Sean McLaughlin
Drilling Manager
Hilcorp Alaska, LLC
3800 Centerpoint Drive, Suite 1400
Anchorage, AK, 99503
Re: Prudhoe Bay Field, Prudhoe Oil Pool, PBU 03-18B
Hilcorp Alaska, LLC
Permit to Drill Number: 225-145
Surface Location: 1483' FSL, 128' FEL, Sec. 10, T10N, R15E, UM, AK
Bottomhole Location: 1931' FNL, 1034' FWL, Sec. 09, T10N, R15E, UM, AK
Dear Mr. McLaughlin:
Enclosed is the approved application for the permit to drill the above referenced well.
Per Statute AS 31.05.030(d)(2)(B) and Regulation 20 AAC 25.071, composite curves for all well
logs run must be submitted to the AOGCC within 90 days after completion, suspension, or
abandonment of this well, or within 90 days of acquisition of the data, whichever occurs first.
This permit to drill does not exempt you from obtaining additional permits or an approval required
by law from other governmental agencies and does not authorize conducting drilling operations
until all other required permits and approvals have been issued. In addition, the AOGCC reserves
the right to withdraw the permit in the event it was erroneously issued.
Operations must be conducted in accordance with AS 31.05 and Title 20, Chapter 25 of the Alaska
Administrative Code unless the AOGCC specifically authorizes a variance. Failure to comply
with an applicable provision of AS 31.05, Title 20, Chapter 25 of the Alaska Administrative Code,
or an AOGCC order, or the terms and conditions of this permit may result in the revocation or
suspension of the permit.
Sincerely,
.
Commissioner
DATED this 7
th day of January 2026.
3-1/2"x3-1/4"9.3#/6.6#/6.5#
Digitally signed by Sean
McLaughlin (4311)
DN: cn=Sean McLaughlin (4311)
Date: 2025.12.30 07:12:11 -
09'00'
Sean
McLaughlin
(4311)
225-145
By Grace Christianson at 1:01 pm, Dec 30, 2025
TS 1/5/26
*Waiver to 20 AAC 25.036 (c)(2)(A)(iv) with compliance to rules in CO 823
*Variance as per 20 AAC 25.112(i): Approved for alternate abandonment plug placement on parent well
contingent upon fully cemented liner on upcoming sidetrack
J.Lau 1/6/25
50-029-20421-02-00
DSR-1/2/26
*AOGCC Witnessed BOP Test to 3500 psi, Annular 2500 psi minimum.
*Post rig service coil perforating approved for max gun length of 500'.
*Window milling approved on service coil
JLC 1/7/2026
01/07/26
01/07/26
To: Alaska Oil & Gas Conservation Commission
From: Trevor Hyatt
Drilling Engineer
Date: December 29, 2025
Re:03-18B Permit to Drill
Approval is requested for drilling a CTD sidetrack lateral from well 03-18A with the Nabors CDR2/CDR3
Coiled Tubing Drilling.
Proposed plan for 03-18B Producer:
See 03-18A Sundry request for complete pre-rig details - Prior to drilling activities, screening will be conducted to
drift for whipstock, caliper and MIT. E-line will set a 4-1/2"x7" whipstock. Coil will mill window pre-rig. If unable to
set the whipstock or mill the window pre-rig, the rig will perform that work.
A coil tubing drilling sidetrack will be drilled with the Nabors CDR2 or CDR3 rig. The rig will move in, test BOPE
and kill the well. If unable to pre-rig, the rig will set the 4-1/2"x7" whipstock and mill a single string 3.80" window +
10' of formation. The well will kick off drilling in the Shublik and lands in the Ivishak. The lateral will continue in the
Ivishak to TD. The proposed sidetrack will be completed with a 3-1/2"x3-1/4"x2-7/8 13Cr solid liner, cemented in
place and selectively perforated post rig (will be perforated with rig if unable to post rig). This completion will
completely isolate and abandon the parent Prudhoe Pool perfs.
The following describes the work planned. A wellbore schematic of the current well and proposed sidetrack is
attached for reference.
Pre-Rig Work:
Reference 03-18A Sundry submitted in concert with this request for full details.
1. Slickline : Dummy WS drift and Caliper 7"
2. E-Line : Set 4-1/2"x7" Whipstock at 10,275 MD at 205 degrees ROHS
3. Fullbore : MIT-IA and/or MIT-T to 2,500 psi (min)
4. Coil : Mill 3.80" Single String 7" Window (if window not possible, mill with rig).
5. Valve Shop : Pre-CTD Tree Work
6. Operations : Remove wellhouse and level pad.
Rig Work: (Estimated to start in February 2026)
1. MIRU and test BOPE 250 psi low and 3,500 psi high (MASP 2,396 psi). Give AOGCC 24hr notice
prior to BOPE test.
2. Mill 3.80 Single String 7" Window (if not already done pre-rig)
3. Drill build section: 4.25" OH, ~410' (35 deg DLS planned).
4. Drill production lateral: 4.25" OH, ~2,371' (12 deg DLS planned). Swap to KWF for liner.
5. Run 3-1/2 x 3-1/4 x 2-7/8 13Cr solid liner
6. Pump primary cement job*: 74 bbls, 15.3 ppg Class G, 1.24 (ft3/sk), TOC at TOL. Set LTP*. If high
losses are encountered during cement job and it is deemed necessary, a cement down squeeze from
TOL to loss zone will be performed with the rig or service coil (if performed by service coil see future
sundry).
7. Only if not able to do with service coil extended perf post rig Perforate Liner with 1-1/4" CS Hydril
8. Freeze protect well to a min 2,200' TVD.
9. Close in tree, RDMO.
Post Rig Work:
1. Valve Shop : Valve & tree work
2. Slickline : SBHPS, set LTP* (if necessary).
3. Service Coil : Post rig RPM and perforate (~30) - see extended perf procedure attached.
4. Testing : Portable test separator flowback.
Producer
Managed Pressure Drilling:
Managed pressure drilling techniques will be employed on this well. The intent is to provide constant bottom hole
pressure by using minimum 8.4 ppg drilling fluid in combination with annular friction losses and applied surface
pressure. Constant BHP will be utilized to reduce pressure fluctuations to help with hole stability. Applying
annular friction and choke pressure also allow use of lighter drilling fluid and minimizes fluid losses and/or
fracturing at the end of the long well bores. A MPD choke for regulating surface pressure and is independent of
the WC choke.
Deployment of the BHA under trapped wellhead pressure may be necessary. Pressure deployment of the BHA
will be accomplished utilizing BHA pipe/slip rams (see attached BOP configurations). The annular preventer will
act as a secondary containment during deployment and not as a stripper.
Operating parameters and fluid densities will be adjusted based on real-time bottom hole pressure measurements
while drilling and shale behavior. The following scenario is expected:
MPD Pressure at the Planned Window (10280' MD -8,621' TVD)
Pumps On Pumps O
A Target BHP at Window (ppg)4,393 psi 4,393 psi
9.8
B -616 psi 0 psi
0.06
C 3,855 psi 3,855 psi
8.6
B+C Mud + ECD Combined 4,472 psi 3,855 psi
(no choke pressure)
A-(B+C)Choke Pressure Required to Maintain 0 psi 538 psi
Target BHP at window and deeper
Operation Details:
Reservoir Pressure:
The estimated reservoir pressure is expected to be 3,276 psi at 8,800 TVD. (7.2 ppg equivalent).
Maximum expected surface pressure with gas (0.10 psi/ft) to surface is 2,396 psi (from estimated
reservoir pressure).
Mud Program:
Drilling: Minimum MW of 8.4 ppg KCL with viscosifier for drilling. Managed pressure used to maintain
constant BHP.
Disposal:
All Class l & II non-hazardous and RCRA-exempt drilling and completion fluids will go to GNI at DS 4.
Fluids >1% hydrocarbons or flammables must go to GNI.
Fluids >15% solids by volume must go to GNI.
Fluids with solids that will not pass through 1/4 screen must go to GNI.
Fluids with PH >11 must go to GNI.
Hole Size:
3.8 to 4.25 hole for the entirety of the production hole section.
Liner Program:
3-1/2", 9.3#, 13Cr/Solid: 8,680' MD 8,710' MD (30' liner)
3-1/4", 6.6#, 13Cr/Solid: 8,710' MD 10,800' MD (2,090' liner)
2-7/8", 6.5#, 13Cr/Solid: 10,800' MD 13,061' MD (2,261' liner)
The primary barrier for this operation: Kill Weight Fluid to provide overbalance as necessary.
A X-over shall be made up to a safety joint including a TIW valve for all tubulars ran in hole.
Jointed Pipe Work String Program:
1-1/4" CS Hydril, 3.02#, P-110: up to 4,000' MD
1 CS Hydril, 2.25#, P-110: up to 4,000' MD
Used for contingency CTD liner cleanout/logging runs, deployment of perforation guns (if performed by
rig), inner string 2-3/8 liner cement jobs and contingency inner string 2-7/8 liner cement jobs.
Well Control:
BOP diagram is attached. MPD and pressure deployment is planned.
Pipe rams, blind rams and the CT pack off will be pressure tested to 250 psi and to 3,500 psi.
The annular preventer will be tested to 250 psi and 2,500 psi.
1.5 wellbore volumes of KWF will be on location at all times during drilling operations.
A X-over shall be available to be made up to a safety joint, with the same OD as coiled tubing, including a
TIW valve for all tubulars ran in hole.
The safety joint will be utilized while running solid/slotted liner, perforation guns and CS Hydril jointed
pipe. The desire is to keep the same standing orders for the entire liner run and not change shut in
techniques from well to well (run safety joint with pre-installed TIW valve). When closing on a safety joint,
2 sets of pipe/slip rams will be available, above and below the flow cross providing better well control
option.
CO823 Hilcorp CTD Qualification Blind-Shear Test: CDR2 test on 09/04/2025 (see Hilcorp Alaska CTD
CO823 Qualification report previously sent to AOGCC for more information).
CO823 Safety Joint Drills: Provide AOGCC opportunity to witness once per well that a CTD liner is
ran.
Directional:
Directional plan attached. Maximum planned hole angle is 97°. Inclination at kick off point is 35°.
Magnetic and inclination surveys will be taken every 30 ft. No gyro will be run.
Distance to nearest property line 24,600 ft
Distance to nearest well within pool 955 ft
Logging:
MWD directional, Gamma Ray and Resistivity will be run through the entire open hole section.
Real time bore pressure to aid in MPD and ECD management.
Perforating:
30' perforated post rig See attached extended perforating procedure.
2.0" Perf Guns at 6 spf
If post rig extended perforating with service coil is not an option, the well will be perforated with the rig or
post rig under this PTD.
The well will be perforated between the CTD whipstock and TD of the newly drilled CTD well, completely
in the Prudhoe Pool.
Formations: Top of Prudhoe Pool is 10,220 MD in the parent
Anti-Collision Failures:
03-23 Fails AC at 12,413 MD (03-18B depth) and 11,269 MD (03-23 depth)
o Center to center distance is 943
o Collision risk is within the same Pool as the offset well
o Close approach is below the production packer
o Offset well is a producer from the same Pool
o No significant difference in pressure expected
o Pad operator will be aware of the failed anticollision scan and is prepared to shut in 03-23 in the event
of a collision.
o At least offset tubing volume of KWF is on location at all times while drilling by well.
o The potential of intersection and proper response will be discussed with the crew.
Hazards:
DS/Pad is an H2S pad. The last H2S reading on 03-18A: NA (injector).
Max H2S recorded on DS/Pad: 1100 ppm (2011).
0 fault crossings expected.
Low lost circulation risk.
Trevor Hyatt CC: Well File
Drilling Engineer Joseph Lastufka
(907-223-3087)
Pre-Rig Service Coil Window Milling
The approved sundry and permit to drill will be posted in the Operations Cabin of the unit during the
entire window milling operation.
Notes for window milling:
Window milling with service CTU operations will fully comply with 20 AAC 25.286(d)(3), including the use
of pressure control equipment, all BHAs fully lubricated and at no point will any BHA be open-hole
deployed.
Window Milling Procedure:
1. Kill well with 1% KCL if necessary. Well may already be killed from previous operations.
2. MU and RIH with window milling assembly Window mill followed by string reamer.
NOTE: Confirm milling BHA configuration prior to job execution due to variations in different service
providers window milling BHAs.
3. RIH & TAG whipstock pinch point, calculate distance till string reamer is out of the window, paint coil flag
and note in WSR.
4. Mill window per vendor procedure. Make note of any WHP changes while milling window in the WSR.
5. Make multiple reciprocating passes through the kickoff point to dress liner exit and eliminate all burs.
Perform gel sweeps as necessary to keep window clean.
Maximum approved distance to reciprocate beyond the window is 15 ft to ensure confidence the window
is prepared for the sidetrack.DO NOT RECIPROCATE DEEPER than 15 ft.
6. Confirm exited liner & string reamer dressed entire window with coil flag and note bottom of window and
total milled depth in WSR.
7. FP well to 2,500 TVD with 60/40 MeOH while POOH.
8. Once on surface inspect BHA, measure OD of mill and string reamer & document in WSR.
9. RDMO
10. Communicate to Operations to tag wing valve Do Not POP.
Pre-Rig Service Coil Window Milling BOP Diagram
Post-Rig Service Coil Perforating Procedure:
Coiled Tubing
Notes:
Due to the necessary open hole deployment of Extended Perforating jobs, 24-hour crew and WSS
coverage is required.
Note: The well will be killed and monitored before making up the initial perfs guns. This will provide
guidance as to whether the well will be killed by bullheading or circulating bottoms up throughout the
job. If pressure is seen immediately after perforating, it will either be killed by bullheading while POOH
or circulating bottoms up through the same port that opened to shear the firing head.
Coil Tubing
1. MIRU Coiled Tubing Unit and spot ancillary equipment.
2. MU nozzle drift BHA (include SCMT and/or RPM log as needed).
3. RIH to PBTD.
a. Displace well with weighted brine while RIH (minimum 8.4 ppg to be overbalanced).
4. POOH (and RPM log if needed) and lay down BHA.
5. After MU MHA and pull testing the CTC, tag-up on the CT stripper to ensure BHA cannot pull through
the brass upon POOH with guns.
6. There will be no perforations to bullhead kill the well. Well will already be loaded w/ weighted brine or KCl
per previous steps. Re-load well at WSS discretion.
7. At surface, prepare for deployment of TCP guns.
8.Confirm well is dead. Bleed any pressure off to return tank. Kill well w/ KWF, weighted brine as needed
(minimum 8.4 ppg). Maintain continuous hole fill taking returns to tank until lubricator connection is
reestablished. Fluids man-watch must be performed while deploying perf guns to ensure the well
remains killed and there is no excess flow.
9.Pickup safety joint and TIW valve and space out before MU guns.Review well control steps with crew
prior to breaking lubricator connection and commencing makeup of TCP gun string. Once the safety joint
and TIW valve have been spaced out, keep the safety joint/TIW valve readily accessible near the working
platform for quick deployment if necessary.
10. Break lubricator connection at QTS and begin makeup of TCP guns and blanks per schedule below.Max
BHA length per PTD is 500ft. Fluids man-watch must be performed while deploying perf guns to ensure
the well remains killed and there is no excess flow.
a. Perforation details
i.Perf Interval:The well will be perforated between the CTD whipstock and TD of the
newly drilled CTD well, completely in the Prudhoe pool.
ii.Perf Length:500
iii.Gun Length:500
iv.Weight of Guns (lbs):2300lbs (4.6ppf)
11. MU lubricator and RIH with perf gun and tie-in to coil flag correlation. Pickup and perforate perforation
intervals (TBD). POOH.
a. Note any tubing pressure change in WSR.
12. After perforating, PUH to top of liner or into tubing tail to ensure debris doesnt fall in on the guns and
stick the BHA.Confirm well is dead and re-kill if necessary before pulling to surface.
13. Pump pipe displacement while POOH.Stop at surface to reconfirm well dead and hole full.
14. Review well control steps with crew prior to breaking lubricator connection and commencing breakdown of
TCP gun string. Standing orders flow chart included with this sundry request. Ensure safety joint and TIW
valve assembly are on-hand before breaking off lubricator to LD gun BHA.
15. Freeze protect well to 2,000 TVD.
16. RDMO CTU.
Coiled Tubing BOPs
Standing Orders for Open Hole Well Control during Perf Gun Deployment
Equipment Layout Diagram
111'
Map Date: 9/5/2025
True Vertical Depth (100 usft/in)3800
4000
4200
4400
4600
4800
5000
5200
5400
5600
5800
6000
6200
6400
6600
6800
7000
7200
7400
7600
South(-)/North(+) (1000 usft/in)-7000
-6500
-6000
-5500
-5000
-4500
-4000
-3500
Well Date
Quick Test Sub to Otis -
Top of 7" Otis 0.0 ft
Distances from top of riser
Excluding quick-test sub
Top of Annular
CL Annular
Bottom Annular
CL Blind/Shears
CL Coiled Tubing Pipe / Slips
Kill Line Choke Line
CL BHA Pipe / Slip
CL Coiled Tubing Pipe / Slips
TV1 TV2
T1 T2
Flow Tee
Master
Master
LDS
IA
OA
LDS
Ground Level
CDR#-AC BOP Schematic
CDR Rig's Drip Pan
Fill Line
Normally Disconnected
HP hose
to Micromotion
LP hose open ended
to Flowline (optional)
Hydril 7 1/16"
Annular
Blind/Shear
CT Pipe/Slips
2 3/8" Pipe/Slips
2 3/8" Pipe/Slips
7-1/16"
5k Mud
Cross
CT Pipe/Slips
BHA Pipe / Slips
nneeeeeceeeeeeeeeeeeeeeeeeeeeeeeeeeee
Revised 7/2022
TRANSMITTAL LETTER CHECKLIST
WELL NAME: ______________________________________
PTD: _____________________________________________
___ Development ___ Service ___ Exploratory ___ Stratigraphic Test ___ Non-Conventional
FIELD: __________________________ POOL: ____________________________________
Check Box for Appropriate Letter / Paragraphs to be Included in Transmittal Letter
CHECK OPTIONS TEXT FOR APPROVAL LETTER
MULTI
LATERAL
(If last two digits
in API number are
between 60-69)
The permit is for a new wellbore segment of existing well Permit
Number _____________, API Number 50-______________________.
Production from or injection into this wellbore must be reported under
the original API Number stated above.
Spacing
Exception
The permit is approved subject to full compliance with 20 AAC 25.055.
Approval to produce or inject is contingent upon issuance of a
conservation order approving a spacing exception. The Operator
assumes the liability of any protest to the spacing exception that may
occur.
Dry Ditch Sample
All dry ditch sample sets submitted to the AOGCC must be in no greater
than 30-foot sample intervals from below the permafrost or from where
samples are first caught and 10-foot sample intervals through target
zones.
Non-
Conventional
Well
Please note the following special condition of this permit: Production or
production testing of coal bed methane is not allowed for this well until
after the Operator has designed and implemented a water-well testing
program to provide baseline data on water quality and quantity. The
Operator must contact the AOGCC to obtain advance approval of such
a water-well testing program.
Well Logging
Requirements
Regulation 20 AAC 25.071(a) authorizes the AOGCC to specify types
of well logs to be run. In addition to the well logging program proposed
by the Operator in the attached application, the following well logs are
also required for this well:
Per Statute AS 31.05.030(d)(2)(B) and Regulation 20 AAC 25.071,
composite curves for all well logs run must be submitted to the AOGCC
within 90 days after completion, suspension, or abandonment of this
well, or within 90 days of acquisition of the data, whichever occurs first.
PRUDHOE BAY PRUDHOE OIL
PBU 03-18B
225-145
WELL PERMIT CHECKLISTCompanyHilcorp North Slope, LLCWell Name:PRUDHOE BAY UNIT 03-18BInitial Class/TypeDEV / 1-OILGeoArea890Unit11650On/Off ShoreOnProgramDEVWell bore segAnnular DisposalPTD#:2251450Field & Pool:PRUDHOE BAY, PRUDHOE OIL - 640150NA1 Permit fee attachedYes ADL0283282 Lease number appropriateYes3 Unique well name and numberYes PRUDHOE BAY, PRUDHOE OIL - 640150 - governed by CO 341J4 Well located in a defined poolYes5 Well located proper distance from drilling unit boundaryYes6 Well located proper distance from other wellsYes7 Sufficient acreage available in drilling unitYes8 If deviated, is wellbore plat includedYes9 Operator only affected partyYes10 Operator has appropriate bond in forceYes11 Permit can be issued without conservation orderYes12 Permit can be issued without administrative approvalYes13 Can permit be approved before 15-day waitNA14 Well located within area and strata authorized by Injection Order # (put IO# in comments) (For NA15 All wells within 1/4 mile area of review identified (For service well only)No16 Pre-produced injector: duration of pre-production less than 3 months (For service well only)NA17 Nonconven. gas conforms to AS31.05.030(j.1.A),(j.2.A-D)Yes18 Conductor string providedYes19 Surface casing protects all known USDWsYes20 CMT vol adequate to circulate on conductor & surf csgYes21 CMT vol adequate to tie-in long string to surf csgYes22 CMT will cover all known productive horizonsYes23 Casing designs adequate for C, T, B & permafrostYes24 Adequate tankage or reserve pitYes *Variance as per 20 AAC 25.112(i): Approved for alternate abandonment plug with fully cemented liner.25 If a re-drill, has a 10-403 for abandonment been approvedYes26 Adequate wellbore separation proposedNA27 If diverter required, does it meet regulationsYes28 Drilling fluid program schematic & equip list adequateYes *Waiver to 20 AAC 25.036 (c)(2)(A)(iv) with compliance to rules in CO 823.29 BOPEs, do they meet regulationYes 5K.30 BOPE press rating appropriate; test to (put psig in comments)Yes31 Choke manifold complies w/API RP-53 (May 84)Yes32 Work will occur without operation shutdownYes Max H2S recorded on DS/Pad: 1100 ppm (2011).33 Is presence of H2S gas probableNA34 Mechanical condition of wells within AOR verified (For service well only)No DS 03 wells are H2S-bearing. H2S measures are required.35 Permit can be issued w/o hydrogen sulfide measuresYes Expected pressure is 0.374 psi/ft (7.2 ppg EMW)36 Data presented on potential overpressure zonesNA37 Seismic analysis of shallow gas zonesNA38 Seabed condition survey (if off-shore)NA39 Contact name/phone for weekly progress reports [exploratory only]ApprTCSDate1/5/2026ApprJJLDate1/6/2026ApprTCSDate1/5/2026AdministrationEngineeringGeologyGeologic Commissioner:Date:Engineering Commissioner:DatePublic CommissionerDateJLC 1/7/2026