes No 25.
26.
Was hydraulic fracturing used during completion? Yes No
DEPTH INTERVAL (MD)AMOUNT AND KIND OF MATERIAL USED
27.
Date First Production: N/A - Injection Well Method of Operation (Flowing, gas lift, etc.):
Hours Tested: Production for Gas-MCF:
Test Period
Casing Press: Calculated Gas-MCF: Oil Gravity - API (corr):
Press. 24-Hour Rate
Flow Tubing
SIZE DEPTH SET (MD)
10 Yards
Sr Res EngSr Pet GeoSr Pet Eng
6-1/2"
6475'4.5"
N/A
Oil-Bbl:Water-Bbl:
Water-Bbl:
PRODUCTION TEST
Date of Test:Oil-Bbl:
6332'MD/4066'TVD
6453'MD/4098'TVD
BOTTOM
13.5"Lead: 473bbls 11ppg class G
Tail: 60bbls 15.8ppg class G
CASING
1665'MD/1639'TVD
SETTING DEPTH TVD
473252
474539
CEMENTING RECORD
5993854
If Yes, list each interval open (MD/TVD of Top and Bottom; Perforation Size and
Number; Date perf'd or liner run):
Liner: (2/20/2025) 6453'-16387'MD/4098'-4204'TVD
Gas-Oil Ratio:Choke Size:
suspension, or abandonment; or within 90 days of acquisition of the log, whichever occurs first. Types of logs to be listed include, but are not limited to: mud
log, spontaneous potential, gamma ray, caliper, resistivity, porosity, magnetic resonance, dipmeter, formation tester, temperature, cement evaluation, casing
collar locator, jewelry, and perforation record. Acronyms may be used. Attach a separate page only if necessary.
N/A
41'
40'
Per 20 AAC 25.283 (i)(2) attach electronic information
6639'40'
78.67
45.5
120'
TOP
SETTING DEPTH MD
PACKER SET (MD/TVD)
6453'
42"
12.6
41'
29.7
40'
40'
2803'
If Yes, list each interval open (MD/TVD of Top and Bottom; Perforation Size
and Number; Date perf'd or liner run):
WT. PER
FT.GRADE
GR, RES, DEN, DIR, NEU, POR, SONIC, CALIPER, MUD, Ultrasonic Imaging
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
WELL COMPLETION OR RECOMPLETION REPORT AND LOG
ConocoPhillips Alaska, Inc.
WAG
Gas
2/24/2025 224-151
50-103-20903-00-00
KRU 3S-714
1/28/2025
16392'MD/4204'TVD
N/A
63.2
P.O.Box 100360, Anchorage, AK 99510-0360
476193
2763' FSL, 33740' FWL S18 T12N R8E, UM
1876' FNL, 2726' FEL S30 T12N R8E, UM
2/16/2025
5993899
Kuparuk River Field/ Coyote Oil Pool
ADL380107, ADL0392374
LONS 01-013
5983986
TOP HOLE SIZE AMOUNT
PULLED
ACID, FRACTURE, CEMENT SQUEEZE, ETC.
CASING, LINER AND CEMENTING RECORD
List all logs run and, pursuant to AS 31.05.030 and 20 AAC 25.071, submit all electronic data within 90 days of completion,
57 bbls of 15.3ppg class G9-7/8"
TUBING RECORD
277bbls of 15.3ppg class G16387'4098'
W
d 1b
0 D p
op and B om; Perf
L
s
((atta
Form 10-407 Revised 10/2022 Due within 30 days of Completion, Suspension, or Abandonment
Complete
2/24/2025
JSB
RBDMS JSB 040125
G
Received 3/21/2025
DSR-4/7/25VTL 7/30/2025
Conventional Core(s): Yes No Sidewall Cores:
30.
MD TVD
Surface Surface
1421 1408
1644 1619
1665 1639
1808 1768
2108 2024
Base West Sak 2693 2452
C-80 3059 2666
C-50 4823 3417
C-35 5771 3870
6431 4093
16392 4204
31. List of Attachments:
Directional Survey, Well Schematic, Cement Operations, Operations Summary
32. I hereby certify that the foregoing is true and correct to the best of my knowledge.
Contact Name: Abby Warren
Digital Signature with Date:
Contact Phone:907-240-9293
General:
Item 1a:
Item 1b:
Item 4b:
Item 9:
Item 15:
Item 19:
Item 20:
Item 22:
Item 23:
Item 24:
Item 27:
Item 28:
Item 30:
Item 31:Pursuant to 20 AAC 25.070, attach to this form: well schematic diagram, summary of daily well operations, directional or inclination survey, and
other tests as required including, but not limited to: core analysis, paleontological report, production or well test results.
Report measured depth and true vertical thickness of permafrost. Provide MD and TVD for the top and base of permafrost in Box 29.
Attached supplemental records should show the details of any multiple stage cementing and the location of the cementing tool.
If this well is completed for separate production from more than one interval (multiple completion), so state in item 1, and in item 23 show the
producing intervals for only the interval reported in item 26. (Submit a separate form for each additional interval to be separately produced,
showing the data pertinent to such interval).
Provide a listing of intervals cored and the corresponding formations, and a brief description in this box. Pursuant to 20 AAC 25.071, submit
detailed descriptions, core chips, photographs, and all subsequent laboratory analytical results, including, but not limited to: porosity,
permeability, fluid saturation, fluid composition, fluid fluorescence, vitrinite reflectance, geochemical, or paleontology.
Method of Operation: Flowing, Gas Lift, Rod Pump, Hydraulic Pump, Submersible, Water Injection, Gas Injection, Shut-in, or Other (explain).
Provide a listing of intervals tested and the corresponding formation, and a brief summary in this box. Submit detailed test and analytical
laboratory information required by 20 AAC 25.071.
Review the reporting requirements of 20 AAC 25.071 and, pursuant to AS 31.05.030, submit all electronic data within 90 days of completion,
suspension, or abandonment; or 90 days after log acquisition, whichever occurs first.
Well Class - Service wells: Gas Injection, Water Injection, Water-Alternating-Gas Injection, Salt Water Disposal, Water Supply for Injection,
Observation, or Other.
Ugnu A
Report the Division of Oil & Gas / Division of Mining Land and Water: Plan of Operations (LO/Region YY-123), Land Use Permit (LAS 12345),
and/or Easement (ADL 123456) number.
The Kelly Bushing, Ground Level, and Base Flange elevations in feet above Mean Sea Level. Use same as reference for depth measurements
given in other spaces on this form and in any attachments.
The API number reported to AOGCC must be 14 digits (ex: 50-029-20123-00-00).
This form and the required attachments provide a complete and concise record for each well drilled in Alaska. Submit a current well schematic
diagram with each 10-407. Submit 10-407 and attachments in PDF format to aogcc.permitting@alaska.gov. All laboratory analytical reports from
a well must be submitted to the AOGCC, no matter when the analyses are conducted per 20 AAC 25.071.
Information to be attached includes, but is not limited to: summary of daily operations, wellbore schematic, directional or inclination survey, as-built, core
analysis, paleontological report, production or well test results, per 20 AAC 25.070.
Multiple completion is defined as a well producing from more than one pool with production from each pool completely segregated. Each
segregated pool is a completion.
TPI (Top of Producing Interval).
Authorized Name and
INSTRUCTIONS
Contact Emai:abby.warren@conocophillips.com
Authorized Title: Drilling Engineer
West Sak
If Yes, list formations and intervals cored (MD/TVD, From/To), and briefly summarize lithology and presence of oil, gas or water (submit separate pages if
needed). Submit detailed descriptions, core chips, photographs, and all subsequent laboratory analytical results per 20 AAC 25.071 no matter when acquired.
Attached Seperately
Formation Name at TD:
Nanushuk
Yes No
Well tested? Yes No
28. CORE DATA
If Yes, list intervals and formations tested, briefly summarizing test results for
each. Attach separate pages if needed and submit detailed test info including
reports and Excel or ASCII tables per 20 AAC 25.071.
NAME
Permafrost - Top
Ugnu C
29. GEOLOGIC MARKERS and POOL BOUNDARIES: (list all encountered)FORMATION TESTS
Top of Productive Interval:
Nanushuk
Permafrost - Base
Ugnu B
N
Form 10-407 Revised 10/2022 Submit in PDF format to aogcc.permitting@alaska.gov
In
t
e
r
m
e
d
i
a
t
e
I
C
a
s
i
n
g
7-
5
/
8
"
2
9
.
7
#
L
8
0
H
5
6
3
+
6
2
9
'
33
.
7
#
P
1
1
0
S
H
5
6
3
H
e
a
v
y
H
e
e
l
66
3
9
'
M
D
/
4
1
3
9
'
T
V
D
Ba
s
e
P
e
r
m
16
4
4
'
M
D
/
16
2
0
'
T
V
D
In
t
e
r
m
e
d
i
a
t
e
I
T
O
C
55
3
0
'
M
D
/
3
7
6
5
'
T
V
D
Su
r
f
a
c
e
C
a
s
i
n
g
10
-
3
/
4
"
4
5
.
5
#
L
8
0
H
5
6
3
28
0
3
'
M
D
/
2
5
2
0
'
T
V
D
Ce
m
e
n
t
e
d
t
o
S
u
r
f
a
c
e
Le
a
d
:
1
1
.
0
p
p
g
D
e
e
p
C
R
E
T
E
|
Ta
i
l
:
1
5
.
8
p
p
g
C
l
a
s
s
G
20
"
9
4
#
H
4
0
I
n
s
u
l
a
t
e
d
C
o
n
d
u
c
t
o
r
12
0
'
M
D
/
T
V
D
-
Ce
m
e
n
t
e
d
t
o
S
u
r
f
a
c
e
Pr
o
d
u
c
t
i
o
n
T
O
L
Pr
o
d
u
c
t
i
o
n
L
i
n
e
r
T
o
p
P
K
R
Pr
o
d
u
c
t
i
o
n
L
i
n
e
r
4-
1
/
2
"
1
2
.
6
#
P
1
1
0
-
S
H
5
6
3
16
3
8
7
'
M
D
/
4
2
0
4
'
T
V
D
3S
-
7
1
4
F
I
N
A
L
To
p
C
o
y
o
t
e
64
2
6
'
M
D
/
4
0
9
1
'
T
V
D
Up
p
e
r
C
o
m
p
l
e
t
i
o
n
:
1.
2
e
a
.
G
a
s
L
i
f
t
M
a
n
d
r
e
l
s
2.
H
E
S
O
p
s
i
s
S
i
n
g
l
e
D
o
w
n
h
o
l
e
G
a
u
g
e
3.
H
E
S
7
-
5
/
8
"
x
4
-
1
/
2
"
T
N
T
P
a
c
k
e
r
4.
A
r
s
e
n
a
l
5
,
5
0
0
p
s
i
G
l
a
s
s
D
i
s
k
S
u
b
5.
S
L
B
3
.
7
5
"
D
B
N
i
p
p
l
e
P
r
o
f
i
l
e
6.
H
E
S
S
e
l
f
-
A
l
i
g
n
i
n
g
M
u
l
e
s
h
o
e
w
i
t
h
B
a
k
e
r
S
h
e
a
r
L
o
c
a
t
o
r
Lo
w
e
r
C
o
m
p
l
e
t
i
o
n
:
1.
B
a
k
e
r
F
l
e
x
l
o
c
k
L
i
n
e
r
H
a
n
g
e
r
/
Z
X
P
P
a
c
k
e
r
2.
A
U
F
r
a
c
S
l
e
e
v
e
s
4.
C
i
t
a
d
e
l
M
O
A
S
S
h
o
e
64
5
3
'
M
D
/
4
0
9
8
'
T
V
D
Page 1/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
1/25/2025
21:00
1/26/2025
00:00
3.00 MIRU, MOVE MOB P Stomp out motor, pump and pits. Put all
on suspension. Raise C section and
lower cattle shute. Skid rig floor and
lower derrick. Pull pits off rig mats.
0.0 0.0
1/26/2025
00:00
1/26/2025
02:30
2.50 MIRU, MOVE MOB P Raise cellar walls, Unpin pipe shed and
stomp out from sub.
0.0 0.0
1/26/2025
02:30
1/26/2025
05:00
2.50 MIRU, MOVE MOB P Continue stomp pipe shed 50' turn and
place on suspention. Pull pipe shed off
mats
0.0 0.0
1/26/2025
05:00
1/26/2025
06:00
1.00 MIRU, MOVE MOB P Stomp sub off well center at 0500hrs. 0.0 0.0
1/26/2025
06:00
1/26/2025
14:00
8.00 MIRU, MOVE MOB P Install Jeep onto sub, Move sub off
mats. Spot mats on 3S-714 well, Spot
sub on 3S-714 well at 13:30 hrs.
0.0 0.0
1/26/2025
14:00
1/26/2025
18:00
4.00 MIRU, MOVE MOB P Move pipe shed with trucks close to
Stomping position. Stomp pipe shed and
shim and pin to sub.
0.0 0.0
1/26/2025
18:00
1/26/2025
19:30
1.50 MIRU, MOVE MOB P Raise and secure derrick. Set pits and
pump modules.
0.0 0.0
1/26/2025
19:30
1/26/2025
22:00
2.50 MIRU, MOVE MOB P Skid rig floor to drilling position, Crane in
MPD choke skid and control panel.
0.0 0.0
1/26/2025
22:00
1/27/2025
00:00
2.00 MIRU, MOVE MOB P Lower C section, Raise cattle shute,
(change HP hose in pump room) Set
mats and move casing shed into
postion.
0.0 0.0
1/27/2025
00:00
1/27/2025
02:30
2.50 MIRU, MOVE MOB P Set motor module in place, Lower cellar
walls, Stomp in casing module.
0.0 0.0
1/27/2025
02:30
1/27/2025
10:00
7.50 MIRU, MOVE MOB P Hooking up interconnections. Prep to
scope up derrick. Run steam to rig floor,
Work on rig acceptance checklist.
0.0 0.0
1/27/2025
10:00
1/27/2025
11:00
1.00 MIRU, MOVE MOB P Swap rig to highline power at 09:40 hrs.
Scope up derrick.
Rig accepted at 11:00 hrs 1-27-25
0.0 0.0
1/27/2025
11:00
1/27/2025
19:00
8.00 MIRU, MOVE RURD P Install surface riser and 4" conductor
valves. M/U bell nipple flange, M/U Joes
box and insulate. Install 90' mouse hole,
N/U jet and fill up lines, Install trip
nipple.
SIMOPS: P/U BHA tools, Derrick
inspection, Stock pits with chemicals,
Take on mud to pits.
0.0 0.0
1/27/2025
19:00
1/27/2025
21:00
2.00 MIRU, MOVE BHAH P P/U and rack back 5" HWT drill pipe and
jars.
0.0 0.0
1/27/2025
21:00
1/27/2025
22:30
1.50 MIRU, MOVE BHAH P P/U BHA #1, 13.5" Clean out assy.
Tagged at 43' MD
13.5" Kymera Bit
8" Ultra XL-HP motor (1.5°)
12-1/8" Stabilizer
Filter sub
X/O
5" HWT DP
0.0 43.0
1/27/2025
22:30
1/28/2025
00:00
1.50 MIRU, MOVE REAM P Break circulation, Pressure test surface
system to 3500psi (good test) Wash and
ream 20" conductor from 43' MD to 132'
MD.
GPM: 450
PSI: 580 Off
PSI: 630 On
RPM: 30
TRQ: 2-4k
ROT: 56k
43.0 132.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 2/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
1/28/2025
00:00
1/28/2025
00:30
0.50 MIRU, MOVE DDRL P Drill 13.5” hole f/ 132’ to 200’ MD/TVD
WOB: 2k
GPM: 450
PSI: 600
RPM: 30
TQ: 2k
PU: 54k
SO: 59k
ROT: 60k
AST: 0.0 hrs
ART: 0.5 hrs
Bit hrs: 1.2 hrs
132.0 200.0
1/28/2025
00:30
1/28/2025
01:30
1.00 SURFAC, DRILL BKRM P BROOH from 200' MD to 45' MD.
GPM: 450
PSI: 600
RPM: 30
TQ: 1-2k
200.0 0.0
1/28/2025
01:30
1/28/2025
04:00
2.50 SURFAC, DRILL BHAH P Continue P/U 13.5" BHA #1. Continue
wash in hole to 200' MD . Take Gyro
survey at 20" conductor at 132' MD.
0.0 137.0
1/28/2025
04:00
1/28/2025
06:00
2.00 SURFAC, DRILL DDRL P Drill 13.5” hole from 200’ to 341’
MD/TVD
WOB: 2k
GPM: 600
PSI: 600
RPM: 40
TQ: 2k
PU: 72k
SO: 77k
ROT: 76k
AST: 0.5 hrs
ART: 1.8 hrs
Bit hrs: 2.5 hrs
200.0 341.0
1/28/2025
06:00
1/28/2025
12:00
6.00 SURFAC, DRILL DDRL P Drill 13.5” hole from 341’ to 778’ MD
777' TVD
WOB: 2k
GPM: 600
PSI: 600
RPM: 40
TQ: 2k
PU: 72k
SO: 77k
ROT: 76k
AST: 0.5 hrs
ART: 2.5 hrs
Bit hrs: 5.5 hrs
Jar: 0.7 hrs
341.0 778.0
1/28/2025
12:00
1/28/2025
18:00
6.00 SURFAC, DRILL DDRL P Drill 13.5” hole from 341’ MD to 778’ MD
777' TVD
WOB: 15k
GPM: 600
PSI: 1497
RPM: 40
TQ: 2k
ROT: 86k
ECD: 9.9 ppg
AST: 0.7 hrs
ART: 3.2 hrs
Bit hrs: 9.4 hrs
Jar: 4.6 hrs
778.0 1,255.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 3/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
1/28/2025
18:00
1/29/2025
00:00
6.00 SURFAC, DRILL DDRL P Drill 13.5” hole from 778’ MD to 2000’
MD 1,937' TVD
WOB: 5k
GPM: 700
PSI: 2180
RPM: 40
TQ: 5k
ROT: 122k
ECD: 10.1 ppg
AST: 2.2 hrs
ART: 1.7 hrs
Bit hrs: 13.3 hrs
Jar: 8.5 hrs
1,255.0 2,000.0
1/29/2025
00:00
1/29/2025
10:00
10.00 SURFAC, DRILL DDRL P Drill 13.5” hole from 2000’ MD to 2808’
MD 2522' TVD.
Section TD 2808' MD/ 2522' TVD
WOB: 5k
GPM: 700
PSI: 2176
RPM: 60
TQ: 6k
ROT: 118k
ECD: 10.3 ppg
AST: 3.5 hrs
ART: 2.7 hrs
Bit hrs: 19.5 hrs
Jar: 14.7 hrs
2,000.0 2,808.0
1/29/2025
10:00
1/29/2025
11:30
1.50 SURFAC, TRIPCAS CIRC P Circulate BU while BROOH 1 std.
700 GPM
2205 PSI
60 RPM
4-6k TQ
10.3ppg ECD
2,808.0 2,750.0
1/29/2025
11:30
1/29/2025
12:00
0.50 SURFAC, TRIPCAS OWFF P Flow check.
Static loss rate of 12 BPH
2,750.0 2,750.0
1/29/2025
12:00
1/29/2025
14:00
2.00 SURFAC, TRIPCAS OWFF T Low volume of mud in pits. Take on mud
from ball mill.
2,750.0 2,750.0
1/29/2025
14:00
1/29/2025
18:00
4.00 SURFAC, TRIPCAS BKRM P BROOH f/ 2750' to 1908'.
700 GPM
2076 PSI
60 RPM
5k TQ
2,750.0 1,908.0
1/29/2025
18:00
1/29/2025
19:00
1.00 SURFAC, TRIPCAS CIRC P Pump sweep and circulate hole clean.
700 GPM
2075 PSI
1,908.0 1,813.0
1/29/2025
19:00
1/29/2025
19:30
0.50 SURFAC, TRIPCAS OWFF P Flow check and blow down TD.
Static loss rate of 12 BPH.
1,813.0 1,813.0
1/29/2025
19:30
1/29/2025
20:00
0.50 SURFAC, TRIPCAS TRIP P Attempt to POOH on elevators.
Observed 40k OP at 1730'. Drop back
down to 1813'.
1,813.0 1,813.0
1/29/2025
20:00
1/29/2025
22:00
2.00 SURFAC, TRIPCAS PMPO P Pump OOH f/ 1813' to BHA.
400 GPM
785 PSI.
1,813.0 780.0
1/29/2025
22:00
1/30/2025
00:00
2.00 SURFAC, TRIPCAS BHAH P Flow check and rack back HWDP 780.0 230.0
1/30/2025
00:00
1/30/2025
04:00
4.00 SURFAC, TRIPCAS BHAH P Finish Pumping OOH racking back
HWDP. LD BHA to surface.
230.0 0.0
1/30/2025
04:00
1/30/2025
04:30
0.50 SURFAC, CASING CLEN P Clean and clear rig floor. Stage casing
equipment.
0.0 0.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 4/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
1/30/2025
04:30
1/30/2025
05:30
1.00 SURFAC, CASING RURD P RU casing running equipment. 0.0 0.0
1/30/2025
05:30
1/30/2025
06:30
1.00 SURFAC, CASING PUTB P MU 10 3/4" 45.5# L-80 H563 shoe track
and RIH. Threadlock each joint.
0.0 171.0
1/30/2025
06:30
1/30/2025
12:00
5.50 SURFAC, CASING PUTB P RIH w/ 10 3/4" 45.50# L-80 H563 casing
to 1980'.
16.2k MU TQ
171.0 1,980.0
1/30/2025
12:00
1/30/2025
12:30
0.50 SURFAC, CASING CIRC P Circulate BU at 1980'. Stage rate up to 8
BPM.
8 BPM
211PSi
1,980.0 1,980.0
1/30/2025
12:30
1/30/2025
16:00
3.50 SURFAC, CASING PUTB P RIH w/ 10 3/4" 45.50# L-80 H563 casing
f/ 1980' to 2761'.
16.2k MU TQ
1,980.0 2,761.0
1/30/2025
16:00
1/30/2025
17:00
1.00 SURFAC, CASING PUTB P MU hanger and landing joint. Attempt to
Land hanger. Unsuccessful. Tagging up
at 2800'. Attempt to wash/rotate down
with no success.
8 BPM
265 PSI
5 RPM
10k TQ
2,761.0 2,800.0
1/30/2025
17:00
1/30/2025
21:00
4.00 SURFAC, CASING PUTB T Decison made to space out with pup
joints. LD landing joint/hanger joint. LD
joint # 64. MU spaceout pups Hanger
joint and landing joint. Attempt to wash
down. Tag 1ft from landing out at 2796'.
Work string and attempt to land hanger.
1-2 inches from landing out.
2,796.0 2,796.0
1/30/2025
21:00
1/30/2025
23:00
2.00 SURFAC, CASING PUTB T Blow down TD. Drain stack to check if
landed. Discovered landing ring had
shifted. Discuss with office and decision
made to use emergency slips.
2,796.0 2,796.0
1/30/2025
23:00
1/31/2025
00:00
1.00 SURFAC, CASING PUTB T LD landing joint and hanger joint. MU
and RIH with joints #64 and #66 + 15'
pup joint. Tagged at 2800'. Attempt to
wash down with no success.
Decision made to cement at 2800'.
Note: coupling 5.5' below landing ring.
2,800.0 2,800.0
1/31/2025
00:00
1/31/2025
02:00
2.00 SURFAC, CEMENT CIRC P Stage up pumps to 8 BPM. Circulate
and condition mud for cement job.
8 BPM
200 PSI
2,800.0 2,800.0
1/31/2025
02:00
1/31/2025
03:00
1.00 SURFAC, CEMENT RURD P Blow down TD. RU cement lines. 2,800.0 2,800.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 5/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
1/31/2025
03:00
1/31/2025
07:00
4.00 SURFAC, CEMENT CMNT P Test lines to 3500 PSI. Pump 100 BBLS
10.5 PPG MudPush @ 5.5 BPM/200
PSI. Drop bottom plug. Pump 473 BBLS
11.0 PPG lead cement (Cement wet @
03:30hrs). MudPush observed at
surface at 340 BBLS cement pumped.
Pump 60 BBLS 15.8 PPG tail cement
(Cement wet @ 05:07hrs). FCP - 282
PSI @ 5 BPM. SD. Drop top plug. Pump
20 BBLS FW with cement unit. Swap to
rig pumps. Displace with 9.5 PPG spud
mud. Bump plug with calculated strokes.
244 BBLS / 2423 strokes, FCP - 905
PSI @ 3 BPM. Pressure up to 1500
PSI. Hold for 5 minutes. Check floats.
Good. Cement in place at 07:00hrs on
1/31/24.
Note: Cement to Surface - 110 BBLS.
Lost returns at 1400 strokes into
displacement. Worked string and rotate
with no improvement. Cement was still
at surface when ND risers.
2,800.0 2,800.0
1/31/2025
07:00
1/31/2025
10:00
3.00 SURFAC, WHDBOP CLEN P Blow down lines. Flush all surface
equipment w/ black water. Clean joes
box,valves and cuttings pit.
0.0 0.0
1/31/2025
10:00
1/31/2025
14:30
4.50 SURFAC, WHDBOP NUND T ND lower riser and prep for casing cut.
Make cut on 10 3/4" casing.
SimOps: RD casing equipment. LD
mousehole. Clean out manifolds on
MP#1 and #2.
0.0 0.0
1/31/2025
14:30
1/31/2025
17:00
2.50 SURFAC, WHDBOP NUND T LD cut jt. (34.48'). ND risers and remove
starting head.
0.0 0.0
1/31/2025
17:00
1/31/2025
19:30
2.50 SURFAC, WHDBOP NUND T Cut conductor. Dress off conductor
stump.
SimOps: LD casing equiment. Stage
wellhead and emergency slips.
0.0 0.0
1/31/2025
19:30
1/31/2025
21:30
2.00 SURFAC, WHDBOP NUND T Install faceplate and slips per
StreamFlo. Cut and dress off surface
casing stump.(1.8' cut).
SimOps: Stage wellhead in BOP deck.
Prep adaptor flange.
0.0 0.0
1/31/2025
21:30
1/31/2025
23:00
1.50 SURFAC, WHDBOP NUND P Install wellhead and test to 2000 PSI.
Pad operator approved orientation.
0.0 0.0
1/31/2025
23:00
2/1/2025
00:00
1.00 SURFAC, WHDBOP NUND P Install adapter flange. 0.0 0.0
2/1/2025
00:00
2/1/2025
03:30
3.50 SURFAC, WHDBOP NUND P NU high pressure riser,BOP, choke and
kill lines.
0.0 0.0
2/1/2025
03:30
2/1/2025
08:00
4.50 SURFAC, WHDBOP NUND P Torque down riser and BOPE bolts. MU
flow line and jet lines. Install mousehole.
Seal up Joes box. RU MPD lines. MU
orbit valve.
0.0 0.0
2/1/2025
08:00
2/1/2025
09:00
1.00 SURFAC, WHDBOP RURD P Set test plug. MU MPD test cap. flood
lines.
0.0 0.0
2/1/2025
09:00
2/1/2025
10:00
1.00 SURFAC, WHDBOP MPDA P Test MPD equipment 250 psi low/ 1500
psi high.
0.0 0.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 6/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/1/2025
10:00
2/1/2025
18:00
8.00 SURFAC, WHDBOP BOPE P Test BOPE: 7-5/8" test joint- Annular
250/3500 PSI for 5min each. UPRs 7-
5/8" casing ram / 4" kill line / HCR Kill
and Choke / Manual Choke and Kill / 5"
FOSVs #1 and #2 / Dart valve to
250/5000 PSI for 5 min each.
Blind/Shear rams- 250/5000 PSI for 5
min each 5" test joint- Annular 250/3500
PSI for 5 min each. LPRs 2-7/8" x 5"
VBRs 250/5000 PSI for 5 min each.
Accumulator drawdown- ACC = 3000
PSI. Manifold = 1500 PSI. 1925 PSI
post function. 200 PSI increase = 13
sec. Full system recovery = 65 sec.
Nitrogen 6 bottles average = 1941 PSI.
Closing times - Annular= 10 sec.UPRs =
6 sec. LPRs = 5 sec. Blind/Shears = 5
sec. Choke HCR = 2 sec. Kill HCR = 2
sec. Test PVT Gain/Loss and flow out
alarms. Test LEL and H2S alarms.
Witnessed waived by AOGCC Cam St
John
0.0 0.0
2/1/2025
18:00
2/1/2025
18:45
0.75 SURFAC, DRILLOUT RURD P Retrieve test plug. Install 10.0" ID wear
bushing.
0.0 0.0
2/1/2025
18:45
2/1/2025
19:45
1.00 SURFAC, DRILLOUT CLEN P Clean and clear rig floor. BD choke and
kill lines. PJSM on BHA. Stage BHA
0.0 0.0
2/1/2025
19:45
2/1/2025
22:00
2.25 SURFAC, DRILLOUT BHAH P MU and RIH w/ BHA #2 to 716'. 0.0 716.0
2/1/2025
22:00
2/1/2025
23:30
1.50 SURFAC, DRILLOUT TRIP P RIIH w/ BHA on 5" DP to 2500'. 716.0 2,500.0
2/1/2025
23:30
2/2/2025
00:00
0.50 SURFAC, DRILLOUT CIRC P Break circulation and wash down to
2594 while performing shallow test on
MWD. Good test.
2,500.0 2,594.0
2/2/2025
00:00
2/2/2025
01:30
1.50 SURFAC, DRILLOUT PRTS P RU test equipment. Test casing to 3500
PSI f/ 30 minutes. Good test. 7 BBLs
pumped/returned. RD test equipment.
2,594.0 2,594.0
2/2/2025
01:30
2/2/2025
02:00
0.50 SURFAC, DRILLOUT WASH P Wash down and tag plugs at 2710'. 2,594.0 2,710.0
2/2/2025
02:00
2/2/2025
06:30
4.50 SURFAC, DRILLOUT DRLG P Drill out plugs/FC/shoetrack/FS to 2800'.
DRill new formation to 2828' MD.
630 GPM
1140 PSI
2-16k WOB
60-80 RPM
4-10k TQ
124k ROT
2,710.0 2,828.0
2/2/2025
06:30
2/2/2025
07:30
1.00 SURFAC, DRILLOUT FIT P Backream back into shoe. RU test
equipment. Perform LOT to 16.2ppg
EMW. RD test equipment.
2,828.0 2,828.0
2/2/2025
07:30
2/2/2025
08:30
1.00 INTRM1, DRILL DISP P RIH to 2806'. Pump HiVis spacer and
displace hole to 9.5ppg NAF OBM.
2,828.0 2,828.0
2/2/2025
08:30
2/2/2025
10:30
2.00 INTRM1, DRILL CLEN P Blow down TD. Clean surface
equipment. PU MPD equipment.
2,828.0 2,828.0
2/2/2025
10:30
2/2/2025
13:30
3.00 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 2828'
MD to 2973' MD /2620' TVD.
650 GPM
1180 PSI
3k WOB
80 RPM
4k TQ
9.9ppg ECD
124k ROT
2.4 Bit hrs
17.1 Jar hrs
2,828.0 2,973.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 7/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/2/2025
13:30
2/2/2025
14:00
0.50 INTRM1, DRILL CIRC P Circulate BU.
675 GPM
1300 PSI
80 RPM
3k TQ
2,973.0 2,973.0
2/2/2025
14:00
2/2/2025
15:00
1.00 INTRM1, DRILL MPDA P Retrieve trip nipple and install MPD
bearing assembly.
2,973.0 2,973.0
2/2/2025
15:00
2/2/2025
18:00
3.00 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 2973'
MD to 3133' MD /2707' TVD. Holding
125 PSI w/ MPD on connections
650 GPM
1365 PSI
8k WOB
150 RPM
5k TQ
10.2ppg ECD
128k PU
118k SO
120k ROT
4.3 Bit hrs
19 Jar hrs
2,973.0 3,133.0
2/2/2025
18:00
2/3/2025
00:00
6.00 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 3133'
MD to 3502' MD /2842' TVD. Holding
125 PSI w/ MPD on connections.
640 GPM
1765 PSI
7k WOB
120 RPM
6k TQ
10.3ppg ECD
138k PU
108k SO
120k ROT
9.2 Bit hrs
23.9 Jar hrs
3,133.0 3,502.0
2/3/2025
00:00
2/3/2025
06:00
6.00 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 3502'
MD to 4009' MD /3025' TVD. Holding
150 PSI w/ MPD on connections.
700 GPM
2075 PSI
7k WOB
140 RPM
6k TQ
10.5ppg ECD
138k PU
105k SO
122k ROT
18.4 Bit hrs
33.1 Jar hrs
3,502.0 4,009.0
2/3/2025
06:00
2/3/2025
12:00
6.00 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 4009'
MD to 4621' MD /3314' TVD. Holding
150 PSI w/ MPD on connections.
700 GPM
2200 PSI
7k WOB
140 RPM
6k TQ
10.7ppg ECD
147k PU
102k SO
125k ROT
18.4 Bit hrs
33.1 Jar hrs
4,009.0 4,621.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 8/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/3/2025
12:00
2/3/2025
21:30
9.50 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 4621'
MD to 5307' MD / 3531' TVD. Holding
11.3 ppg w/ MPD.
700 GPM
2365 PSI
6k WOB
140 RPM
6k TQ
11.3ppg ECD
160k PU
108k SO
132k ROT
23.3 Bit hrs
38 Jar hrs
4,621.0 5,307.0
2/3/2025
21:30
2/3/2025
22:00
0.50 INTRM1, DRILL SVRG P Service Top Drive. 5,307.0 5,307.0
2/3/2025
22:00
2/4/2025
00:00
2.00 INTRM1, DRILL RGRP T Troubleshoot Top Drive. Faults out and
loses rotation. Having to SD and reset.
5,307.0 5,307.0
2/4/2025
00:00
2/4/2025
02:00
2.00 INTRM1, DRILL RGRP T Troubleshoot Top Drive. Replace
Inverter.
5,307.0 5,307.0
2/4/2025
02:00
2/4/2025
02:30
0.50 INTRM1, DRILL SVRG P Service top drive. 5,307.0 5,307.0
2/4/2025
02:30
2/4/2025
06:00
3.50 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 5307'
MD to 5519' MD / 3760' TVD. Holding
11.3 ppg w/ MPD.
700 GPM
2410 PSI
6k WOB
140 RPM
7k TQ
11.3ppg ECD
157k PU
112k SO
129k ROT
29.1 Bit hrs
43.8 Jar hrs
5,307.0 5,519.0
2/4/2025
06:00
2/4/2025
12:00
6.00 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 5,519'
MD to 5,889' MD / 3918' TVD. Holding
11.3 ppg w/ MPD.
700 GPM
2480 PSI
7k WOB
140 RPM
3-6k TQ
11.3ppg ECD
175k PU
110k SO
141k ROT
34.1 Bit hrs
48.8 Jar hrs
5,519.0 5,889.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 9/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/4/2025
12:00
2/4/2025
17:00
5.00 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 5,889'
MD to 6,178' MD / 4020' TVD. Holding
11.3 ppg w/ MPD.
700 GPM
2560 PSI
7k WOB
140 RPM
3-6k TQ
11.3ppg ECD
175k PU
110k SO
141k ROT
38.1 Bit hrs
52.8 Jar hrs
5,889.0 6,178.0
2/4/2025
17:00
2/4/2025
18:15
1.25 INTRM1, DRILL CIRC T Circulate bottom up, while BROOH from
6,178' to 6,087' MD with
700 GPM
2552 PSI
100 RPM
5k TQ
11.3ppg ECD
45% FO
140k ROT
6,178.0 6,087.0
2/4/2025
18:15
2/4/2025
19:00
0.75 INTRM1, DRILL RURD T Change out MPD bearing do to leak at
seal.
6,087.0 6,087.0
2/4/2025
19:00
2/4/2025
19:30
0.50 INTRM1, DRILL WASH P Wash down from 6,087' to 6,178' MD
with following paramters, while down
linking:
700 GPM
2540 PSI
100 RPM
6k TQ
6,087.0 6,178.0
2/4/2025
19:30
2/5/2025
00:00
4.50 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 6,178'
MD to 6,554' MD / 4121' TVD.
700 GPM
2620 PSI
11k WOB
140 RPM
5-6k TQ
11.3ppg ECD
178k PU
108k SO
136k ROT
42.1 Bit hrs
56.8 Jar hrs
6,178.0 6,554.0
2/5/2025
00:00
2/5/2025
02:00
2.00 INTRM1, DRILL DDRL P Drill 9 7/8" Intermediate section f/ 6554'
MD to 6650' MD / 4141' TVD.
700 GPM
2660 PSI
1k WOB
140 RPM
5-6k TQ
11.3ppg ECD
172k PU
112k SO
139k ROT
43.1 Bit hrs
57.8 Jar hrs
6,554.0 6,650.0
2/5/2025
02:00
2/5/2025
02:30
0.50 INTRM1, TRIPCAS SVRG P Service rig 6,650.0 6,650.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 10/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/5/2025
02:30
2/5/2025
04:30
2.00 INTRM1, TRIPCAS RGRP T Discovered flange leaking on pop-off at
MP #1. Repair flange. Circulate with MP
# 2 while repairing. Holding 11.3ppg
EMW with MPD.
340 GPM
960 PSI
130 RPM
5k TQ
6,650.0 6,650.0
2/5/2025
04:30
2/5/2025
05:30
1.00 INTRM1, TRIPCAS CIRC P Circulate rotate and reciprocating from
6,650' to 6,590' MD with following
parameters:
700 GPM
2720 psi
46% FO
130 RPM
5 - 6k TQ
6,650.0 6,590.0
2/5/2025
05:30
2/5/2025
07:00
1.50 INTRM1, TRIPCAS CIRC P Circulate bottom up and reciprocating
from 6,590' to 6,455' MD with following
parameters:
700 GPM
2660 psi
46% FO
120 RPM
5 - 7k TQ
6,590.0 6,455.0
2/5/2025
07:00
2/5/2025
12:00
5.00 INTRM1, TRIPCAS REAM P BROOH from 6,455' to 5,580' MD with
following parameters:
700 GPM
2530 psi
45% FO
11.5 ppg ECD
138k ROT
120 RPM
6 - 8k TQ
Note: SIMOPS Lay down 5" drill pipe
using mouse hole.
6,455.0 5,580.0
2/5/2025
12:00
2/5/2025
18:00
6.00 INTRM1, TRIPCAS REAM P BROOH from 5,580' to 4,190' MD with
following parameters:
700 GPM
2260 psi
45% FO
11.2 ppg ECD
123k ROT
120 RPM
4 - 6k TQ
Note: SIMOPS Lay down 5" drill pipe
using mouse hole.
5,580.0 4,190.0
2/5/2025
18:00
2/6/2025
00:00
6.00 INTRM1, TRIPCAS REAM P BROOH from 4,190' to 2,903' MD with
following parameters:
700 GPM
2003 psi
45% FO
11.2 ppg ECD
123k ROT
120 RPM
2 - 4k TQ
Note: SIMOPS Lay down 5" drill pipe
using mouse hole.
4,190.0 2,903.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 11/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/6/2025
00:00
2/6/2025
00:30
0.50 INTRM1, TRIPCAS PMPO P Pump OOH from 2903' to 2,784' MD
with following parameters:
700 GPM
2000 psi
45% FO
11.3 ppg ECD
123k ROT
Note: SIMOPS Lay down 5" drill pipe
using mouse hole.
2,903.0 2,784.0
2/6/2025
00:30
2/6/2025
02:00
1.50 INTRM1, TRIPCAS CIRC P Pump 40 BBLs Hi VIS sweep and
circulate 2 x BU.
700 GPM
2000 PSI
11.3ppg ECD
2,784.0 2,680.0
2/6/2025
02:00
2/6/2025
05:00
3.00 INTRM1, TRIPCAS SMPD P SOOH f/ 2680' to 790'. Holding 11.3ppg
EMW with MPD.
2,680.0 790.0
2/6/2025
05:00
2/6/2025
06:00
1.00 INTRM1, TRIPCAS OWFF P Relax wellbore and flowcheck. Static. 790.0 790.0
2/6/2025
06:00
2/6/2025
07:00
1.00 INTRM1, TRIPCAS MPDA P Retrieve MPD bearing assembly and
install trip nipple.
790.0 790.0
2/6/2025
07:00
2/6/2025
10:45
3.75 INTRM1, TRIPCAS BHAH P POOH laying down HWDP, jars and
BHA
790.0 0.0
2/6/2025
10:45
2/6/2025
12:00
1.25 INTRM1, CASING RURD P Flush stack, pull wear bushing, clean
and clear rig floor, and function test
BOPs.
0.0 0.0
2/6/2025
12:00
2/6/2025
13:15
1.25 INTRM1, CASING RURD P RU CRT and equipments for 7 5/8"
casing.
0.0 0.0
2/6/2025
13:15
2/6/2025
20:30
7.25 INTRM1, CASING PUTB P PJSM PU and MU shoe track. Run 7-
5/8” Intermediate Casing from surface to
2,790' MD. Filling pipe on the fly on
every 10 joints. Connections are within
MU band. SO weight 130k
o 7-5/8” 33.07# MU TQ is 12.1k ft-lbs
o 7-5/8” 29.06# MU TQ is 10.3k ft-lbs
0.0 2,790.0
2/6/2025
20:30
2/6/2025
21:00
0.50 INTRM1, CASING CIRC P Circulate Bottom Up at 6 bpm / 120 psi,
MW in or out 9.5 ppg.
2,790.0 2,790.0
2/6/2025
21:00
2/7/2025
00:00
3.00 INTRM1, CASING PUTB P Continue Run 7-5/8” Intermediate
Casing from 2,790' to 4,280' MD. Filling
pipe on the fly on every 10 joints.
Connections are within MU band. SO
weight 145k
o 7-5/8” 29.06# MU TQ is 10.3k ft-lbs
2,790.0 4,280.0
2/7/2025
00:00
2/7/2025
02:30
2.50 INTRM1, CASING PUTB P Continue Run 7-5/8” Intermediate
Casing from 4280' to 5270' MD. Filling
pipe on the fly on every 10 joints.
Connections are within MU band. SO
weight 158k
7-5/8” 29.7# MU TQ is 10.3k ft-lbs
4,280.0 5,270.0
2/7/2025
02:30
2/7/2025
03:00
0.50 INTRM1, CASING CIRC P Circulate BU f/ 5270' to 5315'. Stage
rate to 6 BPM 160 PSI.
5,270.0 5,315.0
2/7/2025
03:00
2/7/2025
06:30
3.50 INTRM1, CASING PUTB P Continue Run 7-5/8” Intermediate
Casing from 5270' to 6605' MD. Filling
pipe on the fly on every 10 joints.
Connections are within MU band. SO
weight 158k
7-5/8” 29.7# MU TQ is 10.3k ft-lbs
5,315.0 6,605.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 12/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/7/2025
06:30
2/7/2025
07:00
0.50 INTRM1, CASING PUTB P MU hanger and landing joint. Fill pipe
and land hanger. Float shoe depth
6640'.
6,605.0 6,640.0
2/7/2025
07:00
2/7/2025
09:00
2.00 INTRM1, CEMENT CIRC P Circulate and condition mud. Stage
rates to 7 BPM/ 257 PSI.
6,640.0 6,640.0
2/7/2025
09:00
2/7/2025
12:00
3.00 INTRM1, CEMENT CMNT P Line up to cementers. Load bottom plug
#1 and pump 5 bbls of H2O. Test lines
to 4000 PSI – test good. Shut Down.
Load bottom plug #2 pump 60 BBLS
12.5 PPG Mud Push 5 BPM/150 PSI.
Swap to cementers. Pump 57 BBLs
15.3 PPG Tail cement. Shut Down. Load
top plug. Cementers pump 10 BBLS
FW. Swap to rig pumps. Displace w/ rig
at 6 BPM. Slow rate to 3 BPM at 20
BBLs left. Bump plug at 2873 Stks.
FCP= 380 PSI. Pressure up to 1902 PSI
and hold. Bleed off and check floats.
Good.
Cement in place at 10:51 hrs 02-07-
2025.
6,640.0 6,640.0
2/7/2025
12:00
2/7/2025
13:00
1.00 INTRM1, CEMENT RURD P Blow Down cement line. RD cementing
and CRT / Equipments.
6,640.0 0.0
2/7/2025
13:00
2/7/2025
15:15
2.25 INTRM1, CEMENT RURD P Back out landing joint. Install packoff
and test to 5000 psi for 5 min - test
good. Lay down landing joint.
0.0 0.0
2/7/2025
15:15
2/7/2025
16:15
1.00 INTRM1, WHDBOP RURD P Change upper pipe rams to 2 7/8" x 5"
VBRs. Note SIMOPS changing out
wash pipe on Top Drive.
0.0 0.0
2/7/2025
16:15
2/8/2025
00:00
7.75 INTRM1, WHDBOP BOPE P Test BOP 250/3500 psi low/high, choke
vavles, 1-15, kill HCR, manual kill,
UIBOP, LIBOP, test annuar, upper &
lower VBR's w/ 4" test joint, test super &
manual choke to 2000 psi.
Perform koomey drawdown - ACC =
3000 psi, Manifold = 1500 psi. Acc after
function test 1775 psi, 14 sec to 200 psi,
full system pressure achieved 110 sec.
Nitrogen bottle average 1808 psi.
Closing times annular 17 sec, UPR's 7
sec, LPR's 6 sec, blinds 6 sec, kill HCR
1 sec, choke HCR 1 sec.
Witnessed by AOGCC - Guy Cook
0.0 0.0
2/8/2025
00:00
2/8/2025
01:30
1.50 INTRM1, WHDBOP BOPE P Install 4 1/2" test joint. Test
UPRs/LPRs/HCR choke and manual
choke t/ 250 psi low/ 3500 psi high f/ 5
min ea.
0.0 0.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 13/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/8/2025
01:30
2/8/2025
09:15
7.75 INTRM1, WHDBOP RGRP T Pull test joint and plug, pump out stack,
clean flow box, blow down choke, kill,
jet, hole fill lines. Install test plug and
remove test joint, close blinds, RD orbit
valve, remove trip nipple and katch ken,
RCD head and bag cap. Remove old
annular element and install used
element. Re-install bag cap.
Install MPD equipment, hoses, and orbit
valve. Install and seal joes box. Flood
BOP stack and MPD chokes. Test MPD
equipments to 1400 psi - test good.
Note:SIMOPS pull valves and seat on
Mud Pump #2
Freeze Protect OA: ICP was 600 psi
at .5 BPM, FCP was 770 psi at 2.5 BPM
with 75 bbls of diesel pumped.
0.0 0.0
2/8/2025
09:15
2/8/2025
16:30
7.25 INTRM1, WHDBOP RGRP T PU 4" test joint, test annular 250/3500
psi for 5 min low/high - test passed. PU
4 1/2" test joint and test annular to
250/3500 psi for 5 min low/high - test
failed.
Note: SIMOPS change out KR valve on
koomey. Change out saver sub on Top
Drive.
0.0 0.0
2/8/2025
16:30
2/9/2025
00:00
7.50 INTRM1, WHDBOP RGRP T Pull test joint and plug, pump out stack,
clean flow box, blow down choke, kill,
jet, hole fill lines. Install test plug and
remove test joint, close blinds, RD orbit
valve, remove trip nipple and katch ken,
RCD head and bag cap. Remove old
annular element. Adaptor ring and
Piston ring. Install new element and re-
install bag cap.
0.0 0.0
2/9/2025
00:00
2/9/2025
03:30
3.50 INTRM1, WHDBOP RGRP T Install piston ring,adaptor ring, element
and cap. Purge air from system.
Function annular to break in element.
0.0 0.0
2/9/2025
03:30
2/9/2025
05:00
1.50 INTRM1, WHDBOP BOPE P Test annular w/ 4" and 4 1/2" test joint.
250 psi low/ 3500 psi high f/ 5 min ea.
0.0 0.0
2/9/2025
05:00
2/9/2025
08:00
3.00 INTRM1, WHDBOP RGRP T install RCD head. NU orbit valve. Test
MPD to 250 psi low/ 1400 psi high f/ 5
min ea.
0.0 0.0
2/9/2025
08:00
2/9/2025
09:15
1.25 INTRM1, WHDBOP RURD P Pull test plug and install 7.68" ID wear
bushing.
0.0 0.0
2/9/2025
09:15
2/9/2025
10:30
1.25 INTRM1, WHDBOP RURD P Test mud pumps at low rate for rate
increase. OK.
SimOps: Finish swapping out saver sub
for 4" DP.
0.0 0.0
2/9/2025
10:30
2/9/2025
12:00
1.50 INTRM1, WHDBOP PRTS P Test casing to 4000 PSI for 30 minutes.
Good test.
7 BBLS returned.
0.0 0.0
2/9/2025
12:00
2/9/2025
12:30
0.50 INTRM1, WHDBOP RURD P RD casing test equipment. Blow down
choke and kill. Clean and clear rig floor.
Prep for BHA.
0.0 0.0
2/9/2025
12:30
2/9/2025
15:00
2.50 INTRM1, DRILLOUT BHAH P MU and PU 6 1/2" production BHA 0.0 0.0
2/9/2025
15:00
2/9/2025
18:00
3.00 INTRM1, DRILLOUT TRIP P RIH with 4" doubles from pipe shed from
163' to 2,739' MD SO weight 80k
0.0 2,739.0
2/9/2025
18:00
2/9/2025
18:45
0.75 INTRM1, DRILLOUT CIRC P Perform shallow test for MWD at 300
GPM / 1730 psi - shallow test good.
2,739.0 2,739.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 14/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/9/2025
18:45
2/10/2025
00:00
5.25 INTRM1, DRILLOUT TRIP P RIH with 4" doubles from pipe shed from
2,739' to 6,325' MD SO weight 98k
Note: Log down for 200’ at 450 FPH to
3000’. Continue RIH logging at 1800
FPH to 6325’
2,739.0 6,350.0
2/10/2025
00:00
2/10/2025
01:00
1.00 INTRM1, DRILLOUT SLPC P Cut/Slip drill line (102' cut). 6,350.0 6,350.0
2/10/2025
01:00
2/10/2025
02:00
1.00 INTRM1, DRILLOUT WASH P Wash down f/ 6350' to 6505'. Cement
stringers at 6505'.
250 GPM
1740 PSI
6,350.0 6,505.0
2/10/2025
02:00
2/10/2025
08:00
6.00 INTRM1, DRILLOUT DRLG P Rotate/wash down and tag plugs at
6549'. Drill out FC/shoetrack/FS to
6639'. Clean out rathole to 6650'.Work
through shoe x 2. Drill 22' new formation
to 6672' MD.
6,505.0 6,672.0
2/10/2025
08:00
2/10/2025
09:00
1.00 INTRM1, DRILLOUT CIRC P Circulate and condition mud while
BROOH to inside shoe to 6578'.
250 GPM
1675 PSI
80 RPM
4-5k TQ
6,672.0 6,541.0
2/10/2025
09:00
2/10/2025
10:00
1.00 INTRM1, DRILLOUT LOT P RU test equipment. Perform LOT to
13.7ppg EMW. RD test equipment.
6,541.0 6,578.0
2/10/2025
10:00
2/10/2025
11:00
1.00 PROD1, DRILL MPDA P Retrieve trip nipple. Install MPD bearing
assembly.
6,578.0 6,578.0
2/10/2025
11:00
2/10/2025
12:00
1.00 PROD1, DRILL WASH P Wash back to bottom from 6,578' to
6,672' MD with following parameters
250 GPM
1680 psi
31% FO
6,578.0 6,672.0
2/10/2025
12:00
2/10/2025
18:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
6,672' MD to 7,111' MD / 4181' TVD.
275 GPM
2235 PSI
160 RPM
7k TQ
4k WOB
11.4ppg ECD
143k PU
84k SO
106k ROT
5.1 Bit Hrs
6,672.0 7,111.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 15/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/10/2025
18:00
2/11/2025
00:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
7,111' MD to 7,582' MD / 4182' TVD,
holding 150 psi while drilling and 220 psi
in slips with MPD.
275 GPM
2242 PSI
160 RPM
7k TQ
4k WOB
11.3ppg ECD
148k PU
83k SO
108k ROT
9.7 Bit Hrs
Note: Max gas 247 units @ 7,124' MD
7,111.0 7,582.0
2/11/2025
00:00
2/11/2025
06:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
7,582' to 8,086' MD / 4184' TVD,
holding 165 psi while drilling and 220 psi
in slips with MPD.
275 GPM
2600 PSI
180 RPM
8k TQ
4 - 10k WOB
11.3ppg ECD
155k PU
76k SO
117k ROT
14.1 Bit Hrs
Note: Max gas 137 units @ 7,802' MD
7,582.0 8,086.0
2/11/2025
06:00
2/11/2025
10:30
4.50 PROD1, DRILL DDRL P Drill 6 1/2" production section from
8,086' to 8,463' MD / 4190' TVD,
holding 175 psi while drilling and 215 psi
in slips with MPD.
300 GPM
2710 PSI
180 RPM
6 - 8k TQ
4 - 12k WOB
11.5ppg ECD
151k PU
78k SO
105k ROT
17.4 Bit Hrs
Note: Max gas 67 units @ 8,466' MD
8,086.0 8,463.0
2/11/2025
10:30
2/11/2025
11:30
1.00 PROD1, DRILL CIRC T Circulating bottom up, while rotating and
reciprocating pipe with
300 GPM
2700 psi
31% FO
11.5ppg ECD
100 RPM
6 - 7k TQ
8,463.0 8,463.0
2/11/2025
11:30
2/11/2025
12:30
1.00 PROD1, DRILL RURD T Swap out RCD bearing, while
maintaining back pressure @ 230 psi.
8,463.0 8,463.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 16/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/11/2025
12:30
2/11/2025
18:00
5.50 PROD1, DRILL DDRL P Drill 6 1/2" production section from
8,463' to 9,031' MD / 4187' TVD,
holding 175 psi while drilling and 230 psi
in slips with MPD.
300 GPM
2790 PSI
180 RPM
6 - 8k TQ
17k WOB
11.6ppg ECD
165k PU
79k SO
119k ROT
21.5 Bit Hrs
Note: Max gas 182 units @ 8,858' MD
8,463.0 9,031.0
2/11/2025
18:00
2/12/2025
00:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
9,031' to 9,610' MD / 4189' TVD,
holding 173 psi while drilling and 220 psi
in slips with MPD.
300 GPM
2850 PSI
180 RPM
8k TQ
18k WOB
11.6ppg ECD
175k PU
72k SO
110k ROT
25.9 Bit Hrs
Note: Max gas 362 units @ 9,599' MD
9,031.0 9,610.0
2/12/2025
00:00
2/12/2025
06:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
9,610' to 10,163' MD / 4190' TVD,
holding 165 psi while drilling and 210 psi
in slips with MPD.
300 GPM
2940 PSI
180 RPM
8k TQ
5 - 18k WOB
11.9ppg ECD
180k PU
110k ROT
30.3 Bit Hrs
Note: Max gas 497 units @ 9,882' MD
and lost down weight @ 9,976' MD
9,610.0 10,163.0
2/12/2025
06:00
2/12/2025
12:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
10,163' to 10,824' MD / 4191' TVD,
holding 169 psi while drilling and 215 psi
in slips with MPD.
300 GPM
3090 PSI
180 RPM
8 - 9k TQ
10 - 19k WOB
12.1ppg ECD
196k PU
113k ROT
35.0 Bit Hrs
Note: Max gas 271 units @ 10,143' MD
10,163.0 10,824.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 17/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/12/2025
12:00
2/12/2025
18:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
10,824' to 11,367' MD / 4191' TVD,
holding 175 psi while drilling and 220 psi
in slips with MPD.
300 GPM
3180 PSI
180 RPM
8 - 9k TQ
10 - 16k WOB
11.9ppg ECD
195k PU
115k ROT
38.7 Bit Hrs
Note: Max gas 179 units @ 11,109' MD
10,824.0 11,367.0
2/12/2025
18:00
2/12/2025
20:30
2.50 PROD1, DRILL DDRL P Drill 6 1/2" production section from
11,367' to 11,530' MD / 4191' TVD,
holding 166 psi while drilling and 213 psi
in slips with MPD.
300 GPM
3180 PSI
180 RPM
8 - 9k TQ
10 - 16k WOB
11.9ppg ECD
195k PU
115k ROT
38.7 Bit Hrs
Note: Encountered fault between
11,340’ to 11,375’ MD
11,367.0 11,530.0
2/12/2025
20:30
2/13/2025
00:00
3.50 PROD1, DRILL CIRC T Rack back stand in mousehole, circulate
across top of hole monitoring loss rates.
Pumped 88 bbls of 35 ppb LCM Pill with
following parameters. BROOH from
11.385' to 11,288' MD and rack back two
stands. Continue pumping across top of
hole with 168 GPM, monitoring static
loss rate at 3.5 BPH. Initial loss rate was
190 to 200 bph.
50 GPM
1040 Psi
13% FO
Note: Holding back pressure at 150 psi,
40 RPM, 8k Torque and 120 RO weight
11,530.0 11,530.0
2/13/2025
00:00
2/13/2025
02:00
2.00 PROD1, DRILL CIRC T Continue pumping across top of hole
with 168 GPM, monitoring static loss
rate at 3.5 BPH, while building 100 ppb
LCM pill. Dynamic loss 60-90 bph at 240
to 300 GPM with no back pressure.
11,530.0 11,530.0
2/13/2025
02:00
2/13/2025
03:30
1.50 PROD1, DRILL CIRC T Drop 1.75" ball inside drill string to open
well commander with 142 / 84 GPM, 20
RPM, 7k torque, ball seat 81 bbls. Well
Commander open at 3815 psi. Dropped
1.698" isolation ball to isolate BHA.
Note: 92 bbls out of 195 bbls total lost
bled back.
11,530.0 11,530.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 18/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/13/2025
03:30
2/13/2025
06:00
2.50 PROD1, DRILL CIRC T Attempt to pump 100 bbls of 100 ppb
LCM Pill. Observed charge pump
Isolation valve failed and contaminating
active mud system with LCM pill.
Continue circulating on pit #2 with 168
GPM, 710 psi, 20 RPM, 6k Torque.
While pumping contaminated pits across
shakers to screen out LCM and build
another 100 ppb LCM pill.
11,530.0 11,530.0
2/13/2025
06:00
2/13/2025
07:45
1.75 PROD1, DRILL CIRC T Rotate and reciprocate pipe with 168
GPM, 710/80 psi, 26% FO, 20 RPM, 5-
6k Torque, 119 ROT. Pumping through
well commander, no losses. Continue
Build 2nd 100ppb LCM pill.
11,530.0 11,530.0
2/13/2025
07:45
2/13/2025
09:30
1.75 PROD1, DRILL CIRC T Pump 108 bbls of 100 ppb LCM pill @ 4
bpm, 585 psi, 30% FO, 20 RPM, 5-6k
TQ, 120 ROT. Chase with NAF, close
MPD chokes @ 1350 stks pumped.
Decrease pump rate to 2 BPM. Pump
106 bbls with choke shut in. Shut down
and monitor pressures. FCP on pump
450 psi, wellbore pressure 284 psi.
Attempt to bleed off SPP. Float stuck
open. Shut down stand pipe and monitor
pressures. Wellbore pressure at 268 psi.
11,530.0 11,530.0
2/13/2025
09:30
2/13/2025
11:30
2.00 PROD1, DRILL CIRC T Continue monitoring wellbore pressure
257 psi @ 11:30. SIMOPS change out
isolation valve on charge lines. Change
out charge pump #1.
11,530.0 11,530.0
2/13/2025
11:30
2/13/2025
13:00
1.50 PROD1, DRILL CIRC T Pump 3 bbls down string with MPD
chokes closed. Stand pipe 245 psi,
wellbore at 267 psi. Stage up pumps to
200 GPM while opening MPD choke,
with 970 psi, 116 psi back pressure,
26% FO, 20 RPM, 5-6k TQ, 116k ROT.
Continue stage up pump to 250 GPM,
1318 psi / 60 psi back pressure, 33%
FO, 20 RPM, 5K TQ, 116k ROT.
Circulate bottom up, shut down pump,
attempt to bleed off stand pipe with 260
psi on wellbore. Float stuck open. Shut
down pump, Open MPD choke. Attempt
to break out Top Drive, 30 bbls bled
back to pits. Unable to drop well
commander closing ball.
11,530.0 11,530.0
2/13/2025
13:00
2/13/2025
15:00
2.00 PROD1, DRILL CIRC T Pump down string with 250 GPM, 1272
psi, 48 psi back pressure, 32% FO, 20
RPM, 5-6k TQ, 117k ROT. Pump 10 bbl
LVT pill and spot at float. Shut down and
bleed off stand pipe while holding 200
psi on back side. Drop well commander
closing ball. Pump ball down @ 4 BPM
with 685 psi, 100 psi back pressure. Ball
on seat at 975 stks, shifted closed at
3600 psi.
11,530.0 11,530.0
2/13/2025
15:00
2/13/2025
16:00
1.00 PROD1, DRILL WASH T Wash down from 11,290' to 11,530' MD
with 210 GPM, 1708 psi, 60 RPM, 7k
TQ, 116k ROT.
11,290.0 11,530.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 19/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/13/2025
16:00
2/13/2025
18:00
2.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
11,530' to 11,663' MD / 4192' TVD,
Close MPD choke on connections
200 GPM
1636 PSI
120 RPM
7 - 8k TQ
5k WOB
10.6ppg ECD
200k PU
122k ROT
42.5 Bit Hrs
Note: Max gas 20 units @ 11,655' MD
11,530.0 11,663.0
2/13/2025
18:00
2/13/2025
20:00
2.00 PROD1, DRILL CIRC P Attempt to make connection float stuck
open. Cycle pumps, open MPD choke.
Attempt to break out Top Drive, 43 bbls
bled back to pits. Unable to floats not
holding circulate bottom up to get 9.4
ppg MW inor out, 200 GPM, 1620 psi,
10.5 ppg ECD, 80 RPM, 6k TQ, 115k
ROT. Observed ECD's drop from 10.5
ppg to 10.3 ppg.
11,663.0 11,663.0
2/13/2025
20:00
2/14/2025
00:00
4.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
11,663' to 11,890' MD / 4192' TVD,
Close MPD choke on connections
200 GPM
1640 PSI
140 RPM
8k TQ
12 - 15k WOB
31% FO
10.6ppg ECD
220k PU
123k ROT
45.8 Bit Hrs
Note: Max gas 223 units @ 11,840' MD
11,663.0 11,890.0
2/14/2025
00:00
2/14/2025
08:30
8.50 PROD1, DRILL DDRL P Drill 6 1/2" production section from
11,890' to 12401' MD / 4192' TVD,
Close MPD choke on connections
220 GPM
1740 PSI
140 RPM
8k TQ
12 - 15k WOB
31% FO
10.5ppg ECD
220k PU
125k ROT
50.5 Bit Hrs
Note: Max gas 223 unit @ 11,840' MD
11,890.0 12,401.0
2/14/2025
08:30
2/14/2025
09:00
0.50 PROD1, DRILL CIRC T While making connection. Drillstring
floats leaking by. Work bleeder valve on
standpipe several times dumping
pressure and floats working. Make
connection
12,401.0 12,401.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 20/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/14/2025
09:00
2/14/2025
12:00
3.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
12,401' to 12,689' MD / 4193' TVD,
Close MPD choke on connections
240 GPM
2350 PSI
160 RPM
8 - 9k TQ
13k WOB
30% FO
10.4ppg ECD
210k PU
137k ROT
54.5 Bit Hrs
Note: Max gas 179 unit @ 12,404' MD
12,401.0 12,689.0
2/14/2025
12:00
2/14/2025
18:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
12,689' to 13,065' MD / 4193' TVD,
Close MPD choke on connections
220 GPM
2180 PSI
120 RPM
8 - 9k TQ
10k WOB
30% FO
10.8ppg ECD
220k PU
143k ROT
58.9 Bit Hrs
Note: Max gas 113 unit @ 13,047' MD
12,689.0 13,065.0
2/14/2025
18:00
2/15/2025
00:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
13,065' to 13,482' MD / 4193' TVD,
Close MPD choke on connections
220 GPM
2230 PSI
120 RPM
8 - 9k TQ
10k WOB
30% FO
10.8ppg ECD
220k PU
143k ROT
63.7 Bit Hrs
Note: Max gas 272 unit @ 13,318' MD
13,065.0 13,482.0
2/15/2025
00:00
2/15/2025
06:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
13482' to 13875' MD / 4193' TVD,
220 GPM
2300 PSI
140 RPM
10k TQ
5-18k WOB
32% FO
10.8ppg ECD
220k PU
143k ROT
68.1 Bit Hrs
Note: Max gas 1266 unit @ 13,598' MD
13,482.0 13,875.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 21/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/15/2025
06:00
2/15/2025
12:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
13,875' to 14,324' MD / 4198' TVD,
240 GPM
2790 PSI
150 RPM
10 - 11k TQ
12k WOB
32% FO
11.1ppg ECD
220k PU
150k ROT
72.7 Bit Hrs
Note: Max gas 946 unit @ 13,972' MD
13,875.0 14,324.0
2/15/2025
12:00
2/15/2025
18:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
14,324' to 14,840' MD / 4200' TVD,
240 GPM
2910 PSI
150 RPM
10 - 11k TQ
12k WOB
32% FO
11.2ppg ECD
265k PU
152k ROT
77.2 Bit Hrs
Note: Max gas 975 unit @ 14,525' MD
14,324.0 14,840.0
2/15/2025
18:00
2/16/2025
00:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
14,840' to 15,310' MD / 4201' TVD,
240 GPM
3000 PSI
150 RPM
10 - 11k TQ
10k WOB
33% FO
11.2ppg ECD
270k PU
152k ROT
81.4 Bit Hrs
Note: Max gas 852 unit @ 15,100' MD
14,840.0 15,310.0
2/16/2025
00:00
2/16/2025
06:00
6.00 PROD1, DRILL DDRL P Drill 6 1/2" production section from
15310' to 15755' MD / 4202' TVD,
240 GPM
3100 PSI
150 RPM
10 - 11k TQ
12k WOB
32% FO
11.4ppg ECD
284k PU
150k ROT
85.5 Bit Hrs
Note: Max gas 458 unit @ 15,553' MD
15,310.0 15,755.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 22/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/16/2025
06:00
2/16/2025
13:15
7.25 PROD1, DRILL DDRL P Drill 6 1/2" production section from
15,755' to 16,392' MD / 4203' TVD,
Close MPD choke on connections
240 GPM
3140 PSI
150 RPM
10 - 13k TQ
13k WOB
33% FO
11.4ppg ECD
305k PU
143k ROT
91.2 Bit Hrs
Note: Max gas 360-470 units @ 16,392'
MD
15,755.0 16,392.0
2/16/2025
13:15
2/16/2025
16:00
2.75 PROD1, TRIPCAS CIRC P Obtain final survey and perform T&D.
Rotate and reciprocate pipe from
16,392' to 16,308', while circulating 2x
Bottom up with:
250 GPM
3375 psi
120 RPM
10-12k Torque
11.4ppg ECD
32% FO
305k PUW
142k ROT
16,392.0 16,308.0
2/16/2025
16:00
2/16/2025
18:00
2.00 PROD1, TRIPCAS OWFF P Fingerprint / relax well at 16,392' MD,
keep string moving with 6 gpm, 7-9k TQ.
Open/close cycles, 5-10 mins per cycle,
initial wellbore pressure 290 psi and
final wellbore pressure 0 psi. Total flow
back to pits 118 bbls. Decrease in flow,
pressure and fluid flow back each cycle.
Close orbit valve, open 2" valve on RCD
and OWFF - well static.
16,308.0 16,308.0
2/16/2025
18:00
2/17/2025
00:00
6.00 PROD1, TRIPCAS BKRM P BROOH from 16,379' to 15,270' MD and
lay down stands of 4" drill pipe in
mousehole with following parameters:
240 GPM
2955 psi
32% FO
10.9 ppg ECD
10 - 13k TQ
120 RPM
144k ROT
16,308.0 15,270.0
2/17/2025
00:00
2/17/2025
06:00
6.00 PROD1, TRIPCAS BKRM P BROOH from 15270' to 13783' MD and
lay down stands of 4" drill pipe in
mousehole with following parameters:
240 GPM
2570 psi
32% FO
10.5 ppg ECD
11k TQ
120 RPM
142k ROT
15,270.0 13,783.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 23/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/17/2025
06:00
2/17/2025
09:30
3.50 PROD1, TRIPCAS BKRM P BROOH from 13783' to 12866' MD
racking back HWDP.
240 GPM
2490 psi
32% FO
10.4 ppg ECD
11k TQ
120 RPM
140k ROT
13,783.0 12,866.0
2/17/2025
09:30
2/17/2025
10:00
0.50 PROD1, TRIPCAS SVRG P Service Top Drive. 12,866.0 12,866.0
2/17/2025
10:00
2/17/2025
12:00
2.00 PROD1, TRIPCAS RGRP T MU TIW, head pin and circulate at 2
bpm, Change out swivel packing on Top
Drive.
12,866.0 12,866.0
2/17/2025
12:00
2/17/2025
18:00
6.00 PROD1, TRIPCAS BKRM P BROOH from 12,866' to 10,852' MD
racking back HWDP. Rack back seven
stand of 4" drill pipe from 10,852' to
10,286' MD.
240 GPM
2490 psi
32% FO
10.1 ppg ECD
11k TQ
120 RPM
115k ROT
12,866.0 11,137.0
2/17/2025
18:00
2/18/2025
00:00
6.00 PROD1, TRIPCAS BKRM P BROOH from 10,286' to 9,312' MD Lay
down 4" drill pipe.
240 GPM
1957 psi
33% FO
10.1 ppg ECD
10k TQ
120 RPM
108k ROT
11,137.0 9,312.0
2/18/2025
00:00
2/18/2025
06:00
6.00 PROD1, TRIPCAS BKRM P BROOH from 9,312' to 7,711' MD Lay
down 4" drill pipe. in mousehole with
following parameters:
240 GPM
1670 psi
33% FO
10.0 ppg ECD
9k TQ
120 RPM
108k ROW
9,312.0 7,711.0
2/18/2025
06:00
2/18/2025
09:00
3.00 PROD1, TRIPCAS BKRM P BROOH from 7,711' to 6,828' MD Lay
down 4" drill pipe. in mousehole with
following parameters:
240 GPM
1664 psi
33% FO
10.1 ppg ECD
8k TQ
120 RPM
110k ROW
7,711.0 6,828.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 24/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/18/2025
09:00
2/18/2025
09:30
0.50 PROD1, TRIPCAS CIRC P Obtain T&D by rotate and reciprocate
pipe from 6,828' to 6,630' MD for the
following parameters:
240 GPM
270 Psi
100k PU
133k SO
110k ROT
6,828.0 6,630.0
2/18/2025
09:30
2/18/2025
11:00
1.50 PROD1, TRIPCAS CIRC P Pump down 1 3/4" ball to open well
commander @ 2 BPM, 280 psi, 15k
torque. Ball on seat at 324stk(27bbls).
Staged up pump and observed shear
ball @ 3480 psi. Confirm well
commander is open by staged pumps to
500 GPM, 2315 psi, 80 rpm, 6-7k
torque, reduce pump rate to 400 gpm,
1687 psi, total strokes pumped 6450stk.
6,630.0 6,630.0
2/18/2025
11:00
2/18/2025
12:30
1.50 PROD1, TRIPCAS CIRC P Fingerprint to relax well at 6,579' MD by
open and close chokes every 5 to 10
minutes interval. Wellbore initial
pressure 80 psi and final 5 psi. Total
BBLs bled back 1.2 bbls. Close orbit
valve and open up 2" valve on RCD.
OWFF - well static.
6,630.0 6,630.0
2/18/2025
12:30
2/18/2025
13:00
0.50 PROD1, TRIPCAS SVRG P Rig service, RU man basket, derrick
board inspection.
6,630.0 6,630.0
2/18/2025
13:00
2/18/2025
17:00
4.00 PROD1, TRIPCAS RGRP T Install toe board and safety restraints to
monkey board while circulating at 84
gpm, 143 psi.
6,630.0 6,630.0
2/18/2025
17:00
2/18/2025
18:30
1.50 PROD1, TRIPCAS RURD P Blow down Top drive. Drop 1 3/4"
colsing ball, pull RCD bearing and install
trip nipple. hole fill line.
6,630.0 6,630.0
2/18/2025
18:30
2/18/2025
19:00
0.50 PROD1, TRIPCAS CIRC P Pressure up at 2 bpm and shift well
commander to closed position at 3536
psi, 2.3 bbls to pressure up. confirm flow
rate to verify well commander closed.
Blow down Top drive. Drop 2.4" OD
hollow drift.
6,630.0 6,475.0
2/18/2025
19:00
2/18/2025
23:00
4.00 PROD1, TRIPCAS TRIP P POOH from 6,475' to 163' MD, while
monitoring disp.
6,475.0 163.0
2/18/2025
23:00
2/18/2025
23:30
0.50 PROD1, TRIPCAS OWFF P Pull drift from pipe. OWFF - Well static.
SIMOPS pull PS-21's
163.0 163.0
2/18/2025
23:30
2/19/2025
00:00
0.50 PROD1, TRIPCAS BHAH P PJSM and started to lay down 6 1/2"
production BHA.
163.0 0.0
2/19/2025
00:00
2/19/2025
02:00
2.00 PROD1, TRIPCAS BHAH P LD BHA to surface. 0.0 0.0
2/19/2025
02:00
2/19/2025
03:00
1.00 COMPZN, CASING CLEN P Clean and clear rig floor. Function
BOPs.
0.0 0.0
2/19/2025
03:00
2/19/2025
04:30
1.50 COMPZN, CASING RURD P RU liner running equipment. 0.0 0.0
2/19/2025
04:30
2/19/2025
10:00
5.50 COMPZN, CASING PUTB P PJSM. RIH with 4 ½” P110S Hyd563
12.6# liner lower completion from
surface to 2.373' MD. Install one 4 1/2" x
6 1/8" Hydroform centralizer per joint.
Applied thin layer of BOL-AG 2000 on
each connection. Install Frac Sleeve
every 11 joints.
Note: MU TQ 5600 ft/lbs.
0.0 2,373.0
2/19/2025
10:00
2/19/2025
10:30
0.50 COMPZN, CASING SVRG P Install PS21's grease / flush, grease
IBOP, blocks, wash pipe.
2,373.0 2,373.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 25/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/19/2025
10:30
2/19/2025
18:00
7.50 COMPZN, CASING PUTB P RIH with 4 ½” P110S Hyd563 12.6# liner
lower completion from 2,373' to 7,154'
MD. Install one 4 1/2" x 6 1/8"
Hydroform centralizer per joint. Applied
thin layer of BOL-AG 2000 on each
connection. Install Frac Sleeve every 11
to 12 joints. Obtain T&D
Up/Down/Rotate at 6,620' MD, PU-72k,
SO-70k, ROT-71k, RPM 20, Torque 2k
Note: MU TQ 5600 ft/lbs.
2,373.0 7,154.0
2/19/2025
18:00
2/19/2025
23:00
5.00 COMPZN, CASING PUTB P RIH with 4 ½” P110S Hyd563 12.6# liner
lower completion from 7,154' to 9,943'
MD. Install one 4 1/2" x 6 1/8"
Hydroform centralizer per joint. Applied
thin layer of BOL-AG 2000 on each
connection. Install Frac Sleeve every 12
joints. Obtain T&D Up/Down/Rotate at
7,570' MD, PU-79k, SO-68k, ROT-72k,
RPM 20/30, Torque 2.8/2.8k. MU TQ
5600 ft/lbs.
7,154.0 9,943.0
2/19/2025
23:00
2/20/2025
00:00
1.00 COMPZN, CASING PUTB P MU ZXP liner hanger and fill with
Zanplex.
RD elevators/bail extensions and CRT.
9,943.0 9,943.0
2/20/2025
00:00
2/20/2025
07:00
7.00 COMPZN, CASING RUNL P RIH w/ 4 1/2" liner on 4" DP and 4"
HWDP f/ 9943' to 15523'. Take ROT
weights and TQ every 1000'.
MD RPM TRQ U/D/R
10,222' 20/30 2.8/3k 80/71/73k
11,164' 20/30 3.5/3.5k87/73/75k
12,107' 20/30 3.8/4k 94/76/100k
13,030' 20/30 4/4.5k 110/88/100k
14,876' 20/30 5.6/6.5k146/105/125k
15,523' 20/30 7/7.5k 170/110/132k
9,943.0 15,523.0
2/20/2025
07:00
2/20/2025
09:30
2.50 COMPZN, CASING RUNL P RIH with 4 1/2" Liner on 4" DP/HWDP
from 15,523' to 16,245' MD SOW 110k.
Drift HWDP out of derrick with 1.9" OD
drift. AT16,267' MD loss 10k SOW,
Rotate down to 16,392' MD with 20
RPM, 7k TQ, ROW 140k, PU to 16,387'
MD.
15,523.0 16,245.0
2/20/2025
09:30
2/20/2025
10:00
0.50 COMPZN, CEMENT RURD P MU cement head to drill string, RU
cement head. Line up to fill string and
vent air from string.
16,245.0 16,387.0
2/20/2025
10:00
2/20/2025
11:00
1.00 COMPZN, CEMENT CIRC P Stage pump up to 4 bpm, 220 psi with
9.5 ppg BARAECD, 124 bbl observed
returns, isolate vent. Continue pump
down through drill string. Break
circulation with 2 bpm pressure
increased to 500 psi.
16,387.0 16,387.0
2/20/2025
11:00
2/20/2025
15:30
4.50 COMPZN, CEMENT CIRC P Blow down Top Drive and close IBOP.
Line up to pump down through cement
head. Break circulation with 84 gpm,
660 psi. Pump 40 bbls of HI VIS spacer
until seen to surface with 9.5 ppg
BARAECD @ 2.5 bpm, 650 psi.
16,387.0 16,387.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 26/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/20/2025
15:30
2/20/2025
19:00
3.50 COMPZN, CEMENT CIRC P Pressure test lines to 4200 psi - test
good. Drop 1.5" setting ball. Circulate at
2-3 bpm, 778 psi, ball on seat with 2445
strokes. Pressure up to set hanger to
2500 psi and second time at 2600
psi.Did not set. Pressure up to 2800 psi
and SO 50k .Hanger set at 16,387' MD.
Increased pressure to 3600 psi and hold
for 5 min. Bleed pressure down to 500
psi. Pick up 2' past free travel of 175k,
set 50k down, increased pressure to
shear ball seat at 4327 psi. Pick up 4' to
verified hanger released. Circulation at 3
bpm, 755 psi.
16,387.0 16,387.0
2/20/2025
19:00
2/20/2025
22:30
3.50 COMPZN, CEMENT CMNT P PJSM for cement job. Pressure test
lines to 4000 psi - test good. Pump 50
bbls of 11 ppg of mud push at 3 bpm
with rig. Pumped 277 bbls of 15.3 ppg
cement at 3.5 bpm with SLB. Pump 1
bbl H2O, dropped dart, and pumped 9
bbls of H2O. Displace with rig 140 bbls
of Brine, swap to transition spacer
continue displace at 4 bpm, 960 psi.
Reduce rate to 3 bpm, ICP 806 psi and
bumped plug at 2251 strokes, FCP 1300
psi and hold for 5 min, bleed of pressure
and check floats - float is holding.
16,387.0 16,387.0
2/20/2025
22:30
2/20/2025
23:00
0.50 COMPZN, CEMENT CIRC P Expose the dog subs by PU 8' past
break over 170 k, rotate 20 rpm, 144k
ROTt, set down 50k, rotate for 2 min
twice. Packer set. Pressure up to 500
psi. PU 8' observe pressure drop off,
increased rate to 4 bpm, 550 psi. Flush
out liner top profile, Top of liner at 6,453'
MD.
16,387.0 6,453.0
2/20/2025
23:00
2/21/2025
00:00
1.00 COMPZN, WELLPR CIRC P Pump 100 bbls of cleaning spacer and
chase with CI Brine, circulate surface to
surface at 6 bpm. 750/900 psi.
Note: Observed all of the mudpush at
shakers. Possible traces of cement.
6,453.0 6,453.0
2/21/2025
00:00
2/21/2025
05:00
5.00 COMPZN, WELLPR CLEN P L/D single, R/D cement head. Pull
shaker screens, clean pits, pull PS21's,
clean Joes box/flow line, off load
remaining OBM. Pump surfactant pill f/
trip tanks over shakers, through suction
lines f/pits 1-4,
6,453.0 6,453.0
2/21/2025
05:00
2/21/2025
05:30
0.50 COMPZN, WELLPR PRTS P Close annular, PT well t/3850 psi f/5 min
7bbls to pressure up 7 bbls bled back.
6,453.0 6,453.0
2/21/2025
05:30
2/21/2025
06:00
0.50 COMPZN, WELLPR OWFF P Flow check. Static 6,453.0 6,453.0
2/21/2025
06:00
2/21/2025
06:30
0.50 COMPZN, WELLPR SVRG P Rig Service for Iron roughneck 6,453.0 6,453.0
2/21/2025
06:30
2/21/2025
15:30
9.00 COMPZN, WELLPR TRIP P POOH laying down 4" HWDP/DP from
6,456' to 43' MD. Lay down Baker
running tool.
6,453.0 0.0
2/21/2025
15:30
2/21/2025
16:30
1.00 COMPZN, WELLPR PRTS P Line up and purge kill line close blinds.
Perform JUG test to 3932 psi for 30
minutes, pumped 8 .4 bbls and bleed off
5.8 bbls back. Blow down kill line. Note
good test.
0.0 0.0
2/21/2025
16:30
2/21/2025
19:00
2.50 COMPZN, WELLPR TRIP P RIH with 4" drill pipe from derrick to
4,882' MD. SOW 100k
0.0 4,882.0
2/21/2025
19:00
2/22/2025
00:00
5.00 COMPZN, WELLPR PULD P POOH with 4" drill pipe from 4,882' to
1,041' MD.
4,882.0 1,041.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 27/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/22/2025
00:00
2/22/2025
01:00
1.00 COMPZN, WELLPR PULD P POOH LD 4" DP f/ 1041' to surface. 1,041.0 0.0
2/22/2025
01:00
2/22/2025
03:00
2.00 COMPZN, WELLPR RURD P Pull PS-21 slips. Jet stack and retrieve
wear bushing. Jet landing ring profile.
0.0 0.0
2/22/2025
03:00
2/22/2025
05:00
2.00 COMPZN, RPCOMP RURD P RU volant tool, bail extensions and
handling equipment. RU spool and
spooling unit.
0.0 0.0
2/22/2025
05:00
2/22/2025
19:30
14.50 COMPZN, RPCOMP PUTB P PJSM RIH with 4 1/2" 12.6 #, H563
upper completion from surface to 6,477'
MD. MU torque 3800 ft/Ibs. Test TEC
wire every 1000' and filling on fly with
9.3 ppg CI Brine. Note: SOW 93k.
0.0 6,477.0
2/22/2025
19:30
2/22/2025
21:00
1.50 COMPZN, RPCOMP PUTB P Fully located and set down 10k @
6,477' MD, shear pins with additional
10k. Lay down three joints from 6,477'
to 6,418' MD. MU space out pups. PU
116k, SO 93k,
6,477.0 6,418.0
2/22/2025
21:00
2/23/2025
00:00
3.00 COMPZN, RPCOMP RURD P Lay down CRT. MU hanger and landing
joint. MU TEC wire in hanger. Pressure
test connections to 5000 psi for 5
minutes. Land out hanger at 6,474' MD,
three feet from fully located. Lock down
hanger in well head, pressure test
hanger seals to 5000 psi for 15 minutes.
6,418.0 6,474.0
2/23/2025
00:00
2/23/2025
00:45
0.75 COMPZN, RPCOMP PRTS P Set packer and test tubing: Monitor IA
for leak. Pressure up to 500 PSI on tbg
hold f/ 5 minutes. Pressure up to 4550
PSI for 30 minutes. Test charted.
Note: Packer set and tbg tested.
6,474.0 0.0
2/23/2025
00:45
2/23/2025
01:30
0.75 COMPZN, RPCOMP PRTS P Bleed off tbg pressure to 2200 PSI.
Pressure up and test IA to 3850 PSI for
30 minutes. Charted. Good test. Bleed
IA down to 3000 PSI. Dump pressure on
tbg and shear SOV.
0.0 0.0
2/23/2025
01:30
2/23/2025
02:00
0.50 COMPZN, WHDBOP OWFF P Flow check. Static. 0.0 0.0
2/23/2025
02:00
2/23/2025
03:00
1.00 COMPZN, WHDBOP WWSP P Install BPV.
SimOps: Clean and clear rig floor.
0.0 0.0
2/23/2025
03:00
2/23/2025
06:00
3.00 COMPZN, WHDBOP NUND P ND BOPE and HP riser.
SimOps: Disconnect Ball mill and move
away from rig. Redress MPS to 6 1/2"
liners.
0.0 0.0
2/23/2025
06:00
2/23/2025
07:30
1.50 COMPZN, WHDBOP NUND P ND 5' spool and drilling adapter. 0.0 0.0
2/23/2025
07:30
2/23/2025
12:00
4.50 COMPZN, WHDBOP PULD P PU and MU tubing head adapter, 10K
frac tree.
SIMOPS blow down pump / pits
interconnects and continue dress pump
with 6 1/2" liners.
0.0 0.0
2/23/2025
12:00
2/23/2025
15:30
3.50 COMPZN, WHDBOP RURD P Remove press plate and lay down. MU
and torque tubing adapter. Terminate
Halco TEC wire. Pressure test seals and
flanges to 5000 psi for 15 minutes - test
good. Clean cellar box.
Final readings on TEC line: 1935 PSI
102 deg F
0.0 0.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
Page 28/28
3S-714
Report Printed: 2/25/2025
Operations Summary (with Timelog Depths)
Job: DRILLING ORIGINAL
Time Log
Start Time End Time Dur (hr) Phase Activity Code Time P-T-X Operation Start Depth (ftKB) End Depth (ftKB)
2/23/2025
15:30
2/23/2025
16:30
1.00 COMPZN, WHDBOP RURD P MU 10k frac tree and confirm orientation
with frac supervisor. Install swab valve
and torque. SIMOPS change out saver
sub to 4 1/2" IF. Secure derrick for
scope. RD baker BPA. RU scoping
yokes. Remove kelly hose.
0.0 0.0
2/23/2025
16:30
2/23/2025
17:00
0.50 COMPZN, WHDBOP PRTS P Fill tree with diesel, purge air, RU 10k
test pump, test tree to 250 psi for 5
minutes and 10,000 psi for 15 minutes -
test good. RD test equipments.
0.0 0.0
2/23/2025
17:00
2/23/2025
17:30
0.50 COMPZN, WHDBOP RURD P RIH with T-bar to install tree test dart.
SIMOPS RU frac tree to freeze protect
to LRS.
0.0 0.0
2/23/2025
17:30
2/23/2025
18:00
0.50 COMPZN, WHDBOP FRZP P Pump lines with diesel, pressure test to
2000 psi - test good. SIMOPS RU
scoping lines and blow down H2O.
0.0 0.0
2/23/2025
18:00
2/23/2025
23:00
5.00 COMPZN, WHDBOP FRZP P Start pumping diesel down IA and taking
returns up tubing to the pits. Drop rate
from 1 bpm to 0.4 bpm due to max
pressure at 2000 psi. Line up to bleed
down IA to unit(LRS), bleed back 2.3
bbls to 50 psi. Resume pumping down
to IA with 0.40 bpm, pressure between
1500 to 2500 psi. Shut down as needed
to allow pressure to bleed down FCP
950 psi and pump 94 bbls of diesel.
Note: At 64 bbls away restriction cleared
up. Pumped rest of diesel away at 1
BPM no issues.
SIMOPS Blow down water, bridal up,
scope derrick down, remove bridal lines,
secure top drive and energy track, pull
11 wraps off drawworks, Blow down
steam to sub.
0.0 0.0
2/23/2025
23:00
2/24/2025
00:00
1.00 COMPZN, WHDBOP OWFF P U-Tube IA and tubing equalized to 50
psi.
0.0 0.0
2/24/2025
00:00
2/24/2025
02:00
2.00 COMPZN, WHDBOP MOB P RD squeeze manifold. Remove outer
wing valve. Secure well and RDMO.
SIMOPS put casing shed on
suspension. Blow down rig floor steam
loop. Continue unplugging modules.
0.0 0.0
Rig: DOYON 25
RIG RELEASE DATE 2/24/2025
! "#$
! "%&
%'()
%'()
*+
, + -'&
+
./
+
+
0"12
3+
3+
4&+!"
"
#$
%&' ()* +,-.*
'
2+
+/0%
4
+#$
%&' ()* +,-.*
'
+
1%%
0
4
,+
5,+
*
4 6+
,,+%)'/2$
%
,
)'33,
4 5%%
4
%
67
!8%
91%% $
99$
$%$
3
3
-2&+
-&+
7
2+
2+
879'3
89'
#
5&-+
7*7
7*7
#4))4:)*
.4)*))
*73&7+
7*7
7;< 7*7#7
#7;<*#1
3
:;<
&2
:.<
, 2
:;<
4&,42
&==!7 >7>7# *:) :7*. #4:#*::.)):#7
+/
+
&
+
2
*7 08
/+ ,:./<
:
<
89'
:
<
:;<
879'3
:
<
.= +)*
:)*)7*77*7)*
,
:
<
2,
.,:3<
.
:
<
>:>7#
*#? ?9 !1'?1#,* 4...*
@' ,>:>7#7A#7
!1(?+(=(! 31=!1(?+(9(!
% $4* 4*
@' ,>:>7#7A#
!1(?+(=(! 31=!1(?+(9(!
% $4: * .4.*.
@' ,>:>7#7A#
!1(?+(=(! 31=!1(?+(9(!
% $.4.)* .4#:*:
@ ' ,>:>7#7A##
4
:
<
>
:;<
?
:;<
879'3
:
<
89'
:
<
./
:
<
./
:
<
4
2
:
<
4
7
2
:
<
/
:
<
-
:;9@<.,
* 7*. * * 7* 7* .:*7 #4))4:)* .4)* 7* 7*: *#?',
* 7*7 #*:. * 7* 7*7*# #4))4:)* .4)* 7* 7*# *#?',
. *. 7*:: .*#. . *. 7* *.7* #4))4:)* .4) *. * 7*# *#?',
#.*: *) #*): #.* * *)*# #4))4:))*# .4)#* * *7 *#?',
:* *7# #.*: :* #* *: *) #4))4)7* .4)#* * #*) *#?',
#:* *) #* #*) * * * #4))4)7:*) .4) * *7 * *#?',
. *. *). #7*# . *7 :*# 7*#7*: #4))4).* .4)* * :*. *#?',
:* #*) *: * * *.. *7 #4))4) *) .4)* * .*# *#?',
:* .*. *: :*# * *#:* #4))4) *) .4::*) 7* #*) *#?',
) *: *7# * : )*. *. *: )* #4))4) #* .4:#*) 7*# #* *#?',
477)* *. * 477.* #)* 7*)) *7 #4))4)#.*) .4:* 7* #.*## *#?',
*+
, + -'&
+
./
+
+
0"12
3+
3+
4&+!"
"
#$
%&' ()* +,-.*
'
2+
+/0%
4
+#$
%&' ()* +,-.*
'
+
1%%
0
4
:
<
>
:;<
?
:;<
879'3
:
<
89'
:
<
./
:
<
./
:
<
4
2
:
<
4
7
2
:
<
/
:
<
-
:;9@<.,
47*. :*7 7*.. 47):*. *. #*47#* #4))4).)* .4:* * .:* *#?',
4)#*. * 7*.. 4)7* :*# 7*4.*) #4))4):#* .4*# * :*)) *#?',
4)7*# * 7*.. 4:* 7* *.4)*# #4)) 477 *) .4.#* * 7* *#?',
4:*: #* *7 4* )* #*47)*) #4)) 47.*) .4#:* * *.) *#?',
4 *: *7 :*## 4 .* #*) * 4 77*7 #4)) 47#*: .4 )* *. * *#?',
4#*# 7*7: #*7 4##*7 :*. #.*4 :)*: #4)) 47)*# .4* * 7*7 *#?',
4...* * .*:7 4.)*) * 7*:4#.* #4)) 4* .4*) * ))*: *#?',
4* #* *). 4.))*) 7* :*.4..* #4)) 4:* .4* * * !1(?+(=(!',
4:* .*) *: 4: *. :*: )*.4* #4)) 4.*) .47).* * #)* !1(?+(=(!',
4)7* 7*. * 4:..*7 )*. .*74:7*: #4)) 4* .47:* * ).* !1(?+(=(!',
47*) * )* 4) #*. .* )*#4::* #4)) 4.*# .47# *. *7 .*7 !1(?+(=(!',
47:*: *. 7* 47 *: 7#*) .)*.4).*. #4)) 47 * .47 * #* * !1(?+(=(!',
47*. .*#7 *. 47* *7 7#*47)* #4)) 4 #* #4):)* *# 7*) !1(?+(=(!',
4)*. 7* .*.) 4.* :)*: #*4*) #4)) 4::* #4) )*# *7 * !1(?+(=(!',
4)*: *# #*7 4 .*: # *# ::*4:*. #4)) 4 * #4)7.* *. :7*) !1(?+(=(!',
4 :#* #* * 4 * #)* #*4#*7 #4)) 4 :* #4:#)* * #*7 !1(?+(=(!',
4#:7* :* 7*: 4)* . * ::* 4.* #4)) 4#*7 #4:7.* *: ##* !1(?+(=(!',
4.#* #7*. 7 *) 4 7*: ...*: .* 4*. #4)) 4#..*7 #4 :* * #:.*7 !1(?+(=(!',
4* #*# 7* 4 * .:)*# )*)4 7* #4)) 4#::* #4#* *) .7*): !1(?+(=(!',
4: * #*# 7* # 4#*# * # *4 7* #4)) 4.7*# #4.#* *7 .*. !1(?+(=(!',
4:##*. #*7 7* 4##* * #. *)4 :)* #4)) 4. *) #4.7*. * . * !1(?+(=(!',
4) )*: ##*#. 7 *) 4.7* :* .:*4# *7 #4)) 4.:.*) #4#.* *) .#* !1(?+(=(!',
47 *. #:*. 7#*.7 4.#:* :*. .)*.4#) *) #4)) 4*# #4#7* * 7)*:: !1(?+(=(!',
4* .*7 7.* 47 *. ::7*# #:*#4. * #4)) 4:7*. #4 * * .*# !1(?+(=(!',
4* ..*7) 7.*7 4 .* )*7 :* 4.:*) #4)) 4:* #4.:*. * :#* !1(?+(=(!',
4.*) .)*. 7 *7 4:* ):* :))*4:*# #4)) 4::* #4)* * :* !1(?+(=(!',
4 *) 7*77 ):*: 4: *# 47*. )#*4#* #4)) 4):* #4* #* :#.*7 !1(?+(=(!',
4##* 7*7 ) * 4: .* 47..*: 47#*.4:* #4)) 4).*) #4 *) *# ::* !1(?+(=(!',
4.7)*# 7* )7* : 4::*# 477* 4#*.4:#* #4))#477*) #47.*7 *: )7*:. !1(?+(=(!',
477* 7*7 :* 4)7)*# 4:*# 4.*4: .* #4))#477*7 4):7*7 * )*. !1(?+(=(!',
4)#*7 .:*) :*) 4) *# 4#*. 47*:4:)* #4))#47#* 4:)#*7 *. ).* !1(?+(=(!',
4::)*: .* )* 4)*: 4.:*# 4::*4) *. #4))#477*. 4:7:*. * ))*7 !1(?+(=(!',
4): * ..*: .*# 47#* 4:7* 4 *4)#*) #4))#47:*. 4* *: ).*:7 !1(?+(=(!',
47:* .#* *7 47# * 4::* 4##)*:4))7*) #4))#47)7*) 4.* *# )7*) !1(?+(=(!',
4*: .* * 47) * 4)* 4. *.47*# #4))#47).*7 4##* * )*) !1(?+(=(!',
4.*# .*77 .:*: 4*) 4)*) 4:*:47 * #4))#47)*7 4 .:* * :))*7 !1(?+(=(!',
4.* .7* . * ) 4:*7 4:)* 4:7*4)*: #4))#47)*# 4:.* * ::*) !1(?+(=(!',
4 ##*: #)*: .*: 47* 4)* 4:)*4.*7 #4))#47:* 47 *: *# :#:* !1(?+(=(!',
4##7*7 #)* #)* 4:*7 4..* 4)*4 *: #4))#477*7 4 * *# :*# !1(?+(=(!',
4. * #)*# #.* 4.* 4 )*7 47#*4.*7 #4))#47#* 4 #*. *. :7*. !1(?+(=(!',
*+
, + -'&
+
./
+
+
0"12
3+
3+
4&+!"
"
#$
%&' ()* +,-.*
'
2+
+/0%
4
+#$
%&' ()* +,-.*
'
+
1%%
0
4
:
<
>
:;<
?
:;<
879'3
:
<
89'
:
<
./
:
<
./
:
<
4
2
:
<
4
7
2
:
<
/
:
<
-
:;9@<.,
4)*7 #)* #*: 4 *: 4* 4)*)4*. #4))#47*: 47..*) * .:* !1(?+(=(!',
4:* #)*# :*: 4 *) 477* 47.*4#)* #4))#477#*7 4))7* * )*.. !1(?+(=(!',
4):*7 #)* : * 4 * 47..*) 4:7*.4 7*) #4)) 4)*: 4).* * .: *.. !1(?+(=(!',
#47* #)*#) :* 4#)*7 47*# 4#*4 ##*: #4)) 4)*. 4: *: * . * !1(?+(=(!',
#4* #)*). *7 4#..*: ):* 4 )*)4#7*. #4)) 4::*# 4.* * #:*# !1(?+(=(!',
#4* .7*) )*77 4.* )* 4 :*4##7*# #4)) 4:.*) 4*# *. #:* !1(?+(=(!',
#47#*. .7*: *. 4..7* :#* 4# *#4#).*) #4)) 4:*7 4.#*# * #*7. !1(?+(=(!',
#4))* .*:. *7 47#* : * 4#))*.4. *7 #4)) 47*. 4#).* *# : * !1(?+(=(!',
#4 ) *7 .*7# *)# 4 :*: #7* 4.#*:4.:#*. #4)) 4.#.* 4# *) * *77 !1(?+(=(!',
#4#::*7 .*# *#7 4)* .:* 47* 4*) #4)) 4#::* 4 )*7 * * !1(?+(=(!',
#4.:* . * 7*:) 4:*# .* 4 :*4.)* #4)) 4#* 4 * *# #)*# !1(?+(=(!',
#4*7 .#*# 7* 4:* #.* 4:)*4:7)*# #4)) 4 * 4 7#* *) :*.) !1(?+(=(!',
#4:7* ..*: 7*: 4)7*. #:* 4:#*)4: * #4)) 4.#* 4.:*) * *: !1(?+(=(!',
#4).#* .:*. ))*) 4) .*# *7 4:#*4::* #4)) 4:*) 4* *: :)* !1(?+(=(!',
.47#)*: .)*.# ).*7 4):7*# )*) 4:: *4)* #4)) 4))*: 47* * .*. !1(?+(=(!',
.4#* 7*.7 )* 47* 7*. 4)7.*4) )* #4)) 4 *. 4:*: *. . * !1(?+(=(!',
.4 :* * ) :)* ) 47 * )* 4)*#4))* #4)) 47.* 47* *: # *. !1(?+(=(!',
.4 * *7# :#*#. 47.)*# 7*7 4)#* 477.* #4))4)* 4#:* * * !1(?+(=(!',
.4 .*7 #* :*# 47)*) .7* 4) 7*: 477* #4))4: .*) 4#* *# # * !1(?+(=(!',
.4#)*. .*) * 4.*7 #* 4))*: 47#*: #4))4#.* 4#*7 * .*# !1(?+(=(!',
.4.*. :*: *. 4.*7 * 4)* 47*: #4))4.. * 4#)* *7 *# !1(?+(=(!',
.4.)* :7*# *.# 4 )*. #* 4).* 47:.* #4))4#)*) 4.#*. *) :*.# !1(?+(=(!' ,
.4)*7 :*: *) 4##*) ##*) 4)*7 47)* #4))4##* 4.)* * :*. !1(?+(=(!' ,
.4:* :*7 *# 4.*: :*: 4) * 47 *. #4))4 #:* 4*: * )* !1(?+(=(!' ,
.4)* :.* : *#: 4#*) # *7 4)7 * 4* #4))4.#* 4:*# *7 477*) !1(?+(=(!' ,
477* ::*) *. 4)*. . *# 4:)* 4.* #4))4*. 4)*# *. 47)*: !1(?+(=(!' ,
4 *# ::*) *:7 4:* :*7 4::*. 4:* #4))4)*7 47:* 7*) 4:*:# !1(?+(=(!' ,
47:*) :)*). *# 4:* :*# 4:7* 4)* #4))47:#* 47* * 4 *7 !1(?+(=(!' ,
47*: :)*) *.: 4:* )#*# 4:#.*) 4)* #4))4))* 4* 7*# 4. * !1(?+(=(!' ,
4):*) :)*) *.) 4:*# 477)*. 4: * 4)* #4))4:)* 4 .*) 7*7 4 ##* !1(?+(=(!' ,
4 )*) :)*) *. 4:*. 47*. 4:)*. 4)* #4))4:7 * 4.7* 7* 4# *) !1(?+(=(!' ,
4#: *) :)*) * 4:* 4)*. 4:.*7 4)*# #4))4* 4*# 7* 4.*#) !1(?+(=(!' ,
4.:* :)*) 7*7 4:*) 4:)*# 4:77*. 4)* #4))4.* 4::*. * 4 *:7 !1(?+(=(!' ,
4)7* :)*:: * 4:* 4).* 4:* 4)*) #4))4#7*# 4 7#*. 7*) 4:* !1(?+(=(!' ,
4:.)* :)*) *) 4:* 4 * 4* 47*7 #4))4 *7 4 .* * 4)7*) !1(?+(=(!' ,
4).#* :)*) *7) 4:* 4#.)* 4.7* 47* #4))4* 4 *. 7* 4)) *:7 !1(?+(=(!' ,
:47#)*7 :)*:: *: 4:* 4..*) 4 )*# 47*# #4))4 *: 4 :*# 7* 47: *)) !1(?+(=(!' ,
:4#*: :)*. *7. 4: *7 4#.*7 4:* 47*: #4))4#7*. 4 )*# 7* 4#* !1(?+(=(!' ,
:4 * :)*: * # 4: * 4:#7* 4.* 4* #4))47#.*# 4 .* 7*. 4..*7 !1(?+(=(!' ,
:4 *# :)*: *: 4: * 4) * 4* 4*# #4))4).*# 4 * 7* 4##* !1(?+(=(!' ,
*+
, + -'&
+
./
+
+
0"12
3+
3+
4&+!"
"
#$
%&' ()* +,-.*
'
2+
+/0%
4
+#$
%&' ()* +,-.*
'
+
1%%
0
4
:
<
>
:;<
?
:;<
879'3
:
<
89'
:
<
./
:
<
./
:
<
4
2
:
<
4
7
2
:
<
/
:
<
-
:;9@<.,
:4 #*# :)*. *:. 4:#*7 47.* 477* 4*: #4))4:7* 4 :.* 7* 4 #* !1(?+(=(!' ,
:4#7*. :)*: *:# 4:#* 47* 4.:.*. 4* #4))4.* 4 ))*: 7*7 4#.* !1(?+(=(!' ,
:4.#* :)*# * 4:#*: 4 * 4.*# 4*. #4))4.:* 4#* 7* 4..*#. !1(?+(=(!' ,
:47*# :)*: * # 4:.* 4:* 4..7* 4*7 #4))4#::* 4##* 7* 4*#) !1(?+(=(!' ,
:4: * :)*: *77 4:.*# 4 * 4. :*7 4* #4))4 )#* 4#*# 7*# 4:7*: !1(?+(=(!' ,
:4)7)* :)*: *) 4:.*) 4#7#*# 4. *: 4* #4))4 77*) 4##7*# 7*7 4:):*7. !1(?+(=(!' ,
)477*# :)* *## 4:* 4#):*. 4.* 4 * #4))47*: 4#.* 7* 4):* !1(?+(=(!' ,
)47)*# :)*: * 4:* 4.)*. 4.7* 4 *# #4))4 * 4#* 7* 47*: !1(?+(=(!' ,
)4)* :)*. *): 4::*7 4:#* 4#)* 4 *: #4))4*7 4#)7*. 7*. 4.*# !1(?+(=(!' ,
)4:.*# :)*: *. 4::* 4::* 4#:7* 4#* #4))47*. 4.7*: 7* 4#*#7 !1(?+(=(!' ,
)4:* :)* *)# 4::*: 4)*. 4#..*: 4#*. #4))74)* 4.*7 7* 4 *): !1(?+(=(!' ,
)4 #*: :)*) * 4:)* 47..*7 4##*7 4.*7 #4))74: 7* 4.7*# 7* 4 :*7 !1(?+(=(!' ,
)4#7* :)*# *#. 4:)*# 4#)* 4#)*7 4.* #4))74 .*: 4. * 7* 4#*: !1(?+(=(!' ,
)4..*7 :)*: *): 4:)*) 4#* 4##* 4.* #4))74.##*7 4.#* 7*# 4..*7 !1(?+(=(!' ,
)4#:* :)*): *)# 4)7* 4 .*7 4#* 4.*) #4))74#.7* 4.7* 7* 47* !1(?+(=(!' ,
)4:#*# :)*:: * 4)7* 4 :* 4 ):* 4*7 #4))74 .* 4.:*. 7* 4)*7 !1(?+(=(!' ,
)4) * :)*)# *#. 4)7* 4#.*# 4 :#*# 4* #4))74)*. 4.).*# 7* 4::*#7 !1(?+(=(!' ,
747 *. )7*7 * 4)7* 4.#*: 4 7*. 4* #4))74:7* 4* 7* 4)*7: !1(?+(=(!' ,
74.*. :)*) *.# 4)7* 4)* 4 #.*. 4* #4))74:.* 4 *: 7* 47.*# !1(?+(=(!' ,
74* :)*) *.. 4)7*# 4:* 4 *: 4* #4))747)*. 4:* 7*7 4#* !1(?+(=(!' ,
74.*7 :)*) *:7 4)7*# 4)7* 4 )* 4* #4):)4)):*: 4#*. 7* 4 :*7 !1(?+(=(!' ,
74 )*# :)*) *7: 4)7*. 4)))* 4 .* 4* #4):)4)7.* 4. * 7* 4*: !1(?+(=(!' ,
74# *) :)*) *: 4)7*: 47) * 4 7*# 4*. #4):)4:*. 4.* 7* 4 :*. !1(?+(=(!' ,
74.7:*: :)*:: *)7 4)7*) 4:*# 4)*: 4* #4):)4:* 4::* 7* 4#:*7 !1(?+(=(!' ,
747*) :)*)# *: 4)* 4:7*: 4:7* 4*) #4):)4.#*7 4))*# 7* 4.7:*) !1(?+(=(!' ,
74)* :)*) *77 4)* 4 *) 4.:* 4:*7 #4):)4#7*) 4:7*) 7* 4.))*) !1(?+(=(!' ,
74:)* :)*): *## 4)* 4 .:*. 4#.*. 4:* #4):)4 * 4:* 7*# 4)7* : !1(?+(=(!' ,
74):.* :)*) *77 4)* 4#.*7 4 * 4:* #4):)4 * 4: *7 7*# 4::7*.) !1(?+(=(!' ,
47)*: :)*) * 4)* 4.# *: 4*# 4:* #4):)4#7*: 4: *) 7* 4)7*# !1(?+(=(!' ,
4* :)*) *: 4)*# 4 #* 4* 4:* #4):)4#)*) 4:##* 7* #47#:* # !1(?+(=(!' ,
4. *. :)*) * 4)*. 4::* 4* 4:* #4):)47.* 4:..* 7* #4 *) !1(?+(=(!' ,
4#*7 :)*) *77 4)* 4))*) 477*7 4:*# #4)::4)#* 4:*. 7* #4.*#) !1(?+(=(!' ,
4 #7* :)*) * 4)*: #47* 4:*) 4:*. #4)::4::* 4::)* 7*) #4#*) !1(?+(=(!' ,
4# *# :)*) 7*)) 4)*) #4* 4 * 4:* #4)::4)*) 4)7*. * #4 * !1(?+(=(!' ,
4..*# :)*) 7* 4)*7 #47.* 4#)* 4:*: #4)::4.))* 4)* 7* #4#7*) !1(?+(=(!' ,
4*# :)*) * 4)*7 #4).* 4 #* 4:*: #4)::4.7)* 4)* 7* #4#:)* !1(?+(=(!' ,
4::*) :)*) * 4)* #4:.*: 4*: 4:*) #4)::4#:* 4) * * #4..* # !1(?+(=(!' ,
4)*. :)*) *7 4)* #4 :7*# 4:*7 4)*7 #4)::4 *) 4)#* * #4..*7 !1(?+(=(!' ,
477#*: :)*) * 4)* #4#*. 47*) 4)* #4)::4*: 4)*. 7* #4:# *7 !1(?+(=(!' ,
47)*7 :)*) *. 4)* #4..* 4)7*7 4)* #4)::4 *. 4):#* 7* #4) *7 !1(?+(=(!' ,
*+
, + -'&
+
./
+
+
0"12
3+
3+
4&+!"
"
#$
%&' ()* +,-.*
'
2+
+/0%
4
+#$
%&' ()* +,-.*
'
+
1%%
0
4
:
<
>
:;<
?
:;<
879'3
:
<
89'
:
<
./
:
<
./
:
<
4
2
:
<
4
7
2
:
<
/
:
<
-
:;9@<.,
4:)* :)*) * 4)*. #4#*7 4.*7 4)* #4)::4#* 4)):*) 7* .47:*:# !1(?+(=(!' ,
4:*# :)*) *)# 4)* #4: #* 4.* 4)*# #4)::47.7*7 47* *. .4*: !1(?+(=(!' ,
4#*7 :)*) *. 4)* #4)* 4#*: 4)*# #4):4).:* 47*# 7* .47.*. !1(?+(=(!' ,
4 .:* :)*) *) 4)*: .47)*. 4 7* 4)*. #4):4:#*. 47*) 7* .4).*7 !1(?+(=(!' ,
4##)* :)*) * 4)*) .47* 4)* 4)* #4):4: *: 47 * 7* .4:*:7 !1(?+(=(!' ,
4.#*) :)*) *: 4)*7 .4*: 4*: 4)*: #4):4.)* 47##*. 7* .4 *: !1(?+(=(!' ,
4 *) :)*) *.. 4)* .47* 47.*# 4)*) #4):4.7 *7 47..* 7* .4##:*# !1(?+(=(!' ,
4: * )7* *: 4)* .4)*: 47) *: 4)*) #4):4#* 47:*7 7* .4. * !1(?+(=(!' ,
4)* :)*: *7 4)* .4 : *) 47:*. 4)*) #4):4 7* 47:)*7 7*# .4.*7 !1(?+(=(!' ,
47*) :)*: * 4)*# .4##*7 47*# 47* #4):47* 47))*: 7*# .4:* !1(?+(=(!' ,
47:*. :)*: *)# 4)*: .4..#* 47.* 47*. #4):4 7*7 47*: 7* .4)7* !1(?+(=(!' ,
47*# :)*: * 4) * .4#* 47 )*. 47*) #4):4 *: 4* 7* .4)))* . !1(?+(=(!' ,
4)* :)*: *) 4) *# .4: * 47:* 4* #4):47#*: 4* 7* 47:.* !1(?+(=(!' ,
4:#*7 :)*:# *:) 4) *: .4))* 47.*: 4*. #4):.4).#*. 4 * *. 4#* ) !1(?+(=(!' ,
4 )*# :)*) *.: 4)#* 47*: 47* 4*) #4):.4:* 4#*# 7* 4.#*#. !1(?+(=(!' ,
4#* :)*: 7* 7 4)#* 4* 4)))*7 4* #4):.4:*# 4*# * 4#*.: !1(?+(=(!' ,
4..*: :)*: * 4)#* 4*) 4): *# 4*# #4):.4.)*7 4:#* * 4 )*.# !1(?+(=(!' ,
4##*# :)*# *) 4).* 47#*. 4)* 4*) #4):.4#))* 4):*: 7*# 4#*)# !1(?+(=(!' ,
4: :* :)*: * 4).*# 4)* 4)#*) 4* #4):.4#7*# 4* 7* 4..* !1(?+(=(!' ,
4) * :)*: *#: 4).*: 4 )* 4) * 4*. #4):.4 *. 4#* 7* 47.*: !1(?+(=(!' ,
47 *. :)*: 7* 4)* 4#:*. 4))* 4*) #4):.4* 4)* * 4)*. !1(?+(=(!' ,
4.*# :)*: *.: 4)* 4.*# 4).* 4 * #4):.4* 4#*. *# 4::* !1(?+(=(!' ,
4* :)*: *)) 4)* 4.* 4)7 * 4 *# #4):.4 * 4. * 7*: 4).:*77 !1(?+(=(!' ,
4* :)*: * 4):*7 4:#.*# 4:)*7 4 *: #4):.47 :* 4* 7* :47#:*: !1(?+(=(!' ,
4 7* :)*: *) 4):* 4) .* 4::*# 4#* #4):#4)#*) 4:)* 7* :4 #*.) !1(?+(=(!' ,
4 )#*. :)*: *: 4):*. :47:* 4:.#*# 4#* #4):#4:..*# 47* 7* :4*) !1(?+(=(!' ,
4#::* :)*# *#: 4))*7 :4)* 4:#* 4#*: #4):#4 *: 4#* 7* :4*7# !1(?+(=(!' ,
4.:* :)*: *: 4))* :4*. 4::* 4.* #4):#4.:7*: 4:*. 7* :4 *# !1(?+(=(!' ,
4.*) :)*: *# 4))* :4.* 4:#*7 4.*# #4):#4#::* 4 * 7* :4#7*) !1(?+(=(!' ,
4:.:* :)*: *. 477*7 :4 7.*: 4:*: 4.*: #4):#4 )* 4# *. 7* :4#::*)) !1(?+(=(!' ,
4)#)*. :)*: *7 477* :4 )* 4):*) 4* #4):#4 7* 4.* 7*# :4..*) !1(?+(=(!' ,
#47#*7 :)*: *# 477*. :4#:)*: 4:.* 4* #4):#4 *. 4)* 7* :4.#*# !1(?+(=(!' ,
#4 *) :)*) * 477*) :4.:7*) 4 * 4* #4):#4* 4)* 7* :4:#*# !1(?+(=(!' ,
#4)* :)*: *# 47* :4 * 4.*7 4:* #4):#47*7 4 7* 7* :4) *.# !1(?+(=(!' ,
#4#* :)*: *) 47*. :4:.)*: 4 )*: 4:* #4):#47 *# 4 #* 7* )47#*) !1(?+(=(!' ,
#4 :*# :)*: *# 47*7 :4).* 4:*7 4:*: #4): 4) *7 4 .*. 7* )4#* !1(?+(=(!' ,
#4#*) :)*: *) 47* )47#.* 4#* 4)* #4): 4: *# 4 )* 7* )4.*: !1(?+(=(!' ,
#4.:* :)*) *# 47*# )4#7* 4 *7 4)* #4): 4#*) 4 #7* * )47*77 !1(?+(=(!' ,
#4*. :)*) #*: 47* )4 * 47.*7 4)*# #4): 4.#)*: 4 #* * )4):*#. !1(?+(=(!' ,
#4:7.* :)*) *.7 47*: )4:* 4.):* 4)*. #4): 4#..*7 4 .#* * )4 :)*: !1(?+(=(!' ,
*+
, + -'&
+
./
+
+
0"12
3+
3+
4&+!"
"
#$
%&' ()* +,-.*
'
2+
+/0%
4
+#$
%&' ()* +,-.*
'
+
1%%
0
4
:
<
>
:;<
?
:;<
879'3
:
<
89'
:
<
./
:
<
./
:
<
4
2
:
<
4
7
2
:
<
/
:
<
-
:;9@<.,
#4)7*) :)*) *# 47*) )4 *7 4.:)* 4)* #4): 4 * 4 *) 7* )4#:*) !1(?+(=(!' ,
#4))#*) :)*) *: 47*7 )4#.* 4.)*. 4)*: #4): 4* 4 :* 7*: )4.*.7 !1(?+(=(!' ,
.47)*7 :)*) * 47* )4.*) 4..:* 4 7*7 #4): 4:* 4 )*: 7*. )4.#* !1(?+(=(!' ,
.4:#*: :)*) *7 47* )4 *) 4.##*) 4 7* #4): 4:)* 4#7.* * )4:# *. !1(?+(=(!' ,
.4:7* :)*) 7* 47* )4:7:* 4. 7*) 4 7* #4): 47)#* 4#* 7* )4) *# !1(?+(=(!' ,
.4#:*: :)*)# 7*## 47*# )4::#*. 4.:* 4 7* #4): 47:* 4#*. 7* 747:*: !1(?+(=(!' ,
.4)*7 :)*)# 7*## 47*. )4):* 4.* 4 7* #4):4):#*. 4#:*) 7*7 747#7*7 3B/0/0
Page 1/1
3S-714
Report Printed: 2/25/2025
Cement
Cement Details
Description
Surface String Cement
Cementing Start Date
1/31/2025 03:00
Cementing End Date
1/31/2025 03:00
Wellbore Name
3S-714
Comment
Test lines to 3500 PSI. Pump 100 BBLS 10.5 PPG MudPush @ 5.5 BPM/200 PSI. Drop bottom plug. Pump 473 BBLS 11.0 PPG lead cement (Cement wet @
03:30hrs). MudPush observed at surface at 340 BBLS cement pumped. Pump 60 BBLS 15.8 PPG tail cement (Cement wet @ 05:07hrs). FCP - 282 PSI @ 5
BPM. SD. Drop top plug. Pump 20 BBLS FW with cement unit. Swap to rig pumps. Displace with 9.5 PPG spud mud. Bump plug with calculated strokes. 244
BBLS / 2423 strokes, FCP - 905 PSI @ 3 BPM. Pressure up to 1500 PSI. Hold for 5 minutes. Check floats. Good. Cement in place at 07:00hrs on 1/31/24.
Note: Cement to Surface - 110 BBLS. Lost returns at 1400 strokes into displacement. Worked string and rotate with no improvement. Cement was still at surface
when ND risers.
Cement Stages
Stage # 1
Description
Surface String Cement
Objective Top Depth (ftKB)
40.7
Bottom Depth (ftKB)
2,803.0
Full Return?
No
Vol Cement …Top Plug?
Yes
Btm Plug?
Yes
Q Pump Init (bbl/m…
5
Q Pump Final (bbl/…
3
Q Pump Avg (bbl/…
5
P Pump Final (psi)
985.0
P Plug Bump (psi)
1,500.0
Recip?
No
Stroke (ft) Rotated?
No
Pipe RPM (rpm)
Tagged Depth (ftKB) Tag Method Depth Plug Drilled Out To (ftKB) Drill Out Diameter (in)
Comment
Cement Fluids & Additives
Fluid
Fluid Type Fluid Description Estimated Top (ftKB) Est Btm (ftKB) Amount (sacks) Class Volume Pumped (bbl)
Yield (ft³/sack) Mix H20 Ratio (gal/sack) Free Water (%) Density (lb/gal) Plastic Viscosity (cP) Thickening Time (hr) CmprStr 1 (psi)
Additives
Additive Type Concentration Conc Unit label
Surface String Cement
Page 1/1
3S-714
Report Printed: 2/25/2025
Cement
Cement Details
Description
Intermediate String 1 Cement
Cementing Start Date
2/7/2025 09:00
Cementing End Date
2/7/2025 11:00
Wellbore Name
3S-714
Comment
Line up to cementers. Load bottom plug #1 and pump 5 bbls of H2O. Test lines to 4000 PSI – test good. Shut Down. Load bottom plug #2 pump 60 BBLS 12.5
PPG Mud Push 5 BPM/150 PSI. Swap to cementers. Pump 57 BBLs 15.3 PPG Tail cement. Shut Down. Load top plug. Cementers pump 10 BBLS FW. Swap to
rig pumps. Displace w/ rig at 6 BPM. Slow rate to 3 BPM at 20 BBLs left. Bump plug at 2873 Stks. FCP= 380 PSI. Pressure up to 1902 PSI and hold. Bleed off
and check floats. Good.
Cement in place at 10:51 hrs 02-07-2025.
Cement Stages
Stage # 1
Description
Intermediate String 1
Cement
Objective Top Depth (ftKB)
5,665.0
Bottom Depth (ftKB)
6,639.3
Full Return?
No
Vol Cement …Top Plug?
Yes
Btm Plug?
Yes
Q Pump Init (bbl/m…
7
Q Pump Final (bbl/…
3
Q Pump Avg (bbl/…
6
P Pump Final (psi)
380.0
P Plug Bump (psi)
1,902.0
Recip?
No
Stroke (ft) Rotated?
No
Pipe RPM (rpm)
Tagged Depth (ftKB) Tag Method Depth Plug Drilled Out To (ftKB) Drill Out Diameter (in)
Comment
Load bottom plug #1 and pump 5 bbls of H2O with SLB. Test lines to 4000 PSI – test good. Shut Down. Load bottom plug #2 pump 60 BBLS 12.5 PPG Mud Push
5 BPM/150 PSI. Swap to cementers. Pump 57 BBLs 15.3 PPG Tail cement. Shut Down. Load top plug. Cementers pump 10 BBLS FW. Swap to rig pumps.
Displace w/ rig at 6 BPM. Slow rate to 3 BPM at 20 BBLs left. Bump plug at 2873 Stks. FCP= 380 PSI. Pressure up to 1902 PSI and hold. Bleed off and check
floats. Good.
Cement in place at 10:51 hrs 02-07-2025.
Cement Fluids & Additives
Fluid
Fluid Type
Primary Cement
Fluid Description Estimated Top (ftKB)
5,665.0
Est Btm (ftKB)
6,639.3
Amount (sacks) Class
G
Volume Pumped (bbl)
57.0
Yield (ft³/sack)
1.25
Mix H20 Ratio (gal/sack)
5.43
Free Water (%) Density (lb/gal)
15.30
Plastic Viscosity (cP)
80.0
Thickening Time (hr)
5.00
CmprStr 1 (psi)
Additives
Additive Type Concentration Conc Unit label
Intermediate String 1 Cement
Page 1/1
3S-714
Report Printed: 2/25/2025
Cement
Cement Details
Description
Production String 1 Cement
Cementing Start Date
2/20/2025 19:33
Cementing End Date
2/20/2025 22:30
Wellbore Name
3S-714
Comment
PJSM for cement job. Pressure test lines to 4000 psi - test good. Pump 50 bbls of 11 ppg of mud push at 3 bpm with rig. Pumped 277 bbls of 15.3 ppg cement at
3.5 bpm with SLB. Pump 1 bbl H2O, dropped dart, and pumped 9 bbls of H2O. Displace with rig 140 bbls of Brine, swap to transition spacer continue displace at
4 bpm, 960 psi. Reduce rate to 3 bpm, ICP 806 psi and bumped plug at 2251 strokes, FCP 1300 psi and hold for 5 min, bleed of pressure and check floats - float
is holding.
Cement Stages
Stage # 1
Description
Primary – Full Bore
Objective
Cement 4 1/2" lower liner
completion
Top Depth (ftKB)
3,450.0
Bottom Depth (ftKB)
16,387.0
Full Return?
Yes
Vol Cement …Top Plug?
Yes
Btm Plug?
No
Q Pump Init (bbl/m…
4
Q Pump Final (bbl/…
3
Q Pump Avg (bbl/…
4
P Pump Final (psi)
1,338.0
P Plug Bump (psi)
832.0
Recip?
No
Stroke (ft) Rotated?
No
Pipe RPM (rpm)
Tagged Depth (ftKB) Tag Method Depth Plug Drilled Out To (ftKB) Drill Out Diameter (in)
Comment
Cement Fluids & Additives
Fluid
Fluid Type Fluid Description Estimated Top (ftKB) Est Btm (ftKB) Amount (sacks) Class Volume Pumped (bbl)
Yield (ft³/sack) Mix H20 Ratio (gal/sack) Free Water (%) Density (lb/gal) Plastic Viscosity (cP) Thickening Time (hr) CmprStr 1 (psi)
Additives
Additive Type Concentration Conc Unit label
Production String 1 Cement
1. Type of Request: Abandon Plug Perforations Fracture Stimulate Repair Well Operations shutdown
Suspend Perforate Other Stimulate Pull Tubing Change Approved Program
Plug for Redrill Perforate New Pool Re-enter Susp Well Alter Casing Other: ___________________
2. Operator Name: 4. Current Well Class: 5. Permit to Drill Number:
Exploratory Development
3. Address:Stratigraphic Service
6. API Number:
7. If perforating:8. Well Name and Number:
What Regulation or Conservation Order governs well spacing in this pool?KRU 3S-714
Yes No
9. Property Designation (Lease Number): 10. Field:
Coyote Oil Pool
11.
Total Depth MD (ft): Total Depth TVD (ft): Effective Depth MD: Effective Depth TVD: Junk (MD):
16392 4204 16392 5163 2305 None None
Casing Collapse
Structural
Conductor 20" 132.0
Surface 10-3/4" 2803 5210 2470
Intermediate 7-5/8" 6639 10860 7850
Liner 4-1/2" 16392 11590 9210
Packers and SSSV Type:Packers and SSSV MD (ft) and TVD (ft):
12. Attachments: Proposal Summary Wellbore schematic 13. Well Class after proposed work:
Detailed Operations Program BOP Sketch Exploratory Stratigraphic Development Service
14. Estimated Date for 15. Well Status after proposed work:
Commencing Operations:OIL WINJ WDSPL Suspended
16.Verbal Approval: Date: GAS WAG GSTOR SPLUG
AOGCC Representative: GINJ Op Shutdown Abandoned
Contact Name:Rodrigo Ruysschaert
Rodrigo Ruysschaert Contact Email:Rodrigo.Ruysschaert@cop.com
Contact Phone: 907-621-0671
Authorized Title: Completions Engineer
Conditions of approval: Notify AOGCC so that a representative may witness Sundry Number:
Plug Integrity BOP Test Mechanical Integrity Test Location Clearance
Other Conditions of Approval:
Post Initial Injection MIT Req'd? Yes No
APPROVED BY
Approved by: COMMISSIONER THE AOGCC Date:
Comm. Comm. Sr Pet Eng Sr Pet Geo Sr Res Eng
6599.3
9940.14
4-1/2"
4204.00
92.0
2762.2
MD
132.0
2520.00
4139.00
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
APPLICATION FOR SUNDRY APPROVALS
20 AAC 25.280
ADL380107 / ADL392374
224-151
P.O. Box 100360, Anchorage, Alaska 99510-0360 50-103-20903-00-00
ConocoPhillips Alaska Inc.
Proposed Pools:
Kuparuk Field
AOGCC USE ONLY
Tubing Grade:Tubing MD (ft):
TNT packer: 6331 ft MD/4066 ft TVD
SLZXP packer: 6452 ft MD/4098 ft TVD
Perforation Depth TVD (ft):
L-80
Perforation Depth MD (ft):
Apr 04 2025
Halliburton TNT Prod Packer
Baker SLZXP, No SSSV
Mar 04 2025
Subsequent Form Required:
Suspension Expiration Date:
Will perfs require a spacing exception due to property boundaries?
Current Pools:
MPSP (psi):Plugs (MD):
17. I hereby certify that the foregoing is true and the procedure approved herein will not be deviated from without prior written approval.
Authorized Name and
Digital Signature with Date:
Tubing Size:
PRESENT WELL CONDITION SUMMARY
Length Size TVD Burst
6475
m
n
Pe _
2
66
t e
t t e
N
325-126
By Gavin Gluyas at 8:14 am, Mar 05, 2025
Fracture Stimulate
DSR-3/10/25
10-404
X
SFD 3/24/2025
X
CDW 03/10/2025
A pr 04 2025
WA G
VTL 3/25/2025*&:
Jessie L.
Chmielowski
Digitally signed by Jessie L.
Chmielowski
Date: 2025.03.26 08:22:45 -08'00'03/26/25
RBDMS JSB 032725
Section 1 - Affidavit 10 AAC 25.283 (a)(1)
Exhibit 1 is an affidavit stating that the owners, landowners, surface owners and operators
within one-half mile radius of the current or proposed wellbore trajectory have been provided
notice of operations in compliance with 20 AAC 25.283(a)(1).
Section 2 – Plat 20 AAC 25.283 (2)(A)
Plat 1: Wells within 1/2 mile
Table 1: Wells within 1/2 miles (2)(C)
SECTION 3 – FRESHWATER AQUIFERS 20 AAC 25.283(a)(3)
There are no freshwater aquifers or underground sources of drinking water within a one-half
mile radius of the current or proposed wellbore trajectory.
None as per Aquifer Exemption Title 40 CFR 147.102(b)(3), “That portions of the aquifers on
the North Slope described by a ¼ mile area beyond and lying directly below the Kuparuk
River Unit oil and gas producing field”.
Agree: Aquifers affected by this well are exempt.
This well lies within the Kuparuk River Unit (KRU) boundary of 1984 that forms the basis for the aquifer exemption granted
by Title 40 CFR 147.102(b)(3) according to a recent opinion by the EPA, which states in part:
"In short, EPA finds that the boundary of Alaska’s aquifer exemption at 40 C.F.R. 147.102(b)(3) was determined on May
11, 1984. After a program is approved or promulgated, additions to aquifer exemptions, including boundary expansions to
aquifers or parts thereof, submitted as part of a UIC program cannot change unless EPA approves those additions in
accordance with EPA’s UIC program regulations (See 40 C.F.R. 144.7(b)(1) and (3)).”
(Reference: Email from Evan Osborne, US EPA Region 10, to Steve Davies, AOGCC, dated December 2, 2024.) SFD
SECTION 4 – PLAN FOR BASELINE WATER SAMPLING FOR
WATER WELLS 20 AAC 25.283(a)(4)
There are no water wells located within one-half mile of the current or proposed wellbore
trajectory and fracturing interval.
A water well sampling plan is not applicable.
Agree. SFD
SECTION 5 –DETAILED CEMENTING AND CASING INFORMATION
20 AAC 25.283(a)(5)
All casing is cemented and tested in accordance with 20 AAC 25.030. See Wellbore schematic
for casing details.
SECTION 6 – ASSESSMENT OF EACH CASING AND CEMENTING
OPERATION TO BE PERFORMED TO CONSTRUCT OR REPAIR THE
WELL 20 AAC 25.283(a)(6)
Casing & Cement Assessments:
10 & 3/4” casing cement pump report on 1/31/2025 shows that the original job pumped as
designed. The cement job was pumped with 43 barrels of 11.0 ppg lead cement and 60 barrels
15.8 ppg tail cement. The plug bumped and floats held. Lost returns at 1400 strokes into
displacement. Worked string and rotate with no improvement. Cement was still at surface when
ND risers. Cement to Surface - 110 BBLS.
The 7 & 5/8” casing cement report on 2/7/2025 shows that the job was pumped as designed,
indicating competent cementing operations. The cement job was pumped pump with 60 BBLS
12.5 PPG Mud Push 5 BPM/150 PSI. followed by 57 BBLs 15.3 PPG Tail cement. Bump plug
at 2873 Stks, and floats held. A cement bond log indicates competent cement with a cement
top @ 5530 ft MD / 3765 ft TVD.
Summary
All casing is cemented in accordance with 20 AAC 25.030 and each hydrocarbon zone
penetrated by the well is isolated.
Based on engineering evaluation of the wells referenced in this application, ConocoPhillips has
determined that this well can be successfully fractured within its design limits.
Agree. Top of consistent, excellent bond is 5,575' MD. SFD
g
Cement to Surface - 110 BBLS
Agree. SFD
SECTION 7 – PRESSURE TEST INFORMATION AND PLANS TO
PRESSURE-TEST CASINGS AND TUBINGS INSTALLED IN THE
WELL 20 AAC 25.283(a)(7)
On 2/2/2025 the 10-3/4” casing pressure was tested to 3,500 psi for 30 minutes
On 2/9/2025 the 7-5/8” casing was pressure tested to 4,000 psi for 30 minutes.
On 2/23/2025 the 4-1/2” tubing was pressure tested to 4,550 psi. Good Test.
On 2/23/2024 the 7-5/8” casing by 4-1/2” tubing annulus was pressure tested to 3,850 psi.
Good Test.
AOGCC Required Pressures [all in psi]
Maximum Predicted Treating Pressure (MPTP) 7,075
Annulus pressure during frac 3,500
Annulus PRV setpoint during frac 3,600
7-5/8" Annulus pressure test 3,850
4-1/2" Tubing pressure Test 4,075
Electronic PRV 8,075
Highest pump trip 7,575
A 4550 psi tubing test allows a 4136 psi differential (110%). With 3500 psi backpressure, max surface pressure is limited
to 7636 psi. I will correct step 12 in program to this value. CDW 03/10/2025.
SECTION 8 – PRESSURE RATINGS AND SCHEMATICS FOR THE
WELLBORE, WELLHEAD, BOPE AND TREATING HEAD 20 AAC
25.283(a)(8)
Size Weight, ppf Grade API Burst, psi API Collapse, psi
10-3/4” 45.5 L-80 5,209 2474
7-5/8” 29.7 L-80 6,885 4,789
7-5/8” 33.7 P-110S 10,860 7,870
4-1/2” 12.6 L-80 8,430 7,500
Table 2: Wellbore pressure ratings
Stimulation Surface Rig-Up
FMC 10K Frac Tree
SECTION 9 – DATA FOR FRACTURING ZONE AND CONFINING
ZONES 20 AAC 25.283(a)(9)
CPAI has formed the opinion, based on seismic, well, and other subsurface information
currently available that:
The fracturing zone, the gross Coyote interval, has an average thickness greater than 500 ft
TVD over the course of the lateral section of well 3S-714, from where it intersects the top
formation at 6,431’ MD to TD of the well. The Coyote interval is comprised of thinly interbedded
sandstone and siltstone layers. The sandstone and siltstone components are litharenites,
moderately to well sorted, and are of the size range from silt to very fine sand. The estimated
fracture pressure for the Coyote interval is approximately 12.9-16.1 ppg.
The overlying confining interval is represented by distal toe of slope (deep marine) claystone
with thin siltstone beds of the Cretaceous Seabee Formation. This interval is present in
thicknesses of more than 350’ TVD across the area. The top of the confining intervals starts at
~3,550’ TVDSS (5,210’ MD). Currently, there is no data of the fracture gradient of the overlying
Seabee formation, however, CPAI estimates the fracture closure pressure gradient to be 0.67
psi/ft based on diagnostic fracture injection testing (DFIT). The fracture gradient of the overlying
Seabee formation will be greater than the fracture closure pressure gradient of 0.67 psi/ft.
The lower confining interval of the Coyote comprises slope to basin floor mudstones of the
Torok formation, which are present in thicknesses greater than 300’ TVD across the area. This
same confining zone forms the upper confining interval of the Kuparuk River Unit, Torok Oil
Pool. The estimated fracture gradient for this section ranges from 15-18 ppg. The base of the
gross Coyote interval is estimated from seismic to be at ~4,575 ft TVDSS at the heel, and
~4,840’ ft TVDSS at the toe of the well.
The estimated formation pressure within the Coyote interval is 1715 – 1,840 psi at a depth of
4,150’ TVDSS.
SECTION 10 – LOCATION, ORIENTATION AND A REPORT ON
MECHANICAL CONDITION OF EACH WELL THAT MAY TRANSECT
CONFINING ZONE 20 AAC 25.283(a)(10)
ConocoPhillips has formed the opinion, based on following assessments for each well and
seismic, well, and other subsurface information currently available that none of these wells will
interfere with containment of the hydraulic fracturing fluid within the one-half mile radius of the
proposed wellbore trajectory.
Casing & Cement assessments for all wells that transect the confining zone:
3S-08C: The 7" casing cement report on 03/18/2023 indicates the job was pumped as designed
except for some losses in the last 20 bbls,Pump 5 bbls Mudpush @ 12.8ppg, Test lines to 3000
psi, Con't pump 20 bbls 12.8ppg Mud push, Drop bttm plug, Pump batch mixed 15.8ppg slurry
40.2 bbls , Av PR 3.7 bpm, drop top plug, kick out plug pumping 10 bbls wash up and turn over
to rig. Rig displaced plug w/ 10.2ppg mud Av PR 4 bpm, recipricating 20' strock. Full returns
throughtout job until the last 20 bbls displacement.Casing stuck on the up strock 25' up from
shoe point and 75% loss of returns. Bumper plug with calculated strokes 3231 to 1900 psi.
Held 5 min. Checked floats "OK" Shoe @ 8795' MD / 5848' TVD, 85.24 deg inclination.
3S-08CL1: is a CTD sidetrack, belogs to 3S-08C mother bore 7" casing cement as per 3S-
08C.
3S-08CL1PB1: is a CTD sidetrack that was plugged back entirely with cement, belogs to 3S-
08C mother bore, 7" casing cement as per 3S-08C.
3S-701A: The 7-5/8” casing cement report on 1/20/2023 shows that the job was pumped as
designed, indicating competent cementing operations. The first stage cement job was pumped
with 77 barrels of 15.3 ppg. The plug was bumped and the floats held. A cement bond log
indicates competent cement with a cement top @ 6,800’ MD (3,723’ TVD).
3S-704: The 7-5/8” casing cement report on 1/20/2023 shows that the job was pumped as
designed, indicating competent cementing operations. Pump 59 BBLS 12.5 PPG spacer , drop
bottom plug , pump 62.5 BBLS 15.3 lead CMT Bridgemaker II LCM in the first 41 BBLS , drop
top plug , pump 10 BBLS H2O , chase with 319.5 BBLS 9.6 PPG mud . plugs bump at 319.5
BBLS 3170 STKS , pressure up 500 over T/1300 F/5 min , bleed off check floats, No losses.
The 7-5/8" Intermediate Cement was Logged with sonicscope. TOC identified at 6000 ft.
3S-620: The 7-5/8” casing cement report on 2/16/2015 shows that the job was pumped as
designed, indicating competent cementing operations. 11.5 ppg Mud Push II was pumped
before dropping bottom plug, this was then chased with 15.8 ppg Class G cement and the top
plug was dropped. This was chased with 9.7 ppg mud. The plug bumped, pressured up to 1500
psi and held for 5 min. Floats were checked and they held.
3S-625: The 7-5/8” casing cement report on 9/29/2022 shows that the job was pumped as
designed, indicating competent cementing operations. The first stage cement job was pumped
with 264 barrels of 15.3ppg lead cement and 33 barrels of 15.3ppg tail cement. The cement
was displaced with 574 barrels of 9.6ppg LSND drilling mud. The plug did not bump and 50%
of shoe track volume was pumped. Losses totaled to 21 barrels during the job. Cement floats
jpp
cement bond lo g
,
Logged with sonicscope
held. A cement bond log indicates competent cement with a cement top @ 7,850’ MD (3,970’
TVD).
3S-615: The 7-5/8” casing cement report on 11/13/2022 shows that the job was pumped as
designed, indicating competent cementing operations. The cement job was pumped with 200
barrels of 15.3 ppg lead cement with BMII, followed with 33 barrels of 15.3 ppg tail cement,
displaced with 524 barrels of 9.6 ppg mud. The plug bumped, bled off pressure and pressure
and floats were confirmed to be holding. A cement bond log indicates competent cement with
a cement top @ 5,620 MD (3,340’ TVD).
3S-610:The 7 & 5/8” casing cement report on 3/23/2024 shows that the job was pumped as
designed, indicating competent cementing operations. The cement job was pumped with 201
barrels of 15.3 ppg with BM-II (Bridge Maker II), followed with 22 barrels of 15.3 ppg without
BMII. The plug did not bumped, pressure held at 1140 psi indicating that floats are competent.
A cement bond log indicates competent cement with a cement top @ 3,549 MD (3,156’ TVD).
3S-18: ConocoPhillips Alaska, Inc. performed Plug and Abandonment operations on 3S-18.
Several cement plugs were pumped starting May 2023, including a cement squeeze of the
surface casing from 2840 ft to surface with 104 bbls of 15.8 ppg Class G Cement in the OA.
Last cement plug was pumped on February 2024, completing the P&A of this well with cement
all the way to surface.
PALM 1: Three abandonment cement plugs were pumped in Palm 1 on 02/21/2001. First plug
at 5900-6620 ft with class G 15.8 ppg cement and Second plg at 5880-5200 with class G 15.8
ppg cement, tagged cement at 5247 ft, final abandonment plug at 4700-4100 ft with class G
15.8 ppg cement.
https://ogc-docs.commerce.alaska.gov/weblink/0/doc/18739/Page1.aspx"
3S-22: Original drilling did not cover the zone of interest. A CBL was run prior to the P&A
showing the original cement height at 6255' MD.The P&A of this well included a
perf/wash/cementing operation. A CIBP was set at 5467', the casing was then perforate at
5291-5441', ~68 bbls of cement was pumped leaving cement ~150' above the perfs inside
casing. The cement was then cleaned out inside casing and a CBL was run to confirm cement
in the OHxCasing annulus
3S-17 & 3S-17A: ConocoPhillips Alaska, Inc. performed Plug and Abandonment operations
on 3S-17 and 3S-17A (sidetrack from 3S-17 on 4/29/2003), commencing operations on
4/12/2023 and completing the Plug and Abandonment on 9/25/2023 The top cement job was
performed on 9/5/2023. The casing was cemented to surface.
3S-21:The 7” intermediate was cemented on 3/31/2003 with 36 bbls 15.8 ppg Class “G”,
plug was bumped, slight returns. Calculated cement top at 7,719’ MD.
The well was P&A’d in 2022: 8/12/2022, Set retainer at 9,200’, pumped 25.4 bbls of 15.8 ppg
cement. 16.4 bbls below retainer, 9 bbls above 9/12/2022, Casing perforated at 6,332’-6,482’,
cement with 36 bbls 15.8 ppg. 10/14/2022, 90 bbls 15.8 ppg Class “G” was pumped in OA with
the cement top at surface. 10/17/2022, 250 BBLs of 15.8 ppg Class G Cement laid from 6500'
to surface in production casing.
3S-23:The 7” casing cement report on 4/18/2003 shows 53.5 bbls 15.8 ppg Class “G” was
pumped. Good returns throughout job"
pg p
cement bond log
CBL
cement bond log
pg
cement bond log
3S-24:The 7” casing cement report on 6/3/2003 shows a lead of 75 bbls of Lite Crete
cement was pumped at 4 bpm. Full returns throughout the job and the floats held. A 3-1/2”
production liner was run and cemented 198 bbls of 15.8ppg cement, full returns until 52 bbls
from end of cement job. Bumped the plug and floats held. "
3S-24A: This well was a sidetrack from the 3S-24, sidetracked at 10,509’ MD in 2004. A 3-
1/2” liner was run and cemented with 88 bbls of 15.8ppg Clas “G”. Full returns throughout
job, the plug bumped and the floats held."
3S-701: 1/11/2023 - Pumped 208 bbls of 15.3ppg cement, no losses during the cement job.
Once unlatched, started circulating at 3370' MD, dumped 204 bbls of contaminated mud
3S-626PB1: The 7-5/8” casing cement report on 4/25/2024 shows the job was pumped as
designed, indicating competent cementing operations. The cement job was pumped with 183
bbls of 15.3 ppg cement. The plug bumped and floats held. A cement bond log run on 04/27/24
indicates competent cement with cement top at 4523’ MD/3179’ TVD.
3S-23A: This well was a sidetrack from the 3S-23, sidetracked at 4,090’ MD. The 7” casing
cement report on 5/9/2006 shows the 43 bbls of 15.8 ppg Class “G” cement was pumped.
Approximately 10-15% returns during the job and the plug did not bump. Calculated top of
cement at 9,471’ (10,491’ TD)."
3S-03:The 7” production liner was cemented 53.3 bbls (256 sxs) 15.8ppg Class “G”. Plug
was bumped and the floats held. Calculated cement top at 2,805’ KB"
3S-19: 7” casing cement pump report on 7/2/2003 shows that job was pumped as designed,
indicating competent cementing operations. The cement job was pumped with 15.8ppg Class
G Cement, displaced with seawater. The plug bumped at 2000psi, and the floats were checked
and they held. CBL conducted on 12/22/2012 from 9170ft to surface. CBL log indicates good
to fair cement from 9170ft to 7350ftMD.
3S-626: The 7-5/8” casing cement report on 06/01/2024 shows the job was pumped as
designed, indicating competent cementing operations. The cement job was pumped in two
stages utilizing a stage tool. The first stage cement job had 188 bbls of 15.3 ppg cement. Plug
bumped and floats held. The second stage cement job had 42 bbls of 15.3 ppg cement. Plug
bumped and all indications are the stage tool at 6807’ MD closed. A cement bond log run on
06/03/24 indicates competent cement with cement top at 5908’ MD/3775’ TVD.
jp
cement bond log
CBL
ppg
A cement bond log
SECTION 11 – LOCATION OF, ORIENTATION OF AND GEOLOGICAL
DATA FOR FAULTS AND FRACTURES THAT MAY TRANSECT THE
CONFINING ZONES 20 AAC 25.283(a)(11)
CPAI has formed the opinion, based on seismic, well, and other subsurface information
currently available that one fault transects the Coyote reservoir within one half mile radius of
the 3S-714 wellbore trajectory. This fault may intersect the 3S-714 wellbore trajectory at
~11,206’ MD. This fault is interpreted to have minimal throw at this location (< 5 feet). This fault
has a presumed NW – SE strike and is downthrown to the NE. It is in line with the projection
of the fault that was encountered at the heel of the offset 3S-704 Coyote well. There is no
mapped offset based on seismic in the area where this fault projects to intersect the 3S-714
wellbore.
The interpreted fault should not affect overburden integrity and therefore its presence should
not interfere with containment. If there is any indication that a propagated fracture has
intersected the mapped fault (or any other faults unmapped to date) during fracturing
operations, ConocoPhillips will go to flush and terminate the stage immediately.
SECTION 12 – PROPOSED HYDRAULIC FRACTURING PROGRAM
20 AAC 25.283(a)(12)
3S-626 was completed in 2024 as a horizontal producer in the Torok formation. The well was
completed with a 4.5” tubing upper completion and a 4.5” liner with a ball-actuated sliding
sleeve and plug-actuated sliding sleeve lower completion. The first stage will be pumped
through a toe initiator valve in the toe of the lateral. After the 1st stage frac balls will be dropped
to shift open the 2nd stage sleeve and isolate the first stage. The 2nd stage will then be pumped
and a third ball drop (progressively getting larger) after each remaining stage, these balls will
provide isolation from the previous stage and allow fracturing from the toe of the well towards
the heel. The last three stages will be opened by the plug (Interra’s dissolvable plug).
Proposed Procedure:
Halliburton Pumping Services:
1. Conduct Safety Meeting and Identify Hazards. Inspect Wellhead and Pad Condition
to identify any pre-existing conditions.
2. Ensure the frac tree was tested to 10,000 psi on the rig.
3. Ensure all pre-frac Well work has been completed and confirm the tubing and annulus
are filled with a freeze protect fluid to 2326’ MD/ 2197’ TVD.
4. Ensure the 10-403 Sundry has been reviewed and approved by the AOGCC.
5. MIRU 24 clean insulated Frac tanks (450 bbls usable volume per tank), with a berm
surrounding the tanks that can hold a single tank volume plus 10%. Load tanks with
100ºF treated produced water (approx. 1,130 to 3,350 barrels are required for each
stage with breakdown, maximum pad and pumping down the next ball) [Contingency:
Seawater – the chemical concentrations will be adjusted. See the attached chemical
disclosures for both options].
6. MIRU HES Frac Equipment.
7. PT Surface lines to 10,000 psi using a Pressure test fluid.
8. Test IA Pop off system to ensure lines are clear and all components are functioning
properly.
9. Bring up pumps and increase annulus pressure to 3,500 psi as the tubing pressures
up.
10. Perform DFIT after opening the Alpha Sleeve according to the attached pump
schedule. Ensure sufficient volume is pumped to load the well with Frac fluid, prior to
shut down. Resume pumping to pump Frac Stage 1.
11. Perform minifrac test after opening the frac sleeve for Stage 2. Resume pumping to
pump Frac Stage 2.
12. Pump Frac Stages 3 through 20 by following attached pump schedule at 20-22 bpm
with a maximum expected treating pressure of 8,500 psi.
13. The well is ready for Post Frac well prep/production tree installation and flowback
(after Slickline and Coiled Tubing Cleanout).
Patina tracers Will be pumped in the toe and Resmetrics oil and gas tracers will be
pumped in remaining stages. See Halliburton chemical disclosure sheet which includes
this other chemicals.
Max. surface pressure of
7636 psi.
CDW 03/10/2025.
p
8,500 psi.
Frac Model Result:
SECTION 13 – POST-FRACTURE WELLBORE CLEANUP AND FLUID
RECOVERY PLAN 20 AAC 25.283(a)(13)
Flowback will be initiated through a de-sander unit until the fluids clean up at which time it will
be turned over to production for initial clean up production.
02/07/2025 15:52:12
Cementing Job Report CemCAT v1.7
Well 3S-714
Field GPB
Engineer DCole
Country United States
Client CPAI
SIR No. 1054111.01.13
Job Type INT 1
Job Date 02-07-2025
Time
02/07/2025 06:25:17
02/07/2025 11:05:30
hh:mm:ss
06:25:17
06:45:00
07:05:00
07:25:00
07:45:00
08:05:00
08:25:00
08:45:00
09:05:00
09:25:00
09:45:00
10:05:00
10:25:00
10:45:00
11:05:30 11:05:30
Pressure
PSI
0.00 1000 2000 3000 4000 5000
Density
LB/G
5.0 9.0 13.0 17.0 21.0 25.0
Rate
B/M
0.00 2.0 4.0 6.0 8.0 10.0
WHP
PSI
0.00 1000 2000 3000 4000 5000
Messages
rate checks good
PJSM
Start Job
Water Ahead
Low PT Check Trips
High PT #4000
Reset Total, Vol = 5 bbl
Batching CMT
Rig dropped 1st plug
Rigged pumped Spacer
rigged dropped 2nd bottom plug
Start Cement Slurry
End Cement Slurry
Loading Top Plug
Reset Total, Vol = 57 bbl
Water Behind
End Water Behind
Reset Total, Vol = 10 bbl
Swap to rig for Displacment
CMT @ shoe
Bumped 2873 stks
Checked Floats, Good
End Job
Stopped Acquisition
Customer
CPAI
Job Number
1054111.01.13
Well
3S-714 3S-714
Location (legal)
Kuparuk
Schlumberger Location Job Start
Feb/07/2025
Field
GPB
Formation Name/Type Deviation
deg
Bit Size
9.9 in
Well MD
6650.0 ft
Well TVD
4123.0 ft
County State/Province Alaska
Well Master API/UWI
BHP
psi
BHST
82 degF
BHCT
65 degF
Pore Press. Gradient
lb/gal
Rig Name
D25
Drilled For Service Via
Land
Offshore Zone Well Class Well Type
Drilling Fluid Type Max. Density
lb/gal
Plastic Viscosity
cP
Service Line
Cementing
Job Type
INT 1
Max. Allowed Tub. Press
psi
Max. Allowed Ann. Press
psi
WH Connection
Service Instructions
Pump, Silo, Batchmixer, Compressor
Treat Down
Casing
Displacement
300.0 bbl
Packer Type Packer Depth
ft
Tubing Vol.
bbl
Casing Vol.
305.0 bbl
Annular Vol.
bbl
Openhole Vol.
bbl
Casing/Tubing Secured 1 Hole Vol. Circulated prior to Cement X Casing Tools Squeeze Job
Lift Pressure psi Shoe Type Float Squeeze Type
Pipe Rotated Pipe Reciprocated Shoe Depth 6640.0 ft Tool Type
No. Centralizers 66 Top Plugs 1 Bottom Plugs 2 Stage Tool Type Tool Depth ft
Cement Head Type Stage Tool Depth ft Tail Pipe Size in
Job Scheduled For
Feb/07/2025
Arrived on Location
Feb/07/2025
Leave Location
Feb/07/2025
Collar Type Float Tail Pipe Depth ft
Collar Depth 6541.0 ft Sqz. Total Vol. bbl
Casing/Liner
Depth, ft Size, in Weight, lb/ft Grade Thread
5540.0 7.6 29.7
6640.0 7.6 33.7
Tubing/Drill Pipe
T/D Depth, ft Size, in Weight, lb/ft Grade Thread
Perforations/Open Hole
Top, ft Bottom, ft shot/ft No. of Shots Total Interval
ft ft ft
ft ft Diameter
in ft ft
Cementing Service Report
Date Time
24-hr
clock
Treating
Pressure
PSI
Denisty
LB/G
Rate
B/M
Stage
BBL
TOT
BBL
WHP
PSI
Message
02/07/2025 06:25:17 -17 3.19 0.0 0.0 0.0 117 Started Acquisition
02/07/2025 06:26:17 -15 2.21 3.0 2.0 2.0 116
02/07/2025 06:27:17 -40 1.82 0.0 3.1 3.1 114
02/07/2025 06:28:17 -15 -0.00 3.0 4.7 4.7 104
02/07/2025 06:29:06 -63 0.00 0.0 6.1 6.1 98 rate checks good
02/07/2025 06:29:17 -63 0.00 0.0 6.1 6.1 106
02/07/2025 06:30:17 -70 -0.00 0.0 6.1 6.1 109
02/07/2025 06:31:17 -76 0.01 0.0 6.1 6.1 101
02/07/2025 06:32:17 -68 0.00 0.0 6.1 6.1 84
02/07/2025 06:33:17 -67 0.00 0.0 6.1 6.1 63
02/07/2025 06:34:17 -65 -0.00 0.0 6.1 6.1 89
02/07/2025 06:35:17 -77 0.00 0.0 6.1 6.1 89
02/07/2025 06:36:17 -77 0.01 0.0 6.1 6.1 91
02/07/2025 06:37:17 -78 0.00 0.0 6.1 6.1 92
02/07/2025 06:38:17 -74 0.00 0.0 6.1 6.1 92
02/07/2025 06:39:17 -80 0.00 0.0 6.1 6.1 83
02/07/2025 06:40:17 -66 -0.00 0.0 6.1 6.1 82
02/07/2025 06:41:17 -68 0.00 0.0 6.1 6.1 84
02/07/2025 06:42:17 -68 0.00 0.0 6.1 6.1 79
02/07/2025 06:43:17 -79 0.00 0.0 6.1 6.1 84
02/07/2025 06:44:17 -68 0.00 0.0 6.1 6.1 80
Page 1 of 7
Customer
CPAI
Job Number
1054111.01.13
Well
3S-714 3S-714
Location (legal)
Kuparuk
Schlumberger Location Job Start
Feb/07/2025
Field
GPB
Formation Name/Type Deviation
deg
Bit Size
9.9 in
Well MD
6650.0 ft
Well TVD
4123.0 ft
County State/Province Alaska
Well Master API/UWI
BHP
psi
BHST
82 degF
BHCT
65 degF
Pore Press. Gradient
lb/gal
Rig Name
D25
Drilled For Service Via
Land
Offshore Zone Well Class Well Type
Drilling Fluid Type Max. Density
lb/gal
Plastic Viscosity
cP
Service Line
Cementing
Job Type
INT 1
Max. Allowed Tub. Press
psi
Max. Allowed Ann. Press
psi
WH Connection
Service Instructions
Pump, Silo, Batchmixer, Compressor
Treat Down
Casing
Displacement
300.0 bbl
Packer Type Packer Depth
ft
Tubing Vol.
bbl
Casing Vol.
305.0 bbl
Annular Vol.
bbl
Openhole Vol.
bbl
Casing/Tubing Secured 1 Hole Vol. Circulated prior to Cement X Casing Tools Squeeze Job
Lift Pressure psi Shoe Type Float Squeeze Type
Pipe Rotated Pipe Reciprocated Shoe Depth 6640.0 ft Tool Type
No. Centralizers 66 Top Plugs 1 Bottom Plugs 2 Stage Tool Type Tool Depth ft
Cement Head Type Stage Tool Depth ft Tail Pipe Size in
Job Scheduled For
Feb/07/2025
Arrived on Location
Feb/07/2025
Leave Location
Feb/07/2025
Collar Type Float Tail Pipe Depth ft
Collar Depth 6541.0 ft Sqz. Total Vol. bbl
Casing/Liner
Depth, ft Size, in Weight, lb/ft Grade Thread
5540.0 7.6 29.7
6640.0 7.6 33.7
Tubing/Drill Pipe
T/D Depth, ft Size, in Weight, lb/ft Grade Thread
Perforations/Open Hole
Top, ft Bottom, ft shot/ft No. of Shots Total Interval
ft ft ft
ft ft Diameter
in ft ft
Cementing Service Report
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Date Time
24-hr
clock
Treating
Pressure
PSI
Denisty
LB/G
Rate
B/M
Stage
BBL
TOT
BBL
WHP
PSI
Message
02/07/2025 06:46:17 -75 0.01 0.0 6.1 6.1 80
02/07/2025 06:47:17 -72 0.00 0.0 6.1 6.1 82
02/07/2025 06:48:17 -81 0.00 0.0 6.1 6.1 86
02/07/2025 06:49:17 -76 0.00 0.0 6.1 6.1 87
02/07/2025 06:50:17 -78 0.00 0.0 6.1 6.1 93
02/07/2025 06:51:17 -76 0.00 0.0 6.1 6.1 97
02/07/2025 06:52:17 -72 -0.00 0.0 6.1 6.1 90
02/07/2025 06:53:17 -71 -0.00 0.0 6.1 6.1 87
02/07/2025 06:54:17 -72 -0.00 0.0 6.1 6.1 90
02/07/2025 06:55:17 -72 0.00 0.0 6.1 6.1 91
02/07/2025 06:56:17 -77 0.01 0.0 6.1 6.1 95
02/07/2025 06:57:17 -77 0.00 0.0 6.1 6.1 96
02/07/2025 06:58:17 -73 0.02 0.0 6.1 6.1 107
02/07/2025 06:59:17 -82 0.00 0.0 6.1 6.1 100
02/07/2025 07:00:17 -79 0.00 0.0 6.1 6.1 94
02/07/2025 07:01:17 -80 -0.00 0.0 6.1 6.1 94
02/07/2025 07:02:17 -80 0.00 0.0 6.1 6.1 94
02/07/2025 07:03:17 -78 0.00 0.0 6.1 6.1 92
02/07/2025 07:04:17 -82 -0.00 0.0 6.1 6.1 93
02/07/2025 07:05:17 -86 0.00 0.0 6.1 6.1 92
02/07/2025 07:06:17 -81 0.00 0.0 6.1 6.1 84
02/07/2025 07:07:17 -82 0.00 0.0 6.1 6.1 88
02/07/2025 07:08:17 -84 0.00 0.0 6.1 6.1 91
02/07/2025 07:09:17 -81 -0.00 0.0 6.1 6.1 64
02/07/2025 07:10:17 -84 0.01 0.0 6.1 6.1 134
02/07/2025 07:11:17 -83 -0.00 0.0 6.1 6.1 117
02/07/2025 07:12:17 -82 -0.00 0.0 6.1 6.1 65
02/07/2025 07:13:17 -83 -0.00 0.0 6.1 6.1 64
02/07/2025 07:14:17 -83 -0.00 0.0 6.1 6.1 62
02/07/2025 07:15:17 -83 -0.00 0.0 6.1 6.1 63
02/07/2025 07:16:17 -84 0.00 0.0 6.1 6.1 61
02/07/2025 07:17:17 -82 -0.00 0.0 6.1 6.1 64
02/07/2025 07:18:17 -82 0.00 0.0 6.1 6.1 61
02/07/2025 07:19:17 -82 0.00 0.0 6.1 6.1 62
02/07/2025 07:20:17 -82 0.00 0.0 6.1 6.1 64
02/07/2025 07:21:17 -85 0.00 0.0 6.1 6.1 63
02/07/2025 07:22:17 -84 0.00 0.0 6.1 6.1 60
02/07/2025 07:23:17 -83 0.00 0.0 6.1 6.1 113
02/07/2025 07:24:17 -82 0.00 0.0 6.1 6.1 185
02/07/2025 07:25:17 -34 2.04 0.0 6.1 6.1 195
02/07/2025 07:26:17 -75 1.90 0.0 6.1 6.1 196
02/07/2025 07:27:17 -70 -0.00 0.0 6.1 6.1 212
02/07/2025 07:28:17 -78 -0.00 0.0 6.1 6.1 219
02/07/2025 07:29:17 -74 -0.00 0.0 6.1 6.1 212
02/07/2025 07:30:17 -80 0.00 0.0 6.1 6.1 214
02/07/2025 07:31:17 -74 1.71 0.0 6.1 6.1 234
02/07/2025 07:32:17 -75 0.00 0.0 6.1 6.1 235
02/07/2025 07:33:17 -82 0.00 0.0 6.1 6.1 237
02/07/2025 07:34:17 -89 0.00 0.0 6.1 6.1 246
02/07/2025 07:35:17 -86 0.00 0.0 6.1 6.1 262
02/07/2025 07:36:17 -81 -0.00 0.0 6.1 6.1 262
02/07/2025 07:37:17 -81 -0.00 0.0 6.1 6.1 269
02/07/2025 07:38:17 -81 -0.00 0.0 6.1 6.1 281
02/07/2025 07:39:17 -80 0.00 0.0 6.1 6.1 284
Page 2 of 7
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Date Time
24-hr
clock
Treating
Pressure
PSI
Denisty
LB/G
Rate
B/M
Stage
BBL
TOT
BBL
WHP
PSI
Message
02/07/2025 07:41:17 -82 0.00 0.0 6.1 6.1 310
02/07/2025 07:42:17 -80 0.00 0.0 6.1 6.1 319
02/07/2025 07:43:17 -82 -0.00 0.0 6.1 6.1 329
02/07/2025 07:44:17 -79 0.00 0.0 6.1 6.1 341
02/07/2025 07:45:17 -76 0.00 0.0 6.1 6.1 346
02/07/2025 07:46:17 -78 0.00 0.0 6.1 6.1 373
02/07/2025 07:47:17 -78 -0.00 0.0 6.1 6.1 372
02/07/2025 07:48:17 -80 0.01 0.0 6.1 6.1 366
02/07/2025 07:49:17 -79 -0.00 0.0 6.1 6.1 384
02/07/2025 07:50:17 -79 0.00 0.0 6.1 6.1 417
02/07/2025 07:51:17 -81 -0.00 0.0 6.1 6.1 408
02/07/2025 07:52:17 -82 0.00 0.0 6.1 6.1 414
02/07/2025 07:53:17 -79 0.00 0.0 6.1 6.1 410
02/07/2025 07:54:17 -79 0.00 0.0 6.1 6.1 419
02/07/2025 07:55:17 -79 0.00 0.0 6.1 6.1 409
02/07/2025 07:56:17 -82 0.00 0.0 6.1 6.1 451
02/07/2025 07:57:17 -82 -0.00 0.0 6.1 6.1 435
02/07/2025 07:58:17 -80 0.00 0.0 6.1 6.1 451
02/07/2025 07:59:17 -78 0.00 0.0 6.1 6.1 441
02/07/2025 08:00:17 -82 -0.00 0.0 6.1 6.1 502
02/07/2025 08:01:17 -78 0.00 0.0 6.1 6.1 498
02/07/2025 08:02:17 -80 0.00 0.0 6.1 6.1 506
02/07/2025 08:03:17 -82 0.00 0.0 6.1 6.1 510
02/07/2025 08:04:17 -80 0.00 0.0 6.1 6.1 515
02/07/2025 08:05:17 -81 -0.00 0.0 6.1 6.1 558
02/07/2025 08:06:17 -82 -0.00 0.0 6.1 6.1 538
02/07/2025 08:07:17 -80 0.00 0.0 6.1 6.1 534
02/07/2025 08:08:17 -80 0.00 0.0 6.1 6.1 553
02/07/2025 08:09:17 -80 -0.00 0.0 6.1 6.1 574
02/07/2025 08:10:17 -82 0.00 0.0 6.1 6.1 572
02/07/2025 08:11:17 -78 0.00 0.0 6.1 6.1 565
02/07/2025 08:12:17 -78 0.00 0.0 6.1 6.1 551
02/07/2025 08:13:17 -82 0.00 0.0 6.1 6.1 569
02/07/2025 08:14:17 -81 -0.00 0.0 6.1 6.1 578
02/07/2025 08:15:17 -79 -0.00 0.0 6.1 6.1 573
02/07/2025 08:16:17 -80 0.00 0.0 6.1 6.1 601
02/07/2025 08:17:17 -81 0.00 0.0 6.1 6.1 563
02/07/2025 08:18:17 -59 0.00 0.0 6.1 6.1 578
02/07/2025 08:19:17 -64 0.00 0.0 6.1 6.1 542
02/07/2025 08:20:17 -76 0.00 0.0 6.1 6.1 528
02/07/2025 08:21:17 -78 -0.01 0.0 6.1 6.1 537
02/07/2025 08:22:17 -72 -0.00 0.0 6.1 6.1 502
02/07/2025 08:23:17 -73 0.00 0.0 6.1 6.1 509
02/07/2025 08:24:17 -74 -0.00 0.0 6.1 6.1 470
02/07/2025 08:25:17 -71 0.00 0.0 6.1 6.1 455
02/07/2025 08:26:17 -74 -0.00 0.0 6.1 6.1 451
02/07/2025 08:27:17 -74 0.01 0.0 6.1 6.1 450
02/07/2025 08:27:55 -71 0.00 0.0 0.0 0.0 433 PJSM
02/07/2025 08:28:02 -72 0.00 0.0 0.0 0.0 438 Start Job
02/07/2025 08:28:17 -71 0.00 0.0 0.0 0.0 423
02/07/2025 08:29:17 -73 0.00 0.0 0.0 0.0 421
02/07/2025 08:30:17 -73 0.00 0.0 0.0 0.0 393
02/07/2025 08:31:17 -73 -0.00 0.0 0.0 0.0 370
02/07/2025 08:32:17 -74 0.00 0.0 0.0 0.0 382
Page 3 of 7
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Date Time
24-hr
clock
Treating
Pressure
PSI
Denisty
LB/G
Rate
B/M
Stage
BBL
TOT
BBL
WHP
PSI
Message
02/07/2025 08:34:17 -74 0.00 0.0 0.0 0.0 359
02/07/2025 08:35:17 -77 0.00 0.0 0.0 0.0 352
02/07/2025 08:36:17 -74 -0.00 0.0 0.0 0.0 328
02/07/2025 08:37:17 -72 -0.00 0.0 0.0 0.0 328
02/07/2025 08:38:17 -76 -0.00 0.0 0.0 0.0 327
02/07/2025 08:39:17 -76 0.00 0.0 0.0 0.0 320
02/07/2025 08:40:17 -74 0.00 0.0 0.0 0.0 320
02/07/2025 08:41:17 -72 0.00 0.0 0.0 0.0 312
02/07/2025 08:42:17 -73 0.00 0.0 0.0 0.0 299
02/07/2025 08:43:17 -78 -0.00 0.0 0.0 0.0 296
02/07/2025 08:44:17 -74 0.00 0.0 0.0 0.0 228
02/07/2025 08:45:17 -74 -0.00 0.0 0.0 0.0 83
02/07/2025 08:46:17 -74 -0.00 0.0 0.0 0.0 126
02/07/2025 08:47:17 -76 0.00 0.0 0.0 0.0 149
02/07/2025 08:48:17 -77 0.00 0.0 0.0 0.0 150
02/07/2025 08:49:17 -73 -0.00 0.0 0.0 0.0 299
02/07/2025 08:50:17 -76 -0.00 0.0 0.0 0.0 306
02/07/2025 08:51:17 -74 -0.00 0.0 0.0 0.0 296
02/07/2025 08:52:17 -76 0.00 0.0 0.0 0.0 82
02/07/2025 08:53:17 -76 0.00 0.0 0.0 0.0 264
02/07/2025 08:54:17 -74 0.00 0.0 0.0 0.0 302
02/07/2025 08:55:17 -73 0.00 0.0 0.0 0.0 296
02/07/2025 08:56:17 -76 0.00 0.0 0.0 0.0 294
02/07/2025 08:57:17 -75 -0.00 0.0 0.0 0.0 53
02/07/2025 08:58:17 -77 0.00 0.0 0.0 0.0 54
02/07/2025 08:59:17 -74 -0.00 0.0 0.0 0.0 53
02/07/2025 09:00:17 -66 -0.00 0.0 0.0 0.0 52
02/07/2025 09:01:17 -63 -0.00 0.0 0.0 0.0 51
02/07/2025 09:02:17 -73 0.00 0.0 0.0 0.0 50
02/07/2025 09:03:17 -74 0.00 0.0 0.0 0.0 55
02/07/2025 09:04:08 -76 0.01 0.0 0.0 0.0 53 Water Ahead
02/07/2025 09:04:17 -79 -0.00 0.0 0.0 0.0 49
02/07/2025 09:05:17 -45 0.00 1.6 0.6 0.6 69
02/07/2025 09:06:17 -1 -0.00 2.3 2.5 2.5 71
02/07/2025 09:07:17 -7 2.70 2.3 4.8 4.8 66
02/07/2025 09:08:01 -2 0.00 0.0 5.1 5.1 56 Low PT Check Trips
02/07/2025 09:08:17 1 0.00 0.8 5.1 5.1 58
02/07/2025 09:09:02 676 0.00 0.0 5.2 5.2 735 High PT #4000
02/07/2025 09:09:17 1295 0.00 0.1 5.2 5.2 1362
02/07/2025 09:10:17 4080 -0.00 0.0 5.2 5.2 4119
02/07/2025 09:11:17 1322 0.00 0.0 5.2 5.2 1324
02/07/2025 09:11:27 -12 0.00 0.0 5.2 5.2 54 Reset Total, Vol = 5 bbl
02/07/2025 09:12:17 -18 -0.00 0.0 0.0 5.2 54
02/07/2025 09:13:17 -17 -0.00 0.0 0.0 5.2 56
02/07/2025 09:14:17 -13 0.00 0.0 0.0 5.2 90
02/07/2025 09:15:17 227 0.00 0.0 0.0 5.2 213
02/07/2025 09:16:17 213 8.14 0.0 0.0 5.2 200
02/07/2025 09:17:03 209 8.95 0.0 0.0 5.2 189 Batching CMT
02/07/2025 09:17:17 217 10.44 0.0 0.0 5.2 187
02/07/2025 09:18:17 230 15.12 0.0 0.0 5.2 185
02/07/2025 09:19:17 229 15.89 0.0 0.0 5.2 172
02/07/2025 09:20:17 232 15.56 0.0 0.0 5.2 163
02/07/2025 09:21:17 230 15.57 0.0 0.0 5.2 145
02/07/2025 09:22:17 230 15.54 0.0 0.0 5.2 144
Page 4 of 7
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Date Time
24-hr
clock
Treating
Pressure
PSI
Denisty
LB/G
Rate
B/M
Stage
BBL
TOT
BBL
WHP
PSI
Message
02/07/2025 09:23:43 227 15.54 0.0 0.0 5.2 139 Rig dropped 1st plug
02/07/2025 09:24:01 225 15.54 0.0 0.0 5.2 144 Rigged pumped Spacer
02/07/2025 09:24:17 225 15.54 0.0 0.0 5.2 99
02/07/2025 09:25:17 223 15.54 0.0 0.0 5.2 91
02/07/2025 09:26:17 225 15.54 0.0 0.0 5.2 88
02/07/2025 09:27:17 219 15.53 0.0 0.0 5.2 87
02/07/2025 09:28:17 220 15.54 0.0 0.0 5.2 53
02/07/2025 09:29:17 228 15.53 0.0 0.0 5.2 54
02/07/2025 09:30:17 217 15.52 0.0 0.0 5.2 52
02/07/2025 09:30:18 219 15.53 0.0 0.0 5.2 51 rigged dropped 2nd bottom plug
02/07/2025 09:31:17 223 15.52 0.0 0.0 5.2 49
02/07/2025 09:32:17 213 15.53 0.0 0.0 5.2 50
02/07/2025 09:33:01 211 15.48 0.0 0.0 5.2 52 Start Cement Slurry
02/07/2025 09:33:17 62 15.48 0.0 0.0 5.2 78
02/07/2025 09:34:17 201 15.52 2.7 2.1 7.3 104
02/07/2025 09:35:17 294 15.48 3.7 5.4 10.6 131
02/07/2025 09:36:17 401 15.13 4.0 9.3 14.5 155
02/07/2025 09:37:17 304 15.34 4.0 13.3 18.5 111
02/07/2025 09:38:17 445 15.37 4.0 17.2 22.4 160
02/07/2025 09:39:17 247 15.32 4.0 21.2 26.4 97
02/07/2025 09:40:17 256 15.41 3.7 24.9 30.1 103
02/07/2025 09:41:17 423 15.54 4.0 28.1 33.3 151
02/07/2025 09:42:17 210 15.54 3.0 32.4 37.6 97
02/07/2025 09:43:17 409 15.30 4.0 35.5 40.7 147
02/07/2025 09:44:17 423 15.55 4.0 39.5 44.7 151
02/07/2025 09:45:17 415 15.66 4.0 43.5 48.7 145
02/07/2025 09:46:17 205 15.32 2.7 46.5 51.7 102
02/07/2025 09:47:17 198 15.15 2.7 49.2 54.4 102
02/07/2025 09:48:17 214 15.33 2.7 51.9 57.1 104
02/07/2025 09:49:17 202 15.40 2.7 54.6 59.8 102
02/07/2025 09:50:17 53 15.40 1.6 56.9 62.1 78
02/07/2025 09:50:45 -21 15.35 0.0 57.0 62.2 59 End Cement Slurry
02/07/2025 09:50:59 -19 15.34 0.0 57.0 62.2 58 Loading Top Plug
02/07/2025 09:51:17 -20 15.34 0.0 57.0 62.2 55 Reset Total, Vol = 57 bbl
02/07/2025 09:52:17 23 15.40 0.0 0.0 62.2 56
02/07/2025 09:53:17 58 9.86 0.0 0.0 62.2 54
02/07/2025 09:54:17 52 9.82 0.0 0.0 62.2 57
02/07/2025 09:55:17 50 9.83 0.0 0.0 62.2 54
02/07/2025 09:55:42 46 9.83 0.0 0.0 62.2 55 Water Behind
02/07/2025 09:56:17 279 9.86 3.7 0.7 62.8 155
02/07/2025 09:57:17 207 9.01 4.0 4.6 66.8 88
02/07/2025 09:58:17 195 8.65 4.0 8.6 70.7 87
02/07/2025 09:59:03 13 6.75 0.0 10.0 72.2 50 End Water Behind
02/07/2025 09:59:13 4 6.28 0.0 10.0 72.2 52 Reset Total, Vol = 10 bbl
02/07/2025 09:59:17 1 6.15 0.0 0.0 72.2 52
02/07/2025 09:59:30 12 6.58 0.0 0.0 72.2 74 Swap to rig for Displacment
02/07/2025 10:00:17 51 8.67 0.0 0.0 72.2 80
02/07/2025 10:01:17 61 10.05 0.0 0.0 72.2 229
02/07/2025 10:02:17 55 10.14 0.0 0.0 72.2 235
02/07/2025 10:03:17 56 10.14 0.0 0.0 72.2 202
02/07/2025 10:04:17 60 10.14 0.0 0.0 72.2 201
02/07/2025 10:05:17 -18 9.93 0.0 0.0 72.2 193
02/07/2025 10:06:17 64 9.51 0.0 0.0 72.2 197
02/07/2025 10:07:17 -6 9.12 0.0 0.0 72.2 200
Page 5 of 7
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Date Time
24-hr
clock
Treating
Pressure
PSI
Denisty
LB/G
Rate
B/M
Stage
BBL
TOT
BBL
WHP
PSI
Message
02/07/2025 10:09:17 18 8.83 0.0 0.0 72.2 195
02/07/2025 10:10:17 42 8.40 0.0 0.0 72.2 201
02/07/2025 10:11:17 34 8.43 0.0 0.0 72.2 206
02/07/2025 10:12:17 31 8.44 0.0 0.0 72.2 198
02/07/2025 10:13:17 28 8.48 0.0 0.0 72.2 205
02/07/2025 10:14:17 -23 8.23 0.0 0.0 72.2 210
02/07/2025 10:15:17 -24 7.56 0.0 0.0 72.2 206
02/07/2025 10:16:17 -22 7.11 0.0 0.0 72.2 209
02/07/2025 10:17:17 23 8.28 0.0 0.0 72.2 217
02/07/2025 10:18:17 -20 8.13 0.0 0.0 72.2 217
02/07/2025 10:19:17 -23 7.76 0.0 0.0 72.2 213
02/07/2025 10:20:17 54 7.64 0.0 0.0 72.2 223
02/07/2025 10:21:17 -24 7.72 0.0 0.0 72.2 225
02/07/2025 10:22:17 -20 7.44 0.0 0.0 72.2 212
02/07/2025 10:23:17 -12 7.20 0.0 0.0 72.2 239
02/07/2025 10:24:17 4 7.80 0.0 0.0 72.2 234
02/07/2025 10:25:17 45 7.83 0.0 0.0 72.2 218
02/07/2025 10:26:17 -23 6.93 0.0 0.0 72.2 224
02/07/2025 10:27:17 -11 6.57 0.0 0.0 72.2 218
02/07/2025 10:28:17 -21 7.02 0.0 0.0 72.2 213
02/07/2025 10:29:17 35 7.32 0.0 0.0 72.2 214
02/07/2025 10:30:17 -29 8.27 0.0 0.0 72.2 229
02/07/2025 10:31:17 -32 8.27 0.0 0.0 72.2 242
02/07/2025 10:32:17 -25 8.12 0.0 0.0 72.2 241
02/07/2025 10:33:17 16 7.31 0.0 0.0 72.2 265
02/07/2025 10:34:17 -24 6.94 0.0 0.0 72.2 310
02/07/2025 10:35:17 -31 6.28 0.0 0.0 72.2 296
02/07/2025 10:36:17 30 7.12 0.0 0.0 72.2 331
02/07/2025 10:37:17 1 7.69 0.0 0.0 72.2 331
02/07/2025 10:38:17 -25 6.68 0.0 0.0 72.2 336
02/07/2025 10:39:17 -29 8.27 0.0 0.0 72.2 61
02/07/2025 10:40:17 -28 8.30 0.0 0.0 72.2 393
02/07/2025 10:41:17 -30 8.30 0.0 0.0 72.2 402
02/07/2025 10:41:57 -30 8.31 0.0 0.0 72.2 416 CMT @ shoe
02/07/2025 10:42:17 -30 8.32 0.0 0.0 72.2 425
02/07/2025 10:43:17 -31 7.94 0.0 0.0 72.2 477
02/07/2025 10:44:17 42 7.89 0.0 0.0 72.2 507
02/07/2025 10:45:17 48 8.07 0.0 0.0 72.2 540
02/07/2025 10:46:17 49 8.10 0.0 0.0 72.2 569
02/07/2025 10:47:17 -19 7.29 0.0 0.0 72.2 396
02/07/2025 10:48:17 14 7.06 0.0 0.0 72.2 426
02/07/2025 10:49:17 -31 6.84 0.0 0.0 72.2 431
02/07/2025 10:50:17 -33 6.74 0.0 0.0 72.2 698
02/07/2025 10:50:58 -32 6.72 0.0 0.0 72.2 833 Bumped 2873 stks
02/07/2025 10:51:17 -31 6.70 0.0 0.0 72.2 1411
02/07/2025 10:52:17 -21 6.73 0.0 0.0 72.2 1967
02/07/2025 10:53:17 3 6.77 0.0 0.0 72.2 1954
02/07/2025 10:54:17 7 6.75 0.0 0.0 72.2 1903
02/07/2025 10:55:17 -29 6.74 0.0 0.0 72.2 58
02/07/2025 10:56:17 -33 6.73 0.0 0.0 72.2 55
02/07/2025 10:57:17 -29 6.72 0.0 0.0 72.2 53
02/07/2025 10:58:17 -32 6.71 0.0 0.0 72.2 54
02/07/2025 10:59:17 72 6.73 0.0 0.0 72.2 53
02/07/2025 11:00:17 49 8.09 0.0 0.0 72.2 52
Page 6 of 7
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
Date Time
24-hr
clock
Treating
Pressure
PSI
Denisty
LB/G
Rate
B/M
Stage
BBL
TOT
BBL
WHP
PSI
Message
02/07/2025 11:01:17 64 8.16 0.0 0.0 72.2 51
02/07/2025 11:02:17 -31 3.12 0.0 0.0 72.2 55
02/07/2025 11:03:17 -33 1.67 0.0 0.0 72.2 56
02/07/2025 11:04:17 -33 0.00 0.0 0.0 72.2 56
02/07/2025 11:05:17 -31 -0.00 0.0 0.0 72.2 52
02/07/2025 11:05:27 -30 -0.01 0.0 0.0 0.0 53 End Job
Post Job Summary
Volume of Fluid Injected, bbl
N2 Maximum Rate
4.7
Average Pump Rates, bbl/min
Slurry
3.1
Mud Total Slurry
57.0
Mud
294.0
Spacer
60.0
N2
Treating Pressure Summary, psi Breakdown Fluid
Maximum
4105
Final
-31
Average
252
Bump Plug to
900
Breakdown Type Volume
bbl
Density
lb/gal
Avg. N2 Percent
%
Designed Slurry Volume
57.0 bbl
Displacement
302.0 bbl
Mix Water Temp
80 degF
Cement Circulated to Surface?Volume bbl
Washed Thru Perfs To ft
Customer or Authorized Representative Schlumberger Supervisor
DCole
Circulation Lost Job Completed X
--
Page 7 of 7
Post Job Summary
Volume of Fluid Injected, bbl
N2 Maximum Rate
4.7
Average Pump Rates, bbl/min
Slurry
3.1
Mud Total Slurry
57.0
Mud
294.0
Spacer
60.0
N2
Treating Pressure Summary, psi Breakdown Fluid
Maximum
4105
Final
-31
Average
252
Bump Plug to
900
Breakdown Type Volume
bbl
Density
lb/gal
Avg. N2 Percent
%
Designed Slurry Volume
57.0 bbl
Displacement
302.0 bbl
Mix Water Temp
80 degF
Cement Circulated to Surface?Volume bbl
Washed Thru Perfs To ft
Customer or Authorized Representative Schlumberger Supervisor
DCole
Circulation Lost Job Completed X
--
Well
3S-714 3S-714
Field
GPB
Job Start
Feb/07/2025
Customer
CPAI
Job Number
1054111.01.13
From:Ruysschaert, Rodrigo
To:Davies, Stephen F (OGC)
Cc:Loepp, Victoria T (OGC); Dewhurst, Andrew D (OGC)
Subject:RE: [EXTERNAL]RE: 3S-714 (PTD 224-151) Frac Sundry Submission
Date:Wednesday, March 19, 2025 3:10:49 PM
Attachments:image002.png
Hi again,
Is this the same fault that is mentioned as intersecting 3S-714 at about 11,206’ MD? It is
possible, as the map view projection of the fault that intersects 3S-704 generally aligns with
the fault/fracture seen in 3S-714.
What is the vertical displacement along this fault? It is difficult to determine as there is no
mapped seismic offset at the 3S-714 location. The estimate is 5 feet or less for the feature
identified in the 3S-714 wellbore. It is possible that the feature in 3S-714 is a zero offset
fracture.
Does it penetrate into or through either the upper or lower confining layers for the Coyote
reservoir? If so, please provide details. The feature does not show seismic offset at the top or
base of the Coyote reservoir.
What is the expected azimuth for the planned induced fractures in 3S-714? Fractures are
expected to be longitudinal to the well.
Will any of the induced fractures potentially intersect this fault? Based on expected hydraulic
fracture length, We have spaced out the sleeves above and below the feature to ensure that
the hydraulic fractures do not reach it.
If so, will these constitute a risk to confining fracturing fluids to the planned fracturing
interval?
If so, what mitigation measures does CPAI plan to ensure fracturing fluids and future injection
are confined to the Coyote reservoir?
Regards,
Rodrigo
From: Davies, Stephen F (OGC) <steve.davies@alaska.gov>
Sent: Wednesday, March 19, 2025 12:55 PM
To: Ruysschaert, Rodrigo <Rodrigo.Ruysschaert@conocophillips.com>
Cc: Loepp, Victoria T (OGC) <victoria.loepp@alaska.gov>; Dewhurst, Andrew D (OGC)
<andrew.dewhurst@alaska.gov>
Subject: [EXTERNAL]RE: 3S-714 (PTD 224-151) Frac Sundry Submission
CAUTION:This email originated from outside of the organization. Do not click links or open
attachments unless you recognize the sender and know the content is safe.
Rodrigo,
In addition to my request attached below, while reviewing CPAI’s application I noticed an apparent
fault (represented by a magenta-colored line) intersecting well 3SD-704 on CPAI’s Frac Lease Plat
shown below. This fault appears to closely approach 3S-714.
Questions:
Is this the same fault that is mentioned as intersecting 3S-714 at about 11,206’ MD?
What is the vertical displacement along this fault?
Does it penetrate into or through either the upper or lower confining layers for the Coyote
reservoir? If so, please provide details.
What is the expected azimuth for the planned induced fractures in 3S-714?
Will any of the induced fractures potentially intersect this fault?
If so, will these constitute a risk to confining fracturing fluids to the planned fracturing
interval?
If so, what mitigation measures does CPAI plan to ensure fracturing fluids and future injection
are confined to the Coyote reservoir?
Thanks for Your Help and Be Well,
Steve Davies
Senior Petroleum Geologist
AOGCC
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska Oil and Gas
Conservation Commission (AOGCC), State of Alaska and is for the sole use of the intended recipient(s). It may contain confidential and/or
privileged information. The unauthorized review, use or disclosure of such information may violate state or federal law. If you are an
unintended recipient of this e-mail, please delete it, without first saving or forwarding it, and, so that the AOGCC is aware of the mistake in
sending it to you, contact Steve Davies at 907-793-1224 or steve.davies@alaska.gov.
From: Davies, Stephen F (OGC)
Sent: Wednesday, March 19, 2025 12:13 PM
To: Ruysschaert, Rodrigo <Rodrigo.Ruysschaert@conocophillips.com>
Cc: Loepp, Victoria T (OGC) <victoria.loepp@alaska.gov>; Dewhurst, Andrew D (OGC)
<andrew.dewhurst@alaska.gov>
Subject: RE: 3S-714 (PTD 224-151) Frac Sundry Submission
Thanks for your help with this Rodrigo. Could CPAI please provide a copy of the cement report or the
daily operations summary the provide details for cementing of surface casing?
Thanks Again and Be Well,
Steve Davies
AOGCC
From: Ruysschaert, Rodrigo <Rodrigo.Ruysschaert@conocophillips.com>
Sent: Tuesday, March 4, 2025 4:26 PM
To: Loepp, Victoria T (OGC) <victoria.loepp@alaska.gov>; Davies, Stephen F (OGC)
CAUTION: This email originated from outside the State of Alaska mail system. Do not
click links or open attachments unless you recognize the sender and know the content
is safe.
Some people who received this message don't often get email from rodrigo.ruysschaert@conocophillips.com. Learn
why this is important
<steve.davies@alaska.gov>; Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>; AOGCC
Permitting (CED sponsored) <aogcc.permitting@alaska.gov>
Subject: RE: 3S-714 (PTD 224-151) Frac Sundry Submission
All,
Please find attached the supporting documents for the 3S-714 Frac Sundry.
In the .zip file you will find a .las file that is a combined file for the surface, interm, and prod
sections.
Thanks,
Rodrigo Ruysschaert | Completions Engineer | ConocoPhillips
O: + 1 907-263-3709| M: +1 907-621-0671 | 700 G Street, ATO-1586, Anchorage, AK 99501
From: Ruysschaert, Rodrigo
Sent: Tuesday, March 4, 2025 4:19 PM
To: Loepp, Victoria T (OGC <victoria.loepp@alaska.gov>; Davies, Stephen F (OGC
<steve.davies@alaska.gov>; Dewhurst, Andrew D (OGC <andrew.dewhurst@alaska.gov>; AOGCC
Permitting (CED sponsored <aogcc.permitting@alaska.gov>
Cc: Lee, David L <David.L.Lee@conocophillips.com>; Hobbs, Greg S
<Greg.S.Hobbs@conocophillips.com>; Conklin, Amy A <Amy.A.Conklin@conocophillips.com>;
Dodson, Kate <Kate.Dodson@conocophillips.com>
Subject: 3S-714 (PTD 224-151) Frac Sundry Submission
AOGCC team,
Please find attached the 10-403 application for the 3S-714 Frac Sundry. I will send a separate
email with supporting documents including logs.
Let me know if you have any questions/concerns with the application.
Thank you!
Rodrigo Ruysschaert | Completions Engineer | ConocoPhillips
O: + 1 907-263-3709| M: +1 907-621-0671 | 700 G Street, ATO-1586, Anchorage, AK 99501
From:Davies, Stephen F (OGC)
To:"Ruysschaert, Rodrigo"
Cc:Loepp, Victoria T (OGC); Dewhurst, Andrew D (OGC)
Subject:RE: 3S-714 (PTD 224-151) Frac Sundry Submission
Date:Wednesday, March 19, 2025 12:55:00 PM
Attachments:image004.png
Rodrigo,
In addition to my request attached below, while reviewing CPAI’s application I noticed an apparent
fault (represented by a magenta-colored line) intersecting well 3SD-704 on CPAI’s Frac Lease Plat
shown below. This fault appears to closely approach 3S-714.
Questions:
Is this the same fault that is mentioned as intersecting 3S-714 at about 11,206’ MD?
What is the vertical displacement along this fault?
Does it penetrate into or through either the upper or lower confining layers for the Coyote
reservoir? If so, please provide details.
What is the expected azimuth for the planned induced fractures in 3S-714?
Will any of the induced fractures potentially intersect this fault?
If so, will these constitute a risk to confining fracturing fluids to the planned fracturing
interval?
If so, what mitigation measures does CPAI plan to ensure fracturing fluids and future injection
are confined to the Coyote reservoir?
Thanks for Your Help and Be Well,
Steve Davies
Senior Petroleum Geologist
AOGCC
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska Oil and Gas
Conservation Commission (AOGCC), State of Alaska and is for the sole use of the intended recipient(s). It may contain confidential and/or
privileged information. The unauthorized review, use or disclosure of such information may violate state or federal law. If you are an
unintended recipient of this e-mail, please delete it, without first saving or forwarding it, and, so that the AOGCC is aware of the mistake in
sending it to you, contact Steve Davies at 907-793-1224 or steve.davies@alaska.gov.
From: Davies, Stephen F (OGC)
Sent: Wednesday, March 19, 2025 12:13 PM
To: Ruysschaert, Rodrigo <Rodrigo.Ruysschaert@conocophillips.com>
Cc: Loepp, Victoria T (OGC) <victoria.loepp@alaska.gov>; Dewhurst, Andrew D (OGC)
<andrew.dewhurst@alaska.gov>
Subject: RE: 3S-714 (PTD 224-151) Frac Sundry Submission
Thanks for your help with this Rodrigo. Could CPAI please provide a copy of the cement report or the
daily operations summary the provide details for cementing of surface casing?
Thanks Again and Be Well,
Steve Davies
AOGCC
From: Ruysschaert, Rodrigo <Rodrigo.Ruysschaert@conocophillips.com>
Sent: Tuesday, March 4, 2025 4:26 PM
To: Loepp, Victoria T (OGC) <victoria.loepp@alaska.gov>; Davies, Stephen F (OGC)
CAUTION: This email originated from outside the State of Alaska mail system. Do not
click links or open attachments unless you recognize the sender and know the content
is safe.
Some people who received this message don't often get email from rodrigo.ruysschaert@conocophillips.com. Learn
why this is important
<steve.davies@alaska.gov>; Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>; AOGCC
Permitting (CED sponsored) <aogcc.permitting@alaska.gov>
Subject: RE: 3S-714 (PTD 224-151) Frac Sundry Submission
All,
Please find attached the supporting documents for the 3S-714 Frac Sundry.
In the .zip file you will find a .las file that is a combined file for the surface, interm, and prod
sections.
Thanks,
Rodrigo Ruysschaert | Completions Engineer | ConocoPhillips
O: + 1 907-263-3709| M: +1 907-621-0671 | 700 G Street, ATO-1586, Anchorage, AK 99501
From: Ruysschaert, Rodrigo
Sent: Tuesday, March 4, 2025 4:19 PM
To: Loepp, Victoria T (OGC <victoria.loepp@alaska.gov>; Davies, Stephen F (OGC
<steve.davies@alaska.gov>; Dewhurst, Andrew D (OGC <andrew.dewhurst@alaska.gov>; AOGCC
Permitting (CED sponsored <aogcc.permitting@alaska.gov>
Cc: Lee, David L <David.L.Lee@conocophillips.com>; Hobbs, Greg S
<Greg.S.Hobbs@conocophillips.com>; Conklin, Amy A <Amy.A.Conklin@conocophillips.com>;
Dodson, Kate <Kate.Dodson@conocophillips.com>
Subject: 3S-714 (PTD 224-151) Frac Sundry Submission
AOGCC team,
Please find attached the 10-403 application for the 3S-714 Frac Sundry. I will send a separate
email with supporting documents including logs.
Let me know if you have any questions/concerns with the application.
Thank you!
Rodrigo Ruysschaert | Completions Engineer | ConocoPhillips
O: + 1 907-263-3709| M: +1 907-621-0671 | 700 G Street, ATO-1586, Anchorage, AK 99501
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 1 March 24, 2025 (a) Application for Sundry Approval (a)(1) Affidavit Provided with application. SFD 3/19/2025 (a)(2) Plat Provided with application. SFD 3/19/2025 (a)(2)(A) Well location Provided with application. Well lies in Sections 18, 19, and 30 of T12N, R8E, UM. SFD 3/19/2025 (a)(2)(B) Each water well within ½ mile None: According to the Water Estate map available through DNR’s Alaska Mapper application (accessed online March 19, 2025), there are no wells are used for drinking water purposes are known to lie within ½ mile of the surface location of KRU 3S-714. There are no subsurface water rights or temporary subsurface water rights within 7 miles of the surface location of KRU 3S-714. SFD 3/19/2025 (a)(2)(C) Identify all well types within ½ mile List provided with application. SFD 3/19/2025 (a)(3) Freshwater aquifers: geological name; measured and true vertical depth None. Aquifers affected by this well are exempt. This well lies within the Kuparuk River Unit (KRU) boundary of 1984 that forms the basis for the aquifer exemption granted by Title 40 CFR 147.102(b)(3) according to a recent opinion by the EPA, which states in part: "In short, EPA finds that the boundary of Alaska’s aquifer exemption at 40 C.F.R. 147.102(b)(3) was determined on May 11, 1984. After a program is approved or promulgated, additions to aquifer exemptions, including boundary expansions to aquifers or parts thereof, submitted as part of a UIC program cannot change unless EPA approves those additions in accordance with EPA’s UIC program regulations (See 40 C.F.R. 144.7(b)(1) and (3)).” (Reference: Email from Evan Osborne, US EPA Region 10, to Steve Davies, AOGCC, dated December 2, 2024.) SFD 3/19/2025
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 2 March 24, 2025 (a)(4) Baseline water sampling plan None required. SFD 3/19/2025 (a)(5) Casing and cementing information Provided with application. Proposed schematic attached, as built not generated to date. CDW 03/10/2025 (a)(6) Casing and cementing operation assessment 10-3/4” surface cement job pumped with losses experienced. Cemented to surface with returns. 7-5/8” intermediate casing cemented as designed. CBL (ON File at AOGCC digilogs) indicates TOC of 5530 ft. 4.5” liner at 6452 ft MD, 7-5/8” casing shoe at 6639 ft. CDW 03/10/2025 (a)(6)(A) Casing cemented below lowermost freshwater aquifer and conforms to 20 AAC 25.030 Aquifers are exempt in this area. (See Section (a)(3), above.) SFD 3/19/2025 (a)(6)( B) Each hydrocarbon zone is isolated Yes: Surface casing shoe is located at 2,803’ MD (-2,481’ TVDSS). Although lost returns were reported at 1400 strokes into displacement, the plug bumped and floats held, and 110 barrels of cement were reported at surface. Intermediate casing was set into the Coyote interval at 6,639’ MD (-4,099’ TVDSS) and cemented. Plug bumped, floats held, and the top of cement from CBL is about 5,530’ MD (-3,725’ TVDSS), with the top of consistent, excellent-quality bond at 5,575’ MD (-3,746’ TVDSS). SFD 3/19/2025 (a)(7) Pressure test: information and pressure-test plans for casing and tubing installed in well Provided with application. 3850 psi MITIA tested, 4550 psi MITT tested. CDW 03/10/2025
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 3 March 24, 2025 (a)(8) Pressure ratings and schematics: wellbore, wellhead, BOPE, treating head Provided with application. 10K psi frac tree. max. frac. Pressure indicated as 7075 psi (Corrected max, pressure to 7636 psi surface due to tubing test and backpressure criteria). Pump knock out 7575 and GORV 8075 psi., tree test 10K psi, lines test 10K psi. CDW 03/10/2025 (a)(9)(A) Fracturing and confining zones: lithologic description for each zone (a)(9)(B) Geological name of each zone (a)(9)(C) and (a)(9)(D) Measured and true vertical depths (a)(9)(E) Fracture pressure for each zone Upper confining zones: Seabee Shale consisting of condensed mudstone and thin siltstone that has an aggregate thickness of about 350’ true vertical thickness (TVT). Fracture gradient is expected to range from about 0.67 to 0.84 psi/ft (12.9 to 16.1 ppg EMW). Fracturing Zone: Coyote interval (top at 6,435' MD, equivalent to –4,054' TVDSS) with an average thickness of more than 500' TVT in this area. This well did not penetrate the base of the Coyote. It consists of thinly interbedded layers of very fine-grained sandstone and siltstone. Fracture-closure gradient is expected to be about 0.67 psi/ft (12.9 ppg EMW) based on diagnostic fracture injection testing (DFIT). Lower confining zones: Underlying Torok Formation mudstone that has an aggregate TVT of 300' in this area but was not penetrated by this well. Fracture gradient expected to range from about 0.78 to 0.94 psi/ft (15 to 18 ppg EMW). SFD 3/19/2025 (a)(10) Location, orientation, report on mechanical condition of each well that may transect the confining zones and sufficient information to determine wells will not interfere with containment of hydraulic fracturing fluid within ½ mile of the proposed wellbore trajectory It is highly unlikely that any of the wells or wellbores within a ½-mile radius will interfere with hydraulic fracturing fluids from this operation because of cement isolation and / or separation distance. There are 46 wells (and sidetracks etc) within ½ mile radius of KRU 3S-714 and 24 wells within ½ mile of KRU 3S-714 that penetrate the confining intervals. CPAI has evaluated the cement and zonal isolation of these wells and see no impediment to hydraulic fracturing. SFD 3/24/2025 CDW 03/10/2025
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 4 March 24, 2025 Prioritizing the 24 wells, redrilled wells, and plugged-back welllbores within the ½-mile radius AOR by distance from 3S-714: KRU 3S-22 (203-011) and KRU 3S-21 (203-031) Plugged and Abandoned Service Wells: 3S-22 and 3S-21—which intercept the top of Coyote about 270’ and 300’, respectively, from the similar interception in 3S-417—only the uppermost 6% (34’ / 564’ true vertical thickness) and 9% (34’ / 378’ true vertical thickness), respectively, of the Coyote Interval are cement-isolated behind 7-inch casing with good-quality bonding. However, since this uppermost portion of the Coyote and about 64’ and 54’ true vertical thickness, respectively, of the overlying confining interval are isolated with good-bonding cement in these wells, any frac or subsequent fluids injected should remain confined within the Coyote reservoir. KRU 3S-03 (203-091) Suspended Development Well: In 3S-03, the Coyote reservoir is NOT covered by cement, rather this well was perforated and cement-squeezed across 4980’ to 5130’ MD, a portion of the upper confining interval above the Coyote reservoir. Coyote is isolated by cement from the underlying Kuparuk reservoir by cement. On the cement bond log dated Sept. 5, 2023, the top of good bond for that isolation lies at 6840’ MD (5164’ TVDSS). In 3S-03—which intercepts the top of Coyote about 730’ (horizontally) from the similar interception in 3S-417, and at the base of the induced fractures, the Coyote in 3S-03 lies about 650’ (horizontally) from the 3S-417 wellbore through the reservoir. The induced fractures are expected to propagate parallel to the 3S-417 wellbore, so it is doubtful that SFD 3/24/2025
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 5 March 24, 2025 confinement fracturing fluids will be affected due to separation distance. KRU 3S-18 (202-206) Plugged and Abandoned Development Well: In 3S-18, the top of Coyote reservoir lies at 4666’ MD (-4031’ TVDSS), and the interception of 3S-18 with that top lies about 1000’ (horizontally) from the similar intercept in 3S-417. Although the Coyote was not originally covered by cement, the uppermost Coyote and the lowermost portion of the overlying confining interval were subsequently perforated between 4561’ and 4711’ MD (-3944’ and -4068’ TVDSS) and squeezed with cement. A follow-up CBL across that perf-and-wash interval indicates top of good-bonding cement is at 4562’ MD and extends to the base of the log at 4707’ MD. The Coyote interval is isolated by cement from the underlying Kuparuk reservoir. A CBL run on Feb. 9, 2012 indicates the top of cement isolating production casing lies at 6422’ MD (-5590’ TVDSS), with consistent, very good bonding below about 6572’ MD (-5737’ TVDSS). The underlying Kuparuk reservoir top lies at 6642’ MD (-5806’ TVDSS). The induced fractures are expected to propagate parallel to the 3S-417 wellbore, so it is doubtful that confinement fracturing fluids will be affected due to separation distance. KRU_3S-704 (222-142) Active Development Well: The interception in 3S-704 lies 1200’ (horizontally) from the similar interception in 3S-714. In 3S-704, the Coyote is reservoir top at 7026’ MD (-4031’ TVDSS) is isolated by 7-5/8" intermediate casing and cement. TOC from CBL lies at about 5,600' MD, with good bonding from about 6000’ MD (3689’ TVDSS) down to the base of the CBL at 6835’ MD and SFD 3/24/2025
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 6 March 24, 2025 presumably down to the underlying casing shoe at 7316’ MD (-4070’ TVDSS). KRU_3S-701 (222-133) Plugged and Abandoned Exploratory (Delineation) Well: The interception in 3S-701 lies 1300’ (horizontally) from the similar interception in 3S-714. Coyote interval from 4790’ to 5388’ MD (-4031’ to 4329’ TVDSS) in this pilot well is isolated by and abandonment plug pumped from 2088’ to 5597’ MD. The Coyote intervals in the 18 remaining wells, redrilled wells, and plugged-back wellbores within the ½-mile radius Area of Review all lie more than ¼ mile from the 3S-714 wellbore path through the Coyote reservoir. The estimated maximum induced fracture half-length of 450’, the expected fracture growth azimuth of about 350 degrees (approximately parallel with the 3S-714 wellbore in the reservoir, and the separation distances of more than ¼ mile from the Coyote interval open to 3S-714 make it highly unlikely that any of these 18 wells, redrilled wells, and wellbores will interfere with confinement of fracturing fluids. SFD 3/24/2025 (a)(11) Faults and fractures, Sufficient information to determine no interference with containment of the hydraulic fracturing fluid within ½ mile of the proposed wellbore trajectory One. The operator has identified one fault of minimal vertical displacement that may intersect the well at about 11,206' MD. The operator reports that there is no mapped seismic offset at the 3S-714 wellbore, consequently this “fault” does not show any offset at the top or base of the Coyote reservoir. It is not expected to affect overburden integrity of containment of fracturing fluids. However, if there are indications that a fracture has intersected a fault or natural-fracture interval during frac operations, the operator will go to flush and terminate the stage immediately. SFD 3/24/2025
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 7 March 24, 2025 (a)(12) Proposed program for fracturing operation Provided with application. CDW 03/10/2025 (a)(12)(A) Estimated volume Provided with application. 45K bbl total dirty vol. 6M lb total proppant CDW 03/10/2025 (a)(12)(B) Additives: names, purposes, concentrations Provided with application. CDW 03/10/2025 (a)(12)(C) Chemical name and CAS number of each Provided with application. Halliburton and Petina and Resmetrics tracers disclosure provided. CDW 03/10/2025 (a)(12)(D) Inert substances, weight or volume of each Provided with application. CDW 03/10/2025 (a)(12)(E) Maximum treating pressure with supporting info to determine appropriateness for program Simulation shows max surface pressure 7075 psi. Max. 7636 psi allowable treating pressure (based on 4550 psi tubing test and 3500 psi backpressure). Max pressure is 7575 psi to 8075 psi to Pump shutdown. With 3500 psi back pressure IA (IA popoff set 3600 psi), max tubing differential should be 4136 psi. CDW 03/10/2025 (a)(12)(F) Fractures – height, length, MD and TVD to top, description of fracturing model Provided with application. The anticipated half-lengths of the induced fractures range from 330’ to 450’ according to the Operator’s computer simulation. Computer simulation indicates the anticipated height of the induced fractures will range from 200’ to 215’ (shallowest TVD of about 3,983’ and deepest TVD of about 4,200’), so induced fractures may penetrate into, but not through, the overlying confining Seabee Shale that is about 350’ thick in this area. SFD 3/19/2025 (a)(13) Proposed program for post-fracturing well cleanup and fluid recovery Well cleanout and flowback procedure provided with application. No disposal identified CDW 03/10/2025 (b)Testing of casing or intermediate casing Tested >110% of max anticipated pressure 3500 psi back pressure, plan to test to 3850 psi, popoff set as 3600 psi CDW 03/10/2025
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 8 March 24, 2025 (c) Fracturing string (c)(1) Packer >100’ below TOC of production or intermediate casing 4.5” tubing will be anchored with a packer set at approx. 6331 ft, liner top of 6452 ft and 7-5/8” casing shoe of 6639 ft. TOC in 7-5/8” casing at 5530 ft (SonicScope on file at AOGCC)- CBL conservatively shows good cement at area of interest so no cement concerns. CDW 03/10/2025 (c)(2) Tested >110% of max anticipated pressure differential Tubing test of 4550 psi. Max pressure differential is estimated as 4136 psi (7636 with 3500 psi backpressure) so test of 4550 psi satisfies 110% CDW 03/10/2025 (d) Pressure relief valve Line pressure <= test pressure, remotely controlled shut-in device 10K psi line pressure test, pump knock out 7575 psi with max. global kickout 8075 psi. IA PRV set as 3600 psi. CDW 03/10/2025 (e) Confinement Frac fluids confined to approved formations Provided with application. CDW 03/10/2025 (f) Surface casing pressures Monitored with gauge and pressure relief device IA PRV set at 3600 psi. Surface annulus open. Frac pressures continuously monitored. CDW 03/10/2025 (g) Annulus pressure monitoring & notification 500 psi criteria During hydraulic fracturing operations, all annulus pressures must be continuously monitored and recorded. If at any time during hydraulic fracturing operations the annulus pressure increases more than 500 psig above those anticipated increases caused by pressure or thermal transfer, the operator shall: CDW 03/10/2025 (g)(1) Notify AOGCC within 24 hours (g)(2) Corrective action or surveillance (g)(3) Sundry to AOGCC (h) Sundry Report (i) Reporting (i)(1) FracFocus Reporting (i)(2) AOGCC Reporting: printed & electronic (j) Post-frac water sampling plan Not required (see Section (a)(3), above). SFD 3/19/2025
20 AAC 25.283 Hydraulic Fracturing Application – Checklist KRU 3S-714 (PTD No. 224-151; Sundry No. 325-126) Paragraph Sub-Paragraph Section Complete? AOGCC Page 9 March 24, 2025 (k) Confidential information Clearly marked and specific facts supporting nondisclosure Non-confidential well. SFD 3/19/2025 (l) Variances requested Modifications of deadlines, requests for variances or waivers No plan for post fracture water well analysis. Commission may require this depending on performance of the fracturing operation.
T + 1 337.856-7201
1058 Baker Hughes Drive
Broussard, LA 70518, USA
Mar 21, 2025
AOGCC
Attention: Meredith Guhl
333 W. 7th Ave., Suite 100
Anchorage, Alaska 99501-3539
Subject:Final Log Distribution for ConocoPhillips Alaska, Inc.
KRU 3S-714
Kuparuk River
API #: 50-103-20903-00-00
Permit No: 224-151
Rig: Doyon 25
The final Coil deliverables were uploaded via https://copsftp.sharefile.com/ for the above well.
Items delivered: Digital Las Data, Graphic Images CGM/PDF and Survey Files.
Thank you.
Signature of receiver & date received:
Please return transmittal letter to:
Hampton, Jerissa
Jerissa.Hampton@conocophillips.com
Luis G Arismendi
Luis.arismendi@bakerhughes.com
224-151
T40237
Gavin Gluyas Digitally signed by Gavin Gluyas
Date: 2025.03.26 08:51:16 -08'00'
WELL NAME API #SERVICE ORDER #FIELD NAMESERVICE DESCRIPTION DELIVERABLE DESCRIPTION DATA TYPE DATE LOGGEDCOLOR PRINTS E-Delivery3S-714 50-103-20903-00-00 224-151 KUPARUK RIVER MEMORY Top Of Cement PROCESSED 19-Feb-25 1Transmittal Receipt________________________________X____________________________________________Print Name Signature DatePlease return via courier or sign/scan and email a copy to Schlumberger.Abhattacharya@slb.comSLB Auditor - A Transmittal Receipt signature confirms that a package (box, envelope, etc.) has been received and the contents of the package have been verified to match the media noted above. The specific content of the CDs and/or hardcopy prints may or may not have been verified for correctness or quality level at this point.# Schlumberger-Private224-151T40180
SAMPLE TRANSMITTAL
TO: AOGCC
333 WEST 7T" SUITE 100
ANCH. AK. 99501
279-1433
OPERATOR: CPAI
SAMPLE TYPE: Dry Cuttings
SAMPLES SENT:
3S-714
6600-16392
4 Boxes
SENT BY: M. McCRACKEN
DATE: 02/27/2025
AIR BILL: N/A
CPAI: CPA12025022701
CHARGE CODE: N/A
NAME: 3S-714
NUMBER OF BOXES: 4 Boxes
UPON RECEIPT OF THESE SAMPLES, PLEASE NOTE ANY DISCREPANCIES AND RETURN A SIGNED COPY
OF THIS FORM TO:
CONOCOPHILLIPS, ALASKA
700 G ST
ATO-380
ANCHORAGE, AK. 99510
ATTN: MIKE McCRACKEN
State of Alaska Mike.mccracken@conocophillips.com
Alaska Oil and Gas Conservation Commission
333 W. 7th Ave., Ste.100
RECEIVED: Amhom e, AK 99501 '✓
RECEIVED
FEB 2 7 2025
AOGCC
STATE OF ALASKA
OIL AND GAS CONSERVATION COMMISSION
BOPE Test Report for:
Reviewed By:
P.I. Suprv
Comm ________KUPARUK RIV UNIT 3S-714
JBR 03/19/2025
MISC. INSPECTIONS:
FLOOR SAFTY VALVES:CHOKE MANIFOLD:BOP STACK:
ACCUMULATOR SYSTEM:MUD SYSTEM:
P/F P/F
P/FP/FP/F
Visual Alarm
QuantityQuantity
Time/Pressure
SizeQuantity
Number of Failures:1
4" and 4.5" test joints used for testing. The annular failed on the 4" test joint. The element was changed out and tested after I
left location. I asked them to send me the test charts for these two tests after the new element was installed.
Test Results
TEST DATA
Rig Rep:E. Potter/B. WillardOperator:ConocoPhillips Alaska, Inc.Operator Rep:L. Shirley/A. Negusse
Rig Owner/Rig No.:Doyon 25 PTD#:2241510 DATE:2/8/2025
Type Operation:DRILL Annular:
250/3500Type Test:OTH
Valves:
250/3500
Rams:
250/3500
Test Pressures:Inspection No:bopGDC250209070408
Inspector Guy Cook
Inspector
Insp Source
Related Insp No:
INSIDE REEL VALVES:
Quantity P/F
(Valid for Coil Rigs Only)
Remarks:
Test Time 10
MASP:
1503
Sundry No:
Control System Response Time (sec)
Time P/F
Housekeeping:P
PTD On Location P
Standing Order Posted P
Well Sign P
Hazard Sec.P
Test Fluid W
Misc NA
Upper Kelly 1 P
Lower Kelly 1 P
Ball Type 2 P
Inside BOP 1 P
FSV Misc 0 NA
15 PNo. Valves
1 PManual Chokes
1 PHydraulic Chokes
0 NACH Misc
Stripper 0 NA
Annular Preventer 1 13 5/8" 5000 F
#1 Rams 1 2 7/8"x5" VB P
#2 Rams 1 Bllind/Shear P
#3 Rams 1 2 7/8"x5" VB P
#4 Rams 0 NA
#5 Rams 0 NA
#6 Rams 0 NA
Choke Ln. Valves 1 3 1/8" 5000 P
HCR Valves 2 3 1/8" 5000 P
Kill Line Valves 2 3 1/8" 5000 P
Check Valve 0 NA
BOP Misc 0 NA
System Pressure P3000
Pressure After Closure P1775
200 PSI Attained P14
Full Pressure Attained P110
Blind Switch Covers:PAll Stations
Bottle precharge P
Nitgn Btls# &psi (avg)P6@1808
ACC Misc NA
P PTrip Tank
P PPit Level Indicators
P PFlow Indicator
P PMeth Gas Detector
P PH2S Gas Detector
NA NAMS Misc
Inside Reel Valves 0 NA
Annular Preventer P17
#1 Rams P7
#2 Rams P6
#3 Rams P6
#4 Rams NA0
#5 Rams NA0
#6 Rams NA0
HCR Choke P1
HCR Kill P1
9
9
9
9999
9
9
9
&KDUWIRU$QQXODUUHWHVWLVDWWDFKHG
Annular Preventer F
annular failed on the 4" test joint element was changed out and tested after I
left location
#01&5FTU"OOVMBS3FUFTU
%PZPO,364
15%
"0($$*OTQCPQ(%$
CAUTION: This email originated from outside the State of Alaska mail system. Do not
click links or open attachments unless you recognize the sender and know the content
is safe.
From:Rixse, Melvin G (OGC)
To:AOGCC Records (CED sponsored)
Subject:20250113 1330 Hyd Fracture PTD 224-151 - KRU 3S-714
Date:Monday, January 13, 2025 3:37:35 PM
From: Warren, Abby <Abby.Warren@conocophillips.com>
Sent: Monday, January 13, 2025 1:37 PM
To: Rixse, Melvin G (OGC) <melvin.rixse@alaska.gov>; Loepp, Victoria T (OGC)
<victoria.loepp@alaska.gov>; Davies, Stephen F (OGC) <steve.davies@alaska.gov>; Dewhurst,
Andrew D (OGC) <andrew.dewhurst@alaska.gov>
Cc: Hobbs, Greg S <Greg.S.Hobbs@conocophillips.com>
Subject: PTD 224-151 - KRU 3S-714
All
I was looking over the permit after approval and noticed there was an error. 3S-714 will be
hydraulicly fractured. Because the well is an injector, the logs required for cement quality are
already required by the current approved permit. The approved sonic scope will confirm the
top of cement for injector service and the stimulation. A 10-403 will be submitted for approval
prior to fracturing. I apologize for the oversight.
Please let me know if there are any questions
Thanks,
Abby Warren
Staff Drilling Engineer
C: 907-240-9293
Alaska Oil and Gas
Conservation Commission
333 West Seventh Avenue
Anchorage, Alaska 99501-3572
Main: 907.279.1433
Fax: 907.276.7542
www.aogcc.alaska.gov
Chris Brillon
Wells Engineering Manager
Conoco Phillips Alaska, Inc.
700 G Street
Anchorage, AK, 99501
Re: Kuparuk River Field, Coyote Oil Pool, KRU 3S-714
Conoco Phillips Alaska, Inc.
Permit to Drill Number: 224-151
Surface Location: 2517 FNL, 1066 FEL, S18 T12N R8E, UM
Bottomhole Location: 2450 FNL, 2707 FEL, S18 T12N R8E, UM
Dear Mr. Brillon:
Enclosed is the approved application for the permit to drill the above referenced well.
Per Statute AS 31.05.030(d)(2)(B) and Regulation 20 AAC 25.071, composite curves for all well
logs run must be submitted to the AOGCC within 90 days after completion, suspension, or
abandonment of this well, or within 90 days of acquisition of the data, whichever occurs first.
This permit to drill does not exempt you from obtaining additional permits or an approval required
by law from other governmental agencies and does not authorize conducting drilling operations
until all other required permits and approvals have been issued. In addition, the AOGCC reserves
the right to withdraw the permit in the event it was erroneously issued.
Operations must be conducted in accordance with AS 31.05 and Title 20, Chapter 25 of the Alaska
Administrative Code unless the AOGCC specifically authorizes a variance. Failure to comply
with an applicable provision of AS 31.05, Title 20, Chapter 25 of the Alaska Administrative Code,
or an AOGCC order, or the terms and conditions of this permit may result in the revocation or
suspension of the permit.
Sincerely,
Gregory C. Wilson
Commissioner
DATED this 9th day of January 2025.
.
Gregory C. Wilson Digitally signed by Gregory C.
Wilson
Date: 2025.01.09 13:22:54 -09'00'
1a. Type of Work: 1b. Proposed Well Class: Exploratory - Gas Service - WAG Service - Disp 1c. Specify if well is proposed for:
Drill Lateral Stratigraphic Test Development - Oil Service - Winj Single Zone Coalbed Gas Gas Hydrates
Redrill Reentry Exploratory - Oil Development - Gas Service - Supply Multiple Zone Geothermal Shale Gas
2. Operator Name: 5. Bond: Blanket Single Well 11. Well Name and Number:
Bond No.
3. Address: 6. Proposed Depth: 12. Field/Pool(s):
MD: 16,392 TVD: 4204
4a. Location of Well (Governmental Section): 7. Property Designation:
Surface:
Top of Productive Horizon: 8. DNR Approval Number: 13. Approximate Spud Date:
Total Depth: 9. Acres in Property: 14. Distance to Nearest Property:
4b. Location of Well (State Base Plane Coordinates - NAD 27): 10. KB Elevation above MSL (ft): 39.5 15. Distance to Nearest Well Open
Surface: x- 476193 y- 5993898 Zone- 4 24 to Same Pool: 1293' to 3S-704
16. Deviated wells: Kickoff depth: 400 feet 17. Maximum Potential Pressures in psig (see 20 AAC 25.035)
Maximum Hole Angle: 90° degrees Downhole: Surface:
Hole Casing Weight Grade Coupling Length MD TVD MD TVD
42" 20" 94# H40 Welded 92 40 40 92 92
13-1/2" 10-3/4" 45.5# L80 H563 2747 40 40 2747 2496
9-7/8" 7-5/8" 29.7# L80 H563 5741 40 40 5741 3865
9-7/8" 7-5/8" 33.7# P110S H563 800 5741 3865 6541 4124
6-1/2" 4-1/2" 12.6# P110-S H563 10026 6366 4082 16392 4204
19.PRESENT WELL CONDITION SUMMARY (To be completed for Redrill and Re-Entry Operations)
Junk (measured):
TVD
Hydraulic Fracture planned? Yes No
20. Attachments: Property Plat BOP Sketch Drilling Program Time v. Depth Plot Shallow Hazard Analysis
Diverter Sketch Seabed Report Drilling Fluid Program 20 AAC 25.050 requirements
Contact Name:
Chris Brillon Contact Email:abby.warren@cop.com
Wells Engineering Manager Contact Phone: 907-240-9293
Date:
Permit to Drill API Number: Permit Approval
Number:Date:
Conditions of approval :
Samples req'd: Yes No Mud log req'd: Yes No
H2S measures: Yes No Directional svy req'd: Yes No
Spacing exception req'd: Yes No Inclination-only svy req'd: Yes No
Post initial injection MIT req'd: Yes No
APPROVED BY
Approved by: COMMISSIONER THE COMMISSION Date:
Comm. Comm. Sr Pet Eng Sr Pet Geo Sr Res Eng
1924
P.O. Box 100360 Anchorage, Alaska, 99510-0360
2517 FNL, 1066 FEL, S18 T12N R8E, UM ADL380107 / ADL392374
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
PERMIT TO DRILL
20 AAC 25.005
ConocoPhillips Alaska Inc 59-52-180 3S-714
2530 FNL, 3992 FEL, S18, T12N, R8E, UM
2450 FNL, 2707 FEL, S18 T12N R8E, UM 2448 / 2459
GL / BF Elevation above MSL (ft):
18. Casing Program: Specifications Top - Setting Depth - Bottom Cement Quantity, c.f. or sacks
(including stage data)
Total Depth MD (ft): Total Depth TVD (ft): Plugs (measured): Effect. Depth MD (ft): Effect. Depth TVD (ft):
Casing Length Size Cement Volume MD
Intermediate
Surface
Conductor/Structural
Perforation Depth MD (ft): Perforation Depth TVD (ft):
Liner
Production
If checked, well may not be used to explore for, test, or produce coalbed methane, gas hydrates, or gas contained in shales:
21. I hereby certify that the foregoing is true and the procedure approved herein will not be
deviated from without prior written approval.
Authorized Name:
Authorized Title:
Authorized Signature:
Abby Warren
Commission Use Only
See cover letter for other
requirements.
Kuparuk River Field
Coyote Oil Pool
1/5/2025
1892' to ADL380107
1115 sx of 15.3 ppg Class G + Add's
196 sx of 15.3 ppg Class G + 17 sx of 15.3
ppg Class G
Cement to surface with 4 yds slurry
1148 sx of 11.0 ppg DeepCRETE + 272 sx of
15.8 ppg Class G
1503
Form 10-401 Revised 3/2021 This permit is valid for 24 months from the date of approval per 20 AAC 25.005(g)
'HF
By Grace Christianson at 4:16 pm, Dec 06, 2024
X
224-151
DSR-12/16/24
Service - WAG
Initial BOP test to 5000 psig; subsequent BOP test to 3500 psig
Annular preventer test to 2500 psig
Intermediate I cement evaluation may use SonicScope under the attached Conditions of Approval
Surface casing LOT and annular LOT to the AOGCC as soon as available
BOPE testing on a 21-day interval is approved with the attached conditions
50-103-20903-00-00
Diverter variance request granted per 20 AAC 20.035(h)(2),
A.Dewhurst 08JAN25MGR09JAN2024
KRU
&':
&':IRU-/&
Gregory C. Wilson Digitally signed by Gregory C. Wilson
Date: 2025.01.09 13:18:38 -09'00'
01/09/25
01/09/25
RBDMS JSB 011325
KRU 3S-714 PTD224-151 Conditions of Approval
Approval is granted to run the LWD-Sonic on upcoming well with the following
provisions:
1. CPAI will provide a written log evaluation/interpretation to the AOGCC along with the log
as soon as they become available. The evaluation is to include/highlight the intervals of
competent cement that CPAI is using to meet the objective requirements for annular
isolation, reservoir ĖŜĺīÍťĖĺIJϠϙĺŘϙèĺIJƱIJĖIJČϙƏĺIJôϙĖŜĺīÍťĖĺIJϙôťèϟϙŘĺŽĖîĖIJČϙťēôϙīĺČϙſĖťēĺŪťϙÍIJϙ
evaluation/interpretation is not acceptable.
2. LWD sonic logs must show free pipe and Top of Cement, just as the e-line log does. CPAI
must start the log at a depth to ensure the free pipe above the TOC is captured as well as
the TOC. Starting the log below tēôϙÍèťŪÍīϙiϙæÍŜôîϙĺIJϙèÍīèŪīÍťĖĺIJŜϙŕŘôîĖèťĖIJČϙÍϙîĖƯôŘôIJťϙ
TOC will not be acceptable.
3. CPAI will provide a cement job summary report and evaluation along with the cement log
and evaluation to the AOGCC when they become available
4. CPAI will provide the results of the FIT when available.
5. Depending on the cement job results indicated by the cement job report, the logs and
the FIT, remedial measures or additional logging may be required.
CPAI’s request to allow BOPE testing on a 21-day interval is approved with the
following conditions:
- CPAI must continue to implement the Between Wells Maintenance Program as approved
by AOGCC.
- The initial test after rigging up BOPE to drill a well must be to the rated working pressure
as provided in API Standard 53.
- CPAI is encouraged to take advantage of opportunities to test within the 21-day time limit.
- CPAI must adhere to original equipment manufacturer recommendations and
replacement
parts for BOPE.
- Requests for extensions beyond 21 days must include justĖƱèÍťĖĺIJϙſĖťēϙŜŪŕŕĺŘťĖIJČ
information demonstrating the additional time is necessary for well control purposes or to
mitigate a stuck drill string.
ConocoPhillips Alaska, Inc.
Post Office Box 100360
Anchorage , Alaska 99510-0360
Telephone 907-276-1215
December 6, 2024
Alaska Oil and Gas Conservation Commission
333 West 7th Avenue, Suite 100
Anchorage, Alaska 99501
Re: Application for Permit to Drill 3S-714
Dear Sir or Madam:
ConocoPhillips Alaska, Inc. hereby applies for a Permit to Drill an onshore Coyote Injector well from the 3S drilling pad. Th e
intended spud date for this well is January 5, 2025. It is intended that Doyon 25 be used to drill the well.
3S-714 will utilize a 13-1/2" surface hole drilled to TD and 10-3/4" casing will be set and cemented to surface. As noted in
section 4 of the attached proposed drilling program, the low maximum anticipated surface pressure of the well allows use of
a three preventer BOPE per 20 AAC 25.035 (e) (1) (A) (i-iii). The fourth preventer will contain solid body pipe rams that will be
sized for the intermediate casing string. The 9-7/8" intermediate hole will be drilled and topset the Coyote reservoir. A 7-5/8"
casing string will be set and cemented from TD to secure the shoe and cover a 500’ MD or 250’ TVD above any hydrocarbon-
bearing zones per AOGCC regulations.
The 6-1/2" production interval will be drilled horizontally and geo-steered within the Coyote formation. The well will be
completed as a cemented, fracture stimulated Injector with 4-1/2" liner with frac sleeves. The upper completion will include a
production packer with GLM’s and a downhole guage tied back to surface.
It is requested that a variance of the diverter requirement under 20 AAC 25.035 (h)(2) is granted. There has been multiple
wells drilled on pad which have not encountered any shallow gas or had any issues related to hydrates.
A variance is also requested for a BOPE test interval of 21 days for this project. Doyon 25 supported the CPAI BOPE between
well maintenance program through COVID and has maintained 73% first time pass rate along with a 99% effectiveness for all
components tested in 2024 to date. The variance allows effective drilling and completion of the long lateral of this well.
Please find attached the information required by 20 ACC 25.005 (a) and (c) for your review. Pertinent information
attached to this application includes the following:
1.Form 10-401 Application for Permit to Drill per 20 ACC 25.005 (a)
2.Proposed drilling program
3.Proposed drilling fluids program summary
4.Proposed completion diagram
5.Pressure information as required by 20 ACC 25.005 (c) (4) (a-c)
6.Directional drilling / collision avoidance information as required by 20 ACC 25.050 (b)
Information pertinent to the application that is presently on file at the AOGCC:
1.Diagrams of the BOP equipment, diverter equipment and choke manifold lay out as required by 20 ACC
25.035 (a) and (b).
2.A description of the drilling fluids handling system.
3.Diagram of riser set up.
If you have any questions or require further information, please contact Abby Warren at 907-240-9293
(abby.warren@cop.com) or Chris Brillon at 907-265-6120.
Sincerely, cc:
3S-714 Well File / Jenna Taylor ATO 1804
David Lee ATO 1552
Abby Warren Chris Brillon ATO 1548
Drilling Engineer
Support granting diverter waiver: See page 5. SFD
requested that a variance of the diverter requirement under 20 AAC 25.035 (h)(2) is granted
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 1 | 14
3S-714 Well Plan
Application for Permit to Drill
Table of Contents
1. Well Name ............................................................................................................................................. 2
2. Location Summary ................................................................................................................................. 2
3. Proposed Drilling Program ..................................................................................................................... 4
4. BOP and Diverter Information ................................................................................................................ 4
5. MASP Calculations ................................................................................................................................. 6
6. Procedure for Conducting Formation Integrity Tests ............................................................................... 7
7. Casing and Cementing Program .............................................................................................................. 7
8. Drilling Fluid Program ............................................................................................................................ 8
9. Abnormally Pressured Formation Information ........................................................................................ 9
10. Seismic Analysis ..................................................................................................................................... 9
11. Seabed Condition Analysis ..................................................................................................................... 9
12. Evidence of Bonding ............................................................................................................................... 9
13. Discussion of Mud and Cuttings Disposal and Annular Disposal .............................................................. 9
14. Drilling Hazards Summary .................................................................................................................... 10
15. Proposed Completion Schematic .......................................................................................................... 12
16. Area of Review..................................................................................................................................... 13
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 2 | 14
1. Well Name
Requirements of 20 AAC 25.005 (f)
The well for which this application is submitted will be designated as 3S-714
2. Location Summary
Requirements of 20 AAC 25.005(c)(2)
Location at Surface 2517 FNL, 1066 FEL, S18 T12N R8E, UM
NAD27
Northing: 5993897.77
Easting: 476192.99
RKB Elevation 15.5’ AMSL
Pad Elevation 24’ AMSL
Top of Productive Horizon (Heel) 2694 FNL, 3996 FEL, S18 T12N R8E, UM
NAD27
Northing: 5993731.54
Easting: 473263.43
Measured Depth, RKB:6541‘ MD
True Vertical Depth, RKB:4124‘ TVD
True Vertical Depth, SS:4085‘ TVDss
Total Depth (Toe) 2450 FNL, 2707 FEL, S18 T12N R8E, UM
NAD27
Northing: 474552.3
Easting: 5993970.64
Measured Depth, RKB:16392‘ MD
True Vertical Depth, RKB:4204‘ TVD
True Vertical Depth, SS:4164‘ TVDss
Pad Layout
474552.3
See attached emails. -A.Dewhurst 24DEC24
5983970.7
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 3 | 14
Well Plat
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 4 | 14
3. Proposed Drilling Program
Requirements of 20 AAC 25.005(c)(13)
1. MIRU Doyon 25 onto well over pre-installed 20” insulated conductor.
2. Rig up and test riser, dewater cellar as needed.
3. Drill 13-1/2"hole to the surface casing point as per the directional plan, with Spud Mud. (LWD Program: GR/RES/GWD).
4. Run and cement 10-3/4" surface casing to surface. Results of the cement operation will be submitted as soon as possible.
5. Install BOPE with the following equipment/configuration: 13-5/8” annular preventer, 7-5/8"FBR’s, blind ram and 2-7/8” x 5”
VBR’s.
See section 4 for ram configuration justification.
6. Test BOPE to 250 psi low / 5,000 psi high (24-48 hr. regulatory notice).
7. Pick up and run in hole with 9-7/8" drilling BHA to drill intermediate hole section.
8. Chart casing pressure test to 3500 psi for 30 minutes.
9. Drill out shoe track and 20’ of new hole.
10. Perform LOT. Minimum LOT required to drill ahead is 11 ppg EMW.
11. Drill 9-7/8"hole to section TD (LWD Program : GR/RES/DEN/NEU)
12. Run 7 5/8” casing and cement to a minimum of 250’ TVD or 500’ MD above any hydrocarbon bearing zones (cementing
schematic attached). Pressure test casing if possible on plug bump to 3850 psi.
13. Change upper 7-5/8" solid body rams to 2-7/8” x 5” VBR’s. Test BOPE to 250/3,500 psi. (24-48 hr. regulatory notice).
14. Pick up and RIH with 6-1/2” drilling assembly. Log top of cement with sonic tool in recorded mode.
15. Chart casing pressure test to 3,850 psi for 30 minutes if not tested on plug bump.
16. Drill out shoe track and 20 feet of new formation. Perform FIT. Minimum acceptable leak-off for drilling ahead is 10.7 ppg
EMW.
17. Drill 6-1/2" horizontal hole to section TD (LWD Program: GR/RES/Den/Neu).
18. Circulate the hole clean and POOH.
19. Run 4-1/2” liner to TD, set liner hanger and packer.
20. Cement 4-1/2” liner from TD to liner top. POOH LD DP.
21. Pressure test well to 3,850 psi. RU to run upper completion.
22. Run 4-1/2” upper completion with glass plug, production packer, downhole gauge, and gas lift mandrels. Space out and
land tubing hanger.
23. Pressure test hanger seals to 5,000 psi.
24. Pressure test against the glass plug to set production packer, test tubing to 4,550 psi, chart test.
25. Bleed tubing pressure to 2200 psi and test IA to 3,850 psi, chart test.
26. Install HP-BPV and test to 1500 psi.
27. Nipple down BOP.
28. Install tubing head adapter assembly. N/U tree and test to 10,000 psi/10 minutes.
29. Freeze protect down tubing and annulus.
30. Secure well. Rig down and move out.
Please note – This well will be frac’d
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 5 | 14
4. BOP and Diverter Information
Requirements of 20 AAC 25.005(c)(3 & 7)
Please reference BOP and diverter schematics on file for Doyon 25
Doyon 25 will use a BOPE stack equipped with an annular preventer, fixed, 7-5/8" solid body rams,
blind/shear rams and variable bore rams while drilling and running casing in the intermediate section of
3S-714.
3S-714 has a MASP of 1475 psi in the intermediate hole section using the methodology presented in
section 5 MASP calculations. With a MASP less than 3000 psi ConocoPhillips classifies the operation as a
Class 2.
Per 20 AAC 25.035.e.1.A:
For an operation with a maximum potential surface pressure of 3,000 psi or less, BOPE must have at least
three preventers, including:
i. One equipped with pipe rams that fit the size of drill pipe, tubing or casing begin used, except that pipe rams
need not be sized to bottom-hole assemblies and drill collars.
ii. One with blind rams
iii. One annular type
Intermediate Drilling/ Casing
Annular Preventer (iii)
7-5/8" Fixed Rams
Blind/Shear Rams (ii)
VBR’s (i)
Production:
Annular Preventer (iii)
VBR’s (i)
Blind/Shear Rams (ii)
VBR’s (i)
It is requested that a variance of the diverter requirement under 20 AAC 25.035(h)(2) is granted. At 3S,
there has not been significant indication of shallow gas or gas hydrates through the surface hole interval.
There are 7 previously drilled wells (3S-14, 3S-606, 3S-610, 3S-611, 3S-612, 3S-617, 3S-624) within 500’ of
Recommend approving variance based on CPAI analysis mentioned above and AOGCC review o f
drilling reports from KRU 3S-08 and mudlogs of KRU 3S-620 and Palm-1. -A.Dewhurst 12DEC24
variance of the diverter requirement
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 6 | 14
the proposed 3S-714 surface shoe location. None of these wells encountered any significant indication of
shallow gas or gas hydrates.
5. MASP Calculations
Requirements of 20 AAC 25.005(c)(4)
(A) maximum downhole pressure and maximum potential surface pressure;
Maximum Potential Surface Pressure (MPSP) is determined as the lesser of:
Method 1: surface pressure at breakdown of the formation casing seat with a gas gradient to the surface
Method 2: formation pore pressure at the next casing point less a gas gradient to the surface
Method 1 Method 2
= [( ×0.052 ) ] × = ( ) ×
Where:
FG – Fracture gradient at the casing seat in lb/gal
0.052 – Conversion from lb/gal to psi/ft
Gas Gradient – 0.1 psi/ft
TVD – True Vertical Depth of casing seat in ft RKB
Where:
FPP – Formation Pore Pressure at the next casing point
Gas Gradient – 0.1 psi/ft
The following presents data used for calculation of Maximum Potential Surface Pressure (MPSP) while
drilling:
Section Hole Size
Previous CSG Section TD MPSP
psi
MPSP MPSP
Size MD TVD FG
ppg
Pore Pressure
ppg | psi MD TVD Pore Pressure
ppg | psi
Method 1
psi
Method 2
psi
SURF 13-1/2" 20" 120 120 13.2 8.7 54 2747 2496 8.7 1,129 70 70 879
INT1 9-7/8" 10-3/4" 2747 2496 14 8.8 1,142 6541 4124 8.8 1,887 1,475 1,567 1,475
PROD 6-1/2" 7-5/8" 6541 4124 13 8.8 1,887 16392 4204 8.8 1,924 1,504 2,375 1,504
*Maximum potential pore pressure in the Susitna Sand if present
(B) data on potential gas zones;
The planned wellbore is not expected to penetrate any shallow gas zones.
(C) data concerning potential causes of hole problems such as abnormally geo-pressured strata, lost
circulation zones, and zones that have a propensity for differential sticking;
Please see Drilling Hazards Summary
Agree: Drilling records for three wells with surface casing shoes lying within 300' of the proposed
3S-714 surface casing shoe location do not contain any mention of shallow gas or gas hydrates.
Diverter waivers were also granted for each of those three nearby wells. SFD 12/31/2024
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 7 | 14
6. Procedure for Conducting Formation Integrity Tests
Requirements of 20 AAC 25.005 (c)(5)
Drill out casing shoe and perform LOT test or FIT in accordance with the LOT/FIT procedure that
ConocoPhillips Alaska has on file with the Commission.
7. Casing and Cementing Program
Requirements of 20 AAC 25.005 (c)(6)
Casing and Cementing Program
OD
(in)
Hole Size
(in)
Weight
(lb/ft) Grade Conn. Cement Program
20 42 94 H40 Welded Cemented to surface with
10 yds slurry
10-3/4" 13-1/2" 45.5# L80 H563 Cement to Surface
7-5/8" 9-7/8" 29.7#
33.7#
L80
P110S H563 250’ TVD or 500’ MD, whichever is greater, above
highest significant hydrocarbon bearing zone
4-1/2" 6-1/2" 12.6# P110-S H563 Cement to liner top.
10-3/4" Surface Casing run to 2747' MD/ 2496' TVD Cement Plan:
Cement from 2747’ MD to 2247’ (500’ of tail) with DeepCRETE + Adds @ 15.8 ppg, and from 2247' to
surface with 11.0 ppg DeepCRETE. Assume 200% excess annular volume in permafrost and 50% excess
below the permafrost (1754’ MD), zero excess in 20” conductor.
Lead 393 bbls => 1148 sx of 11.0 ppg DeepCRETE + Add's @ 1.92 ft³/sk
Tail 56 bbls => 272 sx of 15.8 ppg Class G + Add's @ 1.16 ft³/sk
7-5/8" Intermediate Casing run to 6541' MD/ 4124' TVD Cement Plan:
Primary cement job consists of a 15.3 ppg slurry designed to be at 6541’ MD, which is 250' TVD above the
prognosed shallowest hydrocarbon bearing zone Top Coyote, K3. If a shallower hydrocarbon zone of
producible volumes, is encountered while drilling, a longer primary job or a 2 nd stage cement job will be
performed to isolate this zone. Assume 30% excess annular volume.
Lead 44 bbls => 196 sx of 15.3 ppg Ext. Class G + Add's @ 1.25 ft³/sk
Tail 4 bbls => 17 sx of 15.3 ppg Class G + Add's @ 1.246 ft³/sk
4-1/2" Production Liner run to 16392' MD/ 4204' TVD Cement Plan:
Primary cement job consists of a 15.3 ppg slurry designed to be at 6366' MD/ 4082' TVD, which is at the
liner top.
Tail 248 bbls => 1115 sx of 15.3 ppg Class G + Add's + Add's @ 1.25 ft³/sk
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 8 | 14
8. Drilling Fluid Program
(Requirements of 20 AAC 25.005(c)(8))
Surface Intermediate Production
Hole Size in 13-1/2" 9-7/8" 6-1/2"
Casing Size in 10-3/4" 7-5/8" 4-1/2"
Density ppg 8.6-9.6 ppg 9.0-10.0 ppg 9.0-10.0 ppg
PV cP ALAP 10-30 10-30
YP lb./100 ft2 35-50 8-16 8-16
Funnel Viscosity s/qt 150-300 40 - 65 40-65
Initial Gels lb./100 ft2 50 N/A N/A
10 Minute Gels lb./100 ft2 60 N/A N/A
API Fluid Loss cc/30 min <45 N/A N/A
HPHT Fluid Loss cc/30 min n/a <4 <4
pH 8.5-9.5 9.5 – 10.0 9.5-10.0
Oil/Water Ratio N/A 65/35 – 70/30 65/35 – 70/30
Surface Hole:
A freshwater Spud Mud will be used for the surface interval. Keep flow line viscosity at ± 200 sec/qt while
drilling and running casing. Reduce viscosity prior to cementing. Maintain mud weight S10.0 ppg by use of
solids control system and dilutions where necessary.
Intermediate:
NAF system will be used. Ensure good hole cleaning by pumping regular sweeps and maximizing fluid
annular velocity. Maintain mud weight from 9.0-10.0 ppg and be prepared to add loss circulations
materials as needed.
Production Hole:
The horizontal production interval will be drilled with NAF system weighted to 9.0-10.0 ppg. MPD will be
available for adding backpressure during connections if necessary.
Diagram of Doyon 25 Mud System on file. Drilling fluid practices will be in accordance with appropriate
regulations stated in 20 AAC 25.033.
All fluid densities to be overbalanced to expected pore pressure. - mgr
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 9 | 14
9. Abnormally Pressured Formation Information
Requirements of 20 AAC 25.005 (c)(9)
N/A - Application is not for an exploratory or stratigraphic test well.
10. Seismic Analysis
Requirements of 20 AAC 25.005 (c)(10)
N/A - Application is not for an exploratory or stratigraphic test well.
11. Seabed Condition Analysis
Requirements of 20 AAC 25.005 (c)(11)
N/A - Application is not for an offshore well.
12. Evidence of Bonding
Requirements of 20 AAC 25.005 (c)(12)
Evidence of bonding for ConocoPhillips Alaska, Inc. is on file with the Commission.
13. Discussion of Mud and Cuttings Disposal and Annular Disposal
Requirements of 20 AAC 25.005 (c)(14)
Waste fluids and cuttings generated during the drilling process will be disposed of by hauling the fluids to
a KRU Class II disposal well at the 1B Facility. If needed, excess cuttings generated will be hauled to Milne
Point or Prudhoe Bay Grind and Inject Facility for temporary storage and eventual processing for injection
down an approved disposal well, or stored, tested for hazardous substances, and (if free of hazardous
substances) used on pads and roads in the Kuparuk area in accordance with a permit from the State of
Alaska.
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 10 | 14
14. Drilling Hazards Summary
13-1/2" Hole | 10-3/4" Casing Interval
Event Risk Level Mitigation Strategy
Conductor Broach Low Monitor cellar continuously during interval.
Well Collision Low First well on Pad, traveling cylinder diagrams
Gas Hydrates Low If observed – control drill, reduce pump rates and circulating time, reduce mud
temperatures
Clay Balling Medium Maintain planned mud parameters and flow rates, Increase mud weight, use weighted
sweeps, reduce fluid viscosity, control ROP
Abnormal Pressure Low Diverter drills, increased mud weight. Shallow hazard study noted minimal risk
Lost Circulation Medium Reduce pump rates, mud rheology, add lost circulation material, use of low density
cement slurries, port collar, control pipe running speeds
9-7/8" Hole | 7-5/8" Casing Interval
Event Risk Level Mitigation Strategy
Lost circulation Low Reduce pump rates, reduce trip speeds, real time ECD monitoring, mud rheology, add
lost circulation material
Hole swabbing on trips Medium Reduce trip speeds, condition mud properties, proper hole filling, pump out of hole, real
time ECD monitoring, MPD stripping practices
Abnormal Pressure in
Overburden Formations Low Well control drills, check for flow during connections, increase mud weight. Shallow
hazard study noted minimal risk
Hole Cleaning Low Monitor ECD and torque/drag trends, control drill and use best hole cleaning practices
6-1/2" Hole | 4-1/2" Liner - Horizontal Production Hole
Event Risk Level Mitigation Strategy
Lost circulation Low Reduce pump rates, reduce trip speeds, real time ECD monitoring, mud rheology, add
lost circulation material
Hole swabbing on trips Medium Reduce trip speeds, condition mud properties, proper hole filling, pump out of hole, real
time ECD monitoring
Abnormal Reservoir Pressure Low Well control drills, check for flow during connections, increased mud weight
Differential Sticking Low Uniform reservoir pressure along lateral, keep pipe moving, control mud weight
Hydrogen Sulfide gas Low H2S drills, detection systems, alarms, standard well control practices, mud scavengers
To be posted in Rig Floor Doghouse Prior to Spud
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 11 | 14
Well Proximity Risks:
3S will be a multi-well pad. Directional drilling / collision avoidance information as required by AOGCC 20
ACC 25.050 (b) is provided in the following attachments.
3S-714 well has one close approach with the abandoned 3S-14 well.
Drilling Area Risks:
Reservoir Pressure:
Unlikely to encounter any abnormal pressure however, the rig will be prepared to weight up if
required.
Weak sand stringers could be present in the overburden. LCM material will be available to seal in
losses in the intermediate section.
Lost Circulation:
Standard LCM material and well bore strengthening pills are expected to be effective in dealing
with lost circulation if needed.
Swabbed Kicks
Good drilling practices will be stressed to minimize the potential of taking swabbed kicks.
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 12 | 14
15. Proposed Completion Schematic
3S-714 AOGCC 10-401 APD
12/24/2024
3S-714 AOGCC 10-401 APD 13 | 15
16. Area of Review
3S-714 Area of Review (AOR)
An Area of Review plot is show below of the 3S-714 injector planned wellpath and offset wells. There are nine
wells (3S-03, 3S-21, 3S-22, 3S-701 and 3S-704) within in the quarter mile review for 3S-714.
3S-714 AOGCC 10-401 APD 12/24/2024 3S-714 AOGCC 10-401 APD 14 | 15
3S-714 AOGCC 10-401 APD 12/24/2024 3S-714 AOGCC 10-401 APD 15 | 15
3S-714 AOGCC 10-401 APD
12/6/2024
3S-714 AOGCC 10-401 APD 13 | 14
16. Area of Review
3S-714 Area of Review (AOR)
An Area of Review plot is show below of the 3S-714 injector planned wellpath and offset wells. There are nine
wells (3S-03, 3S-21, 3S-23, 3S-24, 3S-613, 3S-615, 3S-625, 3S-701 and 3S-704) within in the quarter mile review
for 3S-714.
Superseded by updated AOR. See attached emails. -A.Dewhurst 24DEC24
3S-714 AOGCC 10-401 APD 12/6/2024 3S-714 AOGCC 10-401 APD 14 | 14 Superseded by updated AOR. See attached emails. -A.Dewhurst 24DEC24
40 100
100 200
200 500
500 1000
1000 1500
1500 2000
2000 3000
3000 5000
5000 7000
7000 10000
10000 15000
15000 17000
3S-714 wp08 Plan Summary
3S-714 wp08
3S-03
3S-06
3S-06A
3S-07
3S-08
3S-08A3S-08B
3S-08C
3S-08CL1
3S-08CL1PB1
3S-09
3S-10
3S-14
3S-15
3S-163S-17
3S-17A
3S-18
3S-19
3S-21
3S-22
3S-23
3S-23A
3S-24A
3S-24B
3S-26
PALM 1
3S-611PB1
3S-613
3S-620
3S-701
3S-701A
3S-718
3S-722
3S-703 (P12) wp04
3S-705 (I12) wp09
3S-719 (P02) wp05
3S-721 (I03) wp04
3S-723 wp04
3S-732 (I10) wp04
3S-734 (P04) wp03
3S-736 (I04) wp03
3S-738 (I05) wp04
0
4
Dogleg Severity0 2500 5000 7500 10000 12500 15000
Measured Depth
10-3/4" Surface Casing 7-5/8" Intermediate Casing
4-1/2" Production Liner
50
50
100
100
0
90
180
270
30
210
60
240 120
300
150
330
Travelling Cylinder Azimuth (TFO+AZI) [°] vs Travelling Cylinder Separation [100 usft/in]
3S-09
3S-10
3S-14
3S-15
3S-16
3S-173S-17A
3S-183S-19
3S-610
3S-611
3S-611PB1
3S-612
3S-6133S-615
3S-617
3S-718
3S-719 (P02) wp05
3S-723 wp04
3S-730 (P10) wp04
0
4500
True Vertical Depth0 2000 4000 6000 8000 10000 12000
Vertical Section at 189.20°
10-3/4" Surface Casing
7-5/8" Intermediate Casing
4-1/2" Production Liner
0
28
55
Centre to Centre Separation0 2250 4500 6750 9000 11250 13500 15750
Measured Depth
Equivalent Magnetic Distance
DDI
7.147
SURVEY PROGRAM
Date: 2024-08-28T00:00:00 Validated: Yes Version:
Depth From Depth To Survey/Plan Tool
39.50 1400.00 3S-714 wp08 (3S-714)r.5 SDI_URSA1
1400.00 2747.83 3S-714 wp08 (3S-714)MWD+IFR2+SAG+MS
2747.83 6540.77 3S-714 wp08 (3S-714)
MWD+IFR2+SAG+MS
6540.77 16392.09 3S-714 wp08 (3S-714)MWD+IFR2+SAG+MS
Surface Location
North / 5993648.30
East / 1616225.06
Ground / 24.00
CASING DETAILS
TVD MD Name
2497.00 2747.83 10-3/4" Surface Casing
4124.00 6540.77 7-5/8" Intermediate Casing
4203.50 16392.00 4-1/2" Production LinerMag Model & Date:BGGM2024 01-Dec-24
Magnetic North is 13.96° East of True North (Magnetic Declination)
Mag Dip & Field Strength:80.62° 57190.18nT
SECTION DETAILS
Sec MD Inc Azi TVD +N/-S +E/-W Dleg TFace VSect Annotation
1 39.50 0.00 0.00 39.50 0.00 0.00 0.00 0.00 0.00
2 400.00 0.00 0.00 400.00 0.00 0.00 0.00 0.00 0.00 Start Build 1.00
3 500.00 1.00 340.00 499.99 0.82 -0.30 1.00 340.00 -0.76 Start Build 1.50
4 650.00 3.25 340.00 649.88 6.05 -2.20 1.50 0.00 -5.62 Start Build 2.00
5 1699.35 24.24 340.00 1663.50 239.00 -86.99 2.00 0.00 -222.02 Start 109.67 hold at 1699.35 MD
6 1809.02 24.24 340.00 1763.50 281.31 -102.39 0.00 0.00 -261.32 Start DLS 3.75 TFO -52.59
7 3214.38 69.26 297.50 2721.62 900.03 -836.44 3.75 -52.59 -754.74 Start 348.35 hold at 3214.38 MD
8 3562.73 69.26 297.50 2844.99 1050.44 -1125.41 0.00 0.00 -857.02 Start DLS 3.75 TFO -113.37
9 6670.41 80.00 174.00 4149.14 -302.67 -2920.74 3.75 -113.37 765.70 Start Build 3.00
10 6870.41 86.00 174.00 4173.50 -500.00 -2900.00 3.00 0.00 957.18 Start 20.00 hold at 6870.41 MD
11 6890.41 86.00 174.00 4174.90 -519.84 -2897.91 0.00 0.00 976.43 Start DLS 2.00 TFO -25.19
12 7104.23 89.87 172.18 4182.60 -731.92 -2872.21 2.00 -25.19 1181.67 Start 9287.87 hold at 7104.23 MD
13 16392.09 89.87 172.18 4203.50 -9933.42 -1608.70 0.00 0.00 10062.84 TD at 16392.09
FORMATION TOP DETAILS
TVDPath Formation
1377.50 Top Ugnu
1713.50 Base Permafrost
2022.50 Top West Sak
2456.50 Base West Sak
2665.50 Campanian Sand (C-80)
3414.50 C-50
3885.50 C-35
4083.50 Top Coyote (Top Nanushuk), K3
Plan: 24+39.5 @ 63.50usft (Doyon 25)
Project: Kuparuk River Unit_2Site: Kuparuk 3S PadWell: Plan: 3S-714 (I02)Wellbore: 3S-714Design: 3S-714 wp08-12000-60000South(-)/North(+) (3000 usft/in)-12000 -6000 0 6000 12000West(-)/East(+) (3000 usft/in)3S-714 T1 1320 ft3S-714 I02 T1 0411243S-714 I02 T2 0328243S-714 T2 1320 ft3S-705 (I12) wp093S-734 (P04) wp033S-723 wp043S-243S-24A3S-24B3S-729 (I22A) wp033S-213S-721 (I03) wp043S-033S-701A3S-7013S -2 2
3S-719 (P02) wp053S-6133S-6063S-6113S-722 wp07 - approvewd3S-163S-736 (I04) wp033S-7183S-731 (P07) wp043 S -2 6
3S-730 (P10) wp043S-6123S-6103S-6243S-7223S-08CL13S-08CL1PB13S-093S-7043S-193S-17A 3S -08C3S-083S-08B3S-08A
3S-6263S-153S-6203S-23A3S -23 3S-738 (I05) wp043S -073S-143S-6153S-103S-62510-3/4" Surface Casing7-5/8" Intermediate Casing4-1/2" Production Liner500100015002000250030003500
400041923S-714 wp08Plan View with offset wells
Project: Kuparuk River Unit_2Site: Kuparuk 3S PadWell: Plan: 3S-714 (I02)Wellbore: 3S-714Design: 3S-714 wp08-12000-60000South(-)/North(+) (3000 usft/in)-12000 -6000 0 6000 12000West(-)/East(+) (3000 usft/in)3S-714 T1 1320 ft3S-714 I02 T1 0411243S-714 I02 T2 0328243S-714 T2 1320 ft10-3/4" Surface Casing7-5/8" Intermediate Casing4-1/2" Production Liner500100015002000250030003500
400041923S-714 wp08Plan View with offset wells
019003800True Vertical Depth (950 usft/in)0 3000 6000 9000 12000Vertical Section at 189.20° (1500 usft/in)10-3/4" Surface Casing7-5/8" Intermediate Casing4-1/2" Production Liner10002000300040005000600070008000900010000110001200013000140001500016000Plan: 3S-714 (I02)/3S-714 wp08Start Build 1.00Start Build 1.50Start Build 2.00Start 109.45 hold at 1686.75 MDStart DLS 3.75 TFO -51.99Start 337.83 hold at 3207.96 MDStart DLS 3.75 TFO -113.45Start Build 3.00Start 20.00 hold at 6863.15 MDStart DLS 2.00 TFO -25.19Start 9287.87 hold at 7096.96 MDTD at 16384.83Section View Project: Kuparuk River Unit_2Site: Kuparuk 3S PadWell: Plan: 3S-714 (I02)Wellbore: 3S-714Design: 3S-714 wp08
!""
#$% &'(
($
'(
($
")"&
'(
($
*+++++
,$-(.!
/ "
0 1
!"#$% & '231
0 ( ) *++
,)-.#
#
4
!"#$% & '51
0 .#
#
+/0+- 6
# !
0 .#
#"
1++2#2(#/#(4 (" 5! 7
7
3
"41".
5
4
8 1(
6
5
9
41(04
5 *2+)#24
.#
#
+/0+-65 *
60+
7
18/
0+9
$) +
0+99 +))$)
" ""
:
"
/"(
/ ."(
"" ) "4
!".
;".
8" .
.#
#
1
"4:
"(""""+
66#$
6!!64"#$
"""#$
":;445
":;"
7
7 ""
/ ."(
/"(
;".
!".
<;=7
<=
"" ) "4 8 (/
66!4#$
6!!6"!#$
""#$7!;" """#$
":;45
":;4!
#$
!#$
7
1 ""
>?@
:".!
>2@
1 1"
#.
>?@
5 5."
<==1" >>" ! 4"! 6"4
!3"
#("
1".3
"4
85
3" " 1
!: >231@
>(0@
<=
>(0@
1" "
>?@
<;=7
>(0@
2"A1
!"
4""""""""
1
!:
>(0@
(42 .
$2 (4>7 @
1
!2
>(0@
1>!>"
,-0
,0
9& 1%,(
3
"4%'"6""""
1,?
=1
@=1,?
91
3
"4%'6""""64
1,?
=1
@=1,?
91
3
"4%'64!6"
1,?
=1
@=1,?
91
3
"4%'!6"!6"
,$-(.!
/ "
0 1
!"#$% & '231
0 ( ) *++
,)-.#
#
4
!"#$% & '51
0 .#
#
+/0+- 6
# !
0 .#
#"
1++2#2(#/#(4 (" 5! 7
7
3
"41".
% ""
>?@
#B"(!
>?@
<;=7
>(0@
2:A
>?@
<=
>(0@
5(
1
!
>(0@
3"
1
!
>(0@
1 ..
>?=(0@
,("
>?=(0@
2(
>?=(0@
"
2.
""""""""""""""""""""""""""
""""""""""""""""""""""""""""""""
"""""""""""""4"""""""""
"""""""""!"!44"""!"""
""""""""""4!""6!!""""6!
"""""""""""""46!""""64""
""4!"""6!"!!64
""""""""""""66""64"""!!6!
"6""!6""4"""!6!"
""""""""""6""""""""6"""4!""!64"
""""""""""""6446"""4!""!64"
"44""6464!"4446"
""""""""""""6!"4"66""444!6",""4
5(
1
!
>(0@
% ""
>?@
#B"(!
>?@
<;=7
>(0@
3"
"
>(0@
1 ..
>?=(0@
<=
>(0@
,("
>?=(0@
2(
>?=(0@
(4
3"
1
!
>(0@
"""" """ """ """" """ """""" """ """ """
"""" "" """ "! """4 "" "" """
!""" """ !44 ! "!" " " """
6 4" """ 6" "" "" """
2
).(
6! """ 6!!" " """" 4! "" """
64 """ 6" ! """!"! ! """ """
,0
64"" """ 6!" ! """4 " """ """
6" "! " 6"" !4! ""4 !! ! !!
2
7$
6!4 "4" "! 6!" 4"4" !!" !
,7$
6""4 ! ! 6!!" 4! !
">@
64 !! " 6! """ 4!
6! !! " 64"" 4" """6"" 6 """ """
64" !!" 6" ! 6" 644" "4 "
*
64! !4 "! 644" !! 6" "!4 4
*
!6 !4 4 6"4" 4 !" 6 !
2
4 >2
(!($@'
!6!" 4""" "" 6 !" "! 6" 4
!64" 4!"" "" 6" 4 """""" 6"""" "" """
!64" 4!"" "" 6" ! """4 64 """ """
6" 44 4 64!" 64! "" 64 4 "4
!6" 44 4 6"" "6"!4 """6 6!"4" """ """
,$-(.!
/ "
0 1
!"#$% & '231
0 ( ) *++
,)-.#
#
4
!"#$% & '51
0 .#
#
+/0+- 6
# !
0 .#
#"
1++2#2(#/#(4 (" 5! 7
7
3
"41".
2.
!"=".
!
231
>(0@
!".
>(0@
;".
>(0@
<=
>(0@
<;=7
>(0@
1".2.
/ ."(/"(
1"
#.
>?@
1"
1"C
>?@
,"" 6" 66!"!" 6!6"" 6"""" """":;45 ":;4!"
2+9)A&"4#$!!!#$1%B6!5644'
(+)%+#""""'
"$ 6" 66 6!6"""" 6""""""" """":;"!5 ":;
*+9)
(+)%+#6"""'
"$ 6"" 646 6!6446 6!"4"""" """":;!"5 ":;!!
2+9)A&""#$!"#$1%""B656!"4"'
(+)%+#6"""'
,""4 6"" 646 6!6446 6!"4"""" """":;!"5 ":;!!
*+9)
(+)%+#""""'
3"
1
!
>(0@
5(
1
!
>(0@
".
1"
>"@
-
1"
>"@
". "
">C#$)(+96""64"" ""
>4C,2+(+96""!6"! 4
>C #)+ 8+!6!"" !""
5(
1
!
>(0@
3"
1
!
>(0@
1"
1" "
>?@ /"! .4
1"
>?@
: "
6
09#6"
64 <2$ 6"
6"
6""
6!4 <6!"
6""4 (2
+%(4"'6!!"
64" ("6"
64! (644"
!6
( & %
5#*#'6.6"4"
,$-(.!
/ "
0 1
!"#$% & '231
0 ( ) *++
,)-.#
#
4
!"#$% & '51
0 .#
#
+/0+- 6
# !
0 .#
#"
1++2#2(#/#(4 (" 5! 7
7
3
"41".
5(
1
!
>(0@
3"
1
!
>(0@
<;=7
>(0@
<=
>(0@
/ "
# "
"""" """" """ """ <#+""
"""" "4 "" <#+"
!""" !44 !" " <#+""
6! 6!!" "" 4! "!* !1
64"" 6!" 4 " 8?@
64 6! """ 4! 4* 41
6! 64"" 6"" 6 8?@
!6!" 6 "! 6" <#+""
!64" 6" """" 6"""" """* !4"1
!64" 6" 4 64 8""?@
6" 64!" 64 44* "1
!6" 6"" 6 6!"4" !"
!
!
"
!
#$
#%&'
('#)))))
#%&'
#%&'
*+
,
-.
/%
$0
1
1
!"#$% & '$%() *+ !%,2340
1
- .!
51
!"#$% & '$%() *+ !%,640
1
/0
1
0
0
1($(( )7
1
1 -
6$1
0
81
9
!$(( 2
87
1 ($(( )
0
8
4 1 3+0
/
4)) +
0
4.1
5(6 9002340
1
6$1
4.1
0
7
6$1
6$1
7
01
:
1
0
-$ / 7
8/ /
-
9:4;: <:03 :3+ 5
5 !((=" ((>((( ) )
1+ -
!%$(()
./
1
? /
) @6%$!')
5(6
/$ 1
.8
./7$1 !$# /// 3 A
.6$1
:
;0<
2
.
4
2
;8
<
2
;0<
4>!'>!(!
$%
+.
+ .
21+ *
- %,#$%( @(($((
5(6 *
,
1+"<!"
9"1
4
9 1+ " <! "
2 " 1
@(($(( !@$6
5(6 *
,
1+"<!"
9"1
4
9 1+ " <! "
2 " 1
!@$6 '@%($
5(6 *
,
1+"<!"
9"1
4
9 1+ " <! "
2 " 1
'@%($ '@#!$(#
5(6 *
,
9008%8
%4.
0
6
$
4
;0<
900
6
$
4
;0<
,*
;0<
,*
7
;0<
:
8
.
4
/
(
(
( ($ %$(( !(%$! #6$#6 !$%#(
3
(
(
( #$' 6(($(( !(%$6 #6$#! $'
<
(
(
( 6@%6!$!' %@!%$(( %$% '$% $6!
('
('
(' ('$( (($(( %$# #$ %$!
3
('
('
(' %'$! %($(( %$' #$( $!'
<
('
('
(' @666$#! @#%($(( !$'% !(($#! '$6
('
('
(' ('$( (($(( %$# #$ %$!
3
('
('
(' %'$! %($(( %$' #$( $!'
<
('
('
(' @666$#! @#%($(( !$'% !(($#! '$6
(
(
( %$ %($(( %$ !$%% 6$(
3
(
(
( !%$! !%($(( %$%6 $% !$6'
<
(
(
( '($#' '(($(( '$! %$' !$%
(6
(6
(6 !!$6 !!%$(( $# $' %$6'
3
(6
(6
(6 !6!$ !%$(( %$# $' !$%
<
(6
(6
(6 '($ '(($(( !$ !'$6 !$%!
(6
(6
(6 !!$6 !!%$(( $# $' %$6'
3
(6
(6
(6 !6!$ !%$(( %$# $' !$%
<
(6
(6
(6 '($ '(($(( !$ !'$6 !$%!
(6
(6;
(6; !!$6 !!%$(( $# $' %$6'
3
(6
(6;
(6; !6!$ !%$(( %$# $' !$%
<
(6
(6;
(6; '($ '(($(( !$ !'$6 !$%!
(6
(6
(6 !$!6 !!%$(( $# $6 $(
3
(6
(6
(6 !6$! !%$(( %$!( $ $(#
<
(6
(6
(6 '(!$6 '(($(( !$'! !$(# !$(
(6
(6:
(6: !$!6 !!%$(( $# $6 $((
3
(6
(6:
(6: !6$! !%$(( %$!( $ $(6
<
(6
(6:
(6: '(!$6 '(($(( !$'! !$(# !$(('
(6
(6:;
(6:; !$!6 !!%$(( $# $6 $((
3
(6
(6:;
(6:; !6$! !%$(( %$!( $ $(6
<
(6
(6:;
(6:; '(!$6 '(($(( !$'! !$(# !$((
(#
(#
(# %$(( %($(( #%$# #$% %!$%
3
(#
(#
(# !('$## !(($(( #'$ #!$ !$((
<
(#
(#
(# '(%$%! '(($(( !%$%' 6$%6 $#6
1 /
-2 @
<
)
@ 3
,
-.
/%
$0
1
1
!"#$% & '$%() *+ !%,2340
1
- .!
51
!"#$% & '$%() *+ !%,640
1
/0
1
0
0
1($(( )7
1
1 -
6$1
0
81
9
!$(( 2
87
1 ($(( )
0
8
4 1 3+0
/
4)) +
0
4.1
5(6 9002340
1
9008%8
%4.
0
6
$
4
;0<
900
6
$
4
;0<
,*
;0<
,*
7
;0<
:
8
.
4
/
(
(
( ($!( (($(( %$(# !$# %$!!
3
(
(
( !($6 !(($(( %$66 $6 '$6
<
(
(
( '%'$' '%($(( ($'' #$(% $'
0
/
@
%$'( %($(( $( $(% $!6
0
/
@ 3
@
<
!!$%6 !!%$(( %$! ($( $%%
%
%
% !('$6 !(($(( !$6( !($%! $!'6
3
%
%
% !%'$6! !%($(( !$!' !($( %$#
<
%
%
% ('$% (($(( !%$'! !($%' %$(''
'
'
' '('$# '(($(( $! $( $(%
3
'
'
' '%'$' '%($(( $! $(! '$6
<
'
'
' 6($6 %$(( %$ 6$# '$%
!($( !(($(( '$ '$ !($%
3
!%'$#% !%($(( '$%6 '$( 6$%%
<
@6(($(( @%(($(( %($# !#'$%! '$%!
!($( !(($(( '$ '$ !($%
3
!%'$#% !%($(( '$%6 '$( 6$%%
<
@6(($(( @%(($(( %($# !#'$%6 '$%#
6
6
6 %$! %($(( 6$' 6$! !$6
3
6
6
6 !($! !(($(( 6%$! 6$( !($(6!
<
6
6
6 @%(%$( @(($(( '''$( %66$'6 6$%6
#
#
# 6!$ %$(( ($! ($6 '$##(
3
#
#
# !($ !(($(( (%$!( (!$# $#6
<
#
#
# @#$6 @%$(( @!!($%% @%$ 6$#'
!
!
! 6$%% %$(( $' !$#( 6$6%
1 @ 3
!
!
! (@(6$!! '@!%$(( !6$ '$6 $#%6
1 @
<
!
!
! (@(6$ '@%$(( !#($! 6$% $#
!!
!!
!! %6!$! %%$(( '$ %'$( !#$#6
3
!!
!!
!! '($!! '(($(( '$! %%$# !#$!#
<
!!
!!
!! '@(%$( %@!%($(( !!!$%% 6!$( %$#(
!
!
! !(6$!# !(($(( 6$(! #$66 %6$!'6
3
!
!
! !%6$!6 !%($(( 6$# #$' %$6%
<
!
!
! @'$( %@'(($(( @$( @!6$'( !$%%
!
!
! !($6 !!%$(( 6$(! #$'# %$#
3
!
!
! !%%$6 !%($(( 6$ #$'! %$'6!
<
!
!
! @6$#% %@%(($(( @'#$' @!6$ !6$!(
!
!
! %$! %($(( !($6( !($%( %$%
3
!
!
! %$! %($(( !(%$' !(!$6 #$!
<
!
!
! (@6$6% '@#(($(( @($% @(#$% %$!
!
!
! %$( %($(( !($6( !($%( %$''
3
!
!
! %$( %($(( !(%$' !(!$6 #$
<
!
!
! (@6$6 '@#(($(( @($ @(#$!% %$!(
!
!;
!; %$6( %($(( !($6( !($# %'$6%
3
!
!;
!; %$6( %($(( !(%$' !(!$6 #$%#
<
!
!;
!; (@%($(6 '@#!%$(( @!$' @'$#% $'
!'
!'
!' #%$!% #%($(( !$' !!$ !6$%!#
3
!'
!'
!' #%$'! #%$(( !$% !!$! !6$%%
<
!'
!'
!' @($%% @!%$(( !%($! !($' !%$''
!' :1 :1 #%$!% #%($(( !$' !!$ !6$%!#
3
!' :1 :1 #%$'! #%$(( !$% !!$! !6$%%
<
!' :1 :1 @($%% @!%$(( !%($! !($' !%$''
'('
'('
'(' !@(6$( !@(%($(( $' (($!6 6$''!
3
'('
'('
'(' !@($ !@(%$(( $% (($6 6$6!
<
'('
'('
'(' !@#$6 !@%$(( $(6 $#( $!(
1 /
-2 @
<
)
@ 3
,
-.
/%
$0
1
1
!"#$% & '$%() *+ !%,2340
1
- .!
51
!"#$% & '$%() *+ !%,640
1
/0
1
0
0
1($(( )7
1
1 -
6$1
0
81
9
!$(( 2
87
1 ($(( )
0
8
4 1 3+0
/
4)) +
0
4.1
5(6 9002340
1
9008%8
%4.
0
6
$
4
;0<
900
6
$
4
;0<
,*
;0<
,*
7
;0<
:
8
.
4
/
'(
'(
'( @('$( @(%$(( '$( %$!! $''
3
'(
'(
'( @(#$ @(($(( '$( %$ $(#
<
'(
'(
'( @($ @%($(( '$6 %$% $(!
1 @ @ 3
@
<
'
'
' @#$' @!(($(( $! %$' $'%!
1 @ @ 3
@
<
'
';
'; @#$' @!(($(( $! %$' $'%!
7
4
@
'!
'!
'! #!$# #!%$(( 6$' $# !$%(
1 @ 3
@
<
'!
'!
'! #%($( #%($(( 6$'! $(' !$'!
'
'
' $## %$(( $# ($ $'
3
'
'
' #6$#' (($(( $%! ($6 $%
<
'
'
' 6$6( %($(( %$( ($ $!'
'%
'%
'% %!$% %($(( #$%! $ ($#!
3
'%
'%
'% !%!$ !%($(( #$#6 %$6% $6'
<
'%
'%
'% %!$'' %($(( !$# '$# $!!
'
'
' %$!6 %$(( %'$ %$( #$6
3
'
'
' %(($ %(($(( %'$6 %($6% #$#!
<
'
'
' @$ @(%$(( ($'' (%$ %$!
@ 3
'!(
'!(
'!( '$( %($(( !($(( %$ !'$!6
<
'!(
'!(
'!( %@'%$ @%%$(( (#$!% ''$#% $##%
'!
'!
'! @'($% @%$(( ($ $% '$#%
3
'!
'!
'! @''#$' @!%$(( $%! !$!( %$%
<
'!
'!
'! @%$6 @%!%$(( #$'! %$ $#(
'!%
'!%
'!% #$'( '$ !!$6 !!$6! !!!$(#
3
'!%
'!%
'!% !$6 !%$(( !!%$' !!$6 '$6
<
'!%
'!%
'!% @!'$# %@%(($(( #!$(% #($# !$%#
'!'
'!'
'!' #$'' %($(( !%$ !!#$6 #$(
3
'!'
'!'
'!' $' %$(( !%$' !!#$' $#%
<
'!'
'!'
'!' @'$% @(%($(( %$ '$( 6$'%(
'!'
'!';
'!'; #$'' %($(( !%$ !!#$6 #$(
3
'!'
'!';
'!'; $' %$(( !%$' !!#$' $#%
<
'!'
'!';
'!'; @%%$%6 @#%($(( '$' ##$ #$%
@ 3
(
(
( @!$%( @!%$(( '($ %$( '$%
<
(
(
( @!!$%! @%$(( '$6( %$' '$!
@ 3
(
(
( @!$%( @!%$(( '($ %$ '$6
<
(
(
( @!!$%! @%$(( '$6( %$' '$!%
@ 3
(
(
( #'$(( @((($(( %$( %$' $'
<
(
(
( '@$6 @%!%$(( @!#$% @(!$6 $#
@ 3
6
6
6 '#'$( (($(( '($' %$6% 6$66'
<
6
6
6 $( %($(( '!$ %%$!% 6$''
!!
!!
!! '$'! '%($(( %$! '$% !!$!6
3
!!
!!
!! '$#! '%$(( %$! '$!% !$#%
<
!!
!!
!! 66$' #(($(( '!$' %$%! #$'
'(! B7
/C
'(!
'(! 5(' 6'6$%( 6%$(( !$'( !!%$66 ($!%(
3
'(! B7
/C
'(!
'(! 5(' @(6$!( @(!%$((!$# !!%$ !$'(#
<
'(! B7
/C
'(!
'(! 5(' !@'!%$ !@!%$((6$ %$'! #$6!
( *!,
(
( *!, 5( !#'$6( (($(( !#$! !$%# $'!
3
( *!,
(
( *!, 5( #'$# (($(( !#$' !$!6 $'(
<
( *!,
(
( *!, 5( @'$#6 @%(($((!!$(( !%$%# #$66
(% *!,
(%
(% *!, 5(# '%$#6 %$(( '$% %$ !$(
3
(% *!,
(%
(% *!, 5(# #($' 6(($(( '$' %$!( !!$'
<
(% *!,
(%
(% *!, 5(# '@((!$(' '@((($((!!$!% 6$%( %$'
# *(!,
#
# *(!, 5(% !#'$6( (($(( ##$ #%$( !$%6#
3
# *(!,
#
# *(!, 5(% !$6( !%$(( ##$6 #$# !($(
<
# *(!,
#
# *(!, 5(% @6'6$' @'(($((!6$ !$!' $!
1 /
-2 @
<
)
@ 3
,
-.
/%
$0
1
1
!"#$% & '$%() *+ !%,2340
1
- .!
51
!"#$% & '$%() *+ !%,640
1
/0
1
0
0
1($(( )7
1
1 -
6$1
0
81
9
!$(( 2
87
1 ($(( )
0
8
4 1 3+0
/
4)) +
0
4.1
5(6 9002340
1
9008%8
%4.
0
6
$
4
;0<
900
6
$
4
;0<
,*
;0<
,*
7
;0<
:
8
.
4
/
! *(,
! *(,
! *(, 5( !#'$6( (($(( #$ %$! ($!%%
3
! *(,
! *(,
! *(, 5( '$6( %($(( #$#6 $## !6$(!6
<
! *(,
! *(,
! *(, 5( @#''$!( @6!%$(( @!!$# @6$6 !$(%
7
4
@
! *(,
!
! 5( !$( !%$(( $' #$( !$'!
1 @ 3
! *(,
!
! 5( #'$! %(($(( $ 6$ !$'
1 @
<
! *(,
!
! 5( %'$% %%($(( %$ 6$# !$6#
@ 3
! *!,
! *!,
! *!, 5 @!'$! @%$(( !'$(! !%$'% !$
<
! *!,
! *!,
! *!, 5 @''$# @!%$(( !$! !'$# !$%#
@ 3
!6 *(#,
!6
!6 *(#, 5( @!!$ @(($((!!$ !!$'6 !!$!'%
<
!6 *(#,
!6
!6 *(#, 5( @!6$6 @%($((!$%6 !!$( !!$
@ 3
!# *!!,
!#
!# *!!, 5( @!'$(( @!%$(( !%$#! !$%( !$'
<
!# *!!,
!#
!# *!!, 5( @!6!$%6 @%($(( !%6$%' !6$(6 !$'
@ 3
( *(,
(
( *(, 5( !@(%$ !@(%$((6!$' '#$'# '$%6
<
( *(,
(
( *(, 5( !@(#$6% !@(($((6!$6 '#$6 '$6
*(,
*(, 5( @!6$ @!%$(('$! ('$% $(
3
*(,
*(, 5( @!6$! @(($(('$ ('$!% $(%(
<
*(,
*(, 5( @!#%$ @%$((!($! (#$6% ($6
@ 3
! *(,
!
! *(, 5( !@$6 !@%$((!%$' !$%! #$%%
<
! *(,
!
! *(, 5( !@!6$! !@!!%$((!$# $! #$'
@ 3
*(,
*(, 5( !@$! !@%$((($6# !'$' #$(!
<
*(,
*(, 5( !@%$# !@%$((%$'! $# #$(%
@ 3
@
<
' *(,
'
' *(, 5( !@#!$# !@6(($((($ '$%! $!
@ 3
6 *(%,
6
6 *(%, 5( @!$ !@6%($((($% #$' ($!'
<
6 *(%,
6
6 *(%, 5( @%$'# @!%$((%%$!! %!#$' !($6'
1 /
-2 @
<
)
@ 3
,
-.
/%
$0
1
1
!"#$% & '$%() *+ !%,2340
1
- .!
51
!"#$% & '$%() *+ !%,640
1
/0
1
0
0
1($(( )7
1
1 -
6$1
0
81
9
!$(( 2
87
1 ($(( )
0
8
4 1 3+0
/
4)) +
0
4.1
5(6 9002340
1
(
%(
#((
%(
6((
( ((( '((( #((( !((( %((( 6(((
1
/ +
:
//
(@
(@
( A%
('@
('@
(' A%
('@
('@
(' A6
(@
(@
( A%
(6@
(6@
(6 A%
(6@
(6@
(6 A
(6@
(6;@
(6; A
(6@
(6@
(6 A(
(6@
(6:@
(6: A(
(6@
(6:;@
(6:; A(
(#@
(#@
(# A!
(@
(@
( A'
@
@
A!
%@
%@
% A
'@
'@
' A
@
@
A'
@
@
A!
6@
6@
6 A
#@
#@
# A
!@
!@
! A
!!
!!
!! A
!@
!@
! A
!@
!@
! A
!@
!@
! A#
!@
!@
! A
!@
!;@
!; A(
!'@
!'@
!' A
!'@ :1 @ :1 A!
'('@
'('@
'(' A(
'(@
'(@
'( A(
'@
'@
' A(
'@
';@
'; A(
'!@
'!@
'! A(
'@
'@
' A(
'%@
'%@
'% A(
'@
'@
' A(
'!(@
'!(@
'!( A(
'!@
'!@
'! A(
'!%@
'!%@
'!% A(
'!'@
'!'@
'!' A(
'!'@
'!';@
'!'; A(
(
(
( A(
(@
(@
( A(
(@
(@
( A(
6@
6@
6 A(
!!@
!!@
!! A(
'(! B7
/C@
'(!@
'(! 5(' A(
( *!,@
(@
( *!, 5( A(
(% *!,@
(%@
(% *!, 5(# A(
# *(!,@
#@
# *(!, 5(% A(
! *(,@
! *(,@
! *(, 5( A(
! *(,@
!@
! 5( A(
! *!,@
! *!,@
! *!, 5( A(
!6 *(#,@
!6@
!6 *(#, 5( A(
!# *!!,@
!#@
!# *!!, 5( A(
( *(,@
(@
( *(, 5( A(
*(,@
@
*(, 5( A(
! *(,@
!@
! *(, 5( A(
*(,@
@
*(, 5( A(
' *(,@
'@
' *(, 5( A(
6 *(%,@
6@
6 *(%, 5( A(
: 3 9 3 7 +
/
-
/
.
#6@
D
9/ -2
)
($#E
1/
%(E (= ($(((
4)) +
- 4)) +
) +
-
!"#$% & '$%() *+ !%
1 /
-2 @
<
)
@ 3
,
-.
/%
$0
1
1
!"#$% & '$%() *+ !%,2340
1
- .!
51
!"#$% & '$%() *+ !%,640
1
/0
1
0
0
1($(( )7
1
1 -
6$1
0
81
9
!$(( 2
87
1 ($(( )
0
8
4 1 3+0
/
4)) +
0
4.1
5(6 9002340
1
($((
$((
'$((
#$((
<
( ((( '((( #((( !((( %(((
1
/ +
04 +2
0
/
1
7
4
<
(@
(@
( A%
('@
('@
(' A%
('@
('@
(' A6
(@
(@
( A%
(6@
(6@
(6 A%
(6@
(6@
(6 A
(6@
(6;@
(6; A
(6@
(6@
(6 A(
(6@
(6:@
(6: A(
(6@
(6:;@
(6:; A(
(#@
(#@
(# A!
(@
(@
( A'
@
@
A!
%@
%@
% A
'@
'@
' A
@
@
A'
@
@
A!
6@
6@
6 A
#@
#@
# A
!@
!@
! A
!!
!!
!! A
!@
!@
! A
!@
!@
! A
!@
!@
! A#
!@
!@
! A
!@
!;@
!; A(
!'@
!'@
!' A
!'@ :1 @ :1 A!
'('@
'('@
'(' A(
'(@
'(@
'( A(
'@
'@
' A(
'@
';@
'; A(
'!@
'!@
'! A(
'@
'@
' A(
'%@
'%@
'% A(
'@
'@
' A(
'!(@
'!(@
'!( A(
'!@
'!@
'! A(
'!%@
'!%@
'!% A(
'!'@
'!'@
'!' A(
'!'@
'!';@
'!'; A(
(
(
( A(
(@
(@
( A(
(@
(@
( A(
6@
6@
6 A(
!!@
!!@
!! A(
'(! B7
/C@
'(!@
'(! 5(' A(
( *!,@
(@
( *!, 5( A(
(% *!,@
(%@
(% *!, 5(# A(
# *(!,@
#@
# *(!, 5(% A(
! *(,@
! *(,@
! *(, 5( A(
! *(,@
!@
! 5( A(
! *!,@
! *!,@
! *!, 5( A(
!6 *(#,@
!6@
!6 *(#, 5( A(
!# *!!,@
!#@
!# *!!, 5( A(
( *(,@
(@
( *(, 5( A(
*(,@
@
*(, 5( A(
! *(,@
!@
! *(, 5( A(
*(,@
@
*(, 5( A(
' *(,@
'@
' *(, 5( A(
6 *(%,@
6@
6 *(%, 5( A(
: 3 9 3 7 +
/
-
/
.
#6@
D
9/ -2
)
($#E
1/
%(E (= ($(((
4)) +
- 4)) +
) +
-
!"#$% & '$%() *+ !%
1 /
-2 @
<
)
@ 3
CAUTION: This email originated from outside the State of Alaska mail system. Do not
click links or open attachments unless you recognize the sender and know the content
is safe.
From:Warren, Abby
To:Davies, Stephen F (OGC)
Cc:Dewhurst, Andrew D (OGC)
Subject:RE: [EXTERNAL]KRU 3S-714 (PTD 224-151) - Question
Date:Tuesday, December 31, 2024 8:02:35 AM
Attachments:image001.png
Hi Steve,
In many of the 3S wells we do have unloading events, it’s a combination of several factors, the
unconsolidated nature of 3S surface hole, our high angles in these surface holes, and lower
pump rates when drilling through the permafrost. Prior to the first snippet below we were
drilling at 450-500 gpm so I would suspect that the hole was loading up with cuttings, we then
brought pumps up, cleaned up the wellbore and continued drilling ahead. Before the second
snippet, it was similar, lower pump rate into a higher pump rate, most likely causing a cuttings
bed with the lower flow rate and as we brought the pumps up higher the hole unloaded.
Please let me know if you have any other questions,
Thanks
Abby
From: Davies, Stephen F (OGC) <steve.davies@alaska.gov>
Sent: Monday, December 30, 2024 3:02 PM
To: Warren, Abby <Abby.Warren@conocophillips.com>
Cc: Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>
Subject: [EXTERNAL]KRU 3S-714 (PTD 224-151) - Question
CAUTION:This email originated from outside of the organization. Do not click links or open
attachments unless you recognize the sender and know the content is safe.
Abby,
I’m working with Andy Dewhurst on CPAI’s Permit to Drill application for KRU 3S-714.
Specifically, I’m reviewing CPAI’s request for a diverter waiver and checking the records for
nearby wells. In the daily reports for offset well 3S-606 (PTD 223-111), which is 280' to the
NNE of 3S-714, I don’t see any mention of gas or hydrates in the Daily Ops Summary reports,
but I do see this:
Can you please tell me what caused the 3S-606 hole to unload?
Thanks and Be Well,
Steve Davies
AOGCC
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska Oil
and Gas Conservation Commission (AOGCC), State of Alaska and is for the sole use of the intended recipient(s). It may contain
confidential and/or privileged information. The unauthorized review, use or disclosure of such information may violate state or
federal law. If you are an unintended recipient of this e-mail, please delete it, without first saving or forwarding it, and, so that the
AOGCC is aware of the mistake in sending it to you, contact Steve Davies at 907-793-1224 or steve.davies@alaska.gov
CAUTION: This email originated from outside the State of Alaska mail system. Do not
click links or open attachments unless you recognize the sender and know the content
is safe.
From:Warren, Abby
To:Dewhurst, Andrew D (OGC); Hobbs, Greg S
Cc:Loepp, Victoria T (OGC); Davies, Stephen F (OGC); Guhl, Meredith D (OGC)
Subject:RE: [EXTERNAL]KRU 3S-714 PTD (224-151): Questions
Date:Tuesday, December 24, 2024 8:11:11 AM
Attachments:3S-714 Revised AOR.pdf
Hi Andrew
See Comments below and adjusted table. I revised the AOR portion and have it attached. Let
me know if you would like to see other verbiage.
Total Depth (Toe)2450 FNL, 2707 FEL, S18 T12N R8E, UM
NAD27
Northing: 5983970.7
Easting: 474552.3
Measured Depth, RKB:16392‘ MD
True Vertical Depth, RKB:4204‘ TVD
True Vertical Depth, SS:4164‘ TVDss
Happy Holidays to you all!
Thanks
Abby
From: Dewhurst, Andrew D (OGC) <andrew.dewhurst@alaska.gov>
Sent: Monday, December 16, 2024 1:43 PM
To: Warren, Abby <Abby.Warren@conocophillips.com>; Hobbs, Greg S
<Greg.S.Hobbs@conocophillips.com>
Cc: Loepp, Victoria T (OGC) <victoria.loepp@alaska.gov>; Davies, Stephen F (OGC)
<steve.davies@alaska.gov>; Guhl, Meredith D (OGC) <meredith.guhl@alaska.gov>
Subject: [EXTERNAL]KRU 3S-714 PTD (224-151): Questions
CAUTION:This email originated from outside of the organization. Do not click links or open
attachments unless you recognize the sender and know the content is safe.
Abby,
I am completing my review of the KRU 3S-714 PTD and have a few questions:
Would you double-check the BHL (NAD27 State Plane) coordinates that are presented in
Section 2? It appears that the easting and northings have been swapped. In addition, my
calculations are showing a northings value about 10,000’ less. You are correct, Above is a
corrected table
For Section 16’s Area-of-Review:
Would you please confirm that the following wells that were included in the AOR are
either not within the ¼-mile radius or do not intersect the Coyote stratigraphic interval:
KRU 3S-23A
KRU 3S-24B
KRU 3S-613
KRU 3S-615
KRU 3S-625
KRU 3S-701A (labelled as 3S-701 in the table)
I removed all these in the updated AOR attached
Would you please confirm that the following wells should be included in the AOR:
KRU 3S-18 (50-103-20433-00-00) – I sat down with our directional planner and
ran the scan on my own, it appears this one is outside the ¼ mile by the time we
set intermediate casing. Let me know if I am missing it on this one.
KRU 3S-22 (50-103-20446-00-00) – added to the attached updated AOR
KRU 3S-701 (50-103-20847-00-00) – added to the attached updated AOR
Would you make updates to the table for the following wells:
KRU 3S-03: identify the casing string that covers the Coyote and if no primary
cement isolation, indicate so. Then, in the comments, add a summary of the
planned abandonment activity that will provide isolation - added to the attached
updated AOR
KRU 32-21: was this well also not one that required the perf and wash reservoir
abandonment (similar to KRU 3S-03 above). If so, would you update the table to
show that as originally drilled, there was no isolation and a remedial cementing
job was conducted (with details)? added to the attached updated AOR
Thank,
Andy
Andrew Dewhurst
Senior Petroleum Geologist
Alaska Oil and Gas Conservation Commission
333 W. 7th Ave, Anchorage, AK 99501
andrew.dewhurst@alaska.gov
Direct: (907) 793-1254
Revised 7/2022
TRANSMITTAL LETTER CHECKLIST
WELL NAME: ______________________________________
PTD: _____________________________________________
___ Development ___ Service ___ Exploratory ___ Stratigraphic Test ___ Non-Conventional
FIELD: __________________________ POOL: ____________________________________
Check Box for Appropriate Letter / Paragraphs to be Included in Transmittal Letter
CHECK OPTIONS TEXT FOR APPROVAL LETTER
MULTI
LATERAL
(If last two digits
in API number are
between 60-69)
The permit is for a new wellbore segment of existing well Permit
Number _____________, API Number 50-______________________.
Production from or injection into this wellbore must be reported under
the original API Number stated above.
Spacing
Exception
The permit is approved subject to full compliance with 20 AAC 25.055.
Approval to produce or inject is contingent upon issuance of a
conservation order approving a spacing exception. The Operator
assumes the liability of any protest to the spacing exception that may
occur.
Dry Ditch Sample
All dry ditch sample sets submitted to the AOGCC must be in no greater
than 30-foot sample intervals from below the permafrost or from where
samples are first caught and 10-foot sample intervals through target
zones.
Non-
Conventional
Well
Please note the following special condition of this permit: Production or
production testing of coal bed methane is not allowed for this well until
after the Operator has designed and implemented a water-well testing
program to provide baseline data on water quality and quantity. The
Operator must contact the AOGCC to obtain advance approval of such
a water-well testing program.
Well Logging
Requirements
Regulation 20 AAC 25.071(a) authorizes the AOGCC to specify types
of well logs to be run. In addition to the well logging program proposed
by the Operator in the attached application, the following well logs are
also required for this well:
Per Statute AS 31.05.030(d)(2)(B) and Regulation 20 AAC 25.071,
composite curves for all well logs run must be submitted to the AOGCC
within 90 days after completion, suspension, or abandonment of this
well, or within 90 days of acquisition of the data, whichever occurs first.
224-151
KUPARUK RIVER UNIT KUPARUK RIVER, COYOTE OIL
KRU 3S-714
WELL PERMIT CHECKLISTCompanyConocoPhillips Alaska, Inc.Well Name:KUPARUK RIV UNIT 3S-714Initial Class/TypeSER / PENDGeoArea890Unit11160On/Off ShoreOnProgramSERField & PoolWell bore segAnnular DisposalPTD#:2241510KUPARUK RIVER, COYOTE OIL - 490120NA1 Permit fee attachedInCmpt ADL380107 and ADL3923742 Lease number appropriateYes3 Unique well name and numberYes Kuparuk River Unit, Coyote Oil Pool, CO 8194 Well located in a defined poolYes5 Well located proper distance from drilling unit boundaryNA6 Well located proper distance from other wellsYes7 Sufficient acreage available in drilling unitYes8 If deviated, is wellbore plat includedYes9 Operator only affected partyYes10 Operator has appropriate bond in forceYes11 Permit can be issued without conservation orderYes12 Permit can be issued without administrative approvalYes13 Can permit be approved before 15-day waitYes Area Injection Order No. 4514 Well located within area and strata authorized by Injection Order # (put IO# in comments) (For servInCmpt15 All wells within 1/4 mile area of review identified (For service well only)InCmpt16 Pre-produced injector: duration of pre-production less than 3 months (For service well only)NA17 Nonconven. gas conforms to AS31.05.030(j.1.A),(j.2.A-D)Yes18 Conductor string providedYes SC set at 2747' MD19 Surface casing protects all known USDWsYes 152% excess planned20 CMT vol adequate to circulate on conductor & surf csgNo21 CMT vol adequate to tie-in long string to surf csgYes Production liner fully cemented. IC has adequate cement above reservoir22 CMT will cover all known productive horizonsYes23 Casing designs adequate for C, T, B & permafrostYes Doyon 25 has adequate tankage and good trucking support.24 Adequate tankage or reserve pitNA25 If a re-drill, has a 10-403 for abandonment been approvedYes Baker Hughes collision scan shows no wells with HSE risk.26 Adequate wellbore separation proposedYes Diverter variance granted per 20 AAC 20.035(h)(2)27 If diverter required, does it meet regulationsYes Max reservoir pressure is 1924 psig(9.0 ppg EMW): will drill w/ 9.0-10.0 ppg EMW28 Drilling fluid program schematic & equip list adequateYes29 BOPEs, do they meet regulationYes MPSP is 1503 psig; will initially test BOPs to 5000 psig; subsuquent test to 3500 psig30 BOPE press rating appropriate; test to (put psig in comments)Yes31 Choke manifold complies w/API RP-53 (May 84)Yes32 Work will occur without operation shutdownYes Monitoring required.33 Is presence of H2S gas probableYes34 Mechanical condition of wells within AOR verified (For service well only)Yes H2S encounted in other Torok Oil Pool wells on pad, but not anticipating H2S for Coyote35 Permit can be issued w/o hydrogen sulfide measuresYes Anticipating pore pressure of 8.8 ppg EMW36 Data presented on potential overpressure zonesNA37 Seismic analysis of shallow gas zonesNA38 Seabed condition survey (if off-shore)NA39 Contact name/phone for weekly progress reports [exploratory only]Appr DateApprMGRDate1/9/2025ApprADDDate12/11/2024AdministrationEngineeringGeologyGeologic Commissioner:Date:Engineering Commissioner:DatePublic CommissionerDate