Department of Commerce, Community, and Economic Development
Alaska Oil and Gas Conservation Commission
Loading...
HomeMy WebLinkAbout2003 Alpine Oil PoolConocoPhillips
Alaska, Inc.
March 22, 2004
Alaska Oil and Gas Conservation Commission
Attention: Mr. John Norman
333 West 7th Ave, Suite 100
Anchorage, AK 99501
Chris Alonzo
Alpine Engineering Supervisor
Post Office Box 100360
Anchorage, Alaska 99510-0360
Phone (907) 265-6822
Fax: (907) 265-1515
Subject: Annual Surveillance Report for the Alpine Oil Pool of the Collville River Unit
Dear Commissioner Norman:
ConocoPhillips Alaska, Inc., as Operator and on behalf of the working interest owners
of the Colville River Unit submits this, the Annual Surveillance Report for the Alpine Oil
Pool of the Colville River Unit. This report is submitted in compliance with Rule 8, of
Conservation Order No. 443, and reflects the status of the Alpine Pool of the Colville
River as of February 1, 2004. Attachment 1 illustrates the current unit boundary, which
was revised in June of 2003.
If you have any questions or require additional information, please contact me at
ConocoPhillips Alaska, Inc., P. O. Box 100360, Anchorage, Alaska, 99510-0360,
Telephone: (907) 265-6822.
1.0 Progress of Recovery Projects
1.1 Average Metrics for the time period of February 2003 through January 2004
- Average oil production rate
97.2 MBOPD
- Average gas production rate
113.9 MMSCFD
- Average water production rate
884 BWPD
- Average gas injection rate
99.2 MMSCFD
- Average water injection rate
93.6 MBWPD
- Average produced water inj. Rate
449 BWPD
Annual Surveillance Repoi,
Alpine Oil Pool, Collville River Unit
March 22, 2004
1.2 Cumulative Volumes Produced and Injected through January 2004
- Cumulative oil production through January 2004:
108,047,639 STBO
- Cumulative gas production through January 2004:
117,105,409 MSCF
- Cumulative water production through January 2004:
541,089 STBW
- Cumulative gas injection through January 2004:
101,412,960 MSCF
- Cumulative water injection through January 2004:
96,152,093 STB
1.3 Surface Facility Update
The production facilities installed in 1999-2000 are at full capacity. Crude oil is being
processed and transported via pipeline to Kuparuk's Central Processing Facility 2.
Produced gas and water is re -injected. Produced gas is blended with natural gas
liquids and re -injected for enhanced oil recovery within the Alpine Field. The primary
facility maintenance activity during 2003 occurred between July 28 -August 3, when the
plant was taken down for annual maintenance. The most significant process change
was an upgrade of the condensate pump to increase condensate injection into the MI
blend stream.
1.4 Miscible Water Alternating Gas Flood Management during 2003
Development of the Alpine reservoir is based on a Miscible Water Alternating Gas
(MWAG) project design. Alpine EOR facilities have been described in previous
testimony before the AOGCC. This discussion will provide a narrative update on key
reservoir management issues for the time period of February 2003 through January
2004.
CD1
Attachment 2 gives an overview of the miscible water -alternating -gas (MWAG)
conversion status at CD1 in a tabular form. The MWAG flood has now significantly
matured, as shown in Attachment 3. CD1 averages an HCPV throughput of
approximately 46%. Two wells have completed the target MI slug of approximately
30% HCPV (CD1-21, CD1-23). Three wells, CD1-01, CD1-02 and CD1-13, are on their
2nd cycle of MI, after having been temporarily converted to seawater injection in order to
control rising GOR trends in offset producers. CD1-21 and CD1-31 were also
converted to MI service in 2003, mainly for pressure support, in order to make seawater
available to other wells requiring conversions to seawater injection. Six MWAG
injectors, CD1-03, CD1-23, CD1-26, CD1-37, CD1-39 and CD1-42, have been
converted back to their second cycle of seawater injection duty, in order to alleviate
rising GOR trends in offset producers. Four wells, CD1-16, CD1-33, CD1-36 and CD1-
45, are on their first cycle of MI, and will be converted to seawater injection according to
the response seen in the offset producers.
The main drivers behind the rate of maturation of the different patterns are field offtake,
local re -pressurization schemes to allow for safe development drilling, local voidage
balance requirements, seawater availability, MI enrichment requirements and the
necessity to control GOR within compressor limits.
K
Annual Surveillance Report
Alpine Oil Pool, Collville River Unit
March 22, 2004
CD2
Attachment 4 gives an overview of the MWAG conversion status in a tabular form.
Attachment 5 shows the maturity of the different patterns. CD2 is significantly less
mature than CD1, with only 8.3% overall throughput. This is due to a combination of
factors: production commenced later than at CD1 and offtake rates have been
moderated due to the ongoing development drilling. Also, relatively large pattern
volumes are common at CD2, and lower rock quality will not allow the same processing
rates attained at CD1. Twenty-four MWAG injectors are now in place at CD2. Sixteen
of these are still on their first cycle of seawater injection. Seven wells have been
converted to their first cycle of MI. One well, CD2 -49, has been converted back to
seawater injection after having served as a dry gas and MI injection well during the
period from October 2002 until mid-April 2003. The impetus to convert this well to gas
injection service at a relatively early stage was to spread dry gas injection throughout
the field, and to test the gas flooding potential of the tighter CD2 C sands. The good
response observed in offset producers, suggests that CD2 should deliver similar
recovery factors to CD1.
Overall field response to the MWAG remains excellent. Attachment 6 depicts recovery
vs. throughput for all active MWAG patterns, and attests to the effectiveness of the
EOR flood at Alpine.
1.5 Injectivity of wells on 2nd MWAG cycle
A dozen wells have now been put on seawater injection duty after having served as MI
injectors for some period of time. A reduction in injectivity during the second cycle of
water following gas injection has been noticed in most wells. While the amount varies
from well to well, the loss averages about 50%. This was expected given the fine-
grained Alpine sands coupled with low initial water saturations. These relative
permeability affects have been accounted for in the reservoir simulator. Two wells,
CD1-01 and CD1-02, have seen no or very little reduction in injectivity. This is thought
to be due to a higher level of natural fracturing in that particular area of the field.
1.6 MI Enrichment Issues
The MI stream consists of lean gas from the field gas production stream (blend gas)
and C2+ enriching components extracted from the condensate flash drum and the
Joule Thompson Unit. The supply of enriching components is limited to about 15
mmscf/d. Part of the field management strategy focuses on maintaining the MMP of
the injected MI lower than the average reservoir pressure. This requires a certain
enrichment level of the MI stream that cannot always be achieved by using all the blend
gas. Some of the blend gas must therefore be injected into up -structure lean gas wells
to ensure adequate composition of the MI stream. For optimal EOR performance, the
amount of lean gas injection is kept to a minimum. The CD2 -49 was converted to lean
gas injection in October 2002, to reduce the injection requirements in the eastern up -
structure lean gas injection wells. As additional low GOR CD2 production has been
brought online, the necessity to inject lean gas has been reduced, and CD2 -49 was
subsequently converted to MI to improve pattern EOR performance.
3
Annual Surveillance Repor,
Alpine Oil Pool, Collville River Unit
March 22, 2004
The composition of the injected miscible gas is routinely monitored and adjusted with
the miscible gas/lean gas split to ensure miscibility with the reservoir oil.
1.7 Reservoir Management for 2004
In 2004, reservoir management at Alpine will be driven by field wide production offtake,
re -pressuring CD1 during the summer shutdown, and local re -pressurization schemes
to support development drilling. The plant upgrades that will be implemented during the
July/August 2004 field shutdown will allow significantly higher production and injection
rates than what is currently possible. It is estimated that Alpine production rates will
gradually reach 115,000 to 120,000 bopd after the shutdown. These rates will be
balanced with a projected seawater import rate of 133,000 bwpd. Under this scenario,
it is anticipated that average reservoir pressure will increase.
Some seawater injection will be maintained during the summer shutdown. Most CD1
injectors will be converted to seawater injection prior to the summer shutdown, to allow
re -pressurization of this part of the field, since it is more depleted than CD2, and higher
rates are achievable from the eastern area of the field than from the tighter western
sands.
Based on expected water and gas injection rates, five or six wells at the CD2 pad are
likely to reach their seawater pre-injection target of 10-15% HPCV in 2004.
Conversions from MI back to seawater will occur based on local field performance.
2.0 Alpine Production and Injection by Month
CPAI is planning minor revisions to produced gas volumes based on ongoing metering
studies. We expect to finalize and restate gas production during 2004.
M
Total
Month
Oil
Gas
Water
Wtr Inj
Gas Inj
MI Inj
Gas Inj
MSTBO
MMSCF
MSTBW
MSTBW
MMSCF
MMSCF
MMSCF
02/28/03
2,764.3
3,223.5
20.9
2,673.7
553.7
2,235.5
2,789.2
03/31/03
3,256.0
3,380.7
25.7
2,995.3
773.0
2,146.0
2,919.1
04/30/03
3,121.3
3,343.4
24.0
2,922.1
580.3
2,329.5
2,909.8
05/31/03
3,234.9
3,736.6
29.4
2,891.3
462.8
2,820.1
3,282.9
06/30/03
3,045.7
3,563.0
37.7
2,945.8
422.9
2,711.1
3,134.0
07/31/03
2,482.4
2,678.2
29.0
2,907.0
414.3
1,924.0
2,338.3
08/31/03
2,840.8
3,233.2
33.4
2,878.7
354.1
2,470.6
2,824.7
09/30/03
3,149.0
3,828.0
34.1
2,963.8
738.4
2,623.7
3,362.1
10/31/03
2,772.5
3,760.0
29.2
2,189.6
499.1
2,820.9
3,320.0
11/30/03
3,090.0
3,879.4
20.7
2,887.5
381.8
3,017.0
3,398.8
12/31/03
2,732.1
3,086.4
23.5
3,048.2
307.8
2,300.4
2,608.2
01/31/04
3,251.7
3,678.8
30.2
2,990.7
358.6
2,774.8
3,133.5
CPAI is planning minor revisions to produced gas volumes based on ongoing metering
studies. We expect to finalize and restate gas production during 2004.
M
Annual Surveillance Repoi,
Alpine Oil Pool, Collville River Unit
March 22, 2004
3.0 Survey Results
3.1 Reservoir Pressure Monitoring
During 2003, numerous pressure surveys were conducted in newly drilled and shut in
development wells. The Annual Reservoir Pressure Report was submitted to the
AOGCC on January 28, 2004 (Form 10-412), it documents all subsurface pressure
measurements (interpreted as stable) for Alpine during 2003. The Alpine reservoir is
continuously managed to allow for local pressure build up in areas of development
drilling while maintaining average pattern pressures at or above the level required for
stable production and optimum EOR performance in the rest of the field. Reservoir
pressures are estimated from the Alpine full field simulation model as well as from
inflow performance relation analysis on all drilled producers. Both approaches are
calibrated with actual reservoir pressure measurements collected from static surveys
taken in development wells as well as continuous pressure data from the dedicated
observation wells when available.
Since injector CD2 -35 was redrilled to the 2-35A location, the pressure gauge in Alpine
1 B has been of limited value. The distance between the CD2 -35A wellbore path and the
Alpine 1 B bottom hole location is approximately 250 ft. Thus, the pressure observed in
1 B is heavily influenced by choke changes in 2-35A. The gauges in Bergschrund 2A,
were not functional during 2003. Work is currently underway to determine the cause of
the gauge malfunction, and the necessary steps to repair it. Additional pressure
surveys are planned for development wells in the Bergschrund 2A area.
Drilling problems, perhaps related to low reservoir pressures in the target area were
encountered in five wells during the course of 2003. These occurred in the form of lost
circulation events and differential sticking. There are indications that low pressure,
when present, is not always ubiquitous throughout the entire pattern volume, but rather
local heterogeneity results in low pressure areas due to differential depletion.
3.2 Well Surveillance
As documented in the previous annual report, we continue to work with contractors to
refine the design of a coil tubing conveyed packer flow meter to improve reliability.
These devices offer the best technology to quantitatively evaluate horizontal well
injection and production profiles in Alpine development wells. The packer flow meter
tool was redesigned in early 2003 to increase the durability of the inflatable packer
element. The new tool has been successfully deployed in three injectors and one
producer since the redesign with good results. Usable data was recovered from a
producer packer flow meter profile for the first time in 2003.
In the coming months, we plan to repeat injection profiles on wells receiving water -
following -gas cycles to determine if the profile has changed. Injector logging typically
consists of a packer flow meter profile and one to two temperature -based logging runs
to qualitatively assess the horizontal injection profile. We continue to be encouraged by
the generally favorable injection profiles we see in the Alpine Field.
Annual Surveillance Report
Alpine Oil Pool, Collville River Unit
March 22, 2004
4.0 Field Development
4.1 Development Wells Drilled as of February 1, 2004
- 83 wells drilled total:
0 18 CD1 producers
0 18 CD1 injectors
0 21 CD2 producers
0 24 CD2 injectors
0 2 Disposal wells
4.2 Development Drilling Completed in 2003
Sixteen wells were drilled and completed in calendar year 2003, two more than
expected. Twelve wells were injectors, 4 were producers. A total horizontal section of
75,226 ft was drilled.
Forty-three wells have now been drilled and completed at CD2 as of January 31, 2004.
Attachment 7 lists the Alpine producers and injectors drilled to date and their NAD27,
ASP4 completion coordinates, for both the beginning and end of the horizontal
productive interval in the Alpine sand.
Wells drilled in 2003 were located along the northern and southern periphery and the
western margin of CD2. Drilling peripheral wells equates to greater offsets and longer
wells than have been drilled historically. Operational challenges during 2003 were
locally lower reservoir pressures encountered while drilling the western row of injectors
(CD2 -55, CD2 -40, and CD2 -30). Circulation was lost during the 7" casing cement jobs
in both CD2 -55 and CD2 -30. Both wells were suspended for evaluation and remedial
work before returning and drilling to TD. In CD2 -40, low pressures resulted in
differentially stuck drill pipe in the Alpine C Interval and loss of a drilling bottom hole
assembly (BHA). The well was sidetracked around the BHA and drilled to completion.
Drilling along the northern periphery at CD2, the Alpine C Interval thins but maintains
good reservoir quality. Well CD2 -06 successfully drilled 7,008 feet (93% in zone) of
horizontal section in approximately 20 ft sand with about 100 ft of structural relief.
The southern periphery at CD2 is the more distal margin of the Alpine C Interval.
Reservoir quality decreases and the interval begins to "shale -out" to inter -bedded sands
and silts. This makes it more challenging to keep the horizontal well bore in reservoir
quality sand. This is evident in both CD2-36PB1 and CD2 -36.
The drilling schedule is continually optimized to allow re -pressurization in areas of
development drilling while maintaining sufficient pressure elsewhere to maintain field
deliverability and an efficient EOR process.
Annual Surveillance Report
Alpine Oil Pool, Collville River Unit
March 22, 2004
4.3 Development Drilling in 2004
All remaining wells to be drilled at Alpine are located along the periphery of the field.
Twelve development wells and one "delineation" well are scheduled to be drilled during
2004. Seven of the wells are planned along the southern margin of CD1, one of which
has already been drilled (CD1-07). Five wells are planned at CD2, two along the
southern periphery and three along the western margin. One of the wells along the
western margin has already been drilled this year (CD2 -43).
In addition to the planned development drilling, a delineation well on the northwestern
periphery of CD2 is being evaluated. If drilled, this well will assist with a decision to drill
additional wells in the area, which is outside the scope of the original 94 well
development program.
Attachment 8 lists those wells scheduled for 2004, and Attachment 9 is an Alpine net
pay map with all wells drilled to date and those planned for the remainder of 2004. In
addition, the two remaining wells out of the 94 well development program at CD1 and
seven potential peripheral candidate well locations are also identified on Attachment 9.
These wells will be further evaluated based on 2004 drilling results for potential drilling
in 2005. This plan is subject to change as the drilling schedule is optimized throughout
the course of the year. There will be a break in the drilling schedule for approximately
two months in the March -April 2004 timeframe, to allow for exploration drilling use of the
Alpine drilling rig. Other future breaks in the drilling schedule are also possible.
4.4 Facilities Expansion Evaluation
Currently the combined well productivity from all CD1 and CD2 wells exceeds plant
capacity. Numerous wells are choked back to limit the field oil production rate. Facility
expansions are required to increase the oil production rate. Along with expansion of the
oil train, expansion of the water injection system is required to support the higher
offtake. These projects will add additional reserves to the EOR project by increasing
gas injection rates, water handling limits and the water injection capacity. Two capacity
expansion projects; ACX Phase I and ACX Phase II, have been approved by the Alpine
PA working interest owners. Additional expansion projects are being studied. The
approved expansions are can be summarized as follows.
ACX Phase 1
The Alpine Capacity Expansion Project Phase 1 (ACX1) was approved by the Alpine
working interest owners in April 2003. Equipment is being transported over this winter's
ice road and will be tied into the Alpine facilities during the 2004 summer shutdown.
Startup will occur in late 2004.
The current Alpine oil production of approximately 100 Mbopd (annual average) is
limited by the processing plant capacity and by water injection available for voidage
replacement. The ACX1 Project would increase oil production rates by 5,000 bopd
(gross). The project consists of adding or upgrading equipment to increase the oil
processing capacity and the gas processing capacity, and installing equipment to allow
re-injection of produced water into the Alpine formation. Produced water is currently re-
injected into the Alpine zone in limited quantities. Without ACX1 the produced water
would be disposed of in the Sadlerochit formation as water volumes increase. The
II
Annual Surveillance Report
Alpine Oil Pool, Collville River Unit
March 22, 2004
project would increase the capacity of the produced water handling system from the
current 10 Mbwpd to 100 Mbwpd. The gas processing capacity will be increased from
130 mmscfd to 160 mmscfd.
ACX Phase
The ACX2 project will improve the Alpine recovery process. The ACX2 expansion of
the seawater injection system allows higher throughput rates and increases cumulative
water injection. This results in increased incremental recovery. ACX2 expansion of the
gas handling system increases the volume of miscible injectant available for the MWAG
flood. This results in a larger cumulative volume of miscible injectant in the reservoir,
which results in incrementally higher EOR recovery from the MWAG process.
Conclusion
Alpine reservoir performance remains strong. Development drilling while maintaining
high production rates has been technically challenging, but accomplished with relatively
small impact on development expenditures or material affect on long term production
capacity or reserves. Surveillance tools and techniques are continuing to improve. We
foresee no significant obstacles to continued successful exploitation of the resource at
this time.
Sincerel ,
Chris lonzo
Alpine Engineering Supervisor
cc:
Mr. Mark Meyer, Director
Alaska Department of Natural Resources
Division of Oil & Gas
550 W. 7th Avenue, Suite 8000
Anchorage, Alaska 99501-3560
Ms. Teresa Imm, Resource Development Manager
Arctic Slope Regional Corporation
301 Arctic Slope Avenue, Suite 300
Anchorage, Alaska 99518-3035
Mr. Isaac Nukapigak, President
Kuukpik Corporation
PO Box 187
Nuiqsut, Alaska 99789-0187
Mr. Bill Esco
Anadarko Petroleum Corporation
PO Box 1330
Houston, Texas 77251-1330
1:
Attachment 1 — CRU Boundary as of June, 2003.
Colville River Unit
Colville Delta Area, Alaska.
June, 2003
Unit Boundary
Lease Boundary
- - - - - - - - Tract Boundary
�3 Tract Number
2 4
WLES
0 1 2 4 6
RR04ETERS
01061302A05
Attachment 2 - MWAG conversion status at CD1
CD1-21
5Yv
3J1020p1
17 1'-
IJI
t 1;', 2001
25.5 k
is
Tft9r2003
1-[4-2001
FII
1 NTi200
Converted to 141 in Jlune2002 WAG Converted back to SW in
CDi-03
SS'd
r1 r,2rg1
14.07,
Lr,
6xnpn2
15.2 ro
:, v
771Jt21tt3
6"i?L
2.1
service as part of strategy.
CDi-23
5;V
"rcr2CC1
19. t %
MI
x,
-rc1_002
2i 6°,
5'iv
Zt2pr2gg3
6 i-e�
Converted to MI service in April 2002 as part of WAG strategy. Converted back to SW in
Ju 2003 to m6gate rein GOR in offset (CD1-24'
July 2003 to mitgate rsing GOR in offset (CDt-10)
CDi-261.
+
12920C 1
16.6'6
j MI
7262002
120%
5'.V
gitSt2003
2 %.°t
I
Intially a dry gas disposal well until condensate flash drum became functional (January
CD 1-05
Dry Gas
12=000
0.3%
6
?SV
5°20.200-
22.3 6
2001), then on hil injection to maximize recovery. Converted to SW duty in June 2002 to
mitigate rising GOR in offsets (CE)1-04 and Cl and since it was estimated that little
incremental EOR reserves would be recovered as result of additional Idl injection.
CD1-O6
Drf Gas 12 132CC0 87.2°6
permanent upstructure dry gas injector- also used as black -out fuel source
Converted to MI service in November 2D01 as part of WAG strategy. Converted back to SIA,
CDi-13
SSV
12612rI1
i',r3$b
hil
11 222001 20.7%
5`N
1 Vt'r12002
ts.'._n.Ct
Gil
10-30;2003
2.2°z
duty in November 2002 to mitigate rising GOR in offset(01-111)). Converted back to MI in
2003 as part of WAG strategy.
CD1-14
Dry Gas 914!2C01 2`ti MI 9/102001 2= c t C v >as
2B =GG_
€0 -C
Irry gas injector. MI injector from September 2001 through January 2002.
CDi-16
59V 3ie,2001 14.9°6 tdl eutsfz-0p2 I 11.2%
1 Converted to first cycle MI in November 2002 as part of WAG strategy.
CD1-21
5Yv
3J1020p1
17 1'-
IJI
t 1;', 2001
25.5 k
is
Tft9r2003
1-[4-2001
FII
1 NTi200
Converted to MI seryice in November 2001 as part of WAG strategy. Converted to chase
SW in July 2003 after target slug of 30% HCPV MI was reached- Converted back to MI for
1pressure
-Vi
9r1;20tt3
_pct
111
22 16.3%
5Yv
3tt9+2003
2.1
support in October 2003 as SW was required elsewhere.
CDi-23
5;V
"rcr2CC1
19. t %
MI
x,
-rc1_002
2i 6°,
5'iv
Zt2pr2gg3
6 i-e�
Converted to MI service in April 2002 as part of WAG strategy. Converted back to SW in
Ju 2003 to m6gate rein GOR in offset (CD1-24'
CDi-261.
+
12920C 1
16.6'6
j MI
7262002
120%
5'.V
gitSt2003
2 %.°t
I
Converted to h1I service in July 2002 as part of WAG strategy. Converted back to SW in
2003 to mitigate rising GOR in offset CDt-27
CD 1-31 IPrYGasI MI I 'l:J2001 I 75.=% 11_ 1tr:><r_rr1T 29.7%
CDi-33 5!V I 21MC01 1 Idl 11t5.�
CD1-36 svv I 1262cc1 t7.3%I Ml I�.1=6
CDi-37
CD1-39
CD1-d2
SYV
2212001
16.3'ro
MI
1f.i°!e
^'<ti I
T,2. 20103
3
S'iV
1-[4-2001
25.N'.i
MI
2..6%
-Vi
9r1;20tt3
_pct
111
22 16.3%
5Yv
3tt9+2003
2.1
CD145I SU I 2i 1F2^k
All conversions that occurred in 2003 are underlined in bold
Nomenclature: Sea water injection
Miscible gas injection
00IMP,Dry gas injector
Converted back to MI in 2003 as part of WAG
Converted back to MI in 2003 as part of WAG
Converted back to Win 2003 as part of WAG
Converted to MI seryice iJune 2012 as part Df WAG strategy. Converted back to SW in
Ju " 2DD3 to m ate ricinn GOR in offset CDt-36
Converted to hil service in June 2002 as part of WAG strategy. Converted back to SW in
2003 to mitigate rising GOR in offset CD1-38
Converted to MI service in February 2002 as part of WAG strategy. Converted back to SW
N September 2003 to mitigate rising GOR in offset CD1A4
Converted back to MI in October 2003 as part of WAG strategy.
Attachment 3 - MWAG maturity CD1
CD1 MWAG STATUS
CD1-45
CD1-42
SW
MI
CD1-39
LG
CD1-37
CD1-36
CD1-33
CD1-31
CD1-26
CD1-23
CD1-21
CD1-16
CD1-14
CD1-13
CD1-06
CD1-05
CD1-03
CD1-02
CD1-01
0.00 15.00 30.00 45.00 60.00 75.00 90.00 105.00
CUM HCPVI (%)
Attachment 4 - MWAG conversion status at CD2
- Alpine MWAG Status - CO2
ELL
HPCV injected
Comments
CD2 -D8
CD2 -12
CD2 -15
CD2 -16
CD2 -17
CD2 -18
CD2 -22
1st Irujection cycle
2nd Injection cycle
3rd Injection cycle 4th trajection cycle
Service I Conversion I HPCVI
Service I Conversion I HPCV
I I Service I Conversion I OEsd SeTvicel Conversion I HPCV
CD2 -06
sw
I tsrtn+2no3 1 - 1,4%
CD2 -D8
CD2 -12
CD2 -15
CD2 -16
CD2 -17
CD2 -18
CD2 -22
SW
I 3,'26t20D',�
3Vr
6 [tn;= 7.6'1:,
Yv
>�i4^Or7 F.,�
Gov
7115CZCV.2 1_
5;'v
1gt3n EtD3 r. ~+_.
Sod
6,?,n{IO2 t
CD2 -26
CD2 -29I
CD2 -32
CD2 -35
�,'u
2•=>+2rr% t � � ;
sw
1G'v2C,11
:vv
3r.t�lr:r% > t ls�
Ss'v
4J2n126n;: .s �'<.
CD2 -36
r'%v
4'2_ r'2,7gs t.:,r-G
CD2 -38
SPi 1rni:2r[s2 e<-
GD2-k4
CD2 d6
3';r
`+711112rx.
CD2 -d8
'%i
71[472nG2 t 7°
CD2 -4S
CD2 -51
6IV 2172.TVT2 4.5%
;i 714_ rlt 4.1
CD2 -55
vs'd
t [t.2%
9122'2003
7;232003 3
1011012003
Ell RI2312003
Dry Gas 1011120C2 'v1C-5?b
All conversions that occurred in 2003 are underlined in bold
Nomenclature: Sea water injection
Miscible gas injection
Dry gas Dry gas injector
Converted to first cycle MI in August 2003, as part of WAG strategy.
Converted to first cycle MI in December 2003, as part of WAG strategy.
Converted to first cycle MI in October 2003, as part of WAG strategy.
Converted to first cycle MI in September 2003, as part of WAG strategy.
Converted to first cycle MI in July 2DD3, as part of WAG strategy.
Converted to first cycle MI in October 2003, as part of WAG strategy.
Converted to first cycle MI in March 2003, as part of WAG strategy.
Converted temporarily to dry gas in Oct. 2002, to releave pattern CDt-DF and allow proper
MI enrichment. and to test gas flooding potential of tighter CD2 sand. Converted to hill in
20
n3, as Tess dry gas disposal was required field -woe. Converted back to SW in October
2003 as art of WAG strafe
Attachment 5 - MWAG maturity at CD2
CD2 MWAG STATUS
CD2 -55
CD2 -51
SW
CD2 49
Ml
LG
CD2 -48
CD2 -46
CD2 -44
CD2 -40
CD2 -38
CD2 -36
CD2 -35
CD2 -32
CD2 -29
CD2 -26
CD2 -22
CD2 -18
CD2 -17
CD2 -16
CD2 -15
CD2 -12
CD2 -08
CD2 -06
0 15 30 45 60
CUM HCPVI (%)
Attachment 6 — Recovery - throughput response at Alpine
TPM
Alpine Pattern Performance
o sw bt in TPM
through 1/31/2004
♦ gas bt in TPM
100
♦ CD1
♦ CD2
90-
80
70
a
U
=
w
60
0
0
50
Z
>
40
�-
o
L
♦ •�
30
•
♦
20
10-
0
0
0.1 0.2 0.3 0.4 0.5 0.6 0.7
0.8 0.9 1
Qtinj [fraction HCPVI]
Attachment 7 - All Wells Drilled as of February 1, 2004
Surface
Well
Name
Bottomhole
Well
Name
Well Information
Well
Service
7" Csg
Shoe
Start of Completion End of Completion
X start I Y start I TD I X end I Y end
C D1-01
3
Injector
7752
386223
5977665
10289
384975
5979854
CD1-02
14
Injector
8217
388914
5978054
12773
386773
5982084
CD1-03
21
Injector
7816
387030
5975876
10897
388335
5973121
CD1-04
24
Producer
9444
390285
5979213
13977
392388
5975199
CD1-05
27
Injector
10633
392060
5979100
14515
393833
5975653
C D1-06
82
Injector
13500
395935
5978137
16024
397053
5975880
CD1-09
78
Producer
11894
393604
5979398
15350
395153
5976312
CD1-10
22
Producer
7909
387919
5977328
11693
389639
5973962
CD1-13
23
Injector
8841
389954
5976715
11300
391036
5974524
CD1-14
83
Injector
14073
397422
5974748
18939
399750
5970479
CD1-16
34
Injector
9595
391456
5973711
12600
392819
5971035
C D1-17
77
Producer
13181
395639
5975431
18590
398233
5970693
CD1-21
4
Injector
9049
381897
5979207
11087
380663
5981642
CD1-22
7
Producer
8430
387229
5978470
9236
385833
5981196
CD1-23
36
Injector
11473
394166
5974982
14477
395504
5972306
C D1-24
35
Producer
10771
392946
5974121
13706
394333
5971538
CD1-25
33
Producer
8887
390067
5973033
12147
391614
5970167
CD1-26
32
Injector
8554
388736
5972327
11134
389928
5970058
C D1-27
31
Producer
8500
387434
5971701
11492
388804
5969032
CD1-28
20
Producer
7449
385825
5974800
10468
387228
5972131
CD1-30
10
Producer
9520
380597
5978488
12850
379073
5981447
CD1-31
16
Injector
10388
379306
5977679
14364
377530
5981235
C D1-32
37
Producer
11128
378022
5977019
14353
376466
5979841
CD1-33
19
Injector
7878
384479
5974142
10854
385846
5971484
CD1-34
18
Producer
8410
383109
5973412
11190
384448
5970977
CD1-35
1
Producer
8158
384636
5977159
13450
382165
5981835
CD1-36
2
Injector
7654
383593
5975934
10654
382249
5978602
CD1-37
30
Injector
9095
386288
5970673
12134
387689
5967992
CD1-38
29
Producer
9170
384766
5970331
12240
386136
5967662
CD1-39
28
Injector
10288
383465
5969470
13298
384820
5966793
C D1-40
80
Producer
12042
382644
5967952
15438
384185
5964949
CD1-41
9
Producer
8333
382239
5975219
11170
380948
5977745
CD1-42
15
Injector
9054
380940
5974591
11608
379708
5976828
C D1-43
64
Producer
10065
380436
5972089
12921
381823
5969594
CD1-44
44
Producer
10070
379572
5973840
12811
378333
5976283
CD1-45
17
Injector
9032
381806
5972745
11950
383138
5970171
CD2 -06
70
Injector
9672
371097
5980654
16680
367815
5986842
CD2 -07
72
Injector
10733
373703
1 5981992 1
10868
373652
5982116
CD2 -08
74
Injector
12242
377301
5981635
18050
374588
5986767
CD2 -10
71
Producer
10578
372182
5981985
10702
372141
5982101
Annual Status Update to the , IUnit Plan
Colville River Unit Agreement
February 20, 2002
Surface
Well
Name
Bottomhole
Well
Name
Well
Service
7" Csg
Shoe
Well Information
Start of Completion End
X start Y start TD
of Completion
X end Y end
CD2 -12
68
Injector
8677
368888
5978304
13632
366637
5982712
CD2 -13
73
Producer
10595
376177
5980472
14575
374339
5983995
CD2 -14
41
Producer
7671
371963
5975571
11056
370410
5978577
CD2 -15
66
Injector
9610
366147
5977039
14161
364157
5980881
CD2 -16
38
Injector
9529
375990
5977319
12500
374782
5980013
CD2 -17
40
Injector
8184
373143
5976621
8756
372880
5977129
CD2 -18
65
Injector
12112
362842
5975883
18019
360196
1 5981157
CD2 -19
46
Producer
8769 1
375572
5975100
11714
376897
5972473
CD2 -20
69
Producer
9163
369916
5979552
14570
367451
5984361
CD2 -22
42
Injector
7845
370575
5975090
11134
369051
5978002
CD2 -23
67
Producer
9676
367151
5978350
13438
365445
5981699
CD2 -24
76
Producer
10811
364768
5976380
14301
363212
5979501
CD2 -25
43
Producer
8722
369286
5974237
11994
367790
5977144
CD2 -26
47
Injector
8619
374207
5974408
11238
375406
5972081
CD2 -27
125
Injector
12341
377882
5967149
12659
378052
5966887
CD2 -28
39
Producer
8695
374897
5976522
13200
372799
5980502
CD2 -29
45
Injector
9556
376873
5975841
12560
378234
5973167
CD2 -30
55
Injector
11481
365208
5971300
15700
363297
5975058
CD2 -32
50
Injector
8723
367954
5973557
11720
366579
5976218
CD2 -33B
52
Producer
9982
366697
5972759
13078
365223
5975475
CD2 -34
48
Producer
7802
372917
5973731
8755
373367
5972891
CD2 -35A
61
Injector
9063 1
375633
5971746
13500
377673
5967818
CD2 -36
98
Injector
13523
372734
5964056
17663
374637
5960382
CD2 -37
139
Producer
14162
371724
5963070
17085
373037
5960467
CD2 -38
59
Injector
9209
373424
5969394
13010
375164
5966020
CD2 -39
55
Producer
9122
374692
5970192
12651
376369
5967087
CD2 -40
56
Injector
11208
365766
5970205
14250
367107
5967479
CD2 -41
58
Producer
9532
372019
5968832
13024
373637
5965742
CD2 -42
54
Producer
9633
367542
5970978
13138
369171
5967884
CD2 -43
130
Producer
12978
364372
5968348
13106
364410
5968226
CD2 -44
63
Injector
11319
378889
5972087
14555
380338
5969198
CD2 -45
62
Producer
9972
377360
5971508
13402
378988
5968490
CD2 -46
49
Injector
7879
371539
5973093
11000
372970
5970320
CD2 -47
126
Producer
10840
369515
5967325
14580
371256
5964017
CD2 -48
57
Injector
10074
370711
5968227
13622
372304
5965058
CD2 -49
53
Injector
8890
368809
5971733
11874
370200
5969094
CD2 -50
51
Producer
7906
370190
5972559
11624
371794
5969207
CD2 -51
81
Injector
13246
380600
5968569
17320
382495
5964971
CD2 -52
124
Producer
12897
379311
5967805
16881
381146
5964274
CD2 -55
127
Injector
12210
367567
5966559
15238
368970
5963878
CD2 -58
97
Producer
12129
373889
5965219
16389
375844
5961443
Attachment 8 - Planned Wells for 2004
Well
Surface
Bottom Hole
Well Well Type
Count
Location
Location
Service
Completed:
Horizontal
81
CD2 -43
130
Producer Horizontal
82
CD1-07
107
Injector Horizontal
To Be Drilled:
83
CD1-46
102
Injector
Horizontal
84
CD1-08
106
Producer
Horizontal
85
CD2 -57
96
Injector
Horizontal
86
CD2 -31
134
Producer
Horizontal
87
CD2 -53
95
Producer
Horizontal
88
CD2 -05
132
Producer
Horizontal
CD2-NW-Periph
Delineation
89
CD1-11
105
Injector
Horizontal
90
CD1-12
123
Producer
Horizontal
91
CD1-15
103
Producer
Horizontal
92
CD 1-47
104
Injector
Horizontal