Department of Commerce, Community, and Economic Development
Alaska Oil and Gas Conservation Commission
Loading...
HomeMy WebLinkAboutO 1421. December 18, 2017
2. December 19, 2017
3. March 15, 2018
4.
March 20, 2018
5.
March 15, 2018
6.
April 5, 2018
7.
-------------------
8.
July 16, 2018
9.
August 5, 2018
10. October 24, 2018
11. October 31, 2018
12. January 14, 2019
13. January 15, 2019
14. February 28, 2019
OTHER ORDER 142
Docket Number: OTH-17-056
Ltr from Glacier regarding tubing/annular communication
of RU -3A
Email from AOGCC to Glacier
NOV to Glacier for failure to complete a MIT and failure to
report a pressure communication
Glacier's request for an Informal Review
AOGCC ltr setting Informal Review
Glacier's Informal Review documentation
Ltr and email regarding informal hearing date
CIE Request for reconsideration of Other Order No. 142
Notice of hearing, affidavit of publication, email
distribution, mailings
Transcript and sign -in sheet
CIE's supplemental information request by Commission
Foerster during formal hearing on request for
reconsideration of Other Order 142
CIE request for extension of time
AOGCC letter granting extension of time
CIE response to Other Order 142
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
333 West Seventh Avenue
Anchorage Alaska 99501
Re: Failure to report to AOGCC a pressure communication ) Other Order No. 142 Final
Failure to complete required Mechanical Integrity Test ) Docket OTH-17-056
Redoubt Unit 3A (PTD 2161700) ) December 26, 2018
Area Injection Order (AIO) 32 )
Redoubt Shoal Field, Osprey Platform, )
Redoubt Shoal Unit (RSU) )
DECISION AND ORDER ON RECONSIDERATION
On March 15, 2018, the Alaska Oil and Gas Conservation Commission (AOGCC or Commission)
issued a Notice of Proposed Enforcement Action (Notice) to Cook Inlet Energy, LLC (CIE)
regarding the Redoubt Unit 3A (RU 3A) well. CIE failed to report to AOGCC a pressure
communication and failed to complete the required Mechanical Integrity Test (MIT) in RU 3A.
The Notice proposed specific corrective actions and a $50,000 civil penalty under AS
31.05.150(a). CIE requested an informal review. That review was held April 10, 2018.
After the informal review, Other Order 142 (Order) was issued. On July 16, 2018, CIE requested
reconsideration and oral argument on the Order. AOGCC granted reconsideration. A hearing was
held October 24, 2018. The record was left open pending CIE submission of answers to questions
posed during the hearing. CIE submitted the supplemental information on October 31, 2018.
Summary of Proposed Enforcement Action:
The Notice identified violations by CIE of:
(1) 20 AAC 25.402 (f) and the provisions of Rule 8 of AIO 32 requiring CIE to notify
AOGCC and submit a plan of corrective action when pressure communication,
leakage or lack of injection zone isolation is indicated in RU 3A; and
(2) Rule 6 of AIO 32 requiring CIE to perform an AOGCC witnessed Mechanical
Integrity Test once RU 3A commenced injection for the first time.
Other Order 142 Final
December 26, 2018
Page 2 of 6
The Notice proposed civil penalties of $50,000 as follows:
- $25,000 for the initial violation — failure to notify AOGCC of indication of pressure
communication or leakage in RU 3A as specified in Rule 8 of AIO 32 and AOGCC
regulation 20 AAC 25.402 (f); and
- $25,000 for the initial violation — failure to perform the required MIT of the injection
well in compliance with testing protocols specified in Rule 6 of AIO 32.
The Notice also proposed five actions for CIE to review its regulatory compliance program and
analyze the violations for causes and corrective actions.
Violation - Failure to Report a Pressure Communication or Leakage:
By letter dated December 18, 2017 CIE notified AOGCC that the well was exhibiting potential
tubing (T) by inner annulus (IA) pressure communication while injecting water. In its letter CIE
provided a 30 -day injection pressure plot. CIE reported that after approximately 78 days of
injection the IA pressure began to rise and the field staff bled it down numerous times to keep it
below 200 psi. To confirm the communication, CIE let the pressure build to 1008 psi over 79
days, bled down the pressure, and again let the IA pressure build gradually to 590 psi before
another bleed on December 18, 2017. CIE ultimately notified AOGCC of this pressure
communication via the letter to AOGCC dated December 18, 2017 (received by AOGCC on
December 19, 2017) in which CIE requested to continue water injection.
AOGCC regulations require notification by the next working day if an injection rate, operating
pressure observation, or pressure test indicates pressure communication or leakage in any casing,
tubing, or packer.
Rule 8 of AIO 32 states "Whenever any pressure communication, leakage or lack of injection zone
isolation is indicated by injection rate, operating pressure observation, test, survey, log, or other
evidence, the Operator shall notify the Commission by the next business day and submit a plan of
corrective action (on Form 10-403) for Commission approval. The Operator shall immediately
shut in the well if continued operation would be unsafe, would threaten contamination of
freshwater, or if so directed by the Commission. Monthly reports of daily tubing and casing annuli
Other Order 142 Final
December 26, 2018
Page 3 of 6
pressures and injection rates must be provided to the Commission for all injection wells indicating
well integrity failure or lack of injection zone isolation."
On December 19, 2017 CIE provided pressure and injection data (pdf format) for RU 3A from
June 2, 2017 onwards. CIE's only notice to AOGCC of potential pressure communication
occurred via the December 18, 2017 letter. Information provided by CIE demonstrates significant
pressure anomalies which were not communicated to the AOGCC. Significant IA pressure
increases occurred including the two pressure build up tests: approximately August 18, 2017 to
November 5, 2017 (maximum observed pressure was 1008 psi), and November 5, 2017 to
December 18, 2017 (maximum observed pressure was 590 psi). There is no evidence to suggest
the rate of pressure build was subsiding.
CIE failed to report to AOGCC pressure communication indicating a potential loss of mechanical
integrity on RU 3A by the next working day, a violation of both the regulations and Rule 8.
Violation - Failure to Perform the Required MIT. Demonstration of Tubim/Casing Annulus
Mechanical Integrity:
A review of the well information provided by CIE shows RU 3A was handed over to injection
operations on May 30, 2017, with injection allocated to the well continuously beginning July 1,
2017. Review of the well history demonstrates RU 3A was operating without having passed an
AOGCC-witnessed post-injection MIT. Rule 6 of AIO 32 states "The mechanical integrity of an
injection well must be demonstrated before injection begins, and before returning a well to service
following a workover affecting mechanical integrity. A Commission -witnessed mechanical
integrity test must be performed after injection is commenced for the first time in a well, to be
scheduled when injection conditions (temperature, pressure, rate, etc.) have stabilized. Subsequent
tests must be performed at least once every four years thereafter." In addition to the MIT
requirement in AIO 32, approval of the Permit to Drill for RU 3A was conditioned on a
requirement of a post -initial -injection MIT. CIE operated RU 3A approximately six months
without the required MIT. CIE was notified on December 20, 2017 that RU 3A must pass an
AOGCC-witnessed MIT to continue on injection. A successful MIT was completed December
23, 2017.
Other Order 142 Final
December 26, 2018
Page 4 of 6
Based on information provided by CIE — including the passing MIT on December 23, 2017 —
AOGCC determined that water injection could safely continue if CIE complied with the restrictive
conditions set out in an administrative approval dated December 28, 2017. Approval conditions
included monthly reporting of well pressures, injection rates, and pressure bleeds; installation and
testing of automatic well shut-in equipment linked to the wells inner annulus pressure; and a more
frequent MIT schedule.
CIE failed to complete the AOGCC-witnessed MIT after injection was commenced for the first
time in RU 3A, a violation of Rule 6 of AIO 32.
The Factors Considered in Imposing the Fines. Includin¢ Mitigating Circumstances:
The factors in AS 31.05.150(g) were considered in determining the appropriate penalty. CIE's
four-month delay in reporting significant continuous repressurization events raised possible
serious and substantial issues with the integrity of the RU 3A wellbore. Although no injury to the
public occurred, the potential wellbore failure posed an obvious threat to both public health and
the environment. These violations, which relate to Underground Injection Control Class II well
integrity practices, warrant the imposition of civil penalties. Both of these violations demonstrate
either disregard for or ignorance of CIE's compliance responsibilities. In tum, CIE's failure to
comply with fundamental wellbore mechanical integrity testing requirements raises the potential
for similar behavior with more serious consequences. Mitigating circumstances considered in the
assessment of the proposed civil penalty include the absence of known sources of freshwater in
the Redoubt Unit, as well as the fact that once notified of the violations, CIE demonstrated urgency
in completion of the required MIT and in the installation and testing of the required automatic well
shut-in equipment prerequisite to continued injection in the well.
Findings and Conclusions After Reconsideration:
At the hearing on reconsideration CIE admitted the violations. CIE's arguments — that the penalties
imposed are excessive — were based on a reiteration of its position during informal review: that it
had notified AOGCC as soon as it was satisfied there was a pressure communication and that the
well ultimately passed an MIT.
Other Order 142 Final
December 26, 2018
Page 5 of 6
AOGCC does not agree. CIE was required to notify AOGCC of any indication of a pressure
communication. CIE had that indication four months before it notified AOGCC. CIE's
justification of its delay — essentially that it has no obligation to report until it has satisfied itself
that there is in fact pressure communication — is directly contrary to the language of the
requirement. The fact CIE conducted testing establishes that CIE viewed the circumstances as an
indication of pressure communication. Likewise, the well ultimately passing an MIT does not
mitigate the fact CIE ignored the requirement to conduct the MIT. CIE has presented nothing
which would warrant changing the findings or penalties in the order.
The AOGCC finds that CIE violated 20 AAC 25.402 (f) and the Rules in AIO 32 governing the
Demonstration of Tubing/Casing Annulus Mechanical Integrity and Well Integrity Failure. The
factors set forth in AS 31.05.150(g), including mitigating circumstances were considered. CIE's
commitment to an increased level of oversight as well as review of established training and process
protocols for employees governing injection operations is satisfactory to help prevent further
occurrence of these violations. However, the violations committed by CIE were neither trivial nor
technical. Neither violation can be characterized as an unintended consequence of good faith
attempt at compliance with AOGCC's orders and regulations. AOGCC's assessment as to the
appropriate civil penalties is unchanged.
Now Therefore It Is Ordered That:
CIE is assessed a civil penalty in the amount of $50,000 for violating Rule 6 of AIO 32, Rule 8 of
AIO 32, and 20 AAC 25.402(f), assessed at $25,000 for each violation. If CIE chooses not to
appeal this Order the fine must be paid within 30 days of issuance. If appealed, the fine will be
held in abeyance until the appeal process is complete.
In addition to the civil penalty, within four weeks of the date of the AOGCC's final decision, CIE
shall:
(1) Provide a detailed description of its Underground Injection Control (UIC) regulatory
compliance program;
(2) Provide details of its tracking system for determining when MIT's are required, including
the details of contingencies for wells shut in at the time an MIT is due and its procedures
for notification to the AOGCC, as well as its processes for determining the MIT due date
and identification of past due wells;
Other Order 142 Final
December 26, 2018
Page 6 of 6
(3) Provide a detailed description of its (non-UIC) AOGCC regulatory compliance program,
including its tracking system for determining when compliance requirements are due (e.g.
safety valve testing, custody transfer meter testing, monthly and annual reports etc.);
(4) Provide a Root Cause Analysis addressing the failure to provide a notification of a pressure
communication to AOGCC within the next business day; and
(5) Provide a Root Cause Analysis addressing the failure to complete an AOGCC witnessed
MIT once the well commenced injection and stabilization was achieved.
As an Operator involved in an enforcement action, CIE is required to preserve documents
concerning the above action until after resolution of the proceeding.
Done at Anchorage, Alaska and Dated December 26, 2018.
HoPlisS. French 4CaP. Foerster
Chair, Commissioner Commissioner
cc: Ryan Gross, EPA Region 10
AOGCC Inspectors
APPEAL NOTICE
This order or decision and denial of reconsideration are FINAL and may be appealed to superior court. The appeal
MUST be filed within 33 days after the date on which the AOGCC mails, OR 30 days if the AOGCC otherwise
distributes, this order and decision denying reconsideration.
In computing a period of time above, the date of the event or default after which the designated period begins to run is
not included in the period; the last day of the period is included, unless it falls on a weekend or state holiday, in which
event the period runs until 5:00 p.m. on the next day that does not fall on a weekend or state holiday.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
333 West Seventh Avenue
Anchorage Alaska 99501
Re: Failure to report to AOGCC a pressure communication ) Other Order No. 142 Final
Failure to complete required Mechanical Integrity Test ) Docket OT 4-17-056
Redoubt Unit 3A (PTD 2161700) ) December 26, 2018
Area Injection Order (AIO) 32 )
Redoubt Shoal Field, Osprey Platform, )
Redoubt Shoal Unit (RSU) )
DECISION AND ORDER ON RECONSIDERATION
On March 15, 2018, the Alaska Oil and Gas Conservation Commission (AOGCC or Commission)
issued a Notice of Proposed Enforcement Action (Notice) to Cook Inlet Energy, LLC (CIE)
regarding the Redoubt Unit 3A (RU 3A) well. CIE failed to report to AOGCC a pressure
communication and failed to complete the required Mechanical Integrity Test (MIT) in RU 3A.
The Notice proposed specific corrective actions and a $50,000 civil penalty under AS
31.05.150(a). CIE requested an informal review. That review was held April 10, 2018.
After the informal review, Other Order 142 (Order) was issued. On July 16, 2018, CIE requested
reconsideration and oral argument on the Order. AOGCC granted reconsideration. A hearing was
held October 24, 2018. The record was left open pending CIE submission of answers to questions
posed during the hearing. CIE submitted the supplemental information on October 31, 2018.
Summary of Proposed Enforcement Action:
The Notice identified violations by CIE of:
(1) 20 AAC 25.402 (f) and the provisions of Rule 8 of AIO 32 requiring CIE to notify
AOGCC and submit a plan of corrective action when pressure communication,
leakage or lack of injection zone isolation is indicated in RU 3A; and
(2) Rule 6 of AIO 32 requiring CIE to perform an AOGCC witnessed Mechanical
Integrity Test once RU 3A commenced injection for the first time.
Other Order 142 Final
December 26, 2018
Page 2 of 6
The Notice proposed civil penalties of $50,000 as follows:
- $25,000 for the initial violation — failure to notify AOGCC of indication of pressure
communication or leakage in RU 3A as specified in Rule 8 of AIO 32 and AOGCC
regulation 20 AAC 25.402 (f); and
- $25,000 for the initial violation — failure to perform the required MIT of the injection
well in compliance with testing protocols specified in Rule 6 of AIO 32.
The Notice also proposed five actions for CIE to review its regulatory compliance program and
analyze the violations for causes and corrective actions.
Violation - Failure to Report a Pressure Communication or Leakage:
By letter dated December 18, 2017 CIE notified AOGCC that the well was exhibiting potential
tubing (T) by inner annulus (IA) pressure communication while injecting water. In its letter CIE
provided a 30 -day injection pressure plot. CIE reported that after approximately 78 days of
injection the IA pressure began to rise and the field staff bled it down numerous times to keep it
below 200 psi. To confirm the communication, CIE let the pressure build to 1008 psi over 79
days, bled down the pressure, and again let the IA pressure build gradually to 590 psi before
another bleed on December 18, 2017. CIE ultimately notified AOGCC of this pressure
communication via the letter to AOGCC dated December 18, 2017 (received by AOGCC on
December 19, 2017) in which CIE requested to continue water injection.
AOGCC regulations require notification by the next working day if an injection rate, operating
pressure observation, or pressure test indicates pressure communication or leakage in any casing,
tubing, or packer.
Rule 8 of AIO 32 states "Whenever any pressure communication, leakage or lack of injection zone
isolation is indicated by injection rate, operating pressure observation, test, survey, log, or other
evidence, the Operator shall notify the Commission by the next business day and submit a plan of
corrective action (on Form 10-403) for Commission approval. The Operator shall immediately
shut in the well if continued operation would be unsafe, would threaten contamination of
freshwater, or if so directed by the Commission. Monthly reports of daily tubing and casing annuli
Other Order 142 Final
December 26, 2018
Page 3 of 6
pressures and injection rates must be provided to the Commission for all injection wells indicating
well integrity failure or lack of injection zone isolation."
On December 19, 2017 CIE provided pressure and injection data (pdf format) for RU 3A from
June 2, 2017 onwards. CIE's only notice to AOGCC of potential pressure communication
occurred via the December 18, 2017 letter. Information provided by CIE demonstrates significant
pressure anomalies which were not communicated to the AOGCC. Significant IA pressure
increases occurred including the two pressure build up tests: approximately August 18, 2017 to
November 5, 2017 (maximum observed pressure was 1008 psi), and November 5, 2017 to
December 18, 2017 (maximum observed pressure was 590 psi). There is no evidence to suggest
the rate of pressure build was subsiding.
CIE failed to report to AOGCC pressure communication indicating a potential loss of mechanical
integrity on RU 3A by the next working day, a violation of both the regulations and Rule 8.
Violation - Failure to Perform the Required MIT. Demonstration of Tubine/Casine Annulus
Mechanical Inteerity:
A review of the well information provided by CIE shows RU 3A was handed over to injection
operations on May 30, 2017, with injection allocated to the well continuously beginning July 1,
2017. Review of the well history demonstrates RU 3A was operating without having passed an
AOGCC-witnessed post-injection MIT. Rule 6 of AIO 32 states "The mechanical integrity of an
injection well must be demonstrated before injection begins, and before returning a well to service
following a workover affecting mechanical integrity. A Commission -witnessed mechanical
integrity test must be performed after injection is commenced for the first time in a well, to be
scheduled when injection conditions (temperature, pressure, rate, etc.) have stabilized. Subsequent
tests must be performed at least once every four years thereafter." In addition to the MIT
requirement in AIO 32, approval of the Permit to Drill for RU 3A was conditioned on a
requirement of a post -initial -injection MIT. CIE operated RU 3A approximately six months
without the required MIT. CIE was notified on December 20, 2017 that RU 3A must pass an
AOGCC-witnessed MIT to continue on injection. A successful MIT was completed December
23, 2017.
Other Order 142 Final
December 26, 2018
Page 4 of 6
Based on information provided by CIE — including the passing MIT on December 23, 2017 —
AOGCC determined that water injection could safely continue if CIE complied with the restrictive
conditions set out in an administrative approval dated December 28, 2017. Approval conditions
included monthly reporting of well pressures, injection rates, and pressure bleeds; installation and
testing of automatic well shut-in equipment linked to the wells inner annulus pressure; and a more
frequent MIT schedule.
CIE failed to complete the AOGCC-witnessed MIT after injection was commenced for the first
time in RU 3A, a violation of Rule 6 of AIO 32.
The Factors Considered in Imoosine the Fines. Including Mitigating Circumstances:
The factors in AS 31.05.150(g) were considered in determining the appropriate penalty. CIE's
four-month delay in reporting significant continuous repressurization events raised possible
serious and substantial issues with the integrity of the RU 3A wellbore. Although no injury to the
public occurred, the potential wellbore failure posed an obvious threat to both public health and
the environment. These violations, which relate to Underground Injection Control Class II well
integrity practices, warrant the imposition of civil penalties. Both of these violations demonstrate
either disregard for or ignorance of CIE's compliance responsibilities. In turn, CIE's failure to
comply with fundamental wellbore mechanical integrity testing requirements raises the potential
for similar behavior with more serious consequences. Mitigating circumstances considered in the
assessment of the proposed civil penalty include the absence of known sources of freshwater in
the Redoubt Unit, as well as the fact that once notified of the violations, CIE demonstrated urgency
in completion of the required MIT and in the installation and testing of the required automatic well
shut-in equipment prerequisite to continued injection in the well.
Findings and Conclusions After Reconsideration:
At the hearing on reconsideration CIE admitted the violations. CIE's arguments —that the penalties
imposed are excessive — were based on a reiteration of its position during informal review: that it
had notified AOGCC as soon as it was satisfied there was a pressure communication and that the
well ultimately passed an MIT.
Other Order 142 Final
December 26, 2018
Page 5 of 6
AOGCC does not agree. CIE was required to notify AOGCC of any indication of a pressure
communication. CIE had that indication four months before it notified AOGCC. CIE's
justification of its delay — essentially that it has no obligation to report until it has satisfied itself
that there is in fact pressure communication — is directly contrary to the language of the
requirement. The fact CIE conducted testing establishes that CIE viewed the circumstances as an
indication of pressure communication. Likewise, the well ultimately passing an MIT does not
mitigate the fact CIE ignored the requirement to conduct the MIT. CIE has presented nothing
which would warrant changing the findings or penalties in the order.
The AOGCC finds that CIE violated 20 AAC 25.402 (f) and the Rules in AIO 32 governing the
Demonstration of Tubing/Casing Annulus Mechanical Integrity and Well Integrity Failure. The
factors set forth in AS 31.05.150(g), including mitigating circumstances were considered. CIE's
commitment to an increased level of oversight as well as review of established training and process
protocols for employees governing injection operations is satisfactory to help prevent further
occurrence of these violations. However, the violations committed by CIE were neither trivial nor
technical. Neither violation can be characterized as an unintended consequence of good faith
attempt at compliance with AOGCC's orders and regulations. AOGCC's assessment as to the
appropriate civil penalties is unchanged.
Now Therefore It Is Ordered That:
CIE is assessed a civil penalty in the amount of $50,000 for violating Rule 6 of AIO 32, Rule 8 of
AIO 32, and 20 AAC 25.402(1), assessed at $25,000 for each violation. If CIE chooses not to
appeal this Order the fine must be paid within 30 days of issuance. If appealed, the fine will be
held in abeyance until the appeal process is complete.
In addition to the civil penalty, within four weeks of the date of the AOGCC's final decision, CIE
shall:
(1) Provide a detailed description of its Underground Injection Control (UIC) regulatory
compliance program;
(2) Provide details of its tracking system for determining when MIT's are required, including
the details of contingencies for wells shut in at the time an MIT is due and its procedures
for notification to the AOGCC, as well as its processes for determining the MIT due date
and identification of past due wells;
Other Order 142 Final
December 26, 2018
Page 6 of 6
(3) Provide a detailed description of its (non-UIC) AOGCC regulatory compliance program,
including its tracking system for determining when compliance requirements are due (e.g.
safety valve testing, custody transfer meter testing, monthly and annual reports etc.);
(4) Provide a Root Cause Analysis addressing the failure to provide a notification of a pressure
communication to AOGCC within the next business day; and
(5) Provide a Root Cause Analysis addressing the failure to complete an AOGCC witnessed
MIT once the well commenced injection and stabilization was achieved.
As an Operator involved in an enforcement action, CIE is required to preserve documents
concerning the above action until after resolution of the proceeding.
Done at Anchorage, Alaska and Dated December 26, 2018.
//signature on file//
Hollis S. French
Chair, Commissioner
cc: Ryan Gross, EPA Region 10
AOGCC Inspectors
//signature on file//
Cathy P. Foerster
Commissioner
APPEAL NOTICE
This order or decision and denial of reconsideration are FINAL and may be appealed to superior court. The appeal
MUST be filed within 33 days after the date on which the AOGCC mails, OR 30 days if the AOGCC otherwise
distributes, this order and decision denying reconsideration.
In computing a period of time above, the date of the event or default after which the designated period begins to run is
not included in the period; the last day of the period is included, unless it falls on a weekend or state holiday, in which
event the period runs until 5:00 p.m. on the next day that does not fall on a weekend or state holiday.
Bernie Karl Gordon Severson Penny Vadla
K&K Recycling Inc. 3201 Westmar Cir. 399 W. Riverview Ave.
P.O. Box 58055
Fairbanks, AK 99711 Anchorage, AK 99508-4336 Soldotna, AK 99669-7714
George Vaught, Jr.
P.O. Box 13557
Denver, CO 80201-3557
Darwin Waldsmith
P.O. Box 39309
Ninilchik, AK 99639
A
Richard Wagner
P.O. Box 60868
Fairbanks, AK 99706
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
333 West Seventh Avenue
Anchorage Alaska 99501
Re: Failure to report to AOGCC a pressure communication ) Other Order No. 142
Failure to complete required Mechanical Integrity Test ) Docket OTH-17-056
Redoubt Unit 3A (PTD 2161700) ) June 25, 2018
Area Injection Order (AIO) 32 )
Redoubt Shoal Field, Osprey Platform, )
Redoubt Shoal Unit (RSU) )
DECISION AND ORDER
On March 15, 2018, the Alaska Oil and Gas Conservation Commission (AOGCC or Commission)
issued a Notice of Proposed Enforcement Action (Notice) to Cook Inlet Energy, LLC (CIE)
regarding the Redoubt Unit 3A (RU 3A) well. CIE failed to report to AOGCC a pressure
communication and failed to complete the required Mechanical Integrity Test (MIT) in RU 3A.
The Notice proposed specific corrective actions and a $50,000 civil penalty under AS
31.05.150(a). CIE requested an informal review. That review was held April 10, 2018.
Summary of Proposed Enforcement Action:
The Notice identified violations by CIE of:
(1) 20 AAC 25.402 (f) and the provisions of Rule 8 of AIO 32 requiring CIE to notify
AOGCC and submit a plan of corrective action when pressure communication,
leakage or lack of injection zone isolation is indicated in RU 3A; and
(2) Rule 6 of AIO 32 requiring CIE to perform an AOGCC witnessed Mechanical
Integrity Test once RU 3A commenced injection for the first time.
The Notice proposed civil penalties of $50,000 as follows:
- $25,000 for the initial violation — failure to notify AOGCC of indication of pressure
communication or leakage in RU 3A as specified in Rule 8 of AIO 32 and AOGCC
regulation 20 AAC 25.402 (f); and
Other Order 142
June 25, 2018
Page 2 of 6
- $25,000 for the initial violation — failure to perform the required MIT of the injection
well in compliance with testing protocols specified in Rule 6 of AIO 32.
The Notice also proposed five actions for CIE to review its regulatory compliance program and
analyze the violations for causes and corrective actions.
Violation - Failure to Report a Pressure Communication or Leakage:
By letter dated December 18, 2017 CIE notified AOGCC that the well was exhibiting potential
tubing (T) by inner annulus (IA) pressure communication while injecting water. In its letter CIE
provided a 30 -day injection pressure plot. CIE reported that after approximately 78 days of
injection the IA pressure began to rise and the field staff bled it down numerous times to keep it
below 200 psi. To confirm the communication, CIE let the pressure build to 1008 psi over 79
days, bled down the pressure, and again let the IA pressure build gradually to 590 psi before
another bleed on December 18, 2017. CIE ultimately notified AOGCC of this pressure
communication via the letter to AOGCC dated December 18, 2017 (received by AOGCC on
December 19, 2017) in which CIE requested to continue water injection.
AOGCC regulations require notification by the next working day if an injection rate, operating
pressure observation, or pressure test indicates pressure communication or leakage in any casing,
tubing, or packer.
Rule 8 of AIO 32 states "Whenever any pressure communication, leakage or lack of injection zone
isolation is indicated by injection rate, operating pressure observation, test, survey, log, or other
evidence, the Operator shall notify the Commission by the next business day and submit a plan of
corrective action (on Form 10-403) for Commission approval. The Operator shall immediately
shut in the well if continued operation would be unsafe, would threaten contamination of
freshwater, or if so directed by the Commission. Monthly reports of daily tubing and casing annuli
pressures and injection rates must be provided to the Commission for all injection wells indicating
well integrity failure or lack of injection zone isolation."
On December 19, 2017 CIE provided pressure and injection data (pdf format) for RU 3A from
June 2, 2017 onwards. CIE's only notice to AOGCC of potential pressure communication
Other Order 142
June 25, 2018
Page 3 of 6
occurred via the December 18, 2017 letter. Information provided by CIE demonstrates significant
pressure anomalies which were not communicated to the AOGCC. Significant IA pressure
increases occurred including the two pressure build up tests: approximately August 18, 2017 to
November 5, 2017 (maximum observed pressure was 1008 psi), and November 5, 2017 to
December 18, 2017 (maximum observed pressure was 590 psi). There is no evidence to suggest
the rate of pressure build was subsiding.
CIE failed to report to AOGCC pressure communication indicating a potential loss of mechanical
integrity on RU 3A by the next working day, a violation of both the regulations and Rule 8.
Violation - Failure to Perform the Required MIT. Demonstration of Tubing/Casing Annulus
Mechanical Integrity:
A review of the well information provided by CIE shows RU 3A was handed over to injection
operations on May 30, 2017, with injection allocated to the well continuously beginning July 1,
2017. Review of the well history demonstrates RU 3A was operating without having passed an
AOGCC-witnessed post-injection MIT. Rule 6 of AIO 32 states "The mechanical integrity of an
injection well must be demonstrated before injection begins, and before returning a well to service
following a workover affecting mechanical integrity. A Commission -witnessed mechanical
integrity test must be performed after injection is commenced for the first time in a well, to be
scheduled when injection conditions (temperature, pressure, rate, etc.) have stabilized. Subsequent
tests must be performed at least once every four years thereafter." In addition to the MIT
requirement in AIO 32, approval of the Permit to Drill for RU 3A was conditioned on a
requirement of a post -initial -injection MIT. CIE operated RU 3A approximately six months
without the required MIT. CIE was notified on December 20, 2017 that RU 3A must pass an
AOGCC-witnessed MIT to continue on injection. A successful MIT was completed December
23, 2017.
Based on information provided by CIE — including the passing MIT on December 23, 2017 —
AOGCC determined that water injection could safely continue if CIE complied with the restrictive
conditions set out in an administrative approval dated December 28, 2017. Approval conditions
included monthly reporting of well pressures, injection rates, and pressure bleeds; installation and
Other Order 142
June 25, 2018
Page 4 of 6
testing of automatic well shut-in equipment linked to the wells inner annulus pressure; and a more
frequent MIT schedule.
CIE failed to complete the AOGCC-witnessed MIT after injection was commenced for the first
time in RU 3A, a violation of Rule 6 of AIO 32.
Mitigating Circumstances:
The factors in AS 31.05.150(g) were considered in determining the appropriate penalty. While the
penalty does not reflect amounts based on per -day assessment, that decision does not minimize
CIE's failure to report the significant repressurization events that occurred four months before
notifying the AOGCC of possible serious and substantial issues with the integrity of the RU 3A
wellbore. The failure to complete the initial post-injection MIT cannot be characterized as a good
faith attempt to comply with the AOGCC's orders and regulations. Although no injury to the
public occurred, the potential wellbore failure posed an obvious threat to both public health and
the environment. Violations relating to Underground Injection Control Class II well integrity
practices warrant the imposition of civil penalties. CIE's failure to comply with fundamental
wellbore mechanical integrity testing requirements raises the potential for similar behavior with
more serious consequences. CIE's failure to notify AOGCC of the pressure communication shows
disregard for or ignorance of CIE's compliance responsibilities. Mitigating circumstances
considered in the assessment of the proposed civil penalty include the absence of known sources
of freshwater in the Redoubt Unit, as well as the fact that once notified of the violations, CIE
demonstrated urgency in completion of the required MIT and in the installation and testing of the
required automatic well shut-in equipment prerequisite to continued injection in the well.
Findings and Conclusions:
The AOGCC finds that CIE violated 20 AAC 25.402 (f) and the Rules in AIO 32 governing the
Demonstration of Tubing/Casing Annulus Mechanical Integrity and Well Integrity Failure.
Mitigating circumstances outlined above were considered in the AOGCC's Notice of Proposed
Enforcement Action and its assessment as to the appropriate civil penalty. CIE has committed to
an increased level of oversight and review of established training and process protocols for
Other Order 142
June 25, 2018
Page 5 of 6
employees governing injection operations. The AOGCC finds CIE's implementation of the
proposed actions to be satisfactory to help prevent further occurrence of these violations.
Now Therefore It Is Ordered That:
CIE is assessed a civil penalty in the amount of $50,000 for violating Rule 6 of AID 32, Rule 8 of
AIO 32, and 20 AAC 25.402(f). If CIE chooses not to appeal this Order the fine must be paid
within 30 days of issuance. If appealed, the fine will be held in abeyance until the appeal process
is complete.
In addition to the civil penalty, within four weeks of the date of the AOGCC's final decision, CIE
shall:
(1) Provide a detailed description of its Underground Injection Control (UIC) regulatory
compliance program;
(2) Provide details of its tracking system for determining when MIT's are required, including
the details of contingencies for wells shut in at the time an MIT is due and its procedures
for notification to the AOGCC, as well as its processes for determining the MIT due date
and identification of past due wells;
(3) Provide a detailed description of its (non-UIC) AOGCC regulatory compliance program,
including its tracking system for determining when compliance requirements are due (e.g.
safety valve testing, custody transfer meter testing, monthly and annual reports etc.);
(4) Provide a Root Cause Analysis addressing the failure to provide a notification of a pressure
communication to AOGCC within the next business day; and
(5) Provide a Root Cause Analysis addressing the failure to complete an AOGCC witnessed
MIT once the well commenced injection and stabilization was achieved.
Other Order 142
June 25, 2018
Page 6 of 6
As an Operator involved in an enforcement action, CIE is required to preserve documents
concerning the above action until after resolution of the proceeding.
Done at Anchorage, Alaska and Dated June 25, 2018.
Hollis S. French
Chair, Commissioner
cc: Ryan Gross, EPA Region 10
AOGCC Inspectors
—
Ca�oerster
Y
Commissioner
AND APPEAL NOTICE
As provided in AS 31.05.080(a), within 20 days after written notice of the entry of this order or decision, or such further
time as the AOGCC grants for good cause shown, a person affected by it may file with the AOGCC an application for
reconsideration of the matter determined by it. If the notice was mailed, then the period of time shall be 23 days. An
application for reconsideration must set out the respect in which the order or decision is believed to be erroneous.
The AOGCC shall grant or refuse the application for reconsideration in whole or in part within 10 days after it is filed.
Failure to act on it within 10 -days is a denial of reconsideration. If the AOGCC denies reconsideration, upon denial, this
order or decision and the denial of reconsideration are FINAL and may be appealed to superior court. The appeal MUST
be filed within 33 days after the date on which the AOGCC mails, OR 30 days if the AOGCC otherwise distributes, the
order or decision denying reconsideration, UNLESS the denial is by inaction, in which case the appeal MUST be filed
within 40 days after the date on which the application for reconsideration was filed.
If the AOGCC grants an application for reconsideration, this order or decision does not become final. Rather, the order
or decision on reconsideration will be the FINAL order or decision of the AOGCC, and it may be appealed to superior
court. That appeal MUST be filed within 33 days after the date on which the AOGCC mails, OR 30 days if the AOGCC
otherwise distributes, the order or decision on reconsideration.
In computing a period of time above, the date of the event or default after which the designated period begins to run is
not included in the period; the last day of the period is included, unless it falls on a weekend or state holiday, in which
event the period runs until 5:00 p.m. on the next day that does not fall on a weekend or state holiday.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION
333 West Seventh Avenue
Anchorage Alaska 99501
Re: Failure to report to AOGCC a pressure communication
Failure to complete required Mechanical Integrity Test
Redoubt Unit 3A (PTD 2161700)
Area Injection Order (AIO) 32
Redoubt Shoal Field, Osprey Platform,
Redoubt Shoal Unit (RSU)
DECISION AND ORDER
Other Order No. 142
Docket OTH-17-056
June 25, 2018
On March 15, 2018, the Alaska Oil and Gas Conservation Commission (AOGCC or Commission)
issued a Notice of Proposed Enforcement Action (Notice) to Cook Inlet Energy, LLC (CIE)
regarding the Redoubt Unit 3A (RU 3A) well. CIE failed to report to AOGCC a pressure
communication and failed to complete the required Mechanical Integrity Test (MIT) in RU 3A.
The Notice proposed specific corrective actions and a $50,000 civil penalty under AS
31.05.150(a). CIE requested an informal review. That review was held April 10, 2018.
Summary of Proposed Enforcement Action:
The Notice identified violations by CIE of
(1) 20 AAC 25.402 (f) and the provisions of Rule 8 of AID 32 requiring CIE to notify
AOGCC and submit a plan of corrective action when pressure communication,
leakage or lack of injection zone isolation is indicated in RU 3A; and
(2) Rule 6 of AID 32 requiring CIE to perform an AOGCC witnessed Mechanical
Integrity Test once RU 3A commenced injection for the first time.
The Notice proposed civil penalties of $50,000 as follows:
- $25,000 for the initial violation — failure to notify AOGCC of indication of pressure
communication or leakage in RU 3A as specified in Rule 8 of AIO 32 and AOGCC
regulation 20 AAC 25.402 (f); and
Other Order 142
June 25, 2018
Page 2 of 6
- $25,000 for the initial violation — failure to perform the required MIT of the injection
well in compliance with testing protocols specified in Rule 6 of AIO 32.
The Notice also proposed five actions for CIE to review its regulatory compliance program and
analyze the violations for causes and corrective actions
Violation - Failure to Renort a Pressure Communication or Leakase:
By letter dated December 18, 2017 CIE notified AOGCC that the well was exhibiting potential
tubing (T) by inner annulus (IA) pressure communication while injecting water. In its letter CIE
provided a 30 -day injection pressure plot. CIE reported that after approximately 78 days of
injection the IA pressure began to rise and the field staff bled it down numerous times to keep it
below 200 psi. To confirm the communication, CIE let the pressure build to 1008 psi over 79
days, bled down the pressure, and again let the IA pressure build gradually to 590 psi before
another bleed on December 18, 2017. CIE ultimately notified AOGCC of this pressure
communication via the letter to AOGCC dated December 18, 2017 (received by AOGCC on
December 19, 2017) in which CIE requested to continue water injection.
AOGCC regulations require notification by the next working day if an injection rate, operating
pressure observation, or pressure test indicates pressure communication or leakage in any casing,
tubing, or packer
Rule 8 of AIO 32 states "Whenever any pressure communication, leakage or lack of injection zone
isolation is indicated by injection rate, operating pressure observation, test, survey, log, or other
evidence, the Operator shall notify the Commission by the next business day and submit a plan of
corrective action (on Form 10-403) for Commission approval. The Operator shall immediately
shut in the well if continued operation would be unsafe, would threaten contamination of
freshwater, or if so directed by the Commission. Monthly reports of daily tubing and casing annuli
pressures and injection rates must be provided to the Commission for all injection wells indicating
well integrity failure or lack of injection zone isolation."
On December 19, 2017 CIE provided pressure and injection data (pdf format) for RU 3A from
June 2, 2017 onwards. CIE's only notice to AOGCC of potential pressure communication
Other Order 142
June 25, 2018
Page 3 of 6
occurred via the December 18, 2017 letter. Information provided by CIE demonstrates significant
pressure anomalies which were not communicated to the AOGCC. Significant IA pressure
increases occurred including the two pressure build up tests: approximately August 18, 2017 to
November 5, 2017 (maximum observed pressure was 1008 psi), and November 5, 2017 to
December 18, 2017 (maximum observed pressure was 590 psi). There is no evidence to suggest
the rate of pressure build was subsiding.
CIE failed to report to AOGCC pressure communication indicating a potential loss of mechanical
integrity on RU 3A by the next working day, a violation of both the regulations and Rule 8.
Violation - Failure to Perform the Reauired MIT. Demonstration of Tubin Casin¢ Annulus
Mechanical Inte¢rity:
A review of the well information provided by CIE shows RU 3A was handed over to injection
operations on May 30, 2017, with injection allocated to the well continuously beginning July 1,
2017. Review of the well history demonstrates RU 3A was operating without having passed an
AOGCC-witnessed post-injection MIT. Rule 6 of AIO 32 states "The mechanical integrity of an
injection well must be demonstrated before injection begins, and before returning a well to service
following a workover affecting mechanical integrity. A Commission -witnessed mechanical
integrity test must be performed after injection is commenced for the first time in a well, to be
scheduled when injection conditions (temperature, pressure, rate, etc.) have stabilized. Subsequent
tests must be performed at least once every four years thereafter." In addition to the MIT
requirement in AIO 32, approval of the Permit to Drill for RU 3A was conditioned on a
requirement of a post -initial -injection MIT. CIE operated RU 3A approximately six months
without the required MIT. CIE was notified on December 20, 2017 that RU 3A must pass an
AOGCC-witnessed MIT to continue on injection. A successful MIT was completed December
23, 2017.
Based on information provided by CIE — including the passing MIT on December 23, 2017
AOGCC determined that water injection could safely continue if CIE complied with the restrictive
conditions set out in an administrative approval dated December 28, 2017. Approval conditions
included monthly reporting of well pressures, injection rates, and pressure bleeds; installation and
Other Order 142
June 25, 2018
Page 4 of 6
testing of automatic well shut-in equipment linked to the wells inner annulus pressure; and a more
frequent MIT schedule.
CIE failed to complete the AOGCC-witnessed MIT after injection was commenced for the first
time in RU 3A, a violation of Rule 6 of AIO 32.
Mitigating Circumstances:
The factors in AS 31.05.150(g) were considered in determining the appropriate penalty. While the
penalty does not reflect amounts based on per -day assessment, that decision does not minimize
CIE's failure to report the significant repressurization events that occurred four months before
notifying the AOGCC of possible serious and substantial issues with the integrity of the RU 3A
wellbore. The failure to complete the initial post-injection MIT cannot be characterized as a good
faith attempt to comply with the AOGCC's orders and regulations. Although no injury to the
public occurred, the potential wellbore failure posed an obvious threat to both public health and
the environment. Violations relating to Underground Injection Control Class II well integrity
practices warrant the imposition of civil penalties. CIE's failure to comply with fundamental
wellbore mechanical integrity testing requirements raises the potential for similar behavior with
more serious consequences. CIE's failure to notify AOGCC of the pressure communication shows
disregard for or ignorance of CIE's compliance responsibilities. Mitigating circumstances
considered in the assessment of the proposed civil penalty include the absence of known sources
of freshwater in the Redoubt Unit, as well as the fact that once notified of the violations, CIE
demonstrated urgency in completion of the required MIT and in the installation and testing of the
required automatic well shut-in equipment prerequisite to continued injection in the well.
Findings and Conclusions:
The AOGCC finds that CIE violated 20 AAC 25.402 (f) and the Rules in AIO 32 governing the
Demonstration of Tubing/Casing Annulus Mechanical Integrity and Well Integrity Failure.
Mitigating circumstances outlined above were considered in the AOGCC's Notice of Proposed
Enforcement Action and its assessment as to the appropriate civil penalty. CIE has committed to
an increased level of oversight and review of established training and process protocols for
Other Order 142
June 25, 2018
Page 5 of 6
employees governing injection operations. The AOGCC finds CIE's implementation of the
proposed actions to be satisfactory to help prevent further occurrence of these violations.
Now Therefore It Is Ordered That:
CIE is assessed a civil penalty in the amount of $50,000 for violating Rule 6 of AIO 32, Rule 8 of
AIO 32, and 20 AAC 25.402(f). If CIE chooses not to appeal this Order the fine must be paid
within 30 days of issuance. If appealed, the fine will be held in abeyance until the appeal process
is complete.
In addition to the civil penalty, within four weeks of the date of the AOGCC's final decision, CIE
shall:
(1) Provide a detailed description of its Underground Injection Control (UIC) regulatory
compliance program;
(2) Provide details of its tracking system for determining when MIT's are required, including
the details of contingencies for wells shut in at the time an MIT is due and its procedures
for notification to the AOGCC, as well as its processes for determining the MIT due date
and identification of past due wells;
(3) Provide a detailed description of its (non-UIC) AOGCC regulatory compliance program,
including its tracking system for determining when compliance requirements are due (e.g.
safety valve testing, custody transfer meter testing, monthly and annual reports etc.);
(4) Provide a Root Cause Analysis addressing the failure to provide a notification of a pressure
communication to AOGCC within the next business day; and
(5) Provide a Root Cause Analysis addressing the failure to complete an AOGCC witnessed
MIT once the well commenced injection and stabilization was achieved.
Other Order 142
June 25, 2018
Page 6 of 6
As an Operator involved in an enforcement action, CIE is required to preserve documents
concerning the above action until after resolution of the proceeding.
Done at Anchorage, Alaska and Dated June 25, 2018.
//signature on file//
Hollis S. French
Chair, Commissioner
cc: Ryan Gross, EPA Region 10
AOGCC Inspectors
//signature on file//
Cathy P. Foerster
Commissioner
As provided in AS 31.05.080(a), within 20 days after written notice of the entry of this order or decision, or such further
time as the AOGCC grants for good cause shown, a person affected by it may file with the AOGCC an application for
reconsideration of the matter determined by it. If the notice was mailed, then the period of time shall be 23 days. An
application for reconsideration must set out the respect in which the order or decision is believed to be erroneous.
The AOGCC shall grant or refuse the application for reconsideration in whole or in part within 10 days after it is filed.
Failure to act on it within 10 -days is a denial of reconsideration. If the AOGCC denies reconsideration, upon denial, this
order or decision and the denial of reconsideration are FINAL and maybe appealed to superior court. The appeal MUST
be filed within 33 days after the date on which the AOGCC mails, OR 30 days if the AOGCC otherwise distributes, the
order or decision denying reconsideration, UNLESS the denial is by inaction, in which case the appeal MUST be filed
within 40 days after the date on which the application for reconsideration was filed.
If the AOGCC grants an application for reconsideration, this order or decision does not become final. Rather, the order
or decision on reconsideration will be the FINAL order or decision of the AOGCC, and it may be appealed to superior
court. That appeal MUST be filed within 33 days after the date on which the AOGCC mails, OR 30 days if the AOGCC
otherwise distributes, the order or decision on reconsideration.
In computing a period of time above, the date of the event or default after which the designated period begins to run is
not included in the period; the last day of the period is included, unless it falls on a weekend or state holiday, in which
event the period runs until 5:00 p.m. on the next day that does not fall on a weekend or state holiday.
Colombie, Jody J (DOA)
From:
Colombie, Jody J (DOA)
Sent:
Monday, June 25, 2018 9:51 AM
To:
David Pascal; Bell, Abby E (DOA); Bixby, Brian D (DOA); Brooks, Phoebe L (DOA); Carlisle,
Samantha J (DOA); Colombie, Jody J (DOA); Cook, Guy D (DOA); Davies, Stephen F (DOA); Earl,
Adam G (DOA); Erickson, Tamara K (DOA); Foerster, Catherine P (DOA); French, Hollis (DOA);
Frystacky, Michal (DOA); Guhl, Meredith D (DOA); Herrera, Matthew F (DOA); Jones, Jeffery B
(DOA); Kair, Michael N (DOA); Laubenstein, Lou (DOA); Loepp, Victoria T (DOA); Martin, Teddy J
(DOA); McLeod, Austin (DOA); Mcphee, Megan S (DOA); Mumm, Joseph (DOA sponsored);
Noble, Robert C (DOA); Paladijczuk, Tracie L (DOA); Pasqual, Maria (DOA); Regg, James B (DOA);
Rixse, Melvin G (DOA); Roby, David S (DOA); Schwartz, Guy L (DOA); Seamount, Dan T (DOA);
Wallace, Chris D (DOA); AK, GWO Projects Well Integrity, AKDCWellIntegrityCoordinator; Alan
Bailey; Alex Demarban; Alicia Showalter; Allen Huckabay; Andrew Vanderlack, Ann Danielson;
Anna Lewallen; Anna Raff; Barbara F Fullmer, bbritch; bbohrer@ap.org; Ben Boettger, Bill Bredar,
Bob Shavelson; Bonnie Bailey, Brandon Viator; Brian Havelock; Bruce Webb; Caleb Conrad; Candi
English; Cody Gauer; Cody Terrell; Colleen Miller, Connie Downing; Crandall, Krissell; D Lawrence;
Dale Hoffman; Danielle Mercurio; Darci Horner, Dave Harbour; David Boelens; David Duffy,
David House; David McCaleb; ddonkel@cfl.rr.com; Diemer, Kenneth J (DNR); DNROG Units (DNR
sponsored); Donna Ambruz; Ed Jones; Elizabeth Harball; Elowe, Kristin; Elwood Brehmer; Evan
Osborne; Evans, John R (LDZIn; Brown, Garrett A (DNR); George Pollock; Gordon Pospisil;
Greeley, Destin M (DOR); Greg Kvokov; Gretchen Stoddard; gspfoff; Hurst, Rona D (DNR); Hyun,
James J (DNR); Jacki Rose; Jason Brune; Jdarlington (jarlington@gmail.com); Jeanne McPherren;
Jerry Hodgden; Jill Simek; Jim Shine; Jim Watt; Jim White (jim4thgn@gmail.com); Young, Jim P
(DNR); Joe Lastufka; Radio Kenai; Burdick, John D (DNR); Easton, John R (DNR); Larsen, John M
(DOR); Jon Goltz; Joshua Stephen; Juanita Lovett, Judy Stanek, Kari Moriarty; Kasper Kowalewski;
Kazeem Adegbola; Keith Torrance; Keith Wiles; Kelly Sperback; Frank, Kevin J (DNR); Kruse,
Rebecca D (DNR); Kyla Choquette, Gregersen, Laura S (DNR); Leslie Smith; Lori Nelson; Luke
Keller, Marc Kovak; Dalton, Mark (DOT sponsored); Mark Hanley (mark.hanley@anadarko.com);
Mark Landt; Mark Wedman; Michael Bill; Michael Calkins; Michael Moora; Michael Quick;
Michael Schoetz; Mike Morgan; MJ Loveland; Motteram, Luke A; Mueller, Marta R (DNR);
Nathaniel Herz; knelson@petroleumnews.com; Nichole Saunders; Nick Ostrovsky; NSK Problem
Well Supv; Patty Alfaro; Paul Craig; Decker, Paul L (DNR); Paul Mazzolini; Pike, Kevin W (DNR);
Randall Kanady; Renan Yanish; Richard Cool; Robert Brelsford; Robert Tirpack; Robert Warthen;
Ryan Gross, Sara Leverette; Scott Griffith; Shahla Farzan; Shannon Donnelly, Sharon Yarawsky;
Skutca, Joseph E (DNR); Smith, Kyle S (DNR); Spuhler, Jes J (DNR); Stephanie Klemmer; Stephen
Hennigan; Stephen Ratcliff; Sternicki, Oliver R; Moothart, Steve R (DNR); Steve Quinn; Suzanne
Gibson; Sheffield@aoga.org; Tanisha Gleason; Ted Kramer, Teresa Imm; Terry Caetano; Tim
Mayers; Todd Durkee; Tom Maloney, Tyler Senden; Umekwe, Maduabuchi P (DNR); Vern
Johnson; Vinnie Catalano; Well Integrity, Well Integrity; Weston Nash; Whitney Pettus; Aaron
Gluzman; Aaron Sorrell; Ajibola Adeyeye; Alan Dennis, Andy Bond; Bajsarowicz, Caroline J; Bruce
Williams; Casey Sullivan; Corey Munk; Don Shaw; Eppie Hogan; Eric Lidji; Garrett Haag; Smith,
Graham O (DNR); Heusser, Heather A (DNR); Fair, Holly S (DNR); Jamie M. Long; Jason
Bergerson; Jesse Chielowski; Jim Magill; Joe Longo; John Martineck, Josh Kindred; Keith Lopez;
Laney Vazquez; Lois Epstein; Longan, Sara W (DNR); Marc Kuck; Marcia Hobson; Matt
Armstrong; Melonnie Amundson; Franger, James M (DNR); Morgan, Kirk A (DNR); Umekwe,
Maduabuchi P (DNR); Pat Galvin; Pete Dickinson; Peter Contreras; Rachel Davis; Richard Garrard;
Richmond, Diane M; Robert Province; Ryan Daniel; Sandra Lemke; Scott Pins; Pollard, Susan R
(LAW); Talib Syed; Tina Grovier (tmgrovier@stoel.com); William Van Dyke; Zachary Shulman
Subject:
Other Order 142 (CIE)
Attachments:
Other 142.pdf
Please see attached.
Re: Failure to report to AOGCC a pressure communication
Failure to complete required Mechanical Integrity Test
Redoubt Unit 3A (PTD 2161700)
Area Injection Order (AIO) 32
Redoubt Shoal Field, Osprey Platform,
Redoubt Shoal Unit (RSU)
Jody J. Co(om6ie
.AOGCC Syecia(-ssistant
.Alaska Oi(and Gas Conservation Commission
333 -West yfi .Avenue
.Anchorage, .Alaska 99501
Office: (907) 793-1221
.Tax: (907) 276-7542
Other Order No. 142
Docket 0TH -17-056
June 25, 2018
1
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska Oil and Gas Conservation
Commission (AOGCC(, State of Alaska and is for the sole use of the intended recipient(s). It may contain confidential and/or privileged information.
The unauthorized review, use or disclosure of such information may violate state or federal law. If you are an unintended recipient of this e-mail,
please delete it without first saving or forwarding it, and, so that the AOGCC is aware of the mistake in sending it to you, contact Jody Colombie at
907.793.1221 or iodv.colombie@alaska.ggy.
Bernie Karl
K&K Recycling Inc. Gordon Severson Penny Vadla
P.O. Box 58055 3201 Westmar Cir. 399 W. Riverview Ave.
Fairbanks, AK 99711 Anchorage, AK 99508-4336 Soldotna, AK 99669-7714
George Vaught, Jr. Darwin Waldsmith Richard Wagner
P.O. Box 13557 P.O. Box 39309 P.O. Box 60868
Denver, CO 80201-3557 Ninilchik, AK 99639 Fairbanks, AK 99706
e, l
U��e�' 1°VV�
Cook Inlet Energy, LLC First National Bank Alaska 219307
601 W. 5th Avenue P.O. Box 100720
Suite 310 Anchorage, AK 99510-0720
Anchorage, AK 99501
Fifty thousand dollars and no cents
Pay to the Alaska Oil & Gas Conservation Commission
Order of 333 West 7th Avenue
Suite 100
Anchorage, AK 99501-3539
DATE-
I AMOUNT
1/1 019
1 $"50 000.00'
T06 Signatures Required for Checks Over $20,000
u'002Lg30?IIn 1:125200060e: 1113L05548611'
From: Cook Inlet Energy, LLC
To: Alaska Oil & Gas Conservation Commis Vendor Code Check Date
333 West 7th Avenue
Suite 100 AOGCC 01/17/2019
Anchorage, AK 99501-3539
Invoice # Invoice Amt
OTH-17-056 50,000.00
Docket OTH-17-0056_ _
Check Amount Check Number
$50,000.00 D-219307
JAN 2 2 c'Qij
A
14
GLACIER
February 281h, 2019
Commissioner Dan Seamount
Commissioner Cathy Foerster
Alaska Oil and Gas Conservation Commission (AOGCC)
333 West 71h Ave., Suite 100
Anchorage, Alaska 99501
RE: Failure to report to AOGCC a pressure communication
Failure to complete required Mechanical Integrity Test
Redoubt Unit 3A (PTD 2161700)
Area Injection Order (AIO) 32
Redoubt Shoal Field, Osprey Platform,
Redoubt Shoal Unit (RSU)
Dear Commissioners,
E. F EE 5 a' tE'i, ,!
MAR G
A0G%;
The following information is in response to the Decision and Order issued on December 26,
2018 to Cook Inlet Energy (CIE). In addition to the civil penalty, the AOGCC required
additional detail on five (5) items regarding internal CIE processes, including two Root Cause
Analyses regarding the violations as described in the Order. Each item is addressed
individually below.
1) Provide a detailed description of CIE's Underground Injection Control (UIC)
regulatory compliance program.
In order to ensure that CIE stays in compliance with the AOGCC UIC Program, CIE
has the following programs in place:
a. CIE follows the AOGCC Sundry process to ensure all requested perforations are
within the specified strata and are approved by AOGCC prior to being added. All
perforations are correlated by the CIE geologists to the RU -01 or RU -02 wells as
required in Rule 1 of AIO 32. The sundries and reports are generated and
submitted by the CIE engineers who are responsible for ensuring the process is
followed correctly for qualified well work.
The approved sundries are reviewed by the VP of Drilling and all
conditions of approval are added to the operations program. The
approved sundries are also reviewed by engineers, drill site managers,
and required field personnel.
GLACIER
b. The wells currently used for injection have been approved by the AOGCC for use
in conformance with specified regulations as stipulated by Rule 2 of AIO 32. Any
additional need in the future for new injection wells or conversions of existing
wells will be applied for by CIE engineers. CIE engineers are responsible for the
submittal of AOGCC required forms and information in order to gain approval by
the AOGCC prior to any work commencing.
c. All field personnel associated with injection activities are trained and aware of
which fluids are authorized for injection. The authorized list is posted in the
control room of the Osprey Platform and Kustatan facility. The lead operator at
the Osprey Platform is required to document the type of fluid(s) being injected.
The details of each injection are captured in a live document. RU -03A is currently
only approved to inject produced water. In the event one of the other authorized
fluids needs to be injected down RU -06, the platform lead operator is required to
have authorization from the VP of Operations prior to the injection. This process
ensures there is a verification both in the field and from management that the
fluid type is approved for injection under the AIO 32 Rule 3. If at any point CIE
were to discover an unauthorized fluid was injected, the Commission would be
notified by the VP of Operations immediately as required by AIO 32 Rule 9.
d. All wells on the Osprey Platform are monitored continuously with real-time
pressure sensors that tie in to the main control room. The injection wells have
sensors dedicated to ensuring the tubing and IA pressures are documented as
required by AIO 32 Rule 5. The real time monitoring also works to ensure the
fluids are not injected at a rate that could induce fractures in the confining strata
as required by AIO 32 Rule 4. The sensors are set with high- and low-pressure
alerts, based on normal operating conditions, that will shut down the injection
automatically if reached. The rate and pressure data during injection is also
monitored by the Lead Operator. Trend data is reviewed to ensure that even
smaller changes are acknowledged and monitored. If there is indication at any
time that fracturing or migration of the injected fluid may be occurring, the well
would be shut in immediately and the VP of Operations would be notified. A
review of the data would be conducted, a plan forward created, and the VP of
Operations would notify the Commission. The VP of Operations would also be
responsible for notifying the Commission by the next business day if any
pressure communication, leakage or lack of injection zone isolation is indicated
by the real-time pressure monitoring, or other evidence as required by AIO 32
Rule 8. All monthly, quarterly, and annual reports required by the Commission
are tracked and submitted by the VP of Operations.
The findings of the RU -03A Root Cause Analysis 2018-01 (see Appendix
4) identified that the results of the first pressure build up test were
perceived as inconclusive which caused a delay in reporting the potential
issue to the Commission. It is CIE's responsibility to analyze the trend
GLACIER
data and notify the Commission of any communication issues within the
required time frame stipulated.
e. The MIT requirement for the injection wells as stated in AIO 32 Rule 6, is tracked
by the Lead Operators, Production Engineers and overseen by the VP of
Operations. The MIT schedule for applicable wells is tracked using an online
database that provides alerts for upcoming test deadlines. Since 2017, CIE has
upgraded that system and is currently actively tracking the MIT required
schedule for the injection wells in TaskOps. For RU -03A the MIT schedule is
dictated by AIO 32.001 requiring a more frequent MIT, every 2 years, rather than
the standard 4 -year schedule. Please see Appendix 1 for additional information
about TaskOps.
As a result of the RU -03A Root Cause Analysis 2018-02 (see Appendix 5),
a gap in the transition of information from drilling to production was
identified, in addition to the requirement to conduct a full review of AIO
32 Rule 6 prior to start or restart of injection. If a new or converted well
is brought online or a major workover is conducted, the Lead Operator is
now required to review the CIE MIT Requirement Flow Chart which is in
accordance with AIO 32 Rule 6 (See Appendix 2). This process will ensure
the initial MIT prior to injection and the MIT once injection conditions
have stabilized are scheduled and conducted as stipulated. Also, a
complete handover of permit to drill and sundry approval conditions will
be conducted prior to the Lead Operator taking control of a well. This
handover will ensure that the Lead Operator is aware of any remaining
conditions that are required by the Commission.
2) Provide details of CIE's tracking system for determining when MIT's are
required, including the details of contingencies for wells shut in at the time an
MIT is due and its procedures for notification to the AOGCC, as well as its
processes for determining the MIT due date and identification of past due
wells.
a) The Lead Operator is responsible for scheduling and tracking the MITs.
Based on the timeline dictated by AIO 32 for RU -06 and AIO 32.001 for RU -
03A the upcoming test due dates have been loaded into TaskOps. TaskOps
provides a calendar view of upcoming tests. The control room also has a
visible list for the timing of the upcoming tests for each well. The most recent
test for RU -06 was May 8, 2015, which is on a 4 -year test cycle based on AIO
32 Rule 6. Since no well work has been conducted on RU -06 effecting the
mechanical integrity of the well, the next scheduled test is May 8, 2019.
GLACIER
For RU -03A, AIO 32.001 currently stipulates the next test is to occur on
December 23, 2019. Upon a successful test the next test date will be
December 23, 2021 due to the 2 -year test cycle requirement.
b) The Lead Operator is responsible for notifying the Commission of the
upcoming test for witness at least 24 hours in advance of the test which is
done by online submission through the AOGCC website. The VP of
Operations is responsible for submitting the CIE MIT report once the test is
complete to the Commission.
c) As a result of the Root Cause Analysis (see Appendix 5), CIE identified a gap
in the process that occurs when a well is converted to injection or a new
injection well is drilled. The requirement of the MIT once injection
parameters stabilized was not identified. In order to ensure the MIT is
conducted in the future, if a new injection well is drilled or existing well is
converted to injection, the Lead Operator is required to complete the CIE MIT
Requirement Flow Chart to ensure the appropriate timing for the required
MLTs is scheduled (see Appendix 2). The schedule would be tracked in
TaskOps. Once the initial MLTs are completed, the schedule would move to a
4 -year cycle under AIO 32 Rule 6 unless otherwise dictated by the
Commission.
d) For any MIT test scheduled in TaskOps, the software identifies if the testis
completed on time or if the due date passes without completion. If the test is
not completed on time, the test is labeled as "Over Due' and a notification is
sent via email to the Lead Operator, CIE Engineers and VP of Operations. The
software will continue to notify the users that the item is over due until the
MIT is conducted and closed out in the software.
e) If a well is shut-in at the time the MIT is due, the Lead Operator is required to
document the required process prior to the well restart which would include
the required MIT. This is noted visually in the Osprey Platform Control
Room, reported to the CIE Engineers, and monitored by VP of Operations.
3) Provide a detailed description of its (non-UIC) AOGCC regulatory compliance
program, including its tracking system for determining when compliance
requirements are due (e.g. safety valve testing, custody transfer meter testing,
monthly and annual reports etc.).
a) CIE has continuously tracked the compliance requirements for all wells
through an infield tracking system. The testing requirements are scheduled
as needed and updated once the test is complete. The tracking system was
overseen by the Lead Operator. Since 2017, the schedule of the tests has
13
GLACIER
been loaded into the online database system, TaskOps. Upcoming tests are
monitored by the Lead Operators and CIE engineers. For safety valve testing,
including surface and sub -surface, the "Well Safety Valve System (SVS)
Testing Decision Matrix" is utilized in order to ensure the Commission
requirements are followed (see Appendix 3). The safety valve tests are on a
6 -month cycle. Meter testing is required at different intervals depending on
the activity, ranging from monthly to 5 -years, and is also tracked through
TaskOps, the due dates are based on the original commissioning of the
meters.
b) Monthly and annual reports are the responsibility of the VP of Operations.
The submittal requirements are tracked electronically depending on the
specific schedule.
4) Provide a Root Cause Analysis addressing the failure to provide a notification
of a pressure communication to AOGCC within the next business day.
Root Cause Analysis 2018-01 included as Appendix 4.
5) Provide a Root Cause Analysis addressing the failure to complete an AOGCC
witnessed MIT once the well commenced injection and stabilization was
achieved.
Root Cause Analysis 2018-02 included as Appendix 5.
If you have any questions, please contact me at (907) 433-3836.
George norris
Executive Vice President & Chief Operating Officer
Cook Inlet Energy, LLC (a Glacier Oil & Gas Corp wholly owned company)
GLACIER APPENDIX I
TaskCps - Regulatory Compliance Tracking Program
Introduction
Regulatory compliance is the awareness of and actions taken to maintain conformance with
relevant laws and regulations. It is achieved through effective task management. Cook Inlet
Energy (CIE) uses TaskOps --- a regulatory compliance software package to assign, alert,
monitor progress, and update regulatory compliance tasks and corrective actions to ensure
timely completion. TaskOps is a web ---based application that is accessed by our personnel
both in the field and in the office. Compliance tasks are input into the system as action
items which are organized into action groups by regulatory requirement. Each group of
action items is displayed in a point and click action table where the compliance tasks can be
viewed, sorted, and updated.
CIE uses TaskOps to provide automated email notification and task action reminders to
required personnel consistent with our chain of command. TaskOps users provide updates
to compliance tasks via the event log which keeps a running history of all activity
associated with each action item. Supporting documents are uploaded and attached to a
compliance task when required. This allows for real ---time task progress communication
and monitoring. TaskOps is a password accessed system
which ensures confidentiality and provides data control.
CIE uses TaskOps to generate a quarterly status report to provide regulatory compliance
task tracking and status to affected facilities and personnel. The reports are generated by
the regulatory compliance software automatically per the CIE defined report schedule and
emailed to the Production Manager, HSE Manager, Production Engineer, and Lead
Operators. TaskOps reports are browser independent and can be viewed from mobile
devices. Reporting can be generated as HTML, Microsoft Excel, or Microsoft Access files.
New Injection yes
Well, Nevdy
Converteo Well?
No l
CIE MIT Requirement Process Flow Chart
Mfr required prior Pau
to start of
Injection
Fail
VP of Drilling submit
Sundry Application
for Required Well
Work untA MIT Pass.
J
Provide MR
restdtsto UVninjecWn
AOGCC
NO lnxcDm
Conditiord
Stablized?
Continue 1
Injection until
Stablized "WVAOGCC
for Witnessed
Fail MITTest
Enter MfT
PUS Requirement in
TaskOps for every 4
year sdtedule.
M
Notify W of Ops and VP
milling
DidWorkover/Well
yes
o -Request
Work affect Mechanical
Authorization to Retest
Integrity?
No
VP of Ops to notify,*Fad
Pau
AOGCC of failed test.
Restart
~
Injection - No
MIT required
-
VP of Drilling submit
Sundry Application
for Required Well
Work untA MIT Pass.
J
Provide MR
restdtsto UVninjecWn
AOGCC
NO lnxcDm
Conditiord
Stablized?
Continue 1
Injection until
Stablized "WVAOGCC
for Witnessed
Fail MITTest
Enter MfT
PUS Requirement in
TaskOps for every 4
year sdtedule.
M
Well Safety Valve System Testing Decision Matrix
and emrtsto
Operatorpeirformsh —fur reale.
SIISfi.Wbn dted:psbrto L
-�bAttgitgaidintodeake Ny r Production Manager
per(orrtwme submits SVStelling
the � records to AOGCC W
Near well in later than the 15th
't,`produeion�N dayo(ng month
// Im following the test
Ye;
Yes
M
xbe& testedrMhi+
d SSSV HI�t. trill mtq
is only a
e safety
ibe
1es.t ,,, 74
wan—mm
hours Or the
Shut-in
M
M
APPENDIX 4 - ROOT CAUSE ANALYSIS REPORT: Failure to provide a notification of a pressure
communication on RU -03A to AOGCC within the next business day.
Cook Inlet Energy
Production
Osprey Platform
Osprey Platform, Cook Inlet, Alaska
RCA 2018-01
04/15/2018
11/05/2017
George Morris, COO; Stephen Ratcliff, VP of Drilling; Don Jones, Drilling Superintendent. Team Leader: David
Pascal, VP of Operations
2.1. Describe the sequence of events that was expected to take place. Attach flowchart if necessary.
Rule 8 of AID 32 requires the AOGCC to be notified by the next business day if pressure communication is indicated.
2.2. Was there a deviation for the expected sequence of events? If yes, describe. Attach flowchart if necessary.
Yes, the AOGCC was not notified immediately as required upon verification of annulus pressure increase.
2.3. Was any deviation from the expected sequence likely to have led to or did contribute to the adverse event? If yes, describe.
Yes, failure to report the communication caused the violation.
2.4. Was the expected sequence described in written policy, procedure, guidelines, or expressed in staff training? If yes, cite the
source.
Yes, the AIO 32 states "Whenever any pressure communication, leakage or lack of injection zone isolation is indicated... the
Operator shall notify the Commission by the next business day with a plan of corrective action for Commission approval."
2.5. Does the expected sequence or process meet any regulatory requirements and/or practice standards? Cite any references
reviewed by the team. If no, describe the the deviation from the requirements.
Yes. AOGCC regulatory requirements.
2.6. Did human action or inaction appear to contribute to the adverse event? If yes, describe the actions and how they contributed.
Yes, upon reviewing the indicators of the tubing and annulus communication, the decision was made to bleed off the pressure. Upon
further review, 2 pressure build up tests were conducted to try to validate the initial data set.
2.7. Did a defect, malfunction, misuse of, or absence of equipment appear to contribute to the event? If yes, describe what equipment
and how it appeared to contribute.
No.
2.8. Was the procedure or activity involved in the event being carried out in the usual location? If no, describe where and why a different
location was utilized.
Yes.
2.9. Was the procedure or activity being carried out by regular staff familiar with the consumer and activity? If no, describe who was
carrying out the activity and why regular staff were not involved.
Yes.
2.10. Were involved staff credentialed/skilled to carry out the tasks expected of them? If no, describe the perceived inadequacy.
Yes.
2.11. Were staff trained to carry out their respective responsibilities? If no, describe the perceived inadequacy.
Yes.
2.12. Were staffing levels considered to have been adequate at the time of the incident? If no, describe why.
Yes.
2.13. Were there other staffing factors identified as responsible for or contributing to the adverse event? If yes, describe those factors.
No.
2.14. Did inaccurate or ambiguous information contribute to or cause the adverse event? If yes, describe what information and how it
contributed.
Yes. Slight changes in annulus pressure can occur due to temperature variations in the fluid being injected compared to the fluid in
the annulus and rate of injection. Uncertainty in the readings caused the delay in the Agency notification.
2.15. Did a lack of communication or incomplete communication contribute to or cause the adverse event? If yes, describe who and
what and how it contributed.
Yes. The lack of direct communication with the Agency regarding the situation led to the violation.
2.16. Did any environmental factors contribute to or cause the adverse event? If yes, describe what factors and how they contributed.
No.
2.17. Did any organizational or leadership factors contribute to or cause the adverse event. If yes, describe what factors and how they
contributed.
Yes. All directly associated personnel are aware of the AIO requirements and should have identified the need for the Agency notification.
2.18. Did any assessment or planning factors contribute to or cause the adverse event? If yes, describe what factors and how they
contributed.
Yes. Proper assessment of the AIO requirements should have been reviewed when a change in the normal well activity was identified.
2.19. What other factors are considered relevant to the adverse event? Describe.
N/A
2.20. Rank order the factors considered responsible for the adverse event, beginning with the proximate cause, followed by the most
important to less important contributory factors. Attach Contributory Factors Diagram, if available.
1. Lack of communication with the AOGCC.
2. Uncertainty in the data resulting in a delay in Agency communication.
3. Lack of reference data for a similar scenario with a new injection well coming on line.
2.21. Was a root cause identified? If yes, describe.
Yes. The uncertainty in the pressure data caused a delay in communicating the issue to AOGCC and a lack of review of the
terms of the AIO 32 Rules prevented the urgency of notification to be identified.
3. RISK REDUCTION ACTIONS TAKEN List the actions that have already been taken to reduce the risk of a future occurrence of ti:-
consideration. Note the date of implementation.
The Rules of AIO 32 have been reviewed with all associated personnel and specifically between the VP of Operations and the
Osprey Platform Operators. Chain of Command for any future annulus communication indicators will require the Platform
Operator to notify the VP of Operations who will generate the Agency notification by the next business day with a plan of corrective
action for Agency approval.
4. INCIDENTAL FINDINGS List and describe any incidental findings that should be carefully reviewed tot correctr� r -.
None.
5. APPROVAL After review of this summary report. all learn members should notify the lean, leader of either their approval or reromrner,.,,::.
revision. Following all revisions the report should be signed by the learn leader prior to submission.
APPENDIX 5 - ROOT CAUSE ANALYSIS REPORT: Failure to complete an AOGCC witnessed MIT
once RU -03A commenced injection and stabilization was achieved.
Cook Inlet Energy
Production
Osprey Platform
Osprey Platform, Cook Inlet, Alaska
RCA 2018-02
04/15/2018
08/01/2017
George Morris, COO: Stephen Ratcliff, VP of Drilling; Don Jones, Drilling Superintendent. Team Leader: David
Pascal, VP of Operations
2.1. Describe the sequence of events that was expected to take place. Attach flowchart if necessary.
RU -03A was drilled and completed. Injection operations commenced July 1, 2017. Once injection conditions stabilized, the AOGCC
should have been notified to witness a MIT.
2.2. Was there a deviation for the expected sequence of events? If yes, describe. Attach flowchart if necessary.
Yes, a MIT was not scheduled once injection commenced and stabilized.
2.3. Was any deviation from the expected sequence likely to have led to or did contribute to the adverse event? If yes, describe
Yes, the conditions of Sundry 317-150 were received by Drilling Department and not communicated to Production and the full
requirement of Rule 6 of AIO 32 was overlooked.
2.4. Was the expected sequence described in written policy, procedure, guidelines, or expressed in staff training? If yes, cite the
source.
Yes, AID 32 Rule 6 states "A Commission -witnessed MIT must be performed after injection is commenced for the first time in a
well, to be scheduled when injection conditions have stabilized."
2.5. Does the expected sequence or process meet any regulatory requirements and/or practice standards? Cite any references
reviewed by the team. If no, describe the the deviation from the requirements.
Yes. AOGCC regulatory requirements.
2.6. Did human action or inaction appear to contribute to the adverse event? If yes, describe the actions and how they contributed.
Yes, the terms of the Approved Sundry was not communicated after the well was handed over to Production from Drilling. The
Rules of AID 32 were not reviewed prior to commencing injection to ensure all requirements were met.
2.7. Did a defect, malfunction, misuse of, or absence of equipment appear to contribute to the event? If yes, describe what equipment
and how it appeared to contribute.
No.
2.8. Was the procedure or activity involved in the event being carried out in the usual location? If no, describe where and why a different
location was utilized.
Yes.
2.9. Was the procedure or activity being carried out by regular staff familiar with the consumer and activity? If no, describe who was
carrying out the activity and why regular staff were not involved.
Yes.
2.10. Were involved staff credentialed/skilled to carry out the tasks expected of them? If no, describe the perceived inadequacy
Yes.
2.11. Were staff trained to carry out their respective responsibilities? If no, describe the perceived inadequacy.
Yes.
2.12. Were staffing levels considered to have been adequate at the time of the incident? If no, describe why.
Yes
2.13. Were there other staffing factors identified as responsible for or contributing to the adverse event? If yes, describe those factors.
IM
2.14. Did inaccurate or ambiguous information contribute to or cause the adverse event? If yes, describe what information and how it
contributed.
No.
2.15. Did a lack of communication or incomplete communication contribute to or cause the adverse event? If yes, describe who and
what and how it contributed.
Yes. Production was not made aware of the Sundry requirement.
2.16. Did any environmental factors contribute to or cause the adverse event? If yes, describe what factors and how they contributed.
No.
2.17. Did any organizational or leadership factors contribute to or cause the adverse event. If yes, describe what factors and how they
contributed.
Yes. All directly associated personnel are aware of the AIO requirements and should have identified the requirement for the MIT.
2.18. Did any assessment or planning factors contribute to or cause the adverse event? If yes, describe what factors and how they
contributed.
Yes. A review of the AIO requirements should have been conducted prior to the start of injection.
2.19. What other factors are considered relevant to the adverse event? Describe.
N/A
2.20. Rank order the factors considered responsible for the adverse event, beginning with the proximate cause, followed by the
most important to less important contributory factors.
1. Lack of review of AIO requirements prior to start of injection.
2. Verification of Sundry conditions prior to handover of well from Drilling Department to Production Department to ensure they are
completed.
2.21. Was a root cause identified? If yes, describe.
Yes. The Rules of the AIO were not reviewed prior to the start of injection and the conditions of the Approved Sundry were
not passed on to Production.
3. RISK REDUCTION ACTIONS TAKEN List the actions that have already been taken to reduce the nsk of a future occurrence of pit,
consideration. Note the date of implementation.
The Rules of AID 32 have been reviewed with all associated personnel and specifically between the VP of Operations and the
Osprey Platform Operators. The specifics of Rule 6 have been discussed with both Drilling and Production to ensure
communication in the future is clear as to when the need for an MIT is required and that the AOGCC must be notified when one is
scheduled.
4. INCIDENTAL FINDINGS List and describe any incidental findings that should be careful(v reviewed for rr•: ; r r
None.
5 -APPROVAL After review of this summary report. all team members should notify, the learn leaderof ererrr.mori,�•r,••r , <;
revision. Following all revisions the report should be signed by the (earn leader prior to submission.
13
THE STATE
01ALASKA
GOVERNOR MIKE DUNLEAVY
January 15, 2019
Elena M. Romerdahl
Counsel for Cook Inlet Energy
Perkins Coie
1029 West Third Avenue, Suite 300
Anchorage, AK 99501-1981
Re: Docket Number: OTH-17-056
Dear Ms. Romerdahl:
Alaska Oil and Gas
Conservation Commission
333 West Seventh Avenue
Anchorage, Alaska 99501-3572
Main: 907.279.1433
Fax: 907.276.7542
w .aogcc.alaska.gov
Your January 14, 2019 letter requesting a 45 -day extension of time until March 9, 2019 to submit
the requested compliance program information and root -cause analyses in the above matter is
GRANTED.
Sincerely,
Hollis S. French
Chair, Commissioner
12
PeRKINSCOIe
January 14, 2019
VIA HAND DELIVERY
Commissioner Hollis S. French, Chair
Alaska Oil and Gas Conservation Commission
333 West 7th Avenue, Suite 100
Anchorage, AK 99501
Re: Docket Number: OTH-17-056
1029 West Third Avenue O +1.907.179.8561
Suite 300 O +1.907.276.3108
Anchorage. AK 99501-1981 perkinscoecom
Elena M. Romerdahl
ERomerdahl@perkinscoie.com
D. +1.907.263.6914
F. +1.907.263.6428
FEC IIIE
JAN 14 2019
ACGCC
Request for Extension of Time to Respond to Request for Information
Dear Mr. French:
On December 25, 2019, the Alaska Oil and Gas Conservation Commission ("the
Commission") issued a final Decision and Order in Docket OTH-17-056 assessing $50,000
in civil penalties and requiring Cook Inlet Energy, LLC ("CIE") to provide information
regarding its regulatory compliance programs and root -cause analyses of the violations
("the Final Order"). The Final Order requires CIE to pay the civil penalties within 30 days
of December 26—by Friday, January 25—and to submit the requested information and
root -cause analyses within four weeks of December 26—by Wednesday, January 23.
CIE does not intend to appeal the Final Order. CIE will pay the $50,000 in assessed
penalties within 30 days of December 26, as required by the Final Order. However, CIE
respectfully requests a 45 -day extension of time until March 9 to submit the requested
compliance program information and root -cause analyses. CIE is currently preparing the
requested information and analyses but was delayed in beginning its preparation due to the
holidays. The requested 45 -day extension will allow CIE to ensure that the information
and analyses it provides to the Commission are thorough and complete. Thank you for
your consideration.
Sincerely,
Elena M. Romerdahl
Counsel for CIE
11
Cook Inlet Energy_
October 31, 2018
VIA HAND DELIVERY
Commissioner Cathy Foerster
Alaska Oil and Gas Conservation Commission
333 West 7th Avenue, Suite 100
Anchorage, AK 99501
RECEIVE®
OCT 11 2018
AOGCC
Re: Supplemental Information Request by Commissioner Foerster During Formal
Hearing on Request for Reconsideration of Other Order 142
Dear Commissioner Foerster:
During the October 24, 2018 hearing on CIE's Request for Reconsideration of Other Order 142,
you requested that Cook Inlet Energy, LLC ("CIE") indicate in writing whether it was complying
with the requirements in AI032.001 prior to the date AIO 32.001 was issued on December 28,
2017. Below is a list of the requirements established by AIO 32.001. Under each requirement,
CIE has indicated whether it was complying with the requirement before AOGCC issued AIO
32.001, and whether CIE is currently complying with the requirement.
AI032.001 Requirements
CIE shall record wellhead pressures and injection rate daily;
a. Before Issuance: Fully compliant.
b. After Issuance: Fully compliant.
2. CIE shall submit to the AOGCC a monthly report of well pressures, injection rates,
and pressure bleeds for all annuli. Bleeds to be flagged on the report;
a. Before Issuance: Compliant with the requirement to submit monthly report of
well pressures and injection rates. Not compliant on submitting monthly
reports of pressure bleeds as it is not required by regulations. However, CIE
keeps logs of pressure bleeds.
b. After Issuance: Fully compliant.
CIE shall perform a mechanical integrity test of the inner annulus every 2 years to the
minimum of 2500 psi;
a. Before Issuance: Fully compliant.
b. After Issuance: Fully compliant.
4. CIE shall install, maintain and operate automatic well shut-in equipment linked to the
well's inner annulus (IA) pressure. The actuation pressure shall not exceed 2,500 psi
for the inner annulus;
a. Before Issuance: Not compliant, as this is not required by AOGCC
regulations. CIE proposed that this condition be included in AIO 32.001
during our discussions with AOGCC.
b. After Issuance: Fully compliant.
5. Testing of the shut in equipment shut -down valve and mechanical or electrical
pressure device shall be performed in conjunction with production well pilots and
safety valves. CIE shall provide to the commission the testing procedure that will be
used to verify integrity of the well shut-in equipment linked to the inner annulus
pressure;
a. Before Issuance: Not compliant, as this is not required by AOGCC
regulations. Like requirement 4, CIE proposed that this condition be included
in AIO 32.001 during our discussions with AOGCC.
b. After Issuance: Fully compliant.
6. CIE shall immediately shut in the well and notify the AOGCC if there is any change
in the well's mechanical condition;
a. Before Issuance: After CIE notified AOGCC that a change in pressure
indicated a potential change in the well's mechanical condition, AOGCC
ordered an MIT. The well passed the MIT, and AOGCC did not require CIE
to shut in the well.
b. After Issuance: Fully compliant.
7. After well shut in due to a change in the well's mechanical condition, AOGCC
approval shall be required to restart injection; and
a. Before Issuance: As noted above, AOGCC did not require the well to be shut
in after the well passed an MIT, but CIE worked with AOGCC on issuance of
AIO 32.001 and necessary approvals to continue injecting
b. After Issuance: Fully compliant.
8. The next required MIT is to be before or during the month of December 2019. The
Commission must be provided the opportunity to witness the MIT for a test to
establish a new test due date.
-2-
a. Before Issuance: Fully compliant (date has not yet occurred).
b. After Issuance: Fully compliant (date has not yet occurred).
Please let us know if we can provide any further clarification. Again, we appreciate the opportunity
to discuss our Request for Reconsideration on Other Order 142 with the Commission. Thank you
for your consideration.
Sincerely,
e" � 3t VV r
� � 1
Dav d Pascal
Vic President of Operations
Cook Inlet Energy, LLC
(907)433-3822
dpascal@glacieroil.com
-3-
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
ALASKA OIL AND GAS CONSERVATION COMMISSION
In the Matter of the Request by Cook )
Inlet Energy, LLC, for Reconsideration )
of Other Order 142, Redoubt Unit 3A Well )
Violations. )
Docket No: OTH 17-056
ALASKA OIL and GAS CONSERVATION COMMISSION
Anchorage, Alaska
October 24, 2018
1:00 o'clock p.m.
PUBLIC HEARING
BEFORE: Hollis French, Chair
Cathy Foerster, Commissioner
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
I
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
Page 2
1
TABLE OF CONTENTS
2
Opening remarks
by Chair French
03
3
Comments by Mr.
Elliott
07
4
Comments by Mr.
Pascal
10
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 3
1 P R O C E E D I N G S
2 (On record)
3 CHAIRMAN FRENCH: I'm going to call the meeting
4 to order. It's 1:00 o'clock in the afternoon of
5 October 24, 2018. We're at 333 West Seventh Avenue,
6 Anchorage, Alaska, the headquarters of the Alaska Oil
7 and Gas Conservation Commission. To my right is
8 Commissioner Cathy Foerster and I'm Hollis French, a
9 Commissioner and the Chair of the Commission.
10 We're here today on docket number 0TH 17-056, a
11 motion for reconsideration dealing with the Redoubt
12 Unit 3A well violations. Cook Inlet Energy has
13 requested a hearing. Upon reconsideration of the above
14 docket we have obviously granted their request and
15 that's why we're all here.
16 Computer Matrix will be recording the
17 proceedings, you can get a copy of the transcript from
18 Computer Matrix Reporting.
19 We've got folks here from Cook Inlet Energy
20 signed up to testify, two people. Are there any other
21 parties planning to testify?
22 (No comments)
23 CHAIRMAN FRENCH: I don't hear or see anyone
24 responding. Commissioners may ask questions during
25 testimony, we may also take a recess to consult with
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 4
1 staff to determine whether additional information or
2 clarifying questions are necessary. If a member of the
3 audience has a question that he or she feels should be
4 asked please submit that question in writing to Jody
5 Colombie. She'll provide the question to us and if we
6 feel it's helpful for us in making our decision we'll
7 ask that question to those of you who are testifying.
8 When you are testifying please keep in mind you must
9 speak into the microphone, check and make sure the
10 little green light is on before you start, that's the
11 most common error we have. Remember to reference your
12 slides. Are you doing a slide show today?
13 UNIDENTIFIED VOICE: No.
14 CHAIRMAN FRENCH: Shaking of heads, no slides.
15 So we don't have to worry about that. I may ask you
16 about some of the material you presented though, but
17 we'll get to that when we get there. Of course keep
18 your testimony relevant to the proceeding today, if you
19 drift off topic we'll ask you to get back on topic.
20 Commissioner Foerster, anything to add before
21 we get started?
22 COMMISSIONER FOERSTER: No. I just have one
23 question. Do you guys prefer to be referred to as Cook
24 Inlet or Glacier?
25 UNIDENTIFIED VOICE: Glacier (indiscernible -
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email sahile@gci.net
r
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
10 please.
11
Page 5
1 away from microphone) parent
company, Cook
Inlet is the
2 subsidiary.....
13
3 REPORTER: Please use
your microphone.
4 CHAIRMAN FRENCH: Oh,
actually why
don't you
5 guys come forward and that'll
be the first
question we
6 ask you once we -- we'll just
go ahead and
get you
7 sworn in and then we'll go from there.
MR. PASCAL: My name is David Pascal.
8 UNIDENTIFIED VOICE:
Sure.
9 CHAIRMAN FRENCH: First
raise your
right hands,
10 please.
11
(Oath administered)
12
IN UNISON: I do.
13
CHAIRMAN FRENCH: Excellent. Please
sit down
14
and
one at a time, we'll start with you, sir,
on the
15
left, my left, identify yourself.
16
MR. PASCAL: My name is David Pascal.
17
CHAIRMAN FRENCH: Green light on your
-- push
18
the
-- there's a little button in the mid --
there you
19
go.
20
MR. PASCAL: There you go.
21
CHAIRMAN FRENCH: Yeah, bingo. Very
good.
22
MR. PASCAL: Oh. My name is David Pascal and
23
I'm
vice president of operations for Glacier
Oil and
24
Gas.
25 CHAIRMAN FRENCH: Okay.
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
I
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 6
1 MR. ELLIOTT: I am Phillip Elliott, I'm the
2 president of Glacier Oil and Glass.
3 CHAIRMAN FRENCH: Okay. And now the question
4 from Commissioner Foerster, how do you -- how do you
5 prefer to -- which company or what subsidiary are we
6 dealing with here at Redoubt?
7 MR. ELLIOTT: I mean, we are dealing with Cook
8 Inlet Energy as the -- as the operator of.....
9 CHAIRMAN FRENCH: Okay.
10 MR. ELLIOTT: .....the assets.
11 CHAIRMAN FRENCH: Okay.
12 MR. ELLIOTT: The -- you know, the vernacular
13 or the doing business as is Glacier.
14 COMMISSIONER FOERSTER: Okay. I was just
15 confused because you all signed is as Glacier.
16 CHAIRMAN FRENCH: Yeah, I'm probably going to
17 stick with Cook Inlet just because -- I mean, if that's
18 the operator, if that's the -- I mean, the hard hats of
19 the guys working out there say Cook Inlet.
20 COMMISSIONER FOERSTER: That's the -- is that
21 the operator of record, Glacier or Cook.....
22 MR. ELLIOTT: The op -- no, they actually say
23 Glacier, but we -- but it is the operator of record.
24 COMMISSIONER FOERSTER: Cook Inlet is the
25 operator of record and the hard hats say Glacier.
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
1 Okay.
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 7
2 CHAIRMAN FRENCH: All right. Clarification.
3 Very good. Who wants to start?
4 MR. ELLIOTT: I will, sir.
5 CHAIRMAN FRENCH: Please.
6 PHILLIP ELLIOTT
7 previously sworn, called as a witness on behalf of CIE,
8 testified as follows on:
9 DIRECT EXAMINATION
10 MR. ELLIOTT: Respected Commissioners, AOGCC
11 staff members and members of the public, thank you for
12 providing us with the opportunity to discuss our
13 request for reconsideration of other order 142 issued
14 on June 25th, 2018. My name is Phillip Elliott and I
15 am the president of Glacier Oil and Gas and its
16 subsidiary, Cook Inlet Energy. My tenure at Glacier
17 started in April of 2015, shortly before the company
18 declared bankruptcy. I along with others, including
19 David Pascal, our VP of operations for Glacier, have
20 been working diligently over the last three years
21 fixing the company, making it a better place to work, a
22 better partner for Alaska, basically trying hard to do
23 the right things. And I think we've accomplished a lot
24 and made a lot of progress. We are clearly not
25 perfect, but there is no doubt that we are much
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
I
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
1 different and a much better company than before
2 bankruptcy.
3 So, I mean, how have we tried to do the right
4 things. I know that the Commission is very focused on
5 P&A liabilities. Proactively we have tackled this
6 problem by P&Aing six wells for about a million
7 dollars. When you put this in context to the number of
8 shut in wells that we operate, this is a fairly
9 impressive endeavor. Our efforts have addressed 40
10 percent of the non -producing wells in our portfolio.
11 Next one of our first projects out of
12 bankruptcy was focused on addressing the antiquated oil
13 processing facility at our West McArthur field. The
14 facility was experiencing spills and increasing safety
15 issues from our perspective. Knowing the situation was
16 not sustainable we engineered a consolidation of the
17 production facility into our nearby Kustatan facility.
18 The cost was material at $4 million, but the results
19 were noticeable. In 2015 and 2016 there were 11 spills
20 related to West McArthur, in 2018 that number has been
21 exactly zero.
22 Compliance matters are one of the most
23 important responsibilities of our company. Prior to
24 bankruptcy I'm almost reluctant to admit how bad we
25 were with regulatory compliance, but we did not have
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 9
1 the dedicated resources necessary period, no reason to
2 make excuses. Since bankruptcy we've hired four
3 subject matter experts to review, refine and/or build
4 our compliance systems and processes. Part of this
5 effort has been focused on building redundancies into
6 our approach so as to avoid compliance failures. Again
7 we are not perfect, but we now have the staff to
8 address the issues.
9 We have implemented a safety first culture and
10 most -- our most valuable resource is our employees and
11 contractors. This approach has permeated our company
12 and paid significant dividends. Knock on wood, we have
13 not had one lost time accident this year, not one.
14 Maybe not as important as everything else we've
15 accomplished, but we did this all, plugged wells, shut
16 down ailing oil processing facilities, built a
17 regulatory compliance function, all the while
18 successfully investing over $60 million in our assets
19 which resulted in increased production.
20 I hope it is clear that we take pride in our
21 operations and are committed to ensuring that we follow
22 all applicable laws and regulations. Also that we have
23 made significant strides in -- since emerging from
24 bankruptcy. I'm not excusing our missteps, but I do
25 commit to working closely with the state and federal
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 10
1 agencies, including the Commission, to ensure that our
2 operations which are exclusively in Alaska, support
3 resource conservation and environmental protection. I
4 do not think there is any other way to approach this,
5 we are all in.
6 Finally we very much value the role the
7 Commission plays in overseeing the responsible
8 development of the state's resources and we are
9 committed to continuing to work with you to ensure that
10 our operations comply with the AOGCC's requirements.
11 I want to thank you again for your time and
12 reconsideration in this matter.
13 With that I'm going to hand it off to David to
14 walk through the technical details of this matter.
15 Thank you.
16 DAVID PASCAL
17 previously sworn, called as a witness on behalf of CIE,
18 testified as follows on:
19 DIRECT EXAMINATION
20 MR. PASCAL: Well, thank you, Phillip, for the
21 statement. And respected Commissioners and staff, once
22 again my name is David Pascal, I'm the vice president
23 of operations for CIE. I've been with the company
24 since September, 2013.
25 On March 15th, 2018 the Commission issued a
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: while@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 11
1 notice of proposed enforcement action to CIE related to
2 the Redoubt Unit 3A well. The notice alleged that CIE
3 failed to report to AOGCC the casing tubing pressure
4 communication and failed to complete the required
5 mechanical integrity test on RU 3A. The notice also
6 proposed specific corrective actions and a $50,000
7 civil penalty.
8 CIE requested an informal review which was held
9 by Commission staff on April 10th, 2018. At the
10 informal review CIE provided details regarding what
11 happened at RU 3A and additional documentation to the
12 Commission staff and requested that the Commission
13 reconsider the notice of proposed enforcement action
14 based on this additional information and documentation
15 that clarified what actually occurred at RU 3A.
16 The next communication CIE received from the
17 Commission was other order 142 which largely restated
18 the claims that were in the notice of proposed
19 enforcement. As were described in our request for
20 reconsideration other order 142 notes that an informal
21 review took place, but does not acknowledge or discuss
22 any of the information and documentation provided to
23 the Commission staff during the April 10th informal
24 review.
25 Under AS 31 05.150 subsection (g), the
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 12
1 Commission is required to consider certain factors when
2 recommending the amount of civil penalty. We believe
3 that the information and documentation presented to the
4 Commission staff during the informal review was
5 relevant to several of these factors. CIEs request
6 for reconsideration of other order 142 requests that
7 the Commission review the information and documents
8 provided to the Commission staff on April 10 and
9 reconsider its decision to impose a $50,000 civil
10 penalty in light of the additional information and
11 documentation.
12 I would therefore like to take a few moments
13 now to briefly summarize the information and
14 documentation CIE provided at the informal review.
15 The first infraction discussed in other order
16 142 was CIE failed to perform an MIT with an AOGCC
17 inspector onsite to witness prior to well start-up.
18 During the April 10 informal review CIE explained that
19 we did in fact perform a successful MIT prior to well
20 start-up. CIE provided Commission staff the
21 documentation of that test. We also attached those
22 documents to our request for reconsideration. Although
23 CIE failed to notify the Commission of the planned test
24 in order to allow for an inspector to be present, the
25 documentation provides proof that CIE did in fact
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 13
1 perform the required test prior to start-up, a fact
2 that is not included in the Commission's order. Upon
3 receiving notification from the Commission that CIE had
4 failed to submit proof of a witnessed MIT, CIE acted
5 immediately to ensure that the second MIT was performed
6 with an AOGCC witness present.
7 Although CIE failed to fully comply with the
8 Commission's MIT requirements, it did comply in part by
9 performing the test prior to start-up as evidenced by
10 the documentation provided to the Commission. More
11 importantly CIE's failure to have a witness present did
12 not result in harm or risk of harm to people or the
13 environment. As I will explain further we believe that
14 the documentation provided during the informal review
15 with our request for reconsideration clearly
16 demonstrates that neither of the infractions cited in
17 other order 142 resulted in harm or risk of harm to
18 people or the environment.
19 Upon discovering that the initial MIT was not
20 properly witnessed, CIE performed a root cause analysis
21 to determine why those conducting the MIT did not
22 contact an inspector to witness the test. We
23 identified a communication gap in the field between
24 departments that we have since corrected by
25 implementing additional system processes and
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch, AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 14
1 redundancies. Prior to initiating any new project now
2 all members of the project team are briefed on the
3 requirements applicable to the project. Project team
4 members provide regular compliance reports to the
5 project lead and the project lead maintains oversight
6 to ensure the project team members are satisfying all
7 compliance requirements.
8 Compliance requirements and satisfaction of
9 those requirements are documented in the compliance
10 program which is called TaskOps. CIE currently has
11 only two class II injection wells and the system we
12 have implemented allows us to ensure that operations at
13 these two class II wells comply with all Commission
14 regulations.
15 In consideration of the fact that CIE acted in
16 good faith, the violation did not pose an actual or
17 potential threat to the public or the environment and
18 CIE immediately conducted a witnessed MIT after it
19 realized that it had not fully complied with AOGCC's
20 regulations, CIE respectfully requests the Commission
21 to reduce the proposed $25,000 civil penalty for this.
22 Second the Commission has imposed an additional
23 penalty of $25,000 for failure to notify the Commission
24 of a tubing annulus communication on RU 3A after the
25 well was brought online. At the informal hearing and
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 15 1
1 in our request for reconsideration we explained in
2 detail the circumstances surrounding the event. We
3 also provided raw data to the Commission for in depth
4 review. As stated in the correspondence between CIE
5 personnel and AOGCC staff, the original pressure
6 response was thought to be due to thermal expansion
7 which is often seen in new completions. The leak was
8 so small that CIE was able to pass an AOGCC conducted
9 MIT on December 23rd, 2017. After additional testing
10 was conducted we determined the amount of leak ranged
11 between .025 gallons per day to .9 gallons per day
12 depending upon compressive (indiscernible). CIE
13 informed the Commission immediately upon determining
14 that there was indeed a tubing annulus communication
15 and not simply a temperature anomaly.
16 Once again CIE acted in good faith, was
17 proactive when an issue was identified and implemented
18 automatic shutdown systems to protect the annulus in
19 case the leak increased. These automatic systems are
20 being tested frequently and regularly and included as
21 part of the SVS testing program. Further, CIE
22 recognizes the Commission would like to receive more
23 frequent communication from CIE and is updating the
24 Commission on a monthly basis regarding the status of
25 the well, including any bleeds. Due to the small
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 16
1 nature of the leak there has been no bleed since CIE
2 notified the Commission of a possible communication.
3 Based upon these facts which were presented at
4 informal review and in our request for reconsideration
5 and particularly the fact that CIE immediately notified
6 the Commission when it determined that there was a
7 possible communication, CIE respectfully requests the
8 Commission reconsider this violation and reduce the
9 fines associated with it.
10 We would also like to take a moment to discuss
11 our communication and cooperation with the AOGCC
12 generally. In the months leading up to the
13 Commission's issuance of other order 142 CIE was
14 working one on one with the AOGCC staff to find a path
15 forward on RU 3A. This resulted in the issuance of AIO
16 32-001 which granted CIE approval to keep injecting
17 into RU 3A not withstanding the known tubing annulus
18 communication. In AIO 32-001 the Commission clearly
19 states quote, the well condition does not compromise
20 overall well integrity so as to threaten human safety
21 or the environment, close quotes. Yet in order 142 the
22 Commission asserts that the potential wellbore failure
23 posed an obvious threat to both public health and the
24 environment, a statement which is inconsistent with the
25 Commission's previously issued AIO.
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste, 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
i
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 17
1 As previously noted we believe that the
2 documents provided the Commission at the informal
3 review and with our request for reconsideration show
4 that although we failed to strictly comply with all the
5 Commission's requirements there was never a threat to
6 public health or safety.
7 CIE has consistently demonstrated its
8 commitment to working with the Commission to resolve
9 issues that may arise and believed it was working
10 cooperatively with the Commission to provide
11 information about the infractions and resolve the
12 Commission's concerns when other order 142 was issued.
13 As noted earlier we are committed to ensuring that our
14 operations comply with all AOGCC requirements and we
15 hope that we can work collaboratively to resolve
16 concerns that the Commission may have in the future.
17 Finally the Commission requested that CIE
18 provided detailed information regarding CIE's
19 compliance programs, processes and tracking systems
20 addressing not only the UIC program, but also every
21 other AOGCC statute and regulation. As we discuss in
22 our request for reconsideration we believe that CIE's
23 record of safety and compliance in Alaska reflects its
24 ability to manage its internal compliance systems.
25 Nevertheless CIE is willing to provide the Commission
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
i 1
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 18
1 with a more detailed summary of CIE's compliance
2 processes and tracking systems in order to demonstrate
3 our commitment to working with the Commission.
4 We want to thank the Commission for providing
5 us with an opportunity to discuss our request for
6 reconsideration and shed light on the matters discussed
7 in other order 142. We want to emphasize again that
8 CIE is dedicated to continuing our work with the
9 Commission to resolve the matters discussed in other
10 order 142 and ensure continued compliance with AOGCC
11 generally. We would be happy to answer any
12 questions the Commission may have for us right now.
13 Thank you.
14 CHAIRMAN FRENCH: Gentlemen, I have a couple
15 questions and I think Commissioner Foerster will as
16 well. But what we're going to do first is take about a
17 10 minute recess while we just tag up with staff about
18 a few details of the informal review and so forth and
19 we'll be back and then go on the record and ask those
20 questions.
21 I will let you know ahead of time I'm probably
22 going to ask and will ask you about this so just make
23 sure that the other folks have access to that pressure
24 trend and when we come back we'll talk about it and a
25 couple other things.
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 19
1 We'll stand in recess.
2 MR. ELLIOTT: I do appreciate it.
3 (Off record)
4 (On record)
5 CHAIRMAN FRENCH: We'll go back on the record,
6 it's about 1:33 in the afternoon.
7 We're going to break -- we're going to take
8 this topic by topic and the first set of questions will
9 come regarding the failure to perform a witnessed MIT.
10 COMMISSIONER FOERSTER: So I'd like to read
11 rule 6 of AIO 32 under which this well operates. The
12 mechanical integrity of an injection well must be
13 demonstrated before injection begins and before
14 returning a well to service following a workover
15 affecting mechanical integrity. A Commission witnessed
16 mechanical integrity test must be performed after
17 injection is commenced for the first time in a well to
18 be scheduled when injection conditions, temperature,
19 pressure, rate, et cetera, have stabilized. Subsequent
20 tests must be performed at least once every four years
21 thereafter.
22 Did you guys comply with that rule?
23 MR. PASCAL: We did do a -- we did an MIT test
24 before the well was put in service.
25 COMMISSIONER FOERSTER: Okay. So you did the
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 20
1 first test?
2
MR. PASCAL: We did the first test.
3
COMMISSIONER FOERSTER:
And then there was the
4
second test.
5
CHAIRMAN FRENCH: Go ahead.
6
COMMISSIONER FOERSTER:
You did the rig test
7
before the.....
8
MR. PASCAL: We did do
a second test, but it
9
was quite late.
10
COMMISSIONER FOERSTER:
How late was -- when
11
was it performed?
12
MR. PASCAL: So if you
go back to attachment --
13
give me one second, attachment
two for the informal
14
documents which has a timeline
of events on it, so the
15
second MIT test was done on the
18th -- on the 23rd of
16
December. I'm sorry.
17
COMMISSIONER FOERSTER:
On the 23rd of
18
December.
19
MR. PASCAL: Yes.
20
COMMISSIONER FOERSTER:
And when was the well
21
brought on production?
22
MR. PASCAL: The well was brought on production
23
1st of July.
24
COMMISSIONER FOERSTER:
The 1st of July. So do
25
you think it took six months for that well to
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
l �
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 21
1 stabilize?
2 MR. PASCAL: No, it did not.
3 COMMISSIONER FOERSTER: That was a rhetorical
4 question, you don't need to answer it.
5 CHAIRMAN FRENCH: Well, actually, I mean, I do
6 have a question about that. How long generally after
7 you bring a well on does it take to have the
8 temperature and pressure conditions stabilize?
9 MR. PASCAL: It depends upon the well exactly
10 because what normally happens in the Cook Inlet is that
11 you're injecting really cold water which is coming
12 across subsea pipelines into relatively warm reservoirs
13 so it takes quite a bit of time for the well to
14 stabilize, probably a quarter or more. A quarter or
15 more.
16 CHAIRMAN FRENCH: Three months?
17 MR. PASCAL: Yeah, depending upon injection
18 rates, pressures, temperatures, conditions and stuff
19 like that. But the point to be taken here is we as
20 Cook Inlet Energy, we never brought a well online, you
21 know, without completely, fully testing it for its
22 mechanical integrity.
23 COMMISSIONER FOERSTER: Okay. So when you
24 state in your testimony that you complied with the
25 regulation, you did not, you did not comply with the
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
1
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 22
1 rule. The rule says that you will perform a test after
2 the well is brought on injection and has stabilized.
3 And you testified that you complied, but you did not,
4 is that accurate?
5 MR. PASCAL: We have complied by bringing a
6 well online with no mechanical integrity issues, we did
7 not call the AOGCC for witness which was regretted
8 obviously.
9 COMMISSIONER FOERSTER: The regulation -- the
10 rule in the injection order requires that as soon as
11 the well is stabilized you will perform another
12 mechanical integrity test. Did you do that? It's a
13 yes or no question.
14 MR. PASCAL: The answer is yes, but it was
15 late.
16
COMMISSIONER
FOERSTER:
As -- the question was
17
as soon as. So yes,
but we were late is not as soon
18
as. So I'll ask the
question again. As soon as the
19
well stabilized did you comply
with the requirement to
20
perform a mechanical
integrity
test and have it
21
witnessed?
22
MR. PASCAL:
The answer
is no.
23
COMMISSIONER
FOERSTER:
Thank you. Whoo. That
24
was painful.
25
Do you have any more --
go ahead, that was the
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 23
1 only question I had.
2 CHAIRMAN FRENCH: On that topic, no, I got the
3 answer to the amount of time. Well, let me just ask
4 who is now in charge, is there a single person in
5 charge at Glacier or Cook Inlet in charge of regulatory
6 compliance?
7 MR. PASCAL: That depends upon what regulatory
8 compliances because there is not only AOGCC, there is
9 ADC, there's ETA, so there's several people within the
10 organization who are responsible for compliance
11 depending upon what task it has.
12 CHAIRMAN FRENCH: And how about for our
13 regulations?
14 MR. PASCAL: For AOGCC compliance we have a
15 drilling and production team and it is the joint
16 efforts of both these teams to ensure that AOGCC
17 compliance requirements are met.
18 CHAIRMAN FRENCH: Okay. Then I want to ask a
19 couple questions about the other violation and that's
20 the failure to notify about a pressure communication.
21 And I'm looking at attachment three which you have --
22 do you have a copy in front of you?
23 MR. ELLIOTT: I do.
24 CHAIRMAN FRENCH: And if I -- it looks to me
25 like there were one, two, three, four, five, six,
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.nel
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 24
1 seven, say eight small pressures up to about 100 pounds
2 and then bleed offs before you really ramped -- allowed
3 the pressure to ramp up to about a thousand pounds,
4 does that look right, about.....
5 MR. PASCAL: That's right.
6 CHAIRMAN FRENCH: .....six, seven, eight bleed
7 offs and then you let the pressure build up to a
8 thousand pounds? This was all taking place -- and the
9 well was brought on in July.....
10 MR. PASCAL: Yes. And just.....
11 CHAIRMAN FRENCH: .....1st of July?
12 MR. PASCAL: .....just to let you know, some of
13 those things may be due to shutting and stopping
14 injection operations into the well. So what happens is
15 when you're injecting cold water you have thermal
16 expansion affects which causes easily a hundred to 200,
17 maybe even sometimes even a 300 psi differences in a
18 well -- while the well is settling up.
19 CHAIRMAN FRENCH: Well, and is that born out by
20 your operation records, were you in fact bringing the
21 well on and shutting it in?
22 MR. PASCAL: Yeah, normally when a new
23 injection well is brought online we take all steps to
24 ensure that we're injecting the right amounts of fluid
25 and we try to optimize our operations between producing
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 25
1 wells and the amount of fluids required to be injected
2 because we are also trying to manage a reservoir
3 here.....
4 CHAIRMAN FRENCH: Sure.
5 MR. PASCAL: .....so depending upon what is
6 replacement ratios and what the well is capable of
7 taking which depends upon permeability and other
8 factors we have to adjust rates. So there's a lot of
9 testing which goes on before we decide on a rate which
10 we have to inject.
11 CHAIRMAN FRENCH: Well, let me stay on this
12 point then for just a minute because you've given me
13 two alternative explanations for these build ups and
14 drop offs in pressures, there were either bleeds or
15 they were operational, bringing the well on and
16 shutting the well in.
17 MR. PASCAL: They're a combination of both.
18 CHAIRMAN FRENCH: So as you sit there today,
19 you know, they were -- were they half and half, half
20 bleeds, half operational shut ins?
21 MR. PASCAL: I don't have the answer right now,
22 but we can get back to you.
23 CHAIRMAN FRENCH: Some combination.....
24 MR. PASCAL: Some combination.
25 CHAIRMAN FRENCH: .....not purely bleeds and
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
i
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 26
1 not purely operational. And it was brought on you said
2 on the 1st of July roughly?
3 MR. PASCAL: I believe that is correct.
4 CHAIRMAN FRENCH: Okay. 1st of July. So July,
5 August, September, three months. So if the well had
6 stabilized after a couple months when the first large
7 pressure build up was allowed to take place from zero
8 to about a thousand psi, that looks to me like it took
9 about a month for that to occur; is that right?
10 MR. PASCAL: That is correct.
11 CHAIRMAN FRENCH: Looking back now at that
12 pressure increase when -- looking back now when do you
13 think you should have let us know about your
14 communication problem?
15 MR. PASCAL: Well, in this case we did our best
16 to collect data and find out if it was a tubing annulus
17 communication. I would like to point out that the
18 whole build up you see right there resulted in less
19 than two gallons of fluid being recovered from the
20 annulus.
21 COMMISSIONER FOERSTER: Did he answer your
22 question.
23 MR. ELLIOTT: But let's clarify that. The
24 first time that there was an anomaly, regardless of
25 what the explanation is, we should have called. That
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH I7-056
Page 27
1 is our forward going process. we thought we had a
2 technical explanation that explained what was going on
3 and it turned out to be incorrect and that's when we
4 called. Going forward it is as soon as we have
5 something that can be explained as a leak, but there
6 are other explanations, that's when we call. And
7 that's when we should have called.
8 MR. PASCAL: And that is why we did two tests,
9 a minimum of two tests to find out what is the amount
10 of leak because it's very impossible to just do one
11 test and find out what is happening. And we realize
12 that, yes, it's a -- it's a leak and it's a really,
13 really small leak and like we said the leak was so
14 small that even today we go and we can pass an MIT test
15 pretty easily. So.....
16 CHAIRMAN FRENCH: I mean, I guess I.....
17 MR. PASCAL: .....that was a time in which we
18 said like, okay, it's a -- we will hand over that
19 information to the AOGCC and work with them to find a
20 solution.
21 CHAIRMAN FRENCH: Right. I mean, you can see
22 it from our perspective, I mean, what's -- there's no
23 downside to reporting a problem, right, there isn't
24 one.....
25 MR. ELLIOTT: Correct.
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 28
1 CHAIRMAN FRENCH: .....in fact you stay out of
2 trouble by reporting the problem?
3 MR. ELLIOTT: Look you're absolutely correct
4 and that -- that is the learning that we've taken away
5 from that.
6 CHAIRMAN FRENCH: Right. It may be a
7 temperature anomaly that goes away in a few days when
8 it all stabilizes, but I'm clear because I told the cop
9 we got a prob -- you know, it might be temperature, it
10 might be pressure, I don't know what it is, but it's --
11 you know, it's getting to be.....
12 MR. ELLIOTT: We fully appreciate.....
13 CHAIRMAN FRENCH: Right.
14 MR. ELLIOTT: .....that. And that's.....
15 CHAIRMAN FRENCH: Right.
16 MR. ELLIOTT: .....that is our operations going
17 forward.
18 COMMISSIONER FOERSTER: Well, I'm troubled by
19 the fact that this is a learning for you because 20 AAC
20 25.402(f), if an injection rate, operating pressure
21 observation or pressure test indicates pressure
22 communication or leakage in any casing, tubing, packer,
23 dah, dah, dah, the operator shall notify the Commission
24 by the next working day. And that rule has been in
25 effect for an awfully long time and it shouldn't be
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Arch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 29
1 something that you learned to comply with recently.
2 MR. PASCAL: And the only answer I can give you
3 on that is as soon as we were able to find out what
4 exactly the leak rate was.....
5 COMMISSIONER FOERSTER: That's not what the
6 rule says.
7 MR. PASCAL: .....we notified the Commission
8 the very next day.
9 COMMISSIONER FOERSTER: That's not what the
10 rule says.
11 CHAIRMAN FRENCH: I think the last point I'm
12 just going to make is that with respect especially to
13 the pressure communication, even if we go out to the
14 end of the second build up which I think was terminated
15 around November 5th if I remember that right from your
16 pleadings, the statute gives the authority to impose a
17 $100,000 find and then $10,000 per day after that. So,
18 I mean, I appreciate you guys coming in and asking for
19 us to lower the fines, but $25,00 is a small fraction
20 of that potential liability, I guess I'll just say
21 that.
22 COMMISSIONER FOERSTER: I have one more
23 question on this (indiscernible - simultaneous
24 speech).....
25 CHAIRMAN FRENCH: Go ahead, Commissioner
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 30
1 Forester.
2 COMMISSIONER FOERSTER: As you know the
3 Commissioners weren't present in the informal review,
4 but the staff that were present took notes and in his
5 notes of your informal review comments, Mr. Regg
6 pointed out that you stated that you were aware of the
7 prob -- that you had a problem in August. Did he take
8 notes correctly or incorrectly?
9 MR. PASCAL: Well, we knew something was
10 happening because the field notified us. I don't know
11 exactly if it was August, but that is when we exactly
12 started doing the test to determine what is going on,
13 to make sure it was not a temperature anomaly.
14 COMMISSIONER FOERSTER: Okay. So that's the
15 point at which 25.402(f) should have kicked in for you
16 is August. And then remind me again when did you
17 report the problem to the AOGCC, what was the date?
18 MR. PASCAL: The problem was reported to the
19 AOGCC on 18th of December.....
20 COMMISSIONER FOERSTER: Okay. So.....
21 MR. PASCAL: .....as soon as the second test
22 was conducted and.....
23 COMMISSIONER FOERSTER: Okay.
24 MR. PASCAL: .....verified.
25 COMMISSIONER FOERSTER: So four months later.
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 tTMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 31
1 Four months later. Okay.
2 Do you have any -- are we done with this one?
3 CHAIRMAN FRENCH: I think we're done with this
4 one.
5 COMMISSIONER FOERSTER: Okay. I've got one
6 more.
7 CHAIRMAN FRENCH: Please go ahead.
8 COMMISSIONER FOERSTER: You made the assertion
9 that our statement in our notice of enforcement and our
10 order regarding this issue was inconsistent with our
11 admin approval. That the admin approval had several
12 conditions and requirements for safe operation. Were
13 you operating in compliance with all of those
14 requirements prior to issuance of the administrative
15 approval? And if your answer is yes I'm going to ask
16 you to take them one by one and explain to me that they
17 were.....
18 MR. PASCAL: I.....
19 COMMISSIONER FOERSTER: .....if you were.
20 MR. PASCAL: .....I just want to understand
21 your question because other order 142 was issued way
22 after 32-001 was issued, it was not prior to that.
23 COMMISSIONER FOERSTER: The administrative
24 approval that allowed you to continue to inject was
25 issued in December?
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 32
1 MR. PASCAL: Yes, and ever since that came in
2 we have been fully compliant with all the requirements
3 of.....
4 COMMISSIONER FOERSTER: Right. Okay. You're
5 not.....
6 MR. PASCAL: .....other order 32.....
7 COMMISSIONER FOERSTER: .....following me.
8 MR. PASCAL: ......001.
9 COMMISSIONER FOERSTER: Okay. Were you -- were
10 you doing all of those things prior to the issuance of
11 that administrative approval?
12 MR. PASCAL: I will have to check and see what
13 32-001 exactly states. Basically from what I recall
14 32-001 exactly states that you shall report pressures
15 and flow rates to the Commission on a monthly basis
16 which we do normally on a -- on our monthly logs to the
17 AOGCC. And it also asks us to do the next MIT text in
18 2019 which we already have it.....
19 COMMISSIONER FOERSTER: So.....
20 MR. PASCAL: .....on track.
21 COMMISSIONER FOERSTER: .....we don't need to
22 do it here today, but we can keep the record open for a
23 few days so that you can respond to my question. And
24 my question is you -- okay, let me explain why I'm
25 asking it. You made the assertion that our statement
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
AOGCC
10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 33
1 that the way you were operating wasn't safe was
2 inconsistent with our AA which says it's safe. And our
3 AA said it's safe because we have all these conditions
4 and requirements. So my question to you is were you
5 complying with all of those conditions and requirements
6 prior to the issuance of the AA to maintain your
7 statement that it was fully safe. Does that make -- do
8 you understand where I'm going with my question?
9 MR. PASCAL: I understand where you're going
10 with your question.....
11 COMMISSIONER FOERSTER: Okay. So.....
12 MR. PASCAL: .....but the point we were trying
13 to make, ma'am, is that, you know, other order 142 is
14 issued way after all this happened and we've been
15 working with the Commission quite closely and we've
16 been fully compliant with, you know.....
17 COMMISSIONER FOERSTER: You're not
18 answering.....
19 MR. PASCAL: ......32-001.
20
COMMISSIONER FOERSTER: .....you're not
21
understanding my question.
You can't
make the
22
assertion that what you were
doing
prior to the
23
issuance of the AA was safe
if you
weren't complying
24
with all the requirements to
ensure
that it was safe.
25
That's all I'm saying. And
if you
can provide me
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK99501 Fax: 907-243-1473 Email: sahile@gci.net
� r
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
Page 34
1 that.....
2 MR. ELLIOTT: We.....
3 MR. PASCAL: I will have to.....
4 MR. ELLIOTT: .....fully understand the
5 question and we'll come.....
6 COMMISSIONER FOERSTER: .....I'd love to hear
7 it and if you can't then we're done.
8 MR. ELLIOTT: .....we will respond to that
9 question.
10 COMMISSIONER FOERSTER: Thank you.
11 CHAIRMAN FRENCH: We'll keep the record open
12 for a week for that piece of information.
13 Other questions, Commissioner Foerster?
14 COMMISSIONER FOERSTER: I'm done.
15 CHAIRMAN FRENCH: I don't have any other
16 questions either. Anything else you guys want to say
17 to wrap up?
18 MR. PASCAL: Thank you.
19 CHAIRMAN FRENCH: It's 1:50 in the afternoon
20 and we're adjourned.
21 (Adjourned)
22 (END OF PROCEEDINGS)
23
24
25
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
� 1
AOGCC 10/24/2018 ITMO: REQUEST BY COOK INLET ENERGY, LLC.,
Docket No. OTH 17-056
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Page 35
TRANSCRIBER'S CERTIFICATE
I, Salena A. Hile, hereby certify that the
foregoing pages numbered 02 through 35 are a true,
accurate, and complete transcript of proceedings in
Docket No: OTH 17-056, transcribed under my direction
from a copy of an electronic sound recording to the
best of our knowledge and ability.
DATE
SALENA A. HILE, (Transcriber)
Computer Matrix, LLC Phone: 907-243-0668
135 Christensen Dr., Ste. 2., Anch. AK 99501 Fax: 907-243-1473 Email: sahile@gci.net
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Docket Number: OTH-17-056
October 24, 2018 at 1:00 pm
NAME AFFILIATION Testifv (ves or no)
�PU`tI D>}S Val,- tkt A- �y CS
p%tIL tLtAn 1- figL - `PES
T So��s
�-4-t,A-o � Tpr -6- kw *,to
675A /00
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Docket Number: OTH-17-056
October 24, 2018 at 1:00 pm
NAME AFFILIATION Testify (yes or no)
>fi-tp pp,s &tr � k,�A— y Cs
Plitt, ti,U0 T L -kr SES
�4,uko 9 TM -6- 40
k t -v e— s n �r—IS �i� tea— Hca
9
STATE OF ALASKA
ADVERTISING
ORDER
NOTICE TO PUBLISHER
SUBMIT N'VOICE SHOWING ADVERTISNG ORDER NO., CERTIFIED
AFFIDAVIT OF PUBLICATION WHA ATTACHED COPY OF ADVERUSMENT.
ADVERTISING ORDERNUMBER
AO-19-004
FROM: AGENCY CONTACT:
Jody Colombic/Samantha Carlisle
Alaska Oil and Gas Conservation Commission DATE OF A.O.AGENCY PHONE:
333 West 7th Avenue 8/2/2018 (907) 279-1433
Anchorage, Alaska 99501
DATES ADVERTISEMENT REQUIRED:
COMPANY CONTACT NAME:
PHONE NUMBER: ASAP
FAX NUMBER:
(907)276-7542
TO PUBLISHER:
Anchorage Daily News, LLC
SPECIAL INSTRUCTIONS:
PO Box 140147
Anchorage, Alaska 99514-0174
TYPE OF ADVERTISEMENT:
LEGAL DISPLAY CLASSIFIED OTH E R(S pacify be low)
DESCRIPTION PRICE
OTH-17-056
Initials of who prepared AO:
Alaska Non -Taxable 92-600185
: SUBMIT:PNtliCH SHOWING ADY.ERTIMN 3:
:-::OBDERNO.; RERTlF1EOAFFIDAYrT OF.:'
.................... _ ... COP. OF
:ruecicAnomaTTH:ATTAeHmcoerof333
... . ... .......:«
AOGCC
West 7th Avenue
Anchorage, Alaska 99501
Pae 1 of ]
Total of
All Pages $ -
REF Type I Number
Amount Date Comments
I PVN IVCO21795
2 Ao AO.19-004
3
4
FIN AMOUNT SY Act. Tem ate PGM LGR Object FY DIST LIQ
1 19 A14100 3046 19
2
3
4
relies A h e: I e
Purchasing Authority's Signature Telephone Number
1. . It and receiAng agency name must appear m ail inwices and documents relating to this purchase.
2. T e state is registered for tax free transactions under Chapter 32, IRS code. Registration number 92-73-0006 K. Items are for the exclusive use of the state and not far
le.
17iSTRIBUTION
Dlvrsion FrsealfOriglnallQ '..Copies
Piilihshor (fssed},llrvLsronFiscal Roeervng .
Form: 02-901
Revised: 8/2/2018
Notice of Public Hearing
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Re: Docket Number: OTH-17-056
Motion for Reconsideration
Redoubt Unit 3A Well Violations
Cook Inlet Energy has requested a hearing upon reconsideration of the above docket. The Alaska
Oil and Gas Conservation Commission (AOGCC) grants their request.
The AOGCC has scheduled a public hearing on the application for October 24, 2018, at 1:00 p.m.
at 333 West 7`^ Avenue, Anchorage, Alaska 99501.
If, because of a disability, special accommodations may be needed to comment or attend the
hearing, contact the AOGCC at (907) 279-1433, no later than October 20, 2018.
Hollis S. French
Chair, Commissioner
Notice of Public Hearing
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Re: Docket Number: OTH-17-056
Motion for Reconsideration
Redoubt Unit 3A Well Violations
Cook Inlet Energy has requested a hearing upon reconsideration of the above docket. The Alaska
Oil and Gas Conservation Commission (AOGCC) grants their request.
The AOGCC has scheduled a public hearing on the application for October 24, 2018, at 1:00 p.m.
at 333 West 7`h Avenue, Anchorage, Alaska 99501.
If, because of a disability, special accommodations may be needed to comment or attend the
hearing, contact the AOGCC at (907) 279-1433, no later than October 20, 2018.
Hsignature on fileH
Hollis S. French
Chair, Commissioner
ANCHORAGE ')A" -'y 'NEWNECOVED
AFFIDAVIT OF PUBLICATION AUG 10 2018
AOGCC
Account #: 270227
ST OF AK/AK OIL AND GAS Order# 0001425713 Product ANC -Anchorage Daily News
CONSERVATION COMMISSION cost $129.50 Placement 0300
333 WEST 7TH AVE STE 100 Position 0301
Aeicunwnrc AV 00501'1580
STATE OF ALASKA
THIRD JUDICIAL DISTRICT
Joleesa Stepetin
being first duly sworn on oath deposes and says
that he/she is a representative of the Anchorage
Daily News, a daily newspaper. That said
newspaper has been approved by the Third
Judicial Court, Anchorage, Alaska, and it now
and has been published in the English language
continually as a daily newspaper in Anchorage,
Alaska, and it is now and during all said time
was printed in an office maintained at the
aforesaid place of publication of said newspaper.
That the annexed is a copy of an advertisement
as it was published in regular issues (and not in
supplemental form) of said newspaper on
August 05, 2018
and that such newspaper was regularly
distributed to its subscribers during all of said
period. That the full amount of the fee charged
for the foregoing publication is not in excess of
the rate charged private individuals.
Subscribed and sworn to before me
this 6th day of August, 2018
Notary Public i and for
The State o aska.
Third Division
Anchorage, Alaska
MY COMMISSION rPIR�E$��
Notice of Public Hearing
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Re: Docket Number: OTH-17-056
Motion for Reconsideration
Redoubt Unit 3A Well Violations
Cook Inlet Energy has requested a hearing upon reconsideration of the
above docket The Alaska Oil and Gas Conservation Commission
(AOGCC) grants their request.
The AOGCC has scheduled a public hearinKK on the application for
October 24, 2018, at 1:00 p.m. at 333 VIM 7th Avenue, Anchorage
Alaska 99501.
If, because of a disability special accommodations may be needed to
comment or attend the hearing, contact the AOGCC at (907) neede 33,
no later than October 20, 2018.
Published: August 5, 2018
//signature on file//
Hollis S. French
Chair, Commissioner
--A �,
Notary Public
BRITNEY L. THOMPSON
State of Alaska
My Commission Expires Feb 23, 2019
Colombie, Jody J (DOA)
From: Colombie, Jody J (DOA)
Sent: Thursday, August 02, 2018 10:11 AM
To: Romerdahl, Elena M. (Perkins Coie); Ballantine, Tab A (LAW); Bell, Abby E (DOA); Bixby, Brian D
(DOA); Boyer, David L (DOA); Brooks, Phoebe L (DOA); Carlisle, Samantha J (DOA); Colombie,
Jody J (DOA); Cook, Guy D (DOA); Davies, Stephen F (DOA); Earl, Adam G (DOA); Erickson,
Tamara K (DOA); Foerster, Catherine P (DOA); French, Hollis (DOA); Frystacky, Michal (DOA);
Guhl, Meredith D (DOA); Herrera, Matthew F (DOA); Jones, Jeffery B (DOA); Kair, Michael N
(DOA); Laubenstein, Lou (DOA); Loepp, Victoria T (DOA); Martin, Teddy J (DOA); McLeod, Austin
(DOA); Mcphee, Megan S (DOA); Mumm, Joseph (DOA sponsored); Noble, Robert C (DOA);
Paladijczuk, Tracie L (DOA); Pasqual, Maria (DOA); Regg, James B (DOA); Rixse, Melvin G (DOA);
Roby, David S (DOA); Schwartz, Guy L (DOA); Seamount, Dan T (DOA); Wallace, Chris D (DOA);
AK, GWO Projects Well Integrity; AKDCWelllntegrityCoordinator; Alan Bailey; Alex Demarban;
Alicia Showalter; Allen Huckabay; Andrew VanderJack, Ann Danielson; Anna Lewallen; Anna Raff;
Barbara F Fullmer; Barbara Kruk; bbritch; bbohrer@ap.org; Ben Boettger, Bill Bredar; Bob
Shavelson; Bonnie Bailey, Brandon Viator; Brian Havelock, Bruce Webb; Caleb Conrad; Candi
English; Cody Gauer; Cody Terrell; Colleen Miller; Connie Downing; Crandall, Krissell; D Lawrence;
Dale Hoffman; Danielle Mercurio; Darci Horner; Dave Harbour; David Boelens; David Duffy;
David House; David McCaleb; David Pascal; ddonkel@cfl.rr.com; Diemer, Kenneth J (DNR);
DNROG Units (DNR sponsored); Donna Ambruz; Ed Jones, Elizabeth Harball; Elowe, Kristin;
Elwood Brehmer, Evan Osborne; Evans, John R (LDZX); Brown, Garrett A (DNR); George Morris;
George Pollock; Gordon Pospisil; Greeley, Destin M (DOR); Greg Kvokov; Gretchen Stoddard;
gspfoff; Hurst, Rona D (DNR); Hyun, James J (DNR); Jacki Rose; Jason Brune; Jdarlington
(arlington@gmail.com); Jeanne McPherren; Jerry Hodgden; Jill Simek; Jim Shine; Jim Watt, Jim
White oim4thgn@gmail.com); Young, Jim P (DNR); Joe Lastufka; Radio Kenai; Burdick, John D
(DNR); Easton, John R (DNR); Larsen, John M (DOR); Jon Goltz; Joshua Stephen; Juanita Lovett;
Judy Stanek; Kari Moriarty; Kasper Kowalewski; Kazeem Adegbola; Keith Torrance; Keith Wiles;
Kelly Sperback; Frank, Kevin J (DNR); Kruse, Rebecca D (DNR); Kyla Choquette; Gregersen, Laura
S (DNR); Leslie Smith; Lori Nelson; Luke Keller, Marc Kovak; Dalton, Mark (DOT sponsored); Mark
Hanley (mark.hanley@anadarko.com); Mark Landt; Mark Wedman; Michael Bill; Michael Calkins;
Michael Moora; Michael Quick, Michael Schoetz, Mike Morgan; MJ Loveland; Motteram, Luke A;
Mueller, Marta R (DNR); Nathaniel Herz; knelson@petroleumnews.com; Nichole Saunders; Nick
Ostrovsky; NSK Problem Well Supv; Patty Alfaro; Paul Craig; Decker, Paul L (DNR); Paul
Mazzolini; Pike, Kevin W (DNR); Randall Kanady; Renan Yanish; Richard Cool; Robert Brelsford;
Robert Tirpack; Robert Warthen; Ryan Gross; Sara Leverette; Scott Griffith; Shahla Farzan;
Shannon Donnelly, Sharon Yarawsky; Skutca, Joseph E (DNR); Smith, Kyle S (DNR); Spuhler, Jes J
(DNR); Stephanie Klemmer; Stephen Hennigan; Stephen Ratcliff; Sternicki, Oliver R, Moothart,
Steve R (DNR); Steve Quinn; Suzanne Gibson; sheffield@aoga.org; Tanisha Gleason; Ted Kramer;
Teresa Imm; Terry Caetano; Tim Mayers; Todd Durkee; Tom Maloney; Tyler Senden; Umekwe,
Maduabuchi P (DNR); Vern Johnson; Vinnie Catalano; Well Integrity, Well Integrity; Weston
Nash; Whitney Pettus; Aaron Gluzman; Aaron Sorrell; Ajibola Adeyeye; Alan Dennis; Andy Bond;
Bajsarowicz, Caroline J; Bruce Williams; Casey Sullivan; Corey Munk; Don Shaw; Eppie Hogan;
Eric Lidji; Garrett Haag; Smith, Graham O (DNR); Heusser, Heather A (DNR); Fair, Holly S (DNR);
Jamie M. Long; Jason Bergerson; Jesse Chielowski; Jim Magill; Joe Longo; John Martineck; Josh
Kindred; Keith Lopez; Laney Vazquez, Lois Epstein; Longan, Sara W (DNR); Marc Kuck, Marcia
Hobson; Matt Armstrong; Melonnie Amundson; Franger, James M (DNR); Morgan, Kirk A (DNR);
Umekwe, Maduabuchi P (DNR); Pat Galvin; Pete Dickinson; Peter Contreras; Rachel Davis;
Richard Garrard; Richmond, Diane M; Robert Province; Ryan Daniel; Sandra Lemke; Scott Pins;
Pollard, Susan R (LAW); Talib Syed; Tina Grovier (tmgrovier@stoel.com); William Van Dyke,
Zachary Shulman
Subject: Public Notice Other -17-056
Attachments: Oth-17-056 Public Hearing Mtn for Reconsideration.pdf
Please see attached Notice Of Hearing.
Docket Number: OTH-17-056
Motion for Reconsideration
Redoubt Unit 3A Well Violations
Jody J. Co(ombie
.AOGCC Specia(.Assistant
.A(aska. Oi(andGas Conservation Commission
333 West Tf .Avenue
.Anchorage, .A(aska 995oi
Office: (907) 793-1221
Fax: (907) 276-7542
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska Oil and Gas Conservation
Commission (AOGCC), State of Alaska and is for the sole use of the intended recipient(s). It may contain confidential and/or privileged information.
The unauthorized review, use or disclosure of such information may violate state or federal law. If you are an unintended recipient of this e-mail,
please delete it, without first saving or forwarding it, and, so that the AOGCC is aware of the mistake in sending it to you, contact Jody Colombie at
907.793.1221 or iodv.colombie@alaska.aov.
Bernie Karl
K&K Recycling Inc.
P.O. Box 58055
Fairbanks, AK 99711
George Vaught, Jr.
P.O. Box 13557
Denver, CO 80201-3557
Gordon Severson
3201 Westmar Cir.
Anchorage, AK 99508-4336
Darwin Waldsmith
P.O. Box 39309
Ninilchik, AK 99639
Penny Vadla
399 W. Riverview Ave.
Soldotna, AK 99669-7714
Richard Wagner
P.O. Box 60868
Fairbanks, AK 99706
E
0
u
v
,0u'o
O
,o yy
CY, N O.
aNOQ�-C
ELI c&
>
O�
UQaG'y o
w
—
a
N ¢ N O
O O Q!
c
W
RECEIVED
JUL 16 20118
AOGCC
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Redoubt Unit 3A (RU 3A) Well Violation Docket No. OTH-17-056
(PTD 2161700)
COOK INLET ENERGY'S REQUEST FOR RECONSIDERATION OF
OTHER ORDER NO. 142
Pursuant to AS 31.05.080(a), Cook Inlet Energy, LLC ("CIE") hereby requests
reconsideration by the Alaska Oil and Gas Conservation Commission ("AOGCC" or
"the Commission") of Other Order No. 142 in Docket OTH-17-056, dated June 25,
2018 ("the Order"). In the Order, the Commission failed to acknowledge facts
presented at the informal review on April 10, 2018 and rejected CIE's requests that the
Commission reduce the civil penalties imposed and revise the scope of its request for
information. CIE respectfully requests that the Commission grant reconsideration of
the Order and issue a new decision imposing civil penalties that are commensurate with
the violations and applicable mitigating factors, and requesting only that information
that the Commission is permitted to request under applicable law.
Docket No. OTH-17-056
Page 1 of 13
BACKGROUND
On March 15, 2018, the Commission issued a Notice of Proposed Enforcement
Action ("the Notice") to CIE alleging that CIE violated 1) 20 AAC 25.4020 and the
provisions of Rule 8 of Administrative Injection Order ("AIO") 32 requiring CIE to
notify AOGCC and submit a plan of corrective action when pressure communication
leakage or lack of injection zone isolation is indicated in Redoubt Unit Well 3A ("RU -
3A"); and 2) Rule 6 of AIO 32 requiring CIE to perform an AOGCC-witnessed
Mechanical Integrity Test ("MIT") once RU -3A commenced injection for the first time.
The Notice proposed a civil penalty of $25,000 for each of the two alleged violations
and requested information from CIE regarding CIE's internal regulatory compliance
programs and tracking systems and a "Root Cause Analysis" for each violation.
CIE requested an informal review of the Notice. The informal review took place
on April 10, 2018 and was attended by George Morris, Senior Vice President of
Engineering and Geoscience, and David Pascal, Production Manager, for CIE; and
Senior Petroleum Engineers Jim Regg and Chris Wallace for AOGCC.' Prior to the
informal review, CIE provided the Commission with six documents, including: a
current wellbore diagram for RU -3A; a timeline of events related to each violation at
1 Affidavit of D. Pascal at ¶ 6.
Docket No. OTH-17-056
Page 2 of 13
RU -3A; a graph depicting hourly data of inner and outer annulus pressures at RU -3A;
documentation of the initial passed MIT that CIE conducted at RU -3A prior to startup;
and hourly data for July 1, 2017 to April 1, 2018 on a compact disk .2 At the informal
review, CIE confirmed that it was not contesting the violations alleged in the Notice
but requested that the proposed penalties for each violation be reduced based on several
applicable mitigating factors and asked that the Commission withdraw its request for
information regarding CIE's internal operations. CIE discussed the root cause for the
two alleged violations and confirmed that it had mitigated the violations by conducting
a successful MIT in April 2017 prior to startup of RU -3A, and by immediately
informing AOGCC when it determined that a potential leak existed.' CIE also
established that it is "committed to an increased level of oversight and review of
established training and process protocols for employees governing injection
operations," which will "help prevent further occurrence" of the violations.'
On June 25, 2018, the Commission issued its Order formally assessing a civil
penalty of $50,000 for violating Rules 6 and 8 of AIO 32 and 20 AAC 25.402, and
2 Id.
' D. Pascal Affidavit at ¶¶ 8-9, 12.
' Order at 4-5.
Docket No. OTH-17-056
Page 3 of 13
(D
requiring that CIE provide AOGCC with: 1) a detailed descripti of CIE's
Z
Underground Injection Control ("UIC") regulatory compliance program; 2) details of
CIE's tracking system for determining when MITs are required, including
contingencies for wells shut in at the time the MIT is due, procedures for notifying
AOGCC, and C's processes for determining the MIT due date and identification of
past due welUs;33)detailed description of CIE's non-UIC AOGCC regulatory
compliance program, including CIE's tracking system for determining when
compliance requirements are due; 4) a "Root Cause Analysis" addressing the failure to
provide a notification of a pressure communication to AOGCC within the next business
day; and 5) a "Root Cause Analysis" addressing the failure to complete an AOGCC-
witnessed MIT once the well commenced injection and stabilization was achieved.5
The civil penalties imposed and information requested by the Commission in the Order
are identical to the civil penalties imposed and information requested in the Notice.
5 Order at 5.
Docket No. OTH-17-056
Page 4 of 13
6
0
U
'L
0
ate,-'�Ci
„aj aiorn.c
w °crn;v
z �u.w
N Q N O
o�o.
0
ARGUMENT
1. The Commission Failed to Account for Mitigating Factors and Information
Presented at the Informal Review When Assessing Civil Penalties Against
CIE.
The civil penalties imposed by the Order are not supported by the facts discussed
in the Order or the information presented by CIE to Mr. Regg and Mr. Wallace at the
informal review. The combined amount for the two one-time civil penalties—
$50,000—is equal to half of the maximum initial civil penalty the Commission may
impose pursuant to AS 31.05.150(a). The Order does not explain the basis for the
assessed penalties, does not discuss the mitigating information provided to Mr. Regg
and Mr. Wallace during the informal review, and does not consider many of the factors
the Commission is required to address when assessing a civil penalty.
When determining the amount of a civil penalty, the Commission is required to
consider the following:
(1) the extent to which the person committing the violation was acting
in good faith in attempting to comply;
(2) the extent to which the person committing the violation acted in a
willful or knowing manner;
(3) the extent and seriousness of the violation and the actual or
potential threat to public health or the environment;
(4) the injury to the public resulting from the violation;
(5) the benefits derived by the person committing the violation from
Docket No. OTH-17-056
Page 5 of 13
the violation;
(6) the history of compliance or noncompliance by the person
committing the violation with the provisions of this chapter, the
regulations adopted under this chapter, and the orders, stipulations, or
terms of permits issued by the commission;
(7) the need to deter similar behavior by the person committing the
violation and others similarly situated at the time of the violation or in
the future;
(8) the effort made by the person committing the violation to correct
the violation and prevent future violations; and
(9) other factors considered relevant to the assessment that are
adopted by the commission in regulation.6 —
The Order does not address the first two factors or factors 5, 6, or 8, all of which were
discussed by CIE during the informal review. The Order does discuss factors 3, 4, and
7 but reaches conclusions regarding these factors that are not supported by the facts
stated in the Order or the information presented at the informal review.
The Order confirms that "no injury to the public occurred" as a result of CIE's
failure to complete the initial post-injection MIT (factor 4), but then states that "the
potential wellbore failure posed an obvious threat to both public health and the
environment" (factor 3).1 The Order cites no facts to support its conclusion that CIE's
6 AS 31.05.150(g)(1)-(9).
' Order at 4.
Docket No. OTH-17-056
Page 6 of 13
delay in obtaining a post-injection MIT resulted in an "obvious threat to both public
health and environment." To the contrary, the Order states that a successful AOGCC-
witnessed MIT was completed December 23, 2017,8 confirming that no threat to public
health or the environment existed as a result of CIE's delay in obtaining the AOGCC-
witnessed MIT at RU -3A. In addition, CIE provided AOGCC with documentation
confirming that CIE conducted a successful MIT prior to startup of RU -3A on April 14,
2017.9 The assertion that CIE's failure to obtain an AOGCC-witnessed MIT posed "an
obvious threat to both public health and the environment" is thus not supported by, and
is in fact inconsistent with, the facts stated in the Order and presented at the informal
review.
The Commission also appears to address factor 7 when it contends that "CIE's
failure to comply with fundamental wellbore mechanical integrity testing requirements
raises the potential for similar behavior with more serious consequences."10 Again, this
assertion is not supported by any facts in the Order and is inconsistent with other
8 Order at 3; see also D. Pascal Affidavit Exhibit 6. The Commission also issued Area
Injection Order No. 32.001 on December 28, 2017 and determined that "water injection
could safely continue" at RU -3A if CIE complied with the conditions of that order.
Order at 3.
9 D. Pascal Affidavit at 19 and Exhibit 5. The Order does not acknowledge that CIE
conducted an MIT prior to startup of RU -3A.
10 Order at 4.
Docket No. OTH-17-056
Page 7 of 13
0
U
U
pp O
C U
� M Y
aj aicCs
C rn
UQy'� o
zsww
aF _
a�0 o
r
N¢N O
o
c
w
statements made by the Commission in the Order. The Commission confirms that "CIE
has committed to an increased level of oversight and review of established training and
process protocols for employees governing injection operations,"11 and finds "CIE's
implementation of the proposed actions to be satisfactory to help prevent further
occurrence of these violations."12 These statements are at odds with the suggestion that
the two one-time violations at issue in the Order "raise[] the potential" for similar more
serious violations in the future.
The Order also fails to discuss CIE's history of compliance with AOGCC's
rules and regulations (factor 6), CIE's good -faith efforts to comply with AIO 32 and
AOGCC regulations (factor 1), and the absence of any willful misconduct by CIE
(factor 2).13 CIE presented facts during the informal review that are relevant to each of
these factors.14 For example, CIE discussed that it has been fully compliant with the
requirements of AIO 32.001 issued December 28, 2017, described in detail its good -
faith efforts to comply with AOGCC rules and regulations both before and after it was
notified of the violations, and provided detailed accounts of CIE's actions leading up
11 Order at 4-5.
12 Order at 5.
13 AS 31.05.150(g)(1)-(2) and (6).
14 See D. Pascal Affidavit at ¶¶ 8, 9, 11, 14 and Exhibits 2-6.
Docket No. OTH-17-056
Page 8 of 13
E
0
u
ti
0
0
o MY
•E?N a
a.cn��3
a aio�-c
w crn v
Z` www
�d 9ons —
a. 0
N Q N 0
� n �
O
rn�
C
_N
W
to the violations to demonstrate that CIE did not engage in willful misconduct.15
The Order states that the Commission considered two mitigating circumstances
when assessing the proposed civil penalty, including the absence of known sources of
freshwater in the Redoubt Unit and CIE's "demonstrated urgency in completion of the
required MIT and in installation and testing of the required automatic well shut-in
equipment" after receiving notification of the violations (factor 8). 16 But there is no
explanation in the Order regarding whether or how the Commission accounted for these
or any of the other mitigating factors discussed above when establishing the amount of
the civil penalties imposed in the Order." CIE therefore respectfully requests
reconsideration of the Order to allow the Commission to consider all of the
AS 31.05.150(g) factors—including those addressed by CIE during the informal
review—and to reduce the civil penalties accordingly.
15 Id.
" Order at 4.
" The Commission's failure to account for mitigating factors presented at the informal
review is supported by the fact that the civil penalties imposed by the Commission in
the Order are identical to the penalties proposed in the Notice.
Docket No. OTH-17-056
Page 9 of 13
E
O
U
pp O
O U
Of+1
aj morns
UQpG'm Eo
Z72 www
2 -0
U � �
N
N ¢ N0
O
rn�
c
w
2. The Order Requests Information that AOGCC Does Not Have Authority to
Obtain.
Reconsideration of the Order is also warranted to revise the scope of the
information requested from CIE by the Commission.
CIE acknowledges that AOGCC has broad authority under its statutes and
regulations to collect information from operators. AOGCC "has authority over all land
subject to the state's police power [and] regulates to prevent waste, insure greater
recovery, protect correlative rights and underground water, and further public health
and safety."' 8 Under state statute, the Commission may collect reports, logs, directional
surveys, and other subsurface information on wells for which the Commission has
issued a permit to drill; oil and gas production records; and plans of development for a
field or pool.19 Under AOGCC's regulations, the Commission may inspect detailed
daily records from well operators, and may collect from operators well records,
production volumes, monthly gas disposition data, reservoir pressure reports, and
geologic data and logs.20 The Commission may also request any "information or
18 Gottstein v. State, Dept. of Natural Resources, 223 P.3d 609, 616 n.14 (Alaska 20 10)
(citing AS 31.05.005(a); AS 31.05.027; AS 31.05.095; AS 31.05.100; AS 31.05.110;
AS 31.05.030) (internal citations omitted).
19 AS 31.05.030.
20 20 AAC 25.230, 20 AAC 25.235, 20 AAC 25.270, 20 AAC 25.071.20 AAC 25.517.
Docket No. OTH-17-056
Page 10 of 13
documentation regarding a matter within the commission's jurisdiction.1121 The
Commission has broad jurisdiction over state wells, reservoirs, drilling, and production,
and broad authority to prescribe through its statutes, regulations, and orders what
operating companies may and may not do when operating in Alaska. The Commission
does not, however, have explicit or implicit22 authority to regulate how operating
companies choose to manage their internal business affairs in order to comply with
AOGCC's regulations, orders, and rules.
The Order's request for detailed information regarding CIE's regulatory
compliance programs, processes, and tracking systems demonstrates an attempt by
AOGCC to regulate how CIE chooses to manage its internal business policies and
procedures. Such internal policies and procedures are not within the scope of the
21 20 AAC 25.300.
22 The Alaska Supreme Court has held that "administrative agencies have implied
powers, relying on the premise that implied powers are sometimes necessary to the
exercise of those powers that the legislature has expressly granted." Alaskan Crude
Corp. v. State, Alaska Oil and Gas Conservation Comm'n, 309 P.3d 1249, 1255 (Alaska
2013) (internal quotation marks and citation omitted). For example, the court has held
that the Commission has the implied power to determine what constitutes a natural gas
exploration facility because it is necessary to exercise its express power to determine
whether a well at a natural gas exploration facility meets criteria that exempt it from oil
discharge prevention requirements. Id. Here, review of CIE's internal procedures and
policies is not "necessary to the furtherance" of the Commission's express power
because the Commission does not have the express power to regulate an operating
company's internal affairs. How CIE chooses to run its business is not necessary for
the Commission to know in order for it to exercise its express powers.
Docket No. OTH-17-056
Page 11 of 13
Commission's jurisdiction. The Commission may require that CIE comply with
AOGCC's regulations and rules, and may penalize CIE for failing to do so,23 but the
Commission does not have authority to regulate how CIE elects to organize and manage
its internal business affairs in order to meet those requirements. The Commission's
request for CIE's internal compliance policies and procedures is thus neither a request
for information that AOGCC has explicit authority to request under statute or
regulation, nor a request for "information or documentation regarding a matter within
the commission's jurisdiction." CIE therefore respectfully requests that the
Commission withdraw the first three requests for information in the Order.
Regarding the Order's last two requests for a "Root Cause Analysis" of each
violation, CIE notes that it provided this information and supporting documentation to
Mr. Regg and Mr. Wallace at the informal review .14 Nevertheless, CIE is happy to
provide the Commission with this analysis again.
23 AOGCC enforces its statutes, regulations, and orders by issuing violations, obtaining
injunctive relief, and imposing civil penalties on operators who fail to comply with
those regulations, orders, and rules. AS 31.05.150-160.
24 D. Pascal Affidavit at 112 and Exhibit 3.
Docket No. OTH-17-056
Page 12 of 13
CONCLUSION
Based on the foregoing, CIE respectfully requests that AOGCC grant
reconsideration of the Order to reassess both the civil penalties imposed and the
information requested in Other Order No. 142.
DATED this 16th day of July, 2018.
Docket No. OTH-17-056
Page 13 of 13
PERKINS COIE LLP
Attorneys for Cook Inlet Energy, Inc.
By:
Elena M. Romerdahl, Alaska Bar No. 1509072
Eric B. Fjelstad, Alaska Bar No. 9505020
V
c
0
FF
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Redoubt Unit 3A (RU 3A) Well Violation Docket No. OTH-17-056
(PTD 2161700)
AFFIDAVIT OF DAVID PASCAL
STATE OF ALASKA )
)ss.
THIRD JUDICIAL DISTRICT )
The undersigned, after first being duly sworn, states as follows:
I, David Pascal, am over the age of 18, competent to testify, and have
personal knowledge of the matters stated in this affidavit.
2. I am the Production Manager at Glacier Oil and Gas Corporation
("Glacier") and its subsidiaries, Cook Inlet Energy, LLC ("CIE") and Savant Alaska, LLC
("Savant'). My business address is 601 W 5th Avenue #310, Anchorage, Alaska, 99501.
3. I have been employed at CIE since September 2013 and have held the
position of Production Manager since August 2014. Prior to that, I held the position of
Reservoir Engineer.
4. As Production Manager at CIE, I am responsible for day to day production
and maintenance operations at all CIE facilities including the Redoubt Unit
5. In March 2018, CIE received a Notice of Proposed Enforcement Action
("Notice") from the Alaska Oil and Gas Conservation Commission ("AOGCC") regarding
the Redoubt Unit 3A ("RU -3A") well stating that CIE failed to report to AOGCC within
the time required by regulation a pressure communication at RU -3A and failed to complete
an AOGCC-noticed Mechanism Integrity Test ("MIT") of RU -3A. The Notice proposed
that CIE provide information to AOGCC and a $50,000 civil penalty.
AFFIDAVIT OF DAVID PASCAL
Docket No. OTH-17-056
-1-
6. CIE requested an informal review of the Notice with AOGCC. The
informal review took place on April 10, 2018. My colleague, George Morris, Senior Vice
President of Engineering and Geoscience for Glacier, CIE, and Savant, and I both attended
the informal review on behalf of CIE. Senior Petroleum Engineers Jim Regg and Chris
Wallace attended the informal review on behalf of AOGCC.
7. Prior to the informal review, I submitted five documents and a compact disk
with data to AOGCC, including: a current wellbore diagram for RU -3A; a timeline of
events related to each violation at RU -3A; a graph depicting hourly data of inner and outer
annulus pressures at RU -3A; documentation of the initial passed MIT that CIE conducted
at RU -3A prior to startup; and hourly data for July 1, 2017 to April 1, 2018 on the compact
disk. The five documents and the transmittal letter dated April 5, 2018 are attached to this
affidavit as Exhibits 1- 6.
8. During the informal review, we explained the timeline of events leading up
to the December 18, 2017 notice to AOGCC of pressure communication. We explained to
Mr. Regg and Mr. Wallace that we reported the pressure communication at RU -3A on
December 18, 2017 because that is the date when we determined that the pressure was e
to a small leak. Prior to that date, we were carefully monitoring, conducting tests, and
assessing the pressure data to ensure the anomalies were not caused duto thermal
expansion.
9. We also reviewed with Mr. Regg and Mr. Wallace the internal CIE
documentation of the successful MIT that CIE conducted at RU -3A on April 14, 2017 prior
to startup. See Affidavit Exhibits 3, 5. The April 14, 2017 MIT confirmed that RU -3A
was fully functional and did not present a risk of health or safety to the public. We also
discussed with Mr. Regg and Mr. Wallace the fact that the successful AOGCC-witnessed
MIT completed on December 23, 2017 confirmed that our internal MIT was accurate, and
that RU -3A continued to present no risk to public health or the environment.
10. We also discussed the civil penalty amount proposed in the Notice of
Proposed Violation with Mr. Regg and Mr. Wallace. We confirmed that we were not
AFFIDAVIT OF DAVID PASCAL
Docket No. OTH-17-056
-2-
R
contesting the proposed violations but requested that the civil penalties be reduced in light
of several mitigating circumstances, including: that CIE conducted a successful MIT prior
to well startup, that the subsequent AOGCC-witnessed MIT was also successful, that CIE
did report the pressure communication at the point that it believed it to indicate a potential
problem, and that no injury to the public occurred.
11. We also brought to the attention of Mr. Regg and Mr. Wallace that we acted
urgently and completed a state -witnessed MIT test when AOGCC pointed out our
deficiency in the witness after we notified them of a possible leak.
12. We also discussed the general timeline of events leading up to the two
violations, see Affidavit Exhibit 3, and explained to Mr. Regg and Mr. Wallace the "root
cause" of each violation: that we reported the pressure communication at RU -3A to
AOGCC immediately after we confirmed that it was indicative of a potential leak; and that
we were aware of the requirement in Administrative Injection Order 32 ("AIO 32") to
conduct an MIT test but the field failed to notify AOGCC for witness while the initial MIT
was conducted.
13. Finally, we briefly discussed with Mr. Regg and Mr. Wallace CIE's internal
compliance policies and programs and confirmed that we are aware of and intend to comply
with all rules in Injection Order 32 and all AOGCC regulations. We also enquired about
AOGCC requirement and overreach on the corrective actions that required information on
other programs and internal policies not related to the Administrative Injection Order in
question.
14. As the Order confirms, no injury to the public has occurred at or near RU-
3A as a result of the two violations. AOGCC confirmed through its successful MIT and
Area Injection Order No. 32.001 issued December 28, 2017 that RU -3A exhibits at least
two competent barriers to the release of well pressure and that the well's condition does
not compromise overall well integrity so as to threaten human safety or the environment.
We also commented that we have been fully compliant with the requirements of Area
Injection Order No. 32.001, including the monthly reporting requirement.
AFFIDAVIT OF DAVID PASCAL
Docket No. OTH-17-056
-3-
15. At the end of the informal review, Mr. Regg and Mr. Wallace confirmed
that what we presented during the informal review would be considered in AOGCC's
final decision.
16. The AOGCC Decision and Order No. 142 is identical to the Notice of
Proposed Violation and does not list, discuss, or take into account any of the information
we provided to Mr. Regg and Mr. Wallace during the informal review.
DATED: July 16, 2018.
Cosa Inlet Energy, LLC
601 West 5th Avenue, Suite 310
Anchorage, AK 99501
Telephone: 907.334.6745
Facsimile: 907.334.6735
Subscribed and sworn to before me this 16 day of��- 2018.
AFFIDAVIT OF DAVID PASCAL
Docket No. OTH-17-056
&."-
9plltry Pulllic Iri and for Alaska
My commission expires: h • 2b 2,V
13
April 5, 2018
Mr. Hollis French
Chair, Commissioner
Alaska Oil and Gas Conservation Commission
333 West 7th Avenue, Suite 100
Anchorage, Alaska 99501-3572
Subject: Re: Docket Number OTH-17-056
Dear Commissioner French,
Glacier Oil and Gas as owner/operator of Cook Inlet Energy LLC (CIE) is respectfully
submitting the following attachments that will be used in discussion during the informal
hearing scheduled for April 10, 2018.
I can be reached at (907) 433-3822 or at dpascalcrTglacieroil.com for any further
information.
Sincerely,
David Pascal
Production Manger
Cook Inlet Energy
A Glacier Oil and Gas Company
Attachments
1. RU -3A: Current Wellbore Diagram
2. RU -3A: Timeline of Events
3. RU -3A: Graph Depicting Hourly Data of Inner and Outer Annulus Pressures
4. RU -3A: Initial Passed MIT Test
5. RU -3A: AOGCC Witnesses Passed MIT Test
6. RU -3A: Hourly Data in .x1xs format from July 1, 2017 to April 1, 2018 (on disk)
D. Pascal Affidavit EXHIBIT 1
Page 1 of 1
GLACIER
Attachment 1
RU -03A WI -Current Completion Schematic
10112" Hale
4 1 I %9 518' Liner Hanger
TOL ® 7,500' MD
Pedora0one
MD I TVD
7.700 7.80 6.20-6.219
].005-].016 6.223-8.233
Top of 7 -5/8"x9 -W" Liner Q 9,103' MD
1z vb^ xol.
812' Hole
Pod&stim a ereds
PaRlni
stini
aMD
ti
MO
1570615997
121p&t2i11
15785-15M0
1582]-1584]
12132-12147
15031-15731
15862-15802
1215&12173
1588&15873
15920.15940
1220-1221]
15925.15973
t 5940.15980
inTr-12233
15945.159M
15052-19772
1230112319
16052-16066
19971hili 8
1232312336
16081.160M
1614418164
12376-12392
1818616155
1239312409
1819046210
1241412435
1625516275
1246512429
16250 16270
1627116295
1248012497
16275-16282
163151035
1251312573
16]7.6.40335
1633618346
1253612538
16356-19378
12546-12563
6 974" Hole
Date: 5Ju1-17
Version: Final
Tubing hanger- 4.909' MCA Box top mnnedion I
4.5" Geoi Box btm connection -10 3 816'
30" 150#A416 1 260 MO
ID -28" Welded 260 TVD
4-112" 15.1# P110 Geomnn - ID 3.832"
7500' MD
13318" 1 6ML40 I 750TMD
ID -12.25" I BTC I 3,024' TVD
67" fish left in hole -21' of lower gun,1 coupler
37" gun and bull now
Obstrudion tagged @ 16352'
52'fish left to hole -6" of lower gun,
1 miler. 38" bun and bull now
412" 15.18 P-110 116,4112- KID
ID -3.832^ GeoConn 12,650'TVD
D. Pascal Affidavit EXHIBIT 2
Page 1 of 1
9618^
4T# L-80
9.335 MD
ID -8.60" BTC
41111
TOC (CBL): 12,9]5' MD
Window
] 518"
29.M L 82
14,176' 731)
ID -6.T5' N 41521
ID,962'Tgi
C
67" fish left in hole -21' of lower gun,1 coupler
37" gun and bull now
Obstrudion tagged @ 16352'
52'fish left to hole -6" of lower gun,
1 miler. 38" bun and bull now
412" 15.18 P-110 116,4112- KID
ID -3.832^ GeoConn 12,650'TVD
D. Pascal Affidavit EXHIBIT 2
Page 1 of 1
Attachment 2
RU -3A Timeline
26 March: Well Spud
14 April: MIT Test
Aug 14: Annular Pressure 5 psi
6 Nov: Annular Pressure 1,000 psi 1
14 Feb: Automatic
Shut -down Test
1
D. Pascal Affidavit EXHIBIT 3
Page 1 of 1
N
Q
3,000
2,500
RMI
Attachment 3
RU -3A Hourly Annular Pressure Trend
1,000
500
0
May 2,
O Inner Annulus Pressure (psi) 0 Outer Annulus Pressure (psi)
1
D. Pascal Affidavit EXHIBIT 4
Page 1 of 1
Cook Inlet Energy_
Operator. Glacier OI and Ga CoraeralNn
Attachment 4
T..• R e kee oe,.rw
Daily Drilling Report
Tel2:
UWI: 50-733-2050400.00 Rig: Glacier 35 Well Type:
Oil DATE: 14 -Apr -2017
Spud: 26 -Mar -2017 Hr:9:00 rinished Drilling Hr: Rig Release:
Hr: Days from Spud: 19.62
Operations at 6:00 : CLEANING PITS
Total Days: 71
24 Hour Summa : CLEAN PIT, DISPLACE ANNULAS W/ CORROSION INHIBITOR, LAND HANGER, R/U AND RUN CBL.
24 Hour Forecast: SLICK LINE GAUGE RING, CLEAN OUT 41/2 LINER
Surface Location: 1AFE Days:
AFE #: 16001":5
Depth at 24:00 16AB2.0Cft Progress: 0.00ft Ground: ft MRCP:
psi 0 ow AFE Estimate: $6,491,727
Temp: 53' F POL: I Cut or Fill: ft Last Press Test:
Daily Cost: $96.485
Weather: Clear and Calm I Correct-Grd: It Last BOP F/T:
4/5/2017 Cum Cost: $4,907,713
Mud Type: Produced H2O I RT -Ground: It LOT/FIT EMW:
12.8 ppg AFE Other: 0
Mud Co.: MI Swaco I RT: It KT:
bbl Total Cost: $4,907,713
TIME I DEPTH DENSITY VIS PV YP GELS ECD WL FC PH
(hr) (ft) (Ppg) (e/qt) (cp) (Ib YP 10s/tOm/30m (ppg) (cc) 1/32 in
SOLIDS MBT CI Ca++ K+ OIL
(A ppb)(Ppm) (%)
90 16482.00 8.4 26
02211
21:00 78482.00 8.4 28
MUD ADDITIVES I AMOUMI Units
11, Deviation Surveys
Depth /Inc. /Azimuth
BHA
O.D. (in) I.D. (in) Length (ft)
ruvis sx
MI Bar SK
me sx
Actimul RD sx
®®
ersawet SK
®
ube 776 sx
alcium Chlonde 1 SK
u -Vis sK
�
afe-Garb 20 2 sx
eepClean 3 drum
Mud losses daily bbl CUM 0 bbl
ker 1 Shaker 2 Shaker 3 Shaker 4 Total Length: ft
Spm Density HIM gpm Density 00 170 770
Total Weight: Ib
Equipment Centrifuge # 1 Centrifuge #VOO
verfloW 00 170 170 Wt Below Jar: Ib
00 170 170
ndefflOW 770 BHA Hours: hrs
PUMP STROKE LINER SPM VOLUME PRESS EK. Pump Output Slaw Pump Rete Preswre Pressure Pressure Pressure
# MODEL Company linl (in) ((mm) loci) (%) Ibbvsut Deplh MhV lad stkl (40 Wk) (50 stk) (60 sa)
7 PZL GD 11 6 60 23265.7374 15W 96 0.092
14175 10.2 510
2 PZL GD 17 6 1 46 1 17837.0653 1125 96 1 01192 1
14175 I 10.2 I 510
TYPE SERIAL NOZZLES (in) EPTH EPT DAY DAY TOTAL OTAL ROP BIT AVG BR CONDITION
tN Size(in) Mfgr NUMBER Or TFA(in-) m(6) OUr In) (ft) hire (ft) hrs ft/hr WT RPM 1 0 D L B G O R
Bil DP DC Jet Vel HHP h m•
No (in) Apv_ m) (in) AV(ftmun) (IUs) f t Hole Dra (PUJSO):
Rotary WT/Tor ue:
Act. I AIIOW Hook Load:
/ Ib
Ib ( Rib
I Ib (static)
MOP: Klb
TIME BREAKDOWN
own 18. . RI Repairs 172 1527.2
SI' 8 Cut Drill Line 45016Drill Stm Tesl
10. surve 3.2517. P u Back
4. RiMove11.
WIretine 91.5018. Cemen .. Other
PS414.
5.Wailing on
6 Circ 147.5012. Cas' 6 Cementi 4.0 19. Fishi
36.00 . Trouble Time
193.7513. Waft on Cemem O.Oin:ctlonalWork6.
2.0014. Ni e U BOP 5.5021. Waiti on Others
OTAL HOURS
Vaab.1422 wenman a - Kesource tnwgy SOMIMS /nc. (403) 245-0220 www.resoumeener9yso/u11onS.c0m Apr/ 26 2017 Page 1 o/ 3
D. Pascal Affidavit EXHIBIT 5
Page 1 of 3
Cook Inlet Energy_
Daily Drilling Report
Te12
r..,.... �i,�..,.
UWI: 50-733.20504-00-00
WELL: RU -03A DATE: 14 -Apr -2017
Remarks:
SAFETY/PLANNING
NO ACCIDENTS / NO SPILLS
OPERATIONS PERSONNEL ON BOARD
2 -GLA
14 -NORDIC
2- BEACON
2 -MI
2-MAGTEC
1 -WAR
1 -BCS
i-BRAMMER
9-TIW
2-POL
FUEL ON BOARD = 17,657 Gal.
FUEL USED= 596 Gal.
POTABLE WATER = 19,298 Gal.
DRILL WATER= 28,630 Gal.
DRILL WATER IN LEGS = 16,422 Gal.
Vim fror4 Time to I Hours Code
I Comments
00:00 01:00 1 1 6
LID 2 JNTS. OF 4 1/2, R/U TO REVERSE CIRC. PRODUCED WATER 6 CORROSION INHIBITOR.
01:00 05:30 4.5 14E
CLEAN PIT 8, VAC SYSTEM DOWN RIG HANDS BUCKET OUT OF PIT WHILE VAC SYSTEM WAS
BEING WORKED ON.
05:30 07:00 1.5 5
REVERSE CIRCULATE AND DISPLACE ANNULUS WITH INHIBITED FLUID AT 5 BPM, 450 PSI.
07:00 09:30 2.5 12D
LID SINGLE OF CASING AND PICK UP SHORTER JOINT FOR SPACE OUT. M/U HANGER AND PUP JOI
INSTALL NEW HANGER SEALS. INSTALL NEW ORING AND WU LANDING JOINT. CONNECT TOP DRIV
_
O STRING. DRAIN STACK AND MAKE SURE LOCK DOWN PINS BACKED COMPLETELY OUT. SLACK
FF STRING. ROTATE STRING TO GET INTO LINER TOP AND TOP OF PBR. LAND HANGER WITH 35K
DOWN ON SEAL ASSEMBLY. PICK UP TO 25K OVERPULL CONTINUE PULLING FOR 50K OVERPULL
N LATCH ASSEMBLY. HOLD OVERPULL FOR 5 MINUTES. GOOD PULL TEST. IRELAND HANGER.
145K PICK UP, 110K SLACK OFF.
0930 10:30 1 12D
RUN IN LOCKDOWN PINS. PRESSURE TEST VOID TO 5,000 PSI. 5MINUTES. GOOD TEST.
10:30 12:00 1.5 12D
RIG UP HIGH PRESSURE LINE TO ANNULUS. PRESSURE TEST ANNULUS SEALS, AND HANGER TO
,500 PSI. 30 MINUTES. GOOD TEST.
12:00 12:30 0.5 12D
BREAK OUT TOP DRIVE. RIG DOWN W EATHERFORS CASING EQUIPMENT.
12:30 16:00 3.5 11F
HOLD PJSM. R/U POLLARD E -LINE. RIH WITH CBL T/ 10,000'. LOWER E -LINE SHEAVE BECAME MOBIL
HEN TAKING PICKUP WEIGHT. SECURE LOWER SHEAVE. POOH, CHANGE LOWER SHEAVE
LOCATION. PIECES OF SEAL FROM LATCH ASSEMBLY ON CBL CETRALIZER.
16:00 20:30 4.5 SD
IRIH WITH CBL. STARTED LOGGING DOWN F/12,500 - TM6,140' WERE WE TAGGED UP FIRM, PICK
ND ATTEMT TO BREAK THROUGH NO GO POOH RID E -LINE UNIT
20:30 23:00 2.5 5D
CONTINUE INJECTING DOWN RU -1, HOUSE KEEPING AROUND RIG FLOOR, ASSIST SLICK LINE
ON RU -7B.
23:00 23:30 0.5 5D
lRIU SLICK LINE ON RU -3A
23:30 00:00 0.5 5D
RIH W/ 3.0 GAUGE RING JUNK BASKET
-
Total 24
- -- --
Version 1422 Wellman 9 - Resource Energy Solutions Inc. (403) 245-0220 w resourceenergysolutions. con; April 26 2017 Page 2 of 2
D. Pascal Affidavit EXHIBIT 5
Page 2 of 3
J
UNIT #3 GLACIER
PSI
0 3000 11:00
05
:10
Apn�.�w5 PS"r .15
W; i -k SPa l s � n 5,c l leol :20
...- .. :25
:30
:35
40
45
50
55
12:DD
:05
:. _: ._ ..... 10
- 15
:20
25
30
:35
40
:45
50
:55
D. Pascal Af davit XHIBIT 5
P ge3of3
Attachment 5
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Mechanical Integrity Test
Submitto: "mrsaa alaskagwAODCCInspecbme0aliakaum, phcebe.brooksisslaske.aov
OPERATOR:
Gleder Oil and Gas
FIELD / UNIT / PAD:
Osprey Platform -Redoubt Unit
DATE:
12123/17
OPERATOR REP:
Lance Anderson
AOGCC REP.
Brian Bixbv
alms.Wallace4alaska pov
Well
RU -9A
Pressures:
Pretest
Initial
15 Min.
30 Min.
45 Min.
60 Min.
PTD
2161]00 Type Inj
W
Tubing
1970
1970
1985
1965
Type Test
P
Packer ND
5989 BBL Pump
3.5
IA
425
1 2810
2810
2810
1
Interval
0
Test psi
2500 I BBL Realm 1
3.5
OA
25
1 35
37
37
Result I
P
Nn4s:
Test for anmlnletralive.1smu'al papanka-k In 250) psi.
Well
Pressures:
Pretest
Initial
15 Min.
30 Min.
45 Min.
60 Min.
PTD
Type Inj
Tubing
Type Teat
Packer ND
BBL Pump
IA
Interval
Test psi
BBL Return I
OA
ResMIN
New;
Well
Pressures:
Pretest
Inkial
15 Min.
30 Min.
45 Min.
60 Min.
PTD
Type Inj
TubingTypa
Test
Packer ND
BBL Pump
IA
Interval
Teat psi
BBL Retum
OA
Result
Ilsesa:
Wall
Pressures:
Pretest
Initial
15 Min.
30 Mi,
45 Min.
60 Min.
PTD
Type Inj
Tubing
Typa Test
Parker ND
8131 Pump
IA
Interval
Test psi
BBL Return
OA
Resuft
N94£:
Wall
Pressures:
Pretest
Initial
15 Min.
30 Min.
45 Min.
60 Min.
PTD
Type MI
Tubing
Type Teat
Packer ND
BBL Pump
IA
Interval
Test psi
BBL Return
OA
Result
Nota:
Wall
Pressures:
Present
Initial
15 Min.
30 Min.
45 Min.
60 Min.
PTD
Type Inj
TubingType
Test
Packer NO
BBL Pump
IA
Imerval
Test psi
BBL Return
OA
Result
I&I
Well
Pressures:
Pretest
Initial
15 Min.
WMin.
45 Min.
60 Min.
PTD
Type Inj
Tubing
Type Test
Packer ND
BBL Pump
N
Interval
Test psi
BBL Return
On
RasuN
NI
Wall
Pressures:
Pretest
Initial
15 Min.
30 Min.
45 Min.
60 Min.
PTD
Type Inj
Tubing
Type Test
Pader NO
BBLPump
IA
Interval
Test psi
BBL Return
OA
Result
sales.
Wine IW COMA
W=W m
G=Gas
Ss Sum
1= mansblal Wa9eaaler
N=NCI InIadYq
TYPE TEST Colina MTERMLC..
P= P—na Tall 1= Iniul can
o=GNH In.. In NOIuI 4=Four Veal rims
a'a F¢WiKO N' Va—
0- GNel lasmee In nils)
Form 10426 (Revised 01201]) ran Ru U 12-MAe aensa.nnx
nanuacaes
P=Pau
F -Feil
D. Pascal Affidavit EXHIBIT 6
Page 1 of 1
7
Colombie, Jody J (DOA)
From: Romerdahl, Elena M. (Perkins Coie) <ERomerdahl@perkinscoie.com>
Sent: Wednesday, August 01, 2018 4:31 PM
To: Colombie, Jody J (DOA)
Subject: RE: Docket Number OTH-18-037
Jody,
I just heard back from my client regarding a date for the hearing. We would like to request Wednesday, October 24 for the
hearing date if that day is still available. Thank you.
Elena
Elena Romerdahl I Perkins Cole LLP
COUNSEL
1029 West Third Avenue Suite 300
Anchorage, AK 99501
D. +1.907.263.6914
M. +1.202.487.8657
E. ERomerdahl(a)oerkinswie.com
PeRKINScoie
From: Colombie, JodyJ (DOA)[mailto:jody.colombie@alaska.gov)
Sent: Wednesday, July 25, 2018 8:42 AM
To: Romerdahl, Elena M. (ANC) <ERomerdahl@perkinscoie.com>
Subject: RE: Docket Number OTH-18-037
MW
From: Romerdahl, Elena M. (Perkins Coie) <ERome rdahICo) perkinscoie.com>
Sent: Tuesday, July 24, 2018 4:08 PM
To: Colombie, Jody 1 (DOA) <jody.colombie@alaska.aov>
Cc: Barbara Kruk <bkruk@elacieroil.com>
Subject: RE: Docket Number OTH-18-037
Jody,
Thank you. I will confer with my client and be in touch this week.
Elena
Elena Romerdahl I Perkins Coie LLP
COUNSEL
1029 West Third Avenue Suite 300
Anchorage, AK 99501
D. +1.907.263.6914
M. +1.202.487.8657
E. ERomerdahiRverkinwoie.com
PeRKwscoie
From: Colombie, JodyJ (DOA) [mailto:iodv.colombie@alaska ¢ov]
Sent: Tuesday, July 24, 2018 11:06 AM
To: Rome?dahl, Elena M. (ANC) <ERomerdahl@perkinscoie.com>; Barbara Kruk <bkruk@Qlacieroil.com>
Subject: Docket Number OTH-18-037
Please see attached.
Barbara can you please forward this email to Carl Giesler.
Jody J• Co(ombie
AOGCC Specia(Assistant
Alaska Oi(andCGas Conservation Commission
333 'Nest 711 Avenue
Anchorage, Alaska 99501
Office: (907) 793-1221
_'ax: (907) 276-7542
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the Alaska Oil and Gas Conservation
Commission (AOGCC), State of Alaska and is for the sole use of the intended recipient(s). It may contain confidential and/or privileged information.
The unauthorized review, use or disclosure of such information may violate state or federal law. If you are an unintended recipient of this e-mail,
please delete it, without first saving or forwarding it, and, so That the AOGCC is aware of the mistake in sending it to you, contact Jody Colombie at
907.793.1221 or iodv.colombieQalaska.aov.
NOTICE: This communication may contain privileged or other confidential information. If you have received it in error, please advise the sender by reply email and
immediately delete the message and any attachments without copying or disclosing the contents. Thank you.
NOTICE: This communication may contain privileged or other confidential information. If you have received it in error, please advise the sender by reply email and
immediately delete the message and any attachments without copying or disclosing the contents. Thank you.
THE STATE
01ALASKA
GOVERNOR BILL WALKER
July 24, 2018
Elena M. Romerdahl
Counsel for Cook Inlet Energy
Perkins Coie
1029 West Third Avenue, Suite 300
Anchorage, AK 99501-1981
Alaska (til and Gas
Conservation Commission
333 West Seventh Avenue
Anchorage, Alaska 99501-3572
Main: 907.279.1433
Fax: 907.276.7542
www.aogcc.alaska.gov
Re: Docket Number:9�H-�= 7 04 h
—sm-gas-1WITteasu
W
e 1 e reek 3 we s
6'�rar�sid�%r h/Gh- pier
Dear Ms. Romerdahl:
The Alaska Oil and Gas Conservation Commission is willing to offer you a hearing on your Motion
for Reconsideration regarding our Other Order No. 142. If you would like to request a hearing on
this matter, please call Jody Colombie at (907) 793-1221 to schedule within five business days.
Sincerely,
Hollis S. French
Chair, Commissioner
cc: Carl Giesler, CEO
Cook Inlet Energy, LLC
601 West 5h Avenue, Suite 310
Anchorage, AK 99501
l•J
GLACIER
April 5, 2018
Mr. Hollis French
Chair, Commissioner
Alaska Oil and Gas Conservation Commission
333 West 7th Avenue, Suite 100
Anchorage, Alaska 99501-3572
Subject: Re: Docket Number OTH-17-056
Dear Commissioner French,
RECEIVED
APR 0 5 20118
Y1OGCC
Glacier Oil and Gas as owner/operator of Cook Inlet Energy LLC (CIE) is respectfully
submitting the following attachments that will be used in discussion during the informal
hearing scheduled for April 10, 2018.
I can be reached at (907) 433-3822 or at dpascalna glacieroil.com for any further
information.
Sincerely,
JAN
David Pascal
Production Manger
Cook Inlet Energy
A Glacier Oil and Gas Company
Attachments
1. RU -3A: Current Wellbore Diagram
2. RU -3A: Timeline of Events
3. RU -3A: Graph Depicting Hourly Data of Inner and Outer Annulus Pressures
4. RU -3A: Initial Passed MIT Test
5. RU -3A: AOGCC Witnesses Passed MIT Test
6. RU -3A: Hourly Data in .xlxs format from July 1, 2017 to April 1, 2018 (on disk)
GLACIER
Attachment 1
RU -03A W1 -Current Completion Schematic
1011x" Hole
412' X 9510' Liner Hanger
TOL @ 7,60T MD
Perforations
DD
],]80-7BUO 6,2IX1-6.219
7,8054,816 6p23-6,233
Top of 7-&5' x 93/8' Liner @ 9,103' MD
121/6• Hole
81M' Hole
Perla bum InWxam
POdlntereBN
&Imeun
4I91),
4WD
MD
1578615200
uNg6m12111
15MS15794
15327-15647
12132-12147
1583145943
15952.15662
1215612173
1599&15079
15920-15940
12202-12217
1592515954
1594615900
12217-12233
15945-15947
16954-1008
12304-12319
19957-16986
1607616096
12323-12336
19081-18000
1614416164
123]8-12392
1616618185
1239512409
16218
1241612435
162]5
1246612-1]9
16266182]0
18295
124661249]
162]51623]
r1.3
12513-12529
1F13616335
18346
125361253963]8
1254612563
Date: 5 -Jul -17
Version: Final
Tubiig harper -4.909' MCA Box top connection /
4.5' GwConn Box ben connection - ID 3.818'
30" 150#AAB 260'MD
ID -28' I Welder! 260 -WO
4-12.15.1# P119 Ge0conn - ID 3.832'
75W MD
133/8^ BB#L20 3,507'MD
I0-1225^ BTC 302 WD
9 &e" 478 LA0 8,332' MD
ID -8.50" BTC 1,d18'WD
TOC (CBLL 12,975' MD
Window
ji7 518" 1 29.7# LA0 1 14,176' MD
ID -6.1&' 1 H dril 521 1 10,962 -WO
67' fish b4 in hole- 21' of Nwer gun, 1 coupler.
37' gun and bull now
ObslruMion tagged @ IM52'
52' fish leo in hole - e' of lower gun,
1 collar, 36' Hun aM bull nolo
612^ 1551#P-110 16,482'M.
ID -3.632• GeoConn 12,6BP WD
RU -3A Timeline
26 March: Well Spud
14 April: MIT Test
u 1 July: Well Start
u
ep
ct 17
ov 17'
ec �
Aug 14: Annular Pressure 5 psi
6 Nov: Annular Pressure 1,000 psi
+__
1IIYi "
14 Feb: Automatic
Shut -down Test
Attachment 2
3,000
2,500
rm
Attachment 3
RU -3A Hourly Annular Pressure Trend
1,000
500
May 23, 2017 Aug 10, 2017 Oct 27, 2017 Jan 13, 2018
0 Inner Annulus Pressure (psi) 0 Outer Annulus Pressure (psi)
Apr 2, 2018
Cook Inlet Energy_
Operator. Glacier Oil and Gas Corporation
Attachment 4
Reporting To: Stephen Ratcliff
Daily Drilling Report
Te12:
Consultant Josh GupL.ToussaM Telt:
UWI: 50.733.20504.00.00 1 Rig: Glacier 35
1 Well Type:
Oil DATE: 14 -Apr -2 17
Spud: 26 -Mar -2017 Hr: 9:00 IFinished Drilling
Hr. Rig Release.
Hr: Days from Spud: 19.62
Operations at 6:00 : CLEANING PITS
Total Days: 71
24 Hour Summary: CLEAN PIT, DISPLACE ANNULAS WI CORROSION INHIBITOR, LAND HANGER, R/U AND RUN CBL.
24 Hour Forecast: SLICK LINE GAUGE RING, CLEAN OUT 4 1/2 LINER
Surface Location:
I AFE Days:
AFE #: 160016-0.0
Depth at 24:00 16,482.0(0 Progress 0.000 Ground:
D MACP:
psi 0 ppg AFE Estimate: $6,491,727
Temp: 53° F IPOL: Cut or Fill:
it I Last Press Test:
Daily Cost: $96,485
Weather: Clear and Calm Correct-Grd:
it I Last BOP FIT:
41512017 Cum Cost: $4,907,713
Mud Type: Produced H2O RT -Ground:
0 LOTIFIT EMW:
12.8 ppg AFE Other: 0
Mud Co.: MI Swaco RT:
8 KT:
bM Total Cost: $4,907,71
TIME I DEPTH DENSITY VIS I PVYP GELS
(h0 101 (Ppg) IS") Ice) (IW100fe) 10M10mrJOm
ECD WL FC PH SOLIDS MBT Cl Ca++ K+ OIL
(ppg) Icc) t132m (%) (PDD) (ppm) (%)
09:00 116482.00 1 8.4 28
21:00 116482.00 1 8.4 28
MUD ADDITIVES Amount Units
'�. Deviation Surveys
Depth Am. lAzmuth
BHA
O.D. (n) I.D. (in) Length (e)
Vis 6th
Bar EM
mN RD ax
I
assete776
axcium
Chloride 1 sx
VN ax
(e -C" 20 2 sx
epCWan 3 dAm
dud braes daily ba ICUM o ba
quipment Centrifuge 1111 Centrifuge # 2 Shaker 1 Shaker 2 Shaker 3 Shaker 4 Total Le it
170
gpm Density His gpm Density His 7 1170' Total Weight: b
O verflm 170 2 1Wt Below Jar: It,
3 200 170 1
rlderBoo, 1 4 1 200 1 170 BHA Hours: he
PUMP STRONE LINER SPM VOLIME PRESSPump Oupul Sbw Pump Rab presses praesuro praBee Preseee
# MODEL connov (in) (m) (9Pn) (psi) (%1Ea. (bbVNk) Depth MAV (30atk) 1 (40 sal (50Mk) (60x)
11 PZL I GO 11 6 60 23265.7374 1500 1 96 1 0.092 1
14175 1 10.2 1 510
21 PZL GO 11 8 1 46 1 17831.0653 1125 1 96 1 0.092 1
14175 1 10.2 1 510
SERIAL NOZZLES (in) DEPTH EP DAY DAY TOTAL TOTAL ROP BIT AVG BIT CONDITION
N Ses(in Mfw TYPE NUMBER OrTFA(10 W(M (8 (0) M (fl) hrs fl4m WT RPM 1 O D L B G O R
BODP DC Jet VN HHP Hob PU/SO:
No (in) AV(fdmin) (in) AV(Nmin) (IVs)
Rotary WT I Torque:
Act. I Allow Hook Load:
MOP: Klb
! b
Ib I fl4D
I No (static)
TIME BREAKDOWN
n 18.00111. R' ib 17.25115.
Pre9ael6 Test BOP
50.50 2. Other 11.
27.25 . S' 8 CN Drill Line
4. 16. DrNI Stem Test
3. Abandonment
10. Su
3. 17. PI Back
4. Mve
11. WleNre 91. 78. Oder
W.R12Servim
5.Weill onCkc
U7. 12. Ca 8 Cemem
4. 19. Fish
TT193.7
13. Wag an Comm
Z. 1/. NI U BOP
.DimclionalWok
5. 21. Wa ' on OrdeN
e. OTALHOURS
Version 1422 Wellman 9 -Rem Energy SaMons Inc. (403)2450220 a%wreswwceenergysNu#ona.com APW262017 Page f o13
Cook Inlet Energy_
Daily Drilling Report
Tele:
i=ce n,yn T„, . Tai:
UWI: 50-733-2050400-00
WELL: RU -03A DATE: 14 -Apr -2017
Remarks:
SAFETY/PLANNING
NO ACCIDENTS / NO SPILLS
OPERATIONS PERSONNEL ON BOARD
2 -GLA
14 -NORDIC
2- BEACON
2. hill
2-MAGTEC
1 -WAR
1-BOS
1-BRAMMER
1 - TIW
2-POL
FUEL ON BOARD = 17,657 Gal.
FUEL USED= 596 Gal.
POTABLE WATER = 19,298 Gal.
DRILL WATER = 28,630 Gal.
DRILL WATER IN LEGS = 16,422 Gal.
ime froff Tlme to Hours Code
Comments
00:00 01:00 1 6
/D 2 JNTS. OF 41/2 R/U TO REVERSE CIRC. PRODUCED WATER 8 CORROSION INHIBITOR.
01:00 05:30 4.5 14E
LEAN PIT 8, VAC SYSTEM DOWN RIG HANDS BUCKET OUT OF PIT WHILE VAC SYSTEM WAS
EING WORKED ON.
05:30 07:00 1.5 5
EVERSE CIRCULATE AND DISPLACE ANNULUS WITH INHIBITED FLUID AT 5 BPM, 450 PSI,
07:00 09:30 2.5 12D
D SINGLE OF CASING AND PICK UP SHORTER JOINT FOR SPACE OUT. M/U HANGER AND PUP JOI
INSTALL NEW HANGER SEALS. INSTALL NEW ORING AND M/U LANDING JOINT. CONNECT TOP DRIV
O STRING. DRAIN STACK AND MAKE SURE LOCK DOWN PINS BACKED COMPLETELY OUT. SLACK
FF STRING. ROTATE STRING TO GET INTO LINER TOP AND TOP OF PBR. LAND HANGER WITH 35K
DOWN ON SEAL ASSEMBLY. PICK UP TO 25K OVERPULL, CONTINUE PULLING FOR 50K OVERPULL
N LATCH ASSEMBLY. HOLD OVERPULL FOR 5 MINUTES. GOOD PULL TEST. IRELAND HANGER.
145K PICKUP, 110K SLACK OFF.
09:30 10:30 1 12D
UN IN LOCKDOWN PINS. PRESSURE TEST VOID TO 5,000 PSI. SMINUTES. GOOD TEST.
10:30 12:00 1.5 12D
G UP HIGH PRESSURE LINE TO ANNULUS. PRESSURE TEST ANNULUS SEALS AND HANGER TO
,500 PSI. 30 MINUTES. GOOD TEST.
12:00 12:30 0.5 12D
BREAK OUT TOP DRIVE, RIG DOWN WEATHERFORS CASING EQUIPMENT.
12:30 16:00 3.5 11F
HOLD PJSM. R/U POLLARD E -LINE. RIH WITH CBL T/ 10.000'. LOWER E -LINE SHEAVE BECAME MOBIL
HEN TAKING PICK UP WEIGHT. SECURE LOWER SHEAVE. POOH. CHANGE LOWER SHEAVE
LOCATION. PIECES OF SEAL FROM LATCH ASSEMBLY ON CBL CETRALIZER.
16:00 20:30 4.5 SO
RIH WITH CBL. STARTED LOGGING DOWN F/12.500 - T/16,140' W ERE WE TAGGED UP FIRM, PICK
ND ATTEMT TO BREAK THROUGH NO GO POOH RID E -LINE UNIT
20:30 23:00 2.5 5D
ONTINUE INJECTING DOWN RU -1, HOUSE KEEPING AROUND RIG FLOOR, ASSIST SLICK LINE
N RU -7B.
23:00 23:30 0.5 5D
VU SLICK LINE ON RU -3A
23:30 00:00 0.5 5D
RIH W/ 3.0 GAUGE RING JUNK BASKET
Total 24
Verson 1422 Wellmn 9 - Resowce Energy Solutions Inc. (4031) 243-0220 minvneso energysolufionscom April 26 2017 Page 2 of 2
PSI
300[
1100
-05
:10
15
:20
:25
:30
:35
.45
:50
:w
12:00
:05
10
:15
-20
-25
:30
35
:40
45
:60
15
Attachment 5
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Mechanical Integrity Test
Submitb: -i m.reoadta1.skaQov: AOGCCInsaectors®alaska.cov: phoeDe-0moks(dalaska.gQv
OPERATOR: Glacier Oil and Gas
FIELD / UNIT / PAD: osprey Platfor,Radoubt Unit
DATE: IMN17
OPERATOR REP: Lente Aamirson
AOGCC REP: Brian Bixby
dens Wallecedialaske apv
Well
RUJA
MTERVRLpWn
Pressures:
Pretest
Initial
15 Min.
30 Min.
45 Min.
60 Min.
4=Foy Year LyM
F=Fal
PTD
2161100 1 Typa Inj
WTubing
1=Ir¢rcLa�'e
1910
197D
1985
1966
n=ria tri. g
Type Test
P
Packer TVD
5989 BBLPump
3.5
IA
TOA
425
2810
2810
2810
Interval
O
Test psi
2500 1 Bill-Return3.5
25
36
31
31
Result
P
H9NSf:
Test fwaeminlNretive applwal paperxorkb2500
p1.
Well
Pressures:
Pretest
tribal
15 Min.
30 Min.
45 Min.
EO Min.
PTD
Type Inj
TubiN
Type Tesl
Packer TVD
BBLPump
IA
Interval
Teat psi
BBL Return
OA
Result
Ratae:
Well
Pressures:
Pretest
Initial
15 Min.
30 Mrs.
45 Min.
BD Min.
PTD
Type lnj
Tubing
Type Test
Packer TVD
BBLPump
IA
Interval
Test psi
BBL Ratum
OA
-
Result
Nele.:
Well
Pressures:
Pretest
Input
15 Mia
30Min.
45 Min.
80 Min.
PTO
Type Inj
Tubing
Type Test
Packer TVD
BBLPump
IA
In*"
Test psi
BBL Return
OA
Result
Netee:
Well
Pressures:
Pretest
Initial
15 Min.
30 Min.
45 Min.
60 Min.
PTD
Type lnj
Tubing
Type Test
Packer TVD
BBLPump
IA
Interval
Test psi
BBL Return
OA
Result
It4ffit
Wall
Pressures:
Pretest
Initial
15 Min.
30 Min.
45 Min.
60 Min.
PID
Type lnl
Tubing
Typa Test
Packer TVD
BBLPump
IA
Inrorval
Test psi
BBL R.W.
OA
Result
NnTas:
Well
Pressures:
Platen
Initial
15 Min.
30 Min.
45 Min.
BO Min.
PTD
Type lnj
Tubing
Type Test
Packer TVD
BBI -Pump
IA
Interval
Test psi
BBL ReturnOA
Result
Notes:
Wall
Pressures:
Pretest
Insist
15 Min.
30 Min.
45 Min.
110 Min.
PTD
Type lnj
Tubirq
Type Test
Packer TVD
BEL Pump
w
Interval
Test psi
BBL Return
OA
Reach
Note.:
TYPE MJ..
TTE TEST Beep
MTERVRLpWn
beuapalee
W-Wabr
P=Pmeun TM
1=lmel Tnl
P•Pa.
G-Gn
0= 0aer(de.teIn NM n)
4=Foy Year LyM
F=Fal
a=Nary
V=raemM Ly Vanann
1=Ir¢rcLa�'e
I.4weval We..
0=0un(aaurma lnnMnl
n=ria tri. g
Farm Ip 26 (Revised0112011) MIT M1TE 17 RnaM.xex
5
THE STATE
01ALASKA
GOVERNOR BILL WALKER
March 15, 2018
CERTIFIED MAIL —
RETURN RECEIPT REQUESTED
7015 0640 0003 5185 6403
Mr. David Pascal
Production Manager
Cook Inlet Energy, LLC.
601 West 5h Avenue, Suite 310
Anchorage, AK 99501
Re: Docket Number: OTH-17-056
Notice of Proposed Enforcement Action
Alaska Oil and Gas
Conservation Commission
Failure to complete a Mechanical Integrity Test (MIT)
Failure to report a pressure communication
Redoubt Unit 3A (PTD 2161700)
Area Injection Order (AIO) 32
Redoubt Shoal Field, Osprey Platform, Redoubt Shoal Unit (RSU)
Dear Mr. Pascal:
333 West Seventh Avenue
Anchorage, Alaska 99501-3572
Main: 907.279.1433
Fax: 907.276.7542
www.00gcc.olaska.gov
As part of the informal review process, Cook Inlet Energy, LLC. (Cook Inlet Energy) has the
opportunity to submit documentary material and make written and oral statements regarding the
above referenced Notice of Proposed Enforcement Action.
The informal review is scheduled for April 10, 2018 at 10:00 a.m. in the AOGCC's Anchorage
office located at 333 West 7ch Avenue.
Copies of all written submissions and summaries of any oral statements planned by Cook Inlet
Energy should be provided to the AOGCC no later than April 5, 2018.
Sincerely,
Hollis S. French
Chair, Commissioner
GLACIER
March 20, 2018
Mr. Hollis French
Chair, Commissioner
Alaska Oil and Gas Conservation Commission
333 West 7th Avenue, Suite 100
Anchorage, Alaska 99501-3572
Subject: Re: Docket Number OTH-17-056
Dear Commissioner French,
RECEIVED
MAR 2 0 2018
AOGCC
Glacier Oil and Gas as owner/operator of Cook Inlet Energy LLC (CIE) is respectfully
requesting the Commission to conduct an informal hearing in relation to the docket. CIE
will be able to address the issues outlined in the docket during the informal meeting and
hopes to come to an amicable resolution with the Commission on this matter
I can be reached at (907) 433-3822 or at dnascal(cp¢laci� ero;l tom for any further
information
Sincerely,
vo-
3�
D id Pascal
Production Manger
Cook Inlet Energy
A Glacier Oil and Gas Company
3
THE STATE
°fALASKA
GOVERNOR BILL WALKER
March 15, 2018
CERTIFIED MAIL —
RETURN RECEIPT REQUESTED
7015 0640 0003 5185 6427
Mr. David Pascal
Production Manager
Cook Inlet Energy, LLC.
601 West 5h Avenue, Suite 310
Anchorage, AK 99501
Alaska Oil and Gas
Conservation Commission
Re: Notice of Proposed Enforcement Action
Failure to complete a Mechanical Integrity Test (MIT)
Failure to report a pressure communication
Redoubt Unit 3A (PTD 2161700)
Area Injection Order (AIO) 32
Redoubt Shoal Field, Osprey Platform, Redoubt Shoal Unit (RSU)
Docket Number: OTH-17-056
Dear Mr. Pascal:
333 West Seventh Avenue
Anchorage, Alaska 99501-3572
Main: 907.279.1433
Fax: 907.276.7542
www.cogcc.alasko.gov
The Alaska Oil and Gas Conservation Commission (AOGCC) hereby notifies Cook Inlet Energy,
LLC (CIE) of a proposed enforcement action.
Nature of the Apparent Violation or Noncompliance (20 AAC 25.535(b)(1)).
CIE violated the provisions of Rule 6 of Area Injection Order 32 (AIO 32) ("Demonstration of
Tubing/Casing Annulus Mechanical Integrity") when it failed to perform an AOGCC witnessed
Mechanical Integrity Test (MIT) after injection was commenced for the first time in the Redoubt
Unit 3A (RU 3A) well.
CIE violated both 20 AAC 25.402 (f) and the provisions of Rule 8 of AIO 32 requiring CIE to
notify AOGCC and submit a plan of corrective action when pressure communication, leakage or
lack of injection zone isolation was indicated in the RU 3A well.
Notice of Proposed Enforcement Action RU 3A
Docket Number: OTH-17-056
March 15, 2018
Page 2 of 5
Basis for Finding the Violation or Noncompliance (20 AAC 25.535(b)(2)).
Failure to Report a Pressure Communication or Leakage. By letter dated December 18, 2017 CIE
notified AOGCC that the well was exhibiting potential tubing (T) by inner annulus (IA) pressure
communication while injecting water.
In its letter CIE provided a 30 -day injection pressure plot. CIE reported that after approximately
78 days of injection the IA pressure began to rise and the field staff bled it down numerous times
to keep it below 200 psi. To confirm the communication, CIE let the pressure build to 1008 psi
over 79 days, bled down the pressure, and again let the IA pressure build gradually to 590 psi
before another bleed on December 18, 2017. CIE ultimately notified AOGCC of this pressure
communication via the letter to AOGCC dated December 18, 2017 (received by AOGCC on
December 19, 2017) in which CIE requested to continue water injection.
AOGCC regulation 20 AAC 25.402 (f) states "Ifan injection rate, operatingpressure observation,
or pressure test indicates pressure communication or leakage in any casing, tubing, or packer, the
operator shall notify the commission by the next working day... "
Rule 8 of AIO 32 states "Whenever any pressure communication, leakage or lack of injection
zone isolation is indicated by injection rate, operating pressure observation, test, survey, log, or
other evidence, the Operator shall notify the Commission by the next business day and submit a
plan of corrective action (on Form 10-403) for Commission approval. The Operator shall
immediately shut in the well if continued operation would be unsafe, would threaten
contamination of freshwater, or if so directed by the Commission. Monthly reports of daily
tubing and casing annuli pressures and injection rates must be provided to the Commission for
all injection wells indicating well integrity failure or lack of injection zone isolation. "
On December 19, 2017 CIE provided pressure and injection data (pdf format, via email) for RU
3A from June 2, 2017 onwards. CIE's only notice to AOGCC of potential pressure communication
occurred via the December 18, 2017 letter. Information provided by CIE demonstrates significant
pressure anomalies which were not communicated to the AOGCC. Significant IA pressure
increases occurred including the two pressure build up tests: approximately August 18, 2017 to
November 5, 2017 (maximum observed pressure was 1008 psi), and November 5, 2017 to
December 18, 2017 (maximum observed pressure was 590 psi). In both cases, there is no evidence
to suggest the rate of pressure build was subsiding.
CIE failed to report to AOGCC pressure communication indicating a potential loss of mechanical
integrity on RU 3A by the next working day, a violation of Rule 8 AIO 32 and State regulations.
Notice of Proposed Enforcement Action RU 3A
Docket Number: OTH-17-056
March 15, 2018
Page 3 of 5
Failure to Perform the Required MIT. A review of the well information provided by CIE shows
RU 3A was handed over to injection operations on May 30, 2017, with injection allocated to the
well continuously beginning July 1, 2017.
In its review of the well history, AOGCC discovered RU 3A was operating without having passed
an AOGCC witnessed post-injection MIT.
Rule 6 of AIO 32 states "The mechanical integrity of an injection well must be demonstrated
before injection begins, and before returning a well to service following a workover affecting
mechanical integrity. A Commission -witnessed mechanical integrity test must be performed
after injection is commenced for the first time in a well, to be scheduled when injection
conditions (temperature, pressure, rate, etc.) have stabilized. Subsequent tests must be
performed at least once every four years thereafter. "
In addition to the MIT requirement in AIO 32, the Permit to Drill for RU 3A included the "Post
Initial Injection MIT req'd" condition of approval.' CIE operated RU 3A approximately six
months without the required MIT. CIE was notified on December 20, 2017 that the well must pass
an AOGCC-witnessed MIT to continue on injection. A successful MIT was witnessed on
December 23, 2017.
Based on information provided by CIE — including the passing of the AOGCC witnessed MIT on
December 23, 2017 — AOGCC determined that water injection could safely continue if CIE
complied with the restrictive conditions set out in an administrative approval dated December 28,
20172. Approval conditions included monthly reporting of well pressures, injection rates, and
pressure bleeds; installation and testing of automatic well shut-in equipment linked to the wells
inner annulus pressure; and a more frequent MIT schedule.
Proposed Action (20 AAC 25.535(b)(3).
Within four weeks of the date of the AOGCC's final decision, CIE shall:
(1) Provide a detailed description of its Underground Injection Control (UIC) regulatory
compliance program;
(2) Provide details of its tracking system for determining when MIT's are required, including
the details of contingencies for wells shut in at the time an MIT is due and its procedures
for notification to the AOGCC, as well as its processes for determining the MIT due date
and identification of past due wells;
(3) Provide a detailed description of its (non-UIC) AOGCC regulatory compliance program,
including its tracking system for determining when compliance requirements are due (e.g.
safety valve testing, custody transfer meter testing, monthly and annual reports etc.);
(4) Provide a Root Cause Analysis addressing the failure to provide a notification of a pressure
communication to AOGCC within the next business day (Rule 8 of AIO 32); and
Permit to Drill # 2161700 dated February 1, 2017.
2 AIO 32.001.
Notice of Proposed Enforcement Action RU 3A
Docket Number: OTH-17-056
March 15, 2018
Page 4 of 5
(5) Provide a Root Cause Analysis addressing the failure to complete an AOGCC witnessed
MIT once the well commenced injection and stabilization was achieved (Rule 6 of AIO
32).
For these violations the AOGCC intends to impose civil penalties on CIE as follows3:
$25,000 for the initial violation — failure to perform the required MIT of the injection
well in compliance with testing protocols specified in Rule 6 of AIO 32.
$25,000 for the initial violation — failure to notify AOGCC of indication of pressure
communication or leakage in RU 3A as specified in Rule 8 of AIO 32 and AOGCC
regulation 20 AAC 25.402 (f).
The total proposed civil penalty is $50,000. The proposed penalty reflects the AOGCC's
consideration of the criteria set forth in AS 31.05.150(g). While the penalty does not reflect
amounts based on per -day assessment, that decision does not minimize CIE's failure to report the
significant repressurization events that occurred four months before notifying the AOGCC of
possible serious and substantial issues with the integrity of the RU 3A wellbore. The failure to
complete the initial post-injection MIT cannot be characterized as a good faith attempt to comply
with the AOGCC's orders and regulations. Although no injury to the public occurred, the potential
wellbore failure posed an obvious threat to both public health and the environment. Violations
relating to Underground Injection Control Class II well integrity practices warrant the imposition
of civil penalties. CIE's failure to comply with the fundamental wellbore mechanical integrity
testing requirements raises the potential for similar behavior with more serious consequences.
CIE's failure to notify AOGCC of the pressure communication shows disregard or ignorance of
CIE's compliance responsibilities. Mitigating circumstances considered in the assessment of the
proposed civil penalty include the operator's compliance history, enforcement and notice of
violation history, and the absence of known sources of freshwater in the Redoubt Unit. Once
AOGCC determined the well was out of compliance, CIE demonstrated an urgency in completion
of the required AOGCC witnessed MIT, and in the installation and testing of the automatic well
shut-in equipment that AOGCC required be installed as conditions for continued injection in the
well.
Rights and Liabilities (20 AAC 25-535(b)(4)).
Within 15 days after receipt of this notification — unless the AOGCC, in its discretion, grants an
extension for good cause shown — CIE may file with the AOGCC a written response that concurs
in whole or in part with the proposed action described herein, requests informal review, or requests
a hearing under 20 AAC 25.540. If a timely response is not filed, the proposed action will be
deemed accepted by default. If informal review is requested, the AOGCC will provide CIE an
opportunity to submit documentary material and make a written or oral statement. If CIE disagrees
with the AOGCC's proposed decision or order after that review, it may file a written request for a
' AS 31.05.150(a) provides for not more than $100,000 for the initial violation and not more than $10,000 for each
day thereafter on which the violation continues.
Notice of Proposed Enforcement Action RU 3A
Docket Number: OTH-17-056
March 15, 2018
Page 5 of 5
hearing within 10 days after the proposed decision or order is issued. If such a request is not filed
within that 10 -day period, the proposed decision or order will become final on the 1 lth day after it
was issued. If such a request is timely filed, the AOGCC will hold its decision in abeyance and
schedule a hearing.
If CIE does not concur in the proposed action described herein, and the AOGCC finds that CIE
has violated or failed to comply with a provision of AS 31.05, 20 AAC 25, or an AOGCC order,
permit or other approval, then the AOGCC may take any action authorized by the applicable law
including ordering one or more of the following: (i) corrective action or remedial work; (ii)
suspension or revocation of a permit or other approval; (iii) payment under the bond required by
20 AAC 25.025; and (iv) imposition of penalties under AS 31.05.150. In taking action after an
informal review or hearing, the AOGCC is not limited to ordering the proposed action described
herein, as long as CIE received reasonable notice and opportunity to be heard with respect to the
AOGCC's action. Any action described herein or taken after an informal review or hearing does
not limit the action the AOGCC may take under AS 31.05.160.
Sincerely,
Hollis S. French
Chair, Commissioner
cc: Ryan Gross, USEPA, Region 10
AOGCC Inspectors
p
Wallace, Chris D (DOA)
From: David Pascal <dpascal@glacieroil.com>
Sent: Tuesday, December 19, 2017 3:15 PM
To: Wallace, Chris D (DOA)
Cc: Schwartz, Guy L (DOA); Regg, James B (DOA)
Subject: Re: Redoubt Unit 3A (PTD 2161700) Annular Pressure [Docket OTH-17-056]
Attachments: RU -3A MIT.pdf; RU -3A Data.pdf (�rP
Chris,
Please see answers below in Red. Please let me know if you have any further questions
David
From: "Wallace, Chris D (DOA)' <chris.wallaceCa�alaska gov>
Date: Tuesday, December 19, 2017 at 11:15 AM
To: David Pascal <dpascalCa)glacieroil.com>
Cc: "Schwartz, Guy L (DOA)' <guy.schwartzPalaska.gov>, "Regg, James B (DOA)' <iim.reggPalaska.gov>
Subject: Redoubt Unit 3A (PTD 2161700) Annular Pressure [Docket OTH-17-0561
David,
AOGCC has received your letter dated December 18, 2017 detailing a tubing/annular communication of RU -3A. It has
prompted a review of this well, our regulations, and the Area Injection Order (AIO) #32 that governs injection operations
in this well.
Our records do not show any mechanical integrity testing for this well? It looks like first injection was in the month of
July 2017.
Initial testing associated with a new well and additional testing with any mechanical integrity change to the well should
have been completed, and once injection has commenced and stabilized as per the permit to drill, sundry applications,
and AID 32 Rule 6. Do you have any information on MIT's completed, witnessed or not, rig or separately, and any
explanation as to why AOGCC doesn't appear to have these records?
MIT was performed on 26th March at 2,500 psi and successfully passed. Please see
first attachment
AIO 32 is available at htt2://aogweb.state.ak.us/ogc/orders/aio/data/aio32.pdf
Rule 5 of AIO 32 details requirements of tubing and annuli pressures being monitored
at least daily. Please provide the Tubing, Inner annuli, outer annuli pressures for
the last 90 days.
Please see second attachment for RU -3A injection and pressure data. Monitored
hourly
Rule 8 of AIO 32 details the notification requirements (next business day) when a
pressure communication is indicated. Please provide when and how AOGCC was notified
or if in fact this letter dated December 18, 2017 is the first AOGCC notification?
Leak is minor (<0.9 gal/day) and was difficult to quantify/detect. AOGCC
was notified as soon as we confirmed our suspicions via the test submitted
Thanks and Regards,
Chris Wallace, Sr. Petroleum Engineer, Alaska Oil and Gas Conservation Commission, 333
West 7th Avenue, Anchorage, AK 99501, (907) 793-1250 (phone), (907) 276-7542 (fax),
chris.wallace@alaska.gov
CONFIDENTIALITY NOTICE: This e-mail message, including any attachments, contains information from the
Alaska Oil and Gas Conservation Commission (AOGCC), State of Alaska and is for the sole use of the intended
1
recipient(s). It may contain confidential and/or privileged information. The unauthorized review, use or
disclosure of such information may violate state or federal law. If you are an unintended recipient of this e-mail,
please delete it, without first saving or forwarding it, and, so that the AOGCC is aware of the mistake in sending
it to you, contact Chris Wallace at 907-793-1250 or chris.wallace@alaska.aov.
1
RECEIVED
DEC 1 9 2017
GLACIER
AQGCC
Dec 18, 2017
Mr. Guy Schwartz,
Senior Petroleum Engineer
Alaska Oil and Gas Conservation Commission
333 West 7th Avenue, Suite 100
Anchorage, Alaska 99501-3572
Subject: RU -3A Annular Pressure
PTD: 216-170
API No: 50-733-20504-01-00
Dear Mr. Schwartz,
We have noticed a possible tubing/annular communication in well RU -3A. The
annulus pressure started to rise about 78 days after the well was completed. We bled it
down several times as it approached 200 psi, but it would not go static. In order to
confirm the communication, the annulus was shut-in and except for one 100 psi bleed
down the pressue was allowed to build to 1,003 psi over 79 days (13 psi/day). The
annulus was bled down to zero and 70 gallons of annular fluid was recovered. The
annulus was again shut-in and monitored. The pressure on the annulus during this
operation has built up to 474 psi (Dec 18) with a rate increase about 13.8 psi/day
We have currently bled down the annulus pressure to 0 psi and will continue to do
periodically, so that the pressure doesn't increase beyond 500 psi. At this point of time
due to the small amount (-0.9 gal/day) it would be difficult to identify the source of the
leak. If the rate of pressure increase exceeds 25psi/day, we would attempt to find the leak
with a Sonic log. Glacier Oil and Gas requests the Commission that we continue to
operate the well, as it is a critical injector to maintain reservoir pressure and resulting in
GLACIER
incremental reserves in the Redoubt field. If any additional information is needed, please
contact me at dpascal(u)glacieroil.com or at (907) 433-3822
Sincerely,
Pascal
tion Manager
Oil and Gas
Attachments
1. Current Wellbore Diagram RU -03
2. Annular Pressure Trend Latest Build-up
GLACIER
r._ -03A W1 -Current Completion Schematic
18 1/2" Hole
4 1/2' X 9 5/8' Liner Hanger
TOL @ ],580'ME)
Perforations
MD
I ND
7,780-7,800
6,203-6,219
],805-7,818
6,223-6233
Top of 7-5/8' x 9-5/8' Liner @ 9,103MD
12 1/4" Hole
8 1/2" Nole
Pei18 Slim Intervals
Pert Intervals
Stini
flMD
ft We
MD
15780-15800
12096-12111
15785.15794
15627-15847
12132-12147
1583145843
15862-15882
12150-12173
15066=15818
15920-15940
12202-12217
15925-15934
15940-15960
12217-12233
15945-15954
16052-16072
12304-12319
16051-16066
16076-16096
1232312338
16081-16090
16144-16161
12376-12392
16166-16185
12393-12409
16198-16216
12419-12435
16255-16275
1246512479
16260-16270
16275-16295
12460.12497
16275-1628]
1631516335
12513-12529
16326.16335
1633646346
12530-12538
16358-16376
1254&12563
6 3/4" Nole
PBTD:
Date: 5.lul-17
Version: Final
Tubing hanger- 4.909' MCA Box top connection I
4.5" GeoConn Box btm connection - ID 3.816'
30" 1 150# A-36 260' MD
I0-28" 1 Welded 1 260' Into
4-1/2" 15.1# P110 Goncourt - ID 3.832"
@ ]500' MD
13 318" fib# L -BD 3,507'MD
ID -12.25" 1 BTC 3,024'ND
95/8" 1 47# L-80 9,332' MD
ID -8.50" BTC 7,416'ND
TOC (CBL): 12,975' MD
Window
] 5I8" 1 29.7# L40 1 14,176' MO
ID -6.]5" N tlri1521 10,962'ND
67' fish left in hole - 21' of lower gun, 1 coupler,
37' gun and bull nose
Obstruction tagged @ 16352'
52' fish left in hole - 6" of lower gun
1 collar, 36" Dun and bull nose
4 1/2" 15Co.1# P-110 16,482' MID
ID -3.832" Geonn 12,650'ND
-If
300
.y
CL
Iu
m
N
N
T 200
a
C
C
C
100
0
11/5/17
RU -3A Annular Pressure
11/13/17 11/20/17 11/28/17 12/5/17