HomeMy WebLinkAbout225-112Nolan Vlahovich Hilcorp Alaska, LLC
Geotech 3800 Centerpoint Drive, Suite 1400
Anchorage, AK 99503
Tele: (907) 564-4558
E-mail: nolan.vlahovich@hilcorp.com
Please acknowledge receipt by signing and returning one copy of this transmittal.
Received By: Date:
Date: 2/4/2026
To: Alaska Oil & Gas Conservation Commission
Natural Resource Technician
333 W 7th Ave Suite 100
Anchorage, AK 99501
SFTP DATA TRANSMITTAL T#20260204
Well API #PTD #Log Date Log
Company Log Type AOGCC
E-Set#
BRU 223-34T 50283202060000 225059 12/31/2025 AK E-LINE Perf
T41308
BRU 244-27 50283201850000 222038 1/2/2026 AK E-LINE Perf
T41309
CLU 11RD 50133205590000 225013 1/2/2026 YELLOWJACKET SCBL
T41310
CLU 11RD 50133205590000 225013 12/19/2025 YELLOWJACKET SCBL
T41310
END 1-25A 50029217220100 197075 11/7/2025 HALLIBURTON COILFLAG
T41311
END 1-25A 50029217220100 197075 12/26/2025 READ PressTempSurvey
T41311
END 2-40 50029225270000 194152 12/18/2025 READ PressTempSurvey
T41312
END 2-52 50029217500000 187092 12/24/2025 HALLIBURTON MFC40
T41313
END 2-56A 50029228630100 198058 1/1/2026 HALLIBURTON COILFLAG
T41314
END 2-56A 50029228630100 198058 1/19/2026 READ CaliperSurvey
T41314
KALOTSA 3 50133206610000 217028 1/14/2026 YELLOWJACKET PERF
T41315
KALOTSA 3 50133206610000 217028 1/9/2026 YELLOWJACKET PERF
T41315
KALOTSA 8 50133207050000 222003 12/18/2025 YELLOWJACKET PERF
T41316
KBU 44-06 50133204980000 200179 12/22/2026 YELLOWJACKET CBL
T41317
KBU 44-06 50133204980000 200179 11/12/2025 YELLOWJACKET PLUG
T41317
KU 24-07RD 50133203520100 205099 1/6/2026 AK E-LINE CBL
T41318
KU 24-07RD 50133203520100 205099 1/6/2026 AK E-LINE Plug/Cement
T41318
KU 24-07RD 50133203520100 205099 1/1/2026 AK E-LINE Plug/Cement/TubingPunch
T41318
MPI-36 50029236770000 220047 1/19/2026 READ CaliperSurvey
T41319
MPI-36 50029236770000 220047 1/19/2026 READ LeakDetectLog
T41319
NCIU A-19 50883201940000 224026 1/7/2025 AK E-LINE Perf
T41320
NFU 42-35 50231200460000 214170 1/8/2026 YELLOWJACKET PERF
T41321
NIK OI24-08 50029234570000 211130 1/19/2026 HALLIBURTON COILFLAG
T41322
ODSN-04 50703206700000 213037 1/20/2026 HALLIBURTON LDL
T41323
ODSN-22 50703207080000 215054 12/20/2025 READ LeakDetection
T41324
PBU 15-11D 50029206530400 225112 1/18/2026 HALLIBURTON RBT-COILFLAG
T41325
PBU 15-43 50029226760000 196083 12/21/2025 HALLIBURTON RBT
T41326
PBU B-30B 50029215420200 225009 1/24/2026 HALLIBURTON RBT-COILFLAG
T41327
PBU C-33B 50029223730200 225096 12/16/2025 HALLIBURTON RBT-COILFLAG
T41328
PBU 15-11D 50029206530400 225112 1/18/2026 HALLIBURTON RBT-COILFLAG
Gavin Gluyas Digitally signed by Gavin Gluyas
Date: 2026.02.05 09:10:43 -09'00'
Nolan Vlahovich Hilcorp Alaska, LLC
Geotech 3800 Centerpoint Drive, Suite 1400
Anchorage, AK 99503
Tele: (907) 564-4558
E-mail: nolan.vlahovich@hilcorp.com
Please acknowledge receipt by signing and returning one copy of this transmittal.
Received By: Date:
PBU D-26B 50029215300200 206098 12/20/2025 HALLIBURTON ISAT T41329
PBU D-26B 50029215300200 206098 12/19/2025 BAKER SPN T41329
PBU F-21A 50029219490100 225019 1/18/2026 HALLIBURTON RBT-COILFLAG T41330
PBU J-21A 50029217050100 225106 1/21/2026 HALLIBURTON RBT-COILFLAG T41331
PBU L-291 50029237790000 224002 12/26/2025 HALLIBURTON RBT T41332
PBU L-291 50029237790000 224002 12/9/2025 YELLOWJACKET RCBL T41332
PBU S-107A 50029220440200 225083 12/8/2025 HALLIBURTON RBT-COILFLAG T41333
PBU S-201A 50029229870100 219092 1/21/2026 HALLIBURTON WFL-TMD3D T41335
PBU S-24B 50029220440200 203163 12/22/2025 HALLIBURTON RBT T41334
PBU S-24B 50029230230100 203163 12/23/2025 HALLIBURTON WFL-TMD3D T41334
SRU 223-15 50133207410000 225123 1/29/2026 YELLOWJACKET GPT-PERF T41336
SRU 223-15 50133207410000 225123 1/20/2026 YELLOWJACKET SCBL T41336
SRU 233-10 50133207400000 225113 12/30/2026 AK E-LINE CBL T41337
SRU 233-10 50133207400000 225113 1/10/2026 YELLOWJACKET SCBL T41337
SRU 233-10 50133207400000 225113 1/6/2026 YELLOWJACKET SCBL T41337
SRU 34-28 50133101580000 163007 1/7/2026 YELLOWJACKET Gamma Ray T41338
SU 32-16 50133207380000 225095 1/17/2026 YELLOWJACKET GPT-PLUG-PERF T41339
SU 32-16 50133207380000 225095 11/22/2025 YELLOWJACKET SCBL T41339
SU 43-10 50133207390000 225107 12/10/2025 YELLOWJACKET SCBL T41340
TBU A-12RD 50883200320100 171029 1/2/2026 AK E-LINE StripGun T41341
TBU D-24A 50733202240100 174064 12/4/2025 AK E-LINE TubingPunch T41342
Please include current contact information if different from above.
Gavin Gluyas Digitally signed by Gavin Gluyas
Date: 2026.02.05 09:11:00 -09'00'
David Douglas Hilcorp Alaska, LLC
Sr. Geotechnician 3800 Centerpoint Drive, Suite 1400
Anchorage, AK 99503
Tele: (907) 777-8337
E-mail: david.douglas@hilcorp.com
Please acknowledge receipt by signing and returning one copy of this transmittal.
Received By: Date:
Date: 01/22/2026
To: Alaska Oil & Gas Conservation Commission
Natural Resource Technician
333 W 7th Ave Suite 100
Anchorage, AK 99501
DATA TRANSMITTAL
WELL: PBU 15-11D + PB1 + PB2
PTD: 225-112
API: 50-029-20653-04-00 (15-11D)
API: 50-029-20653-71-00 (15-11D PB1)
API: 50-029-20653-72-00 (15-11D PB2)
FINAL LWD FORMATION EVALUATION LOGS (12/11/2025 to 12/24/2025)
Multiple Propagation Resistivity & Gamma Ray (2” & 5” MD/TVD Color Logs)
Pressure While Drilling (PWD)
Final Definitive Directional Surveys
SFTP Transfer - Data Main Folders:
SFTP Transfer - Data Sub-Folders:
Please include current contact information if different from above.
T41283
T41284
T41285
Gavin Gluyas Digitally signed by Gavin Gluyas
Date: 2026.01.23 08:54:13 -09'00'
Alaska Oil and Gas
Conservation Commission
333 West Seventh Avenue
Anchorage, Alaska 99501-3572
Main: 907.279.1433
Fax: 907.276.7542
www.aogcc.alaska.gov
Sean McLaughlin
Drilling Manager
Hilcorp Alaska, LLC
3800 Centerpoint Drive, Suite 1400
Anchorage, AK, 99503
Re: Prudhoe Bay Field, Prudhoe Oil, PBU 15-11D
Hilcorp Alaska, LLC
Permit to Drill Number: 225-112
Surface Location: 1997' FNL, 1450' FWL, Sec. 22, T11N, R14E, UM, AK
Bottomhole Location: 1802' FSL, 2639' FEL, Sec. 23, T11N, R14E, UM, AK
Dear Mr. McLaughlin:
Enclosed is the approved application for the permit to drill the above referenced well.
Per Statute AS 31.05.030(d)(2)(B) and Regulation 20 AAC 25.071, composite curves for all well
logs run must be submitted to the AOGCC within 90 days after completion, suspension, or
abandonment of this well, or within 90 days of acquisition of the data, whichever occurs first.
This permit to drill does not exempt you from obtaining additional permits or an approval required
by law from other governmental agencies and does not authorize conducting drilling operations
until all other required permits and approvals have been issued. In addition, the AOGCC reserves
the right to withdraw the permit in the event it was erroneously issued.
Operations must be conducted in accordance with AS 31.05 and Title 20, Chapter 25 of the Alaska
Administrative Code unless the AOGCC specifically authorizes a variance. Failure to comply
with an applicable provision of AS 31.05, Title 20, Chapter 25 of the Alaska Administrative Code,
or an AOGCC order, or the terms and conditions of this permit may result in the revocation or
suspension of the permit.
Sincerely,
Jessie L. Chmielowski
Commissioner
DATED this 31st day of October 2025.
1a. Type of Work: 1b. Proposed Well Class: Exploratory - Gas Service - WAG Service - Disp 1c. Specify if well is proposed for:
Drill Lateral Stratigraphic Test Development - Oil Service - Winj Single Zone Coalbed Gas Gas Hydrates
Redrill Reentry Exploratory - Oil Development - Gas Service - Supply Multiple Zone Geothermal Shale Gas
2. Operator Name: 5. Bond: Blanket Single Well 11. Well Name and Number:
Bond No.
3. Address: 6. Proposed Depth: 12. Field/Pool(s):
MD: 13077' TVD: 8769'
4a. Location of Well (Governmental Section): 7. Property Designation:
Surface:
Top of Productive Horizon: 8. DNR Approval Number: 13. Approximate Spud Date:
Total Depth: 9. Acres in Property: 14. Distance to Nearest Property:
30000'
4b. Location of Well (State Base Plane Coordinates - NAD 27): 10. KB Elevation above MSL (ft): 57.6' 15. Distance to Nearest Well Open
Surface: x- 677402 y- 5959518 Zone- 4 29.14' to Same Pool: 260'
16. Deviated wells: Kickoff depth: 10562 feet 17. Maximum Potential Pressures in psig (see 20 AAC 25.035)
Maximum Hole Angle: 92 degrees Downhole: Surface:
Hole Casing Weight Grade Coupling Length MD TVD MD TVD
3-1/4" 3-1/2" 9.3#/4.6# 13Cr85 STL/H511 2887' 10190' 8115' 13077' 8769'
x2-3/8"
19.PRESENT WELL CONDITION SUMMARY (To be completed for Redrill and Re-Entry Operations)
Junk (measured):
12938
TVD
29 - 109
28 - 2474
26 - 7769
7663 - 8232
8125 - 8546
8132 - 8763
Hydraulic Fracture planned? Yes No
20. Attachments: Property Plat BOP Sketch Drilling Program Time v. Depth Plot Shallow Hazard Analysis
Diverter Sketch Seabed Report Drilling Fluid Program 20 AAC 25.050 requirements
Contact Name: Ryan Ciolkosz
Sean McLaughlin Contact Email:ryan.ciolkosz@hilcorp.com
Drilling Manager Contact Phone:907-244-4357
Date:
Permit to Drill API Number: Permit Approval
Number: Date:
Conditions of approval : If box is checked, well may not be used to explore for, test, or produce coalbed methane, gas hydrates, or gas contained in shales:
Samples req'd: Yes No Mud log req'd: Yes No
H2S measures: Yes No Directional svy req'd: Yes No
Spacing exception req'd: Yes No Inclination-only svy req'd: Yes No
Post initial injection MIT req'd: Yes No
APPROVED BY
Approved by: COMMISSIONER THE COMMISSION Date:
Comm. Comm. Sr Pet Eng Sr Pet Geo Sr Res Eng
November 1, 2025
Surface 2446 13-3/8" 2400 sx Fondu, 400 sx PF C 28 - 2474
10219 - 12977
21. I hereby certify that the foregoing is true and the procedure approved herein will not be
deviated from without prior written approval.
Intermediate
Perforation Depth TVD (ft):
GL / BF Elevation above MSL (ft):
Perforation Depth MD (ft):
9594
300 sx Permafrost 29 - 109
26 - 96209-5/8" 250 sx Class G, 300 sx PF C
Effect. Depth MD (ft): Effect. Depth TVD (ft):
Authorized Title:
Authorized Signature:
3-1/2" x 3-3/16" x 2-7/8"
9445 - 10385
339 sx Class G
128 sx Class G
Liner
Liner
940
555
2758
Liner
Authorized Name:
10380 - 12920
Conductor 20"80
13250 8755
LengthCasing
10860
Cement Volume MDSize
Plugs (measured):
(including stage data)
177 sx Class G
10860 8638
5120
18. Casing Program: Top - Setting Depth - BottomSpecifications
3318
Total Depth MD (ft): Total Depth TVD (ft):
107205344
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
PERMIT TO DRILL
20 AAC 25.005
2438
765' FSL, 598' FWL, Sec. 23, T11N, R14E, UM, AK
1802' FSL, 2639' FEL, Sec. 23, T11N, R14E, UM, AK
78-084
3801 Centerpoint Dr, Suite 1400, Anchorage, AK 99503
Hilcorp North Slope, LLC
1997' FNL, 1450' FWL, Sec. 22, T11N, R14E, UM, AK ADL 028306 & 028307
PBU 15-11D
PRUDHOE BAY, PRUDHOE OIL
Cement Quantity, c.f. or sacks
Commission Use Only
See cover letter for other
requirements.
8229 - 8768
211 sx Class G
10208 - 107634-1/2"
7"
Form 10-401 Revised 3/2021 This permit is valid for 24 months from the date of approval per 20 AAC 25.005(g)
By Grace Christianson at 4:20 pm, Oct 20, 2025
Digitally signed by Sean
McLaughlin (4311)
DN: cn=Sean McLaughlin (4311)
Date: 2025.10.20 15:17:45 -
08'00'
Sean
McLaughlin
(4311)
*Variance as per 20 AAC 25.112(i): Approved for alternate abandonment plug placement on parent well
contingent upon fully cemented liner on upcoming sidetrack.
J.Lau 10/23/25
10,190'
-TS
50-029-20653-04-00
TS 10/23/25
*Waiver to 20 AAC 25.036 (c)(2)(A)(iv)with compliance to rules in CO 823
*AOGCC Witnessed BOP Test to 3500 psi, Annular 2500 psi minimum.
*Post rig service coil perforating approved for max gun length of 500'.
*Window milling approved on service coil
DSR-10/30/25
225-112 10/31/25
10/31/25
To: Alaska Oil & Gas Conservation Commission
From: Ryan Ciolkosz
Drilling Engineer
Date: October 20, 2025
Re:15-11D Permit to Drill
Approval is requested for drilling a CTD sidetrack lateral from well 15-11C with the Nabors CDR2/CDR3
Coiled Tubing Drilling.
Proposed plan for 15-11D Producer:
See 15-11C Sundry request for complete pre-rig details - Prior to drilling activities, screening will be conducted
to drift for whipstock, dummy GLVs, and MIT. Slickline will pull the KB packer and E-line will set a 3-1/4"
whipstock. Coil will mill window pre-rig. If unable to set the whipstock or mill the window pre-rig, the rig will
perform that work.
A coil tubing drilling sidetrack will be drilled with the Nabors CDR2 or CDR3 rig. The rig will move in and test
BOPE. If unable to pre-rig, the rig will set the 3-1/4" whipstock and mill a dual string 2.74" window + 10' of
formation. The well will kick off drilling in Zone 4 and lands in Ivishak Zone 1. The lateral will continue in Zone 1
to TD. The proposed sidetrack will be completed with a 3-1/2" x 2-3/8 13Cr solid liner, cemented in place and
selectively perforated post rig (will be perforated with rig if unable to post rig). This completion will completely
isolate and abandon the parent Prudhoe Pool perfs.
The following describes the work planned. A wellbore schematic of the current well and proposed sidetrack is
attached for reference.
Pre-Rig Work:
Reference 15-11C Sundry submitted in concert with this request for full details.
1. Slickline : Caliper, Dummy GLVS, Pull LTP Packer
2. E-Line : Set 3-1/4 Whipstock top at 10,562 MD at 260° ROHS
3. Coil : Mill 2.74" Window (3-1/4" x 4-1/2" Dual String). (if window not possible, mill
w/ rig)
4. Valve Shop : Pre-CTD Tree Work
5. Operations : Remove wellhouse and level pad.
Rig Work: (Estimated to start in December 2025)
1. MIRU and test BOPE 250 psi low and 3,500 psi high (MASP 2,438 psi). Give AOGCC 24hr notice
prior to BOPE test.
2. Mill 2.74 Dual String 3-1/4 x 4-1/2 Window (if not already done pre-rig)
3. Drill build section: 3.25" OH, ~258' (30 deg DLS planned).
4. Drill production lateral: 3.25" OH, ~2257' (12 deg DLS planned). Swap to KWF for liner.
5. Run 3-1/2 x 2-3/8 13Cr solid liner with BSELRT
6. Pump primary cement job*: 39 bbls, 15.3 ppg Class G, 1.24 (ft3/sk), TOC at TOL. If high losses are
encountered during cement job and it is deemed necessary, a cement down squeeze from TOL to
loss zone will be performed with the rig or service coil (if performed by service coil see future sundry).
7. Only if not able to do with service coil extended perf post rig Perforate Liner with 1" or 1-1/4" CS
Hydril
8. Freeze protect well to a min 2,200' TVD.
9. Close in tree, RDMO.
Post Rig Work:
1. Valve Shop : Valve & tree work
2. Service Coil : Post rig 500'-1000' EAP - see extended perf procedure attached.
3. Slickline : Set LTP* (if necessary). Set live GLVs.
4. Testing : Portable test separator flowback.
Managed Pressure Drilling:
Managed pressure drilling techniques will be employed on this well. The intent is to provide constant bottom hole
pressure by using minimum 8.4 ppg drilling fluid in combination with annular friction losses and applied surface
pressure. Constant BHP will be utilized to reduce pressure fluctuations to help with hole stability. Applying
annular friction and choke pressure also allow use of lighter drilling fluid and minimizes fluid losses and/or
fracturing at the end of the long well bores. A MPD choke for regulating surface pressure and is independent of
the WC choke.
Deployment of the BHA under trapped wellhead pressure may be necessary. Pressure deployment of the BHA
will be accomplished utilizing BHA pipe/slip rams (see attached BOP configurations). The annular preventer will
act as a secondary containment during deployment and not as a stripper.
Operating parameters and fluid densities will be adjusted based on real-time bottom hole pressure measurements
while drilling and shale behavior. The following scenario is expected:
MPD Pressure at the Planned Window (10562' MD -8,364' TVD)
Pumps On Pumps O
A Target BHP at Window (ppg)4,262 psi 4,262 psi
9.8
B -634 psi 0 psi
0.09
C 3,740 psi 3,740 psi
8.6
B+C Mud + ECD Combined 4,374 psi 3,740 psi
(no choke pressure)
A-(B+C)Choke Pressure Required to Maintain -112 psi 522 psi
Target BHP at window and deeper
Operation Details:
Reservoir Pressure:
The estimated reservoir pressure is expected to be 3,318 psi at 8,800 TVD. (7.2 ppg equivalent).
Maximum expected surface pressure with gas (0.10 psi/ft) to surface is 2,438 psi (from estimated
reservoir pressure).
Mud Program:
Drilling: Minimum MW of 8.4 ppg KCL with viscosifier for drilling. Managed pressure used to maintain
constant BHP.
Disposal:
All Class l & II non-hazardous and RCRA-exempt drilling and completion fluids will go to GNI at DS 4.
Fluids >1% hydrocarbons or flammables must go to GNI.
Fluids >15% solids by volume must go to GNI.
Fluids with solids that will not pass through 1/4 screen must go to GNI.
Fluids with PH >11 must go to GNI.
Hole Size:
3.25 hole for the entirety of the production hole section.
Liner Program:
3-1/2", 9.3#, 13Cr Solid: 10,190' MD 10,220' MD (30' liner)
2-3/8", 4.6#, 13Cr Solid: 10,220' MD 13,077' MD (2,857' liner)
The primary barrier for this operation: Kill Weight Fluid to provide overbalance as necessary.
A X-over shall be made up to a safety joint including a TIW valve for all tubulars ran in hole.
Jointed Pipe Work String Program:
1-1/4" CS Hydril, 3.02#, P-110: up to 4,000' MD
1 CS Hydril, 2.25#, P-110: up to 4,000' MD
Used for contingency CTD liner cleanout/logging runs, deployment of perforation guns (if performed by
rig), inner string 2-3/8 liner cement jobs and contingency inner string 2-7/8 liner cement jobs.
Well Control:
BOP diagram is attached. MPD and pressure deployment is planned.
Pipe rams, blind rams and the CT pack off will be pressure tested to 250 psi and to 3,500 psi.
The annular preventer will be tested to 250 psi and 2,500 psi.
1.5 wellbore volumes of KWF will be on location at all times during drilling operations.
A X-over shall be available to be made up to a safety joint, with the same OD as coiled tubing, including a
TIW valve for all tubulars ran in hole.
The safety joint will be utilized while running solid/slotted liner, perforation guns and CS Hydril jointed
pipe. The desire is to keep the same standing orders for the entire liner run and not change shut in
techniques from well to well (run safety joint with pre-installed TIW valve). When closing on a safety joint,
2 sets of pipe/slip rams will be available, above and below the flow cross providing better well control
option.
CO823 Hilcorp CTD Qualification Blind-Shear Test: CDR2 test on 09/04/2025 (see Hilcorp Alaska CTD
CO823 Qualification report previously sent to AOGCC for more information).
CO823 Safety Joint Drills: Provide AOGCC opportunity to witness once per well that a CTD liner is
ran.
Directional:
Directional plan attached. Maximum planned hole angle is 92°. Inclination at kick off point is 30°.
Magnetic and inclination surveys will be taken every 30 ft. No gyro will be run.
Distance to nearest property line 30,000
Distance to nearest well within pool 260
Logging:
MWD directional, Gamma Ray and Resistivity will be run through the entire open hole section.
Real time bore pressure to aid in MPD and ECD management.
Perforating:
500-1000' perforated post rig See attached extended perforating procedure.
1.56" Perf Guns at 6 spf
If post rig extended perforating with service coil is not an option, the well will be perforated with the rig or
post rig under this PTD.
The well will be perforated between the CTD whipstock and TD of the newly drilled CTD well, completely
in the Prudhoe Pool.
Formations: Top of Prudhoe Pool 10,363 MD in the parent
Anti-Collision Failures:
All Wells Pass AC scan
Hazards:
DS 15 is not an H2S pad. The last H2S reading on 15-11C: 10 ppm on 9/12/2025.
Max H2S recorded on DS/Pad: 69 ppm.
0 fault crossings expected.
Low lost circulation risk.
Ryan Ciolkosz CC: Well File
Drilling Engineer Joseph Lastufka
(907-244-4357)
Pre-Rig Service Coil Window Milling
The approved sundry and permit to drill will be posted in the Operations Cabin of the unit during the
entire window milling operation.
Notes for window milling:
Window milling with service CTU operations will fully comply with 20 AAC 25.286(d)(3), including the use
of pressure control equipment, all BHAs fully lubricated and at no point will any BHA be open-hole
deployed.
Window Milling Procedure:
1. Kill well with 1% KCL if necessary. Well may already be killed from previous operations.
2. MU and RIH with window milling assembly Window mill followed by string reamer.
NOTE: Confirm milling BHA configuration prior to job execution due to variations in different service
providers window milling BHAs.
3. RIH & TAG whipstock pinch point, calculate distance till string reamer is out of the window, paint coil flag
and note in WSR.
4. Mill window per vendor procedure. Make note of any WHP changes while milling window in the WSR.
5. Make multiple reciprocating passes through the kickoff point to dress liner exit and eliminate all burs.
Perform gel sweeps as necessary to keep window clean.
Maximum approved distance to reciprocate beyond the window is 15 ft to ensure confidence the window
is prepared for the sidetrack.DO NOT RECIPROCATE DEEPER than 15 ft.
6. Confirm exited liner & string reamer dressed entire window with coil flag and note bottom of window and
total milled depth in WSR.
7. FP well to 2,500 TVD with 60/40 MeOH while POOH.
8. Once on surface inspect BHA, measure OD of mill and string reamer & document in WSR.
9. RDMO
10. Communicate to Operations to tag wing valve Do Not POP.
Pre-Rig Service Coil Window Milling BOP Diagram
Post-Rig Service Coil Perforating Procedure:
Coiled Tubing
Notes:
Due to the necessary open hole deployment of Extended Perforating jobs, 24-hour crew and WSS
coverage is required.
Note: The well will be killed and monitored before making up the initial perfs guns. This will provide
guidance as to whether the well will be killed by bullheading or circulating bottoms up throughout the
job. If pressure is seen immediately after perforating, it will either be killed by bullheading while POOH
or circulating bottoms up through the same port that opened to shear the firing head.
Coil Tubing
1. MIRU Coiled Tubing Unit and spot ancillary equipment.
2. MU nozzle drift BHA (include SCMT and/or RPM log as needed).
3. RIH to PBTD.
a. Displace well with weighted brine while RIH (minimum 8.4 ppg to be overbalanced).
4. POOH (and RPM log if needed) and lay down BHA.
5. After MU MHA and pull testing the CTC, tag-up on the CT stripper to ensure BHA cannot pull through
the brass upon POOH with guns.
6. There will be no perforations to bullhead kill the well. Well will already be loaded w/ weighted brine or KCl
per previous steps. Re-load well at WSS discretion.
7. At surface, prepare for deployment of TCP guns.
8.Confirm well is dead. Bleed any pressure off to return tank. Kill well w/ KWF, weighted brine as needed
(minimum 8.4 ppg). Maintain continuous hole fill taking returns to tank until lubricator connection is
reestablished. Fluids man-watch must be performed while deploying perf guns to ensure the well
remains killed and there is no excess flow.
9.Pickup safety joint and TIW valve and space out before MU guns.Review well control steps with crew
prior to breaking lubricator connection and commencing makeup of TCP gun string. Once the safety joint
and TIW valve have been spaced out, keep the safety joint/TIW valve readily accessible near the working
platform for quick deployment if necessary.
10. Break lubricator connection at QTS and begin makeup of TCP guns and blanks per schedule below.Max
BHA length per PTD is 500ft. Fluids man-watch must be performed while deploying perf guns to ensure
the well remains killed and there is no excess flow.
a. Perforation details
i.Perf Interval:The well will be perforated between the CTD whipstock and TD of the
newly drilled CTD well, completely in the Prudhoe pool.
ii.Perf Length:500
iii.Gun Length:500
iv.Weight of Guns (lbs):2300lbs (4.6ppf)
11. MU lubricator and RIH with perf gun and tie-in to coil flag correlation. Pickup and perforate perforation
intervals (TBD). POOH.
a. Note any tubing pressure change in WSR.
12. After perforating, PUH to top of liner or into tubing tail to ensure debris doesnt fall in on the guns and
stick the BHA.Confirm well is dead and re-kill if necessary before pulling to surface.
13. Pump pipe displacement while POOH.Stop at surface to reconfirm well dead and hole full.
14. Review well control steps with crew prior to breaking lubricator connection and commencing breakdown of
TCP gun string. Standing orders flow chart included with this sundry request. Ensure safety joint and TIW
valve assembly are on-hand before breaking off lubricator to LD gun BHA.
15. Freeze protect well to 2,000 TVD.
16. RDMO CTU.
Coiled Tubing BOPs
Standing Orders for Open Hole Well Control during Perf Gun Deployment
Equipment Layout Diagram
Type text here
Map Date: 10/2/2025
True Vertical Depth (400 usft/in)3200
3400
3600
3800
4000
4200
4400
4600
4800
5000
5200
5400
5600
5800
6000
6200
6400
6600
6800
7000
South(-)/North(+) (1000 usft/in)4000
4500
5000
5500
6000
6500
7000
7500
Well Date
Quick Test Sub to Otis -
Top of 7" Otis 0.0 ft
Distances from top of riser
Excluding quick-test sub
Top of Annular
CL Annular
Bottom Annular
CL Blind/Shears
CL Coiled Tubing Pipe / Slips
Kill Line Choke Line
CL BHA Pipe / Slip
CL Coiled Tubing Pipe / Slips
TV1 TV2
T1 T2
Flow Tee
Master
Master
LDS
IA
OA
LDS
Ground Level
CDR#-AC BOP Schematic
CDR Rig's Drip Pan
Fill Line
Normally Disconnected
HP hose
to Micromotion
LP hose open ended
to Flowline (optional)
Hydril 7 1/16"
Annular
Blind/Shear
CT Pipe/Slips
2 3/8" Pipe/Slips
2 3/8" Pipe/Slips
7-1/16"
5k Mud
Cross
CT Pipe/Slips
BHA Pipe / Slips
nneeeeeceeeeeeeeeeeeeeeeeeeeeeeeeeeee
Revised 7/2022
TRANSMITTAL LETTER CHECKLIST
WELL NAME: ______________________________________
PTD: _____________________________________________
___ Development ___ Service ___ Exploratory ___ Stratigraphic Test ___ Non-Conventional
FIELD: __________________________ POOL: ____________________________________
Check Box for Appropriate Letter / Paragraphs to be Included in Transmittal Letter
CHECK OPTIONS TEXT FOR APPROVAL LETTER
MULTI
LATERAL
(If last two digits
in API number are
between 60-69)
The permit is for a new wellbore segment of existing well Permit
Number _____________, API Number 50-______________________.
Production from or injection into this wellbore must be reported under
the original API Number stated above.
Spacing
Exception
The permit is approved subject to full compliance with 20 AAC 25.055.
Approval to produce or inject is contingent upon issuance of a
conservation order approving a spacing exception. The Operator
assumes the liability of any protest to the spacing exception that may
occur.
Dry Ditch Sample
All dry ditch sample sets submitted to the AOGCC must be in no greater
than 30-foot sample intervals from below the permafrost or from where
samples are first caught and 10-foot sample intervals through target
zones.
Non-
Conventional
Well
Please note the following special condition of this permit: Production or
production testing of coal bed methane is not allowed for this well until
after the Operator has designed and implemented a water-well testing
program to provide baseline data on water quality and quantity. The
Operator must contact the AOGCC to obtain advance approval of such
a water-well testing program.
Well Logging
Requirements
Regulation 20 AAC 25.071(a) authorizes the AOGCC to specify types
of well logs to be run. In addition to the well logging program proposed
by the Operator in the attached application, the following well logs are
also required for this well:
Per Statute AS 31.05.030(d)(2)(B) and Regulation 20 AAC 25.071,
composite curves for all well logs run must be submitted to the AOGCC
within 90 days after completion, suspension, or abandonment of this
well, or within 90 days of acquisition of the data, whichever occurs first.
PRUDHOE OILPRUDHOE BAY
PBU 15-11D
225-112
WELL PERMIT CHECKLISTCompanyHilcorp North Slope, LLCWell Name:PRUDHOE BAY UNIT 15-11DInitial Class/TypeDEV / PENDGeoArea890Unit11650On/Off ShoreOnProgramDEVWell bore segAnnular DisposalPTD#:2251120Field & Pool:PRUDHOE BAY, PRUDHOE OIL - 640150NA1 Permit fee attachedYes ADL028306, ADL0283072 Lease number appropriateYes3 Unique well name and numberYes PRUDHOE BAY, PRUDHOE OIL - 640150 - governed by CO 341J4 Well located in a defined poolYes5 Well located proper distance from drilling unit boundaryNA6 Well located proper distance from other wellsYes7 Sufficient acreage available in drilling unitYes8 If deviated, is wellbore plat includedYes9 Operator only affected partyYes10 Operator has appropriate bond in forceYes11 Permit can be issued without conservation orderYes12 Permit can be issued without administrative approvalYes13 Can permit be approved before 15-day waitNA14 Well located within area and strata authorized by Injection Order # (put IO# in comments) (For NA15 All wells within 1/4 mile area of review identified (For service well only)NA16 Pre-produced injector: duration of pre-production less than 3 months (For service well only)NA17 Nonconven. gas conforms to AS31.05.030(j.1.A),(j.2.A-D)Yes18 Conductor string providedYes19 Surface casing protects all known USDWsYes20 CMT vol adequate to circulate on conductor & surf csgYes21 CMT vol adequate to tie-in long string to surf csgYes22 CMT will cover all known productive horizonsYes23 Casing designs adequate for C, T, B & permafrostYes24 Adequate tankage or reserve pitYes *Variance as per 20 AAC 25.112(i): Approved for alternate abandonment plug w/ fully cemented liner.25 If a re-drill, has a 10-403 for abandonment been approvedYes26 Adequate wellbore separation proposedNA27 If diverter required, does it meet regulationsYes28 Drilling fluid program schematic & equip list adequateYes *Waiver to 20 AAC 25.036 (c)(2)(A)(iv) with compliance to rules in CO 823.29 BOPEs, do they meet regulationYes 5K30 BOPE press rating appropriate; test to (put psig in comments)Yes31 Choke manifold complies w/API RP-53 (May 84)Yes32 Work will occur without operation shutdownYes33 Is presence of H2S gas probableNA The last H2S reading on 15-11C: 10 ppm on 9/12/2025.34 Mechanical condition of wells within AOR verified (For service well only)No DS 15 wells are H2S-bearing. H2S measures are required.35 Permit can be issued w/o hydrogen sulfide measuresYes Expected pressure range is 0.374 psi/ft (7.2 ppg EMW), MPD to be utilized.36 Data presented on potential overpressure zonesNA37 Seismic analysis of shallow gas zonesNA38 Seabed condition survey (if off-shore)NA39 Contact name/phone for weekly progress reports [exploratory only]ApprTCSDate10/22/2025ApprJJLDate10/23/2025ApprTCSDate10/22/2025AdministrationEngineeringGeologyGeologic Commissioner:Date:Engineering Commissioner:DatePublic CommissionerDateJLC 10/31/2025