STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
Disposition
3. Field
Northstar
Volume MCF
4. Operator 5. Month/Year of Disposition
BP Jan-2004 REV 1
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
2. Facility Name
N1
6. Sold
o
Pool Name
Pool Code
Percent
100%
7. Reinjected
7,252,915
Northstar
590100
8. Flared or vented 1 hour or less
695
9. Flared or vented more than 1 hour (see instr.)
5,600
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see instructions)
o
13. TOTAL VOLUME (ITEMS 6-12)
7,259,210
Authorization> 1 hr: '5', bÛ 0 MCF ..:J8fV
Safety
MCF
Lease Use
MCF
Conservation
Waste: MCF
Commission r Date
14. NGL Gas Equivalent
15. Purchased gas
3,616,982
16. Transferred from:
17. Transferred to: (Express as a negative #)
18. Remarks: Gas purchased from Prudhoe was used as follows (all in mscf): fuel gas 609,789, pilot purge 2759, injection 3,004,434. This revision was done to
use the new 10-422 form and to show only the disposition of Northstar produced gas in blocks 6 - 13. The disposition of the purchased gas from
Prudhoe is shown in the Remarks.
I hereby certify that the foregoing is true and correct to the best of my knowledge.
S¡9"""'e Q. O. ~
Title Manager, State Taxes and Royalty
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
ri 2 2 .2
Printed Name
Robert A. Re nolds
Phone (907)564-5028 Date
Form 10-422 Rev. 1/2004
Submit in duplicate
Flare Report NORTHSTAR
~. «"'--'''' Æ" ~ ",,-< " ~"''''< ow '" WM ."YfB Y# ",4~Æ '" > "". _~",et= """" w'" "''' ," "" « <." '" '" ''''',y k ~ '" d, '" <. v f';' >v"" "'" " " m '" "" ~ "
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
1/22/04 4:20 PM 1/22/04 4:39 PM 19 47 Depressurize the Test Sep for NS 29 IA leak test. Equipment Safe Out HP1
1/23104 7:17 AM 1/23104 7:25 AM 8 13 Normal compressor start gas None necessary HPA Start Gas LP
1'23104 7:13 AM 1/23104 7:18 AM 5 11 Normal compressor start up None necessary HP A Start Gas HP1
1/1/04 8:16 AM 1/1/04 8:22 AM 6 12 SOLAR A START UP. NONE. NORMAL START SEQUENCE. Solar A Start Gas LP
1/24/04 3:49 AM 1/24/04 3:56 AM 7 12 Started Solar A none necessary Solar A Start Gas LP
1/21/04 6:18 AM 1/21/04 6:20 AM 2 2 Test sep depressure for NS 29 testing Equipment Safe Out HP1
1/21/04 1 :51 PM 1/21/04 1 :59 PM 8 11 Test seperator depressure for NS 29 IA testing. Equipment Safe Out HP1
1/21/04 6:29 AM 1/21/04 7:12 AM 43 53 Test seperator depressure for NS 29. Equipment Safe Out HP1
Group Total: 161
Unplanned LessThan1 Hour
Group Total: 534
Unplanned GreaterThan1 Hour
1/9104 2:32 PM 1/9/04 5:31 PM 179 351 Level Alarm High-High In crude stabilizer caused from Shut-In all wells, restart plant. Upset HP1
cycling PLC card at Shore Crossing RTU Building.
1/9104 3:08 PM 1/9/04 5:25 PM 137 487 Level Alarm High-High In crude stabilizer caused from Shut-In all wells, restart plant. Equipment Outage LP
cycling PLC card at Shore Crossing RTU Building.
1/15/04 8:44 AM 1/15/04 10:19 AM 95 734 LP compressor 1st stage suction scrubber high level. Cut 011 rates and re-start LP. Upset LP
1/15/04 8:49 AM 1/15/04 10:27 AM 98 491 LP compressor 1 st stage suction scrubber high level. Cut 011 rates and re-start LP. Upset HP1
1/7/04 8:17 AM 1/7/04 10:40 AM 143 1,305 LP Compressor shutdown from High-High level In 1 st stg. Restart compressor, shut-In wells to mltlgete Equipment Outage LP
suction scrubber. flare.
1/7/04 8:18 AM 1/7/04 10:47 AM 149 838 LP Compressor shutdown from High-High level In 1 st stg. Restart compressor, shut-In wells to mitigate Equipment Outage HP1
suction scrubber. flare.
1/12/04 1:03 AM 1/12/04 3:15 AM 132 371 Plant shutdown from LAHH In LP flare scrubber. Shut-In wells, restart plant. Upset HP1
·
..
Flare Repolßt NORTHSTAR
:<>7$#0 ~ øß «""<%" " W ffl W '* 0'74;;< 1> "" '" 'i\""'J'!" =,(~ ,,,,, w~ . "''' "-" ","" -» = '" "" ,,~~ "" "",,,," '<' "",,"~ "''' ".
Start DateITime
End DateITlme
1/12/04 2:15 AM 1/12/04 4:36 AM
1/12/04 3:16 AM 1/12/04 4:48 AM
Group Total:
Report Total:
Minutes MCF
Incident/Cause Description
Remediation Taken
Event Type
141
Plant shutdown from LAHH In LP flare scrubber.
Shut-In wells, restart plant.
Plant Startup
395
92
Plant shutdown from LAHH In LP flare scrubber.
Plant Startup
628
Shut-In wells, restart plant.
5,600
6,295
Flare
LP
HP1
.-
I-
STATE OF ALASKA
ALASKA Oil AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
2. Facility Name
3. Field
4. Operator
5. MonthlYear of Disposition
0290000025
N1
Disposition
Northstar
Volume MCF
BP Feb-2004
20. For production from multiple pools, list contribution of each pool as a percent of Totai
Volume.
6. Sold
o
Pool Name
Pool Code
Percent
100%
7. Reinjected
3,439,262
Northstar
590100
8. Flared or vented 1 hour or less
1,695
9. Flared or vented more than 1 hour (see instr.)
4,707
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see instructions)
o
Authorization >1 hr:
Safety
4Îo'
MCF
~Bt-
13. TOTAL VOLUME (ITEMS 6-12)
3,445,664
Lease Use
MCF
14. NGL Gas Equivalent
15. Purchased gas
2,659,266
Conservation
MCF
Waste:
MCF
17. Transferred to: (Express as a negative #)
Commissi
16. Transferred from:
18. Remarks: Gas purchased from PBU was used as follows (all in mscf): fuel gas 433,144, flared < 1 hour 1013, pilot purge 2581, injection 2,222,528
I hereby certify that the foregoing is true and correct to the best of my knowledge.
Signature Q O. ~~
Printed Name
Robert A. Re nolds
Phone (907)564-5028
Date
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Title Mana er, State Taxes and Royalty
--
ft
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
2/11/04 6:52 AM 2/11/04 6:55 AM 3 6 Bled Down LP compressor for repair work NIA Equipment Safe Out LP
2/15/04 3:49 PM 2/15/04 3:52 PM 3 3 Bled down Water skimmer for safe-out NIA Equipment Outage LP
2/16/04 12:40 AM 2/16/04 12:52 AM 12 16 Bleed down HP separator for plperack work safe-out NIA Equipment Outage HP1
2/15/04 12:48 AM 2/15/04 12:55 AM 7 22 Bleed down HP Separator for Safe-out NIA Equipment Outage HP1
2/15/04 1 :23 AM 2/15/04 2:19 AM 56 234 Bleed down HP Separator for Safe-out NIA Equipment Outage HP1
2/15/04 3:48 PM 2/15/04 3:54 PM 6 9 Bleed down HP Separator for Safe-out NIA Equipment Outage HP1
2/15/04 8:21 PM 2/15/04 8:49 PM 28 218 Blow down following HPA planned shutdown NIA Equipment Outage HP1
2/12/04 1 :47 AM 2/12/04 2:23 AM 36 65 Depressure HP sep for manhole leak repair NIA Equipment Safe Out HP1
2/17/04 8:04 AM 2/17/04 8:08 AM 4 6 Normal flare during HP A start none HPA Start Gas LP
2/17104 7:50 AM 2/17104 7:57 AM 7 30 Normal flare during HP A start sequence none Equipment Outage HP1
2/17104 8:01 AM 2/17/04 8:05 AM 4 4 Normal flaring during HP A start none Equipment Outage HP1
2/27/04 1 :58 PM 2/27/04 2:19 PM 21 185 Normal flaring during HP-B start sequence Equipment Outage HP1
2/27/04 2:21 PM 2/27/04 2:26 PM 5 7 Normal flaring during HP-B start sequence HPB Start Gas LP
2/15/04 5:42 PM 2/15/04 5:54 PM 12 59 Partial vent following HPA planned shutdown NIA Equipment Outage HP1
2/6/04 2:08 AM 2/6/04 2:11 AM 3 12 PM Calibration on FT-4260 None needed. Plant Integrity LP
2/26/04 4:28 PM 2/26/04 4:37 PM 9 11 SAfe-in and purge HPB for restart NIA Equipment Outage HP1
2/26/04 5:00 PM 2/26/04 5:15 PM 15 25 SAfe-In and purge HPB for restart NIA Equipment Outage HP1
2/13104 2:22 AM 2/13/04 2:31 AM 9 13 Sweep HP & Test Header for Dirvert valve work NIA Equipment Safe Out HP1
Group Total: 925 Includes 685 mscf imported gas from PBU flared during production shtdown 2/9-2/20 for LP compressor motor replacement
1 of 2
.rt1
~'
Start DateITl me End DateITlme Minutes
Unplanned LessThan1 Hour
Group Total:
Unplanned GreaterThan1 Hour
2/8104 7:00 AM 2/9104 8:11 AM 71
. 2/8104 5:46 AM 2/8/04 8:23 AM 157
2/23104 7:37 AM 2/23104 9:37 AM 120
- 2/22/04 7:16 PM 2/22/04 9:44 PM 148
2/22/04 10:28 PM 2/22/04 11 :55 PM 87
MCF
Incident/Cause Description
Remediation Taken
Event Type
Flare
1,783 Includes 328 mscf Imported gas from PBU flared during production shtdown 2/9-2/20 for LP compressor motor replacement
577
374
345
607
215
, 2/8104 5:45 AM 2/8104 6:55 AM 70 885
2/22/04 7:28 AM 2/22/04 11 :29 AM 241 1,045
2/22/04 7:49 AM 2/22/04 11 :29 AM 220 439
... 2/22/04 10:28 PM 2/23104 12:07 AM 99 219
Group Total: 4,707
Report
Bringing In wells, purging LP Compressor for start. Shut-In all wells after motor failure on LP Plant Startup HP1
Compressor.
Flaring off of Water Skimmer. Minimize gas rates, not possible to stop without Equipment Outage LP
LP Compressor.
NGL Reboiler level control bridle malfunction Repaired level cantrol bridle Upset HP1
Plant shutdown from PAHH In NGL Surge Tank. Plant blowdown, reset and restart plant. Upset HP1
Plant shutdown from PAHH in NGL Surge Tank. Plant blowdown, reset and restart plant. Plant Startup LP
Purge HPB for restart. None, normal start sequence. HPB Start Gas HP1
Purge LP Compressor for restart. None, normal start sequence. Plant Startup LP
Purge LP Compressor for restart. None, normal start sequence. Plant Startup HP1
Purge LP Compressor for restart. None, normal start sequence. Equipment Outage HP1
2 of 2
-
...
STATE OF ALASKA
ALASKA Oil AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Facility Name
N1
Disposition
3. Field
Northstar
Volume MCF
4< Operator 5. MonthlYear of Disposition
BP Mar-2004
20. For production from muitipie poois, list contribution of each pool as a percent of
Total Volume.
6. Sold
o
Pool Name
Pool Code
Percent
100%
7. Reinjected
7,412,120
Northstar
590100
8. Flared or vented 1 hour or less
3,553
9. Flared or vented more than 1 hour (see instr.)
6,266
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see insiruêtiôñ$)
û
MCF
13. TOTAL VOLUME (ITEMS 6-12)
7,421,939
14. NGL Gas Equivalent
MCF
15. Purchased gas
3,510,646
Waste:
16. Transferred from:
17. Transferred to: (Express as a negative #)
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (i.e. no purchased gas). Gas purchased from
612,933, pilot purge 2759, injection 2,894,954
I hereby certify that the foregoing is true and correct to the best of my knowledge.
Signature
~~
~
Titie Mana er, State Taxes and Ro al
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 2 AAC2 .2
Printed Name
Robert A. Re nolds
Phone (907)564-5028 Date
Form 10-422 Rev. 1/2004
Submit in Duplicate
Flare Report NORTH STAR
v ~"" "7<""
Start Date/Tlrne End Date/Tlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Unplanned LessThan1 Hour
Group Total: 3,553
Unplanned GreaterThan1 Hour
3/19/04 3:27 AM 3/19/04 5:36 AM 129 1,430 HPB step to Idle then SID on valve miss alignment, LP and Cut back wells to reduce flaring rate then Upset HP1
HPA fallowed. restarted plant.
3/19/04 4:20 AM 3/19/04 5:22 AM 62 246 HPB step to Idle then SID on valve miss alignment, LP and Cut back wells to reduce flaring rate then Upset LP
HPA fallowed. restarted plant. '
3/11/04 9:46 PM 3/12/04 12:10 AM 144 682 LP Comp SID from HHL in frist stage suction scrubber sn wells to reduce flare rate and started LP Upset LP
Camp
3/11/04 9:52 PM 3/12/04 12:19 AM 147 448 LP Comp SID from HHL in frist stage suction scrubber sn wells to reduce flare rate and started LP Upset HP1
Comp
3/14/04 12:18 AM 3/14/04 1 :29 AM 71 147 LP Comp SID on 1st stage suction scrubber HHL shut In well to reduce flare rate and restarted LP Upset HP1
Camp
3/14/04 11:16 AM 3/14/04 12:39 PM 83 579 LP Comp SID on 1 st stage suction scrubber HHL shut in well to reduce flare rate and restarted LP Upset LP
Comp
3/14/04 11 :17 AM 3/14/04 12:42 PM 85 361 LP Camp SID on 1st stage suction scrubber HHL shut In well to reduce flare rate and restarted LP Upset HP1
Comp
3/14/04 2:43 PM 3/14/04 3:55 PM 72 164 LP Comp SID on 1st stage suction scrubber HHL shut in well to reduce flare rate and restarted LP Upset HP1
Comp
3/14/04 2:45 PM 3/14/04 3:52 PM 67 187 LP Comp SID on 1st stage suction scrubber HHL shut in well to reduce flare rate and restarted LP Upset LP
Comp
3/20/04 12:16 PM 3/20/04 2:03 PM 107 433 LP compressor SID due to hi hi 1st stage discharge Immediately shut-in the high GOR wells and Equipment Outage LP
temperature restarted the compressor.
3120104 12:20 PM 3120/04 2:04 PM 104 334 LP compressor SID due to hi hi 1 st stage discharge Immediately shut-In the high GOR wells and Equipment Outage HP1
temperature restarted the compressor.
3/22/04 4:01 PM 3/22/04 6:17 PM 136 664 LP compressor SID due to LAHH In the 1 st stage suction Shut In all wells to mitigate flaring. Restart wells Equipment Outage HP1
scrubber. HPA compressor SID when all of the wells were and equipment.
shut in.
Flare Report NORTH STAR ~: ~ ~
Start DateITlme
End Date/Time
3/22/04 4:24 PM 3122/04 6:17 PM
3/25/04 10: 18 PM 3/25/04 11 :24 PM
Group Total:
Report Total:
Minutes
MCF
113
471
66
120
6,266
9,819
Incident/Cause Description
Remediation Taken
Event Type
Flare
LP compressor SID due to LAHH in the 1st stage suction Shut in all wells to mitigate flaring. Restart wells Equipment Outage
scrubber. HPA compressor SID when all of the wells were and equipment.
shut In.
LP
LP shut down due to HH 1st stage scrubber HH from
crudstablllzer carry over.
OSD the plant reset and restarted.
Equipment Outage
HP1
~ ,)Î. .,..
..
,
,
STATE OF ALASKA
ALASKA Oil AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Facility Name
N1
Disposition
3. Field
Northstar
Volume MCF
4. Operator 5. MonthNear of Disposition
BP A r-2004
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
o
Pool Name
Pool Code
Percent
100%
7. Reinjected
6,650,062
Northstar
590100
8. Fiared or vented 1 hour or less
3,092
9. Flared or vented more than 1 hour (see instr.)
6,757
10. Pilot and Purge
o
11. Used for iease operations (specify in Remarks)
o
12. Other (see instructions)
o
Authorization> 1 hr:
Safety
61751
MCF
:JSf-
13. TOTAL VOLUME (ITEMS 6-12)
6,659,911
Lease Use
MCF
14. NGL Gas Equivalent
Waste:
/J
MCF
15. Purchased gas
2,428,373
16. Transferred from:
17. Transferred to: (Express as a negative #)
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (i.e. no purchased gas).
527,739, pilot purge 2670, injection 1,897,964
I hereby certify th~e foregoing' true and correct to the best of my knowledge.
Signature '¿. 0 .
Title
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 20 AAC25.235.
Printed Name
Robert A. Re nolds
Phone (907)564-5028
Form 10-422 Rev. 1/2004
Submit in Duplicate
,
Start DatelTime End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
4/18/04 10:19 AM 4/19104 10:26 AM 7 35 HPA blow down. didnt make it through Its purge rest and started purge again HPA Start Gas HP1
4/25/04 8:22 AM 4/25/04 8:28 AM 6 11 Normai event during start of Solar A. Solar A Start Gas LP
4/17104 12:50 PM 4/17/04 1 :12 PM 22 54 Removed force's from the blowdown valves on HPA. HPA blow down and reset for start up Equipment Safe Out HP1
4/12/04 10:29 AM 4/12/04 11 :00 AM 31 281 Shut down HPA for maintenance. Finish complete biow down. Equipment Safe Out HP1
4/12/04 2:21 PM 4/12/04 3:06 PM 45 54 Shutdown LP Compressor. None - Complete blowdown. Equipment Safe Out HP1
4/12/04 2:42 PM 4/12/04 2:45 PM 3 2 Shutdown LP Compressor. None - Complete blowdown. Equipment Safe Out LP
4/12/04 8:49 AM 4/12/04 8:53 AM 4 8 Shutting Down HPA for maintenance. HPB took the load. Equipment Safe Out HP1
4/12/04 9:07 AM 4/12/04 9:12 AM 5 11 Shutting Down HPA for maintenance. Finished partial blow down. Equipment Safe Out HP1
4/18/04 9:42 AM 4/18'04 10:04 AM 22 115 Start up of HPA none HPA Start Gas HP1
4/18/04 10:32 AM 4/18/04 10:36 AM 4 6 started HPA none Solar A Start Gas LP
Group Total: 575
Unplanned LessThan1 Hour
Group Total: 2,517
Unplanned GreaterThan1 Hour
4/9/04 4:22 PM 4/9/04 5:45 PM 83 201 HHL in 1st. stg. suction scrubber. SII wells, reset and restart. Equipment Outage LP
4/9/04 5:58 PM 4/9/04 7:56 PM 118 317 HHL in 1 st. stg. suction scrubber. 511 wells, reset and restart. Equipment Outage HP1
4/14/04 6:32 PM 4/15/04 4:55 AM 623 1,985 LP compressor shut down. Shut in wells and restart LP compressor. Equipment Outage LP
4/14/04 6:55 PM 4/15104 5:04 AM 609 1,278 LP compressor shut down. Shut in wells and restart LP compressor. Equipment Outage HP1
4/15/04 9:40 AM 4/15/04 12:25 PM 165 653 LP compressor shut down. Shut In wells and restart LP compressor. Equipment Outage LP
4/15/04 9:41 AM 4/15/04 2:25 PM 284 690 LP compressor shut down. Shut in wells and restart LP compressor. Equipment Outage HP1
1 of 2
t'
Start DatelTi me End DateITime Minutes MCF
4/15/04 12:27 PM 4/15/04 2:23 PM 116 535
4/13104 12:13 PM 4/13/04 2:41 PM 148 772
4/13/04 12:19 PM 4/13/04 2:44 PM 145 327
Group Total: 6,757
Report
Incident/Cause Description
Remediation Taken Event Type
LP compressor shut down.
Shut In wells and restart LP compressor. Equipment Outage
Plant start-up after Crude Stabilizer flush.
None - Normal purge sequences for equipment. Plant Startup
Plant start-up after Crude Stabilizer flush.
None· Normal purge sequences for equipment. Plant Startup
Flare
LP
LP
HP1
2 of 2
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Facility Name
N1
Disposition
3. Fieid
Northstar
Volume MCF
4. Operator 5. MonthlYear of Disposition
BP Ma -2004
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
o
Pooi Name
Pool Code
Percent
100%
7. Reinjected
9,933,449
Northstar
590100
8. Fiared or vented 1 hour or less
5,489
9. Flared or vented more than 1 hour (see instr.)
4,796
10. Pilot and Purge
o
11. Used for iease operations (specify in Remarks)
o
Authorization >1 hr: 41'ì~ MCF $,'2--
Safety
MCF
Lease Use
MCF
Conservation
Waste: MCF
Commission Date7 III /1
12. Other (see instructions)
o
13. TOTAL VOLUME (ITEMS 6-12)
9,943,734
14. NGL Gas Equivaient
15. Purchased gas
2,721,755
16. Transferred from:
17. Transferred to: (Express as a negative #)
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (Le. no purchased gas). Gas purchased from PBU was used as follows (all in mscf): fuel gas
605,142, pilot purge 2759, injection 2,113,854
Signature
Title Manager, State Taxes and Royalty
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 20 AAC25.235.
Printed Name
Robert A. Re nolds
Phone (907)564-5028 Date
Form 10-422 Rev. 1/2004
Submit in Duplicate
Start DatelTime End Date/TIme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
5/2104 4:32 PM 5/2104 4:39 PM 7 83 Calibrating HP Flare transmitters N/A Meter Problem HP1
5/2104 4:44 PM 5/2104 4:47 PM 3 43 Calibrating HP Flare transmitters N/A Meter Problem HP2
5/3/04 5:38 PM 5/3/04 5:44 PM 6 17 Calibrating HP Flare transmitters N/A Meter Problem HP1
513104 5:50 PM 5/3/04 5:57 PM 7 240 Calibrating HP flare transmitters N/A Meter Problem HP1
5/23/04 8:23 AM 5/23/04 8:26 AM 3 3 Shut down HPA Compressor for repair. Equipment Outage HP1
5/23/04 9:32 AM 5/23/04 9:37 AM 5 13 Shut down HPA Compressor for repair. Equipment Outage HP1
5/23/04 10:55 AM 5/23/04 11: 26 AM 31 278 Shut down HPA Compressor for repair. Equipment Outage HP1
5/23/04 7:09 PM 5123104 7:17 PM 8 33 Shut down HPA Compressor for repair. Equipment Outage HP1
5/23/04 7:27 PM 5/23/04 7:31 PM 4 5 Shut down HPA Compressor for repair. Equipment Outage LP
5/23/04 8:37 PM 5/23/04 8:43 PM 6 11 Shut down HPA Compressor for repair. Equipment Outage HP1
5/23/04 10:22 PM 5/23/04 10:54 PM 32 226 Shut down HPA Compressor for repair. Equipment Outage HP1
5/11/04 1 :27 AM 5/11/04 1 :33 AM 6 10 Start Solar A none Solar A Start Gas LP
5/24/04 9:58 PM 5/24/04 10:05 PM 7 32 Starting HPA HPA Start Gas HP1
5/24/04 10:11 PM 5/24/04 10:15 PM 4 5 Starting HPA HPA Start Gas LP
Group Total: 1,000
Unplanned LessThan1 Hour
Group Total: 4,489
Unplanned GreaterThan1 Hour
5/25/04 2:25 PM 5/25/04 8:54 PM 389 644 3rd stage scrubber HHL. Caused by NGL upset Plant shut down. Drained NGLS restarted plant Upset HP1
1 of 2
,
Start DatelTime End Date/Tlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
5125/04 2:26 PM 5/25/04 8:44 PM 378 1,207 3rd stage scrubber HHL. Caused by NGL upset Plant shut down. Drained NGLS restarted plant Upset LP
5/12/04 3:03 PM 5/12/04 4:51 PM 108 351 Bringing on wells to start the LP from black out Start the LP Plant Startup LP
5/12/04 3:11 PM 5/12/04 5:02 PM 111 243 Bringing on wells to start the LP from black out Start the LP Plant Startup HP1
5117/04 10:55 AM 5/17/04 12:49 PM 114 55 Calibration error in meter. Corrected at 20:00 on 5/17 None necessary Meter Problem LP
5/17/04 1:05 PM 5/17/04 3:14 PM 129 62 Calibration error in meter. Corrected at 20:00 on 5/17 None necessary Meter Problem LP
5117/04 3:32 PM 5/17/04 5:36 PM 124 59 Calibration error in meter. Corrected at 20:00 on 5/17 None necessary Meter Problem LP
5/17/04 5:54 PM 5/17/04 7:42 PM 108 51 Calibration error In meter. Corrected at 20:00 on 5/17 None necessary Meter Problem LP
5117/04 7:59 PM 5/17/04 9:05 PM 66 31 Calibration error In meter. Corrected at 20:00 on 5/17 None necessary Meter Problem LP
5125/04 2:30 AM 5/25/04 3:40 AM 70 181 NGL Accumulator HHL Plant shut down. Drained NGLS restarted plant Upset LP
5125104 2:32 AM 5125/04 3:50 AM 78 127 NGL Accumulator HHL Plant shut down. Drained NGLS restarted plant Upset HP1
5/11/04 3:45 PM 5/11/04 4:54 PM 69 96 P5-110st power and closed SDV-9221 Shut In well to reduce flare rate. Opened valve Equipment Outage HP1
and started plant.
5/11/04 6:19 PM 5/11/04 7:31 PM 72 262 PS-1 lost power and closed SDV-9221 Shut in well to reduce flare rate. Opened valve Equipment Outage LP
and started plant.
5/11/04 6:26 PM 5/11/04 7:36 PM 70 176 P5-110st power and closed SDV-9221 Shut In well to reduce flare rate. Opened valve Equipment Outage HP1
and started plant.
5/12/04 10:49 AM 5/12/04 11:51 AM 62 1,252 Solar" B " SID, C Solar did not take load - Blackout. OSD Plant, shut-In all wells, restart plant. Upset HP1
Group Total: 4,796
Report
2 of 2
250,000
200,000
~ 150,000
C)
u.
o
:E 100,000
50,000
Northstar Flaring
o
r ::f'(;)(;)" ,.<n(;)(;)" ,n(;)(;)" ,n(;)(;)f}" n(;)(;)f}" n(;)(;)f}" f'\)\)f}" n\)\)f}" n\)\)o, ,.<n\)\)o, ,n\)\)o, n\)~ rJ,(;)çf< ,.<n\)çf< ,n\)~
'Ò'v 0'v "rvv ~'v ~v ~v "rvv n,j-v 0v 0'v ~rvv n,j-v 'Ò'v ,.8'v "rvv
60,000
50,000
40,000
tn
""
C) 30,000
u..
0
:\E
20,000
10,000
Northstar Flaring (7/2003-Present)
o I
~\:)rv ~\:)rv ~\:)rv ~\:)O:J ~\:)rv ~\:)O:J ~\:)O:J ~\:)O:J ~\:)O:J ~~ ~\:)'t'A ~\:)'t'A ~\:)'t'A ~~ ~~
'\ {Ç Q){Ç ,,~<1) ~<1) n}~ vj-<1) '\ {Ç Q){Ç ,,~<1) ~<1) n}<1) vj-<1) '\ {Ç ~<1) ,,~<1)
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Faciiity Name
N1
3. Field
Northstar
Volume MCF
Disposition
6. Sold
o
7. Reinjected
9,431,787
8. Flared or vented 1 hour or less
5,101
9. Flared or vented more than 1 hour (see instr.)
10,113
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see instructions)
o
13. TOTAL VOLUME (ITEMS 6-12)
9,447,001
14. NGL Gas Equivalent
15. Purchased gas
1,848,660
16. Transferred from:
17. Transferred to: (Express as a negative #)
4. Operator 5. MonthlYear of Disposition
BP June-2004
20. For production from multipie pools, list contribution of each pool as a percent of
Total Volume.
Pool Name
Pool Code
Percent
100%
Northstar
590100
Authorization >1 hr:
I D¡ 1(3.
::Jßt2-
Safety
MCF
Lease Use
MCF
Waste:
MCF
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (i.e. no purchased gas).
539,187, pilot purge 2670, injection 1,306,803
I hereby certify that the foregoing is true and correct to the best of my knowledge.
Signature R. O. ~
Title
Printed Name
Robert A. Re nolds
Phone (907)564-5028
Form 10-422 Rev. 1/2004
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 20 AAC25.2 5.
Date
Submit in Duplicate
Start DateITlme End DatelTime Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
6/26/04 2:33 PM 6/26/04 2:37 PM 4 5 1 st start was aborted. Troubleshoot problem, correct and attempt a HPA Start Gas LP
restart.
6/26/04 10:16 PM 6/26/04 10:20 PM 4 4 Another unsuccessful start attempt. HPA Start Gas LP
6/26/04 10:33 PM 6/26/04 10:37 PM 4 5 Another unsuccessful start of HP A. Troubleshoot failure to start. HPA Start Gas LP
6/17/04 10:02 PM 6/17/04 10:10 PM 8 13 Bringing In 011 rate to start LP Compressor Started LP comperssor as soon as we had enough Plant Startup LP
gas
6/26/04 5:16 PM 6/26/04 5:24 PM 8 12 HP A Purge Gas. Start HP A Compressor. Upset LP
6/26/04 10:19 PM 6/26/04 10:25 PM 6 13 HP A purge gas. Troubleshoot cause of shutdown. Upset HP1
6/27/04 9:54 AM 6/27/04 9:58 AM 4 5 HP A Purge gas. Attempted to start the HP A Compressor. HPA Start Gas LP
6/27104 11 :06 AM 6/27/04 11 :09 AM 3 5 HP A Purge gas. Attempted to start the HP A Compressor. HPA Start Gas LP
6/27/04 1 :28 PM 6/27/04 1 :32 PM 4 6 HP A Purge gas. Started the HP A Compressor. HPA Start Gas LP
6/24/04 11 :01 AM 6/24/04 11 :05 AM 4 6 HP B restart. Started the HP B Compressor. HPB Start Gas LP
6/26/04 6:22 PM 6/26/04 6:26 PM 4 5 HP B restart. Trouble shoot failure to start. HPB Start Gas LP
6/26/04 2:20 PM 6/26/04 2:28 PM 8 12 HPA Purge Gas. Attempted to start the HPA Compressor. HPA Start Gas LP
6/26/04 9:30 PM 6/26/04 9:33 PM 3 5 HPA Purge Gas. Attempted to start the HPA Compressor. HP A Start Gas LP
6/17/04 6:50 PM 6/17/04 6:58 PM 8 27 HP-A purge prior to start Started HP-A Plant Startup HP1
6/6/04 8:02 AM 6/6/04 8:05 AM 3 0 HPB Safe out for stack repair and water wash. Normal blowdown. Equipment Safe Out HP2
6/6/04 8:07 AM 6/6/04 8:50 AM 43 542 HPB Safe out for stack repair and water wash. Normal blowdown. Equipment Safe Out HP1
6/6/04 8:48 AM 6/6/04 8:53 AM 5 7 HPB Safe out for stack repair and water wash. Normal blowdown. Equipment Safe Out LP
6/6/04 8:57 AM 6/6/04 9:07 AM 10 16 HPB Safe out for stack repair and water wash. Normal blowdown. Equipment Safe Out HP1
1 of 4
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
6/6/04 9:00 AM 6/6/04 9:05 AM 5 7 HPB Safe out for stack repair and water wash. Normal blowdown. Equipment Safe Out LP
6/6/04 9: 12 AM 6/6/04 9:17 AM 5 6 HPB Safe out for stack repair and water wash. Normal blowdown. Equipment Safe Out LP
6/17/04 10:27 PM 6/17/04 10:53 PM 26 153 LP Compressor purge prior to start Started LP compressor Plant Startup HP1
6/13104 9:08 PM 6/13104 9:18 PM 10 39 Maintenance work. None. HPA Start Gas HP1
6/13104 9:17 PM 6/13104 9:21 PM 4 5 Maintenance work. None. HPA Start Gas LP
6/26/04 2:28 PM 6/26/04 2:32 PM 4 10 Normal flare during HP A start sequence purge. Started the HP A Compressor. Equipment Outage HP1
6/24/04 10:25 AM 6/24/04 10:44 AM 19 85 Normal flare during HP B purge for restart. Allowed to follow normal purge sequence. Equipment Outage HP1
6/24/04 10:50 AM 6/24/04 10:57 AM 7 36 Normal flare during HP B purge for restart. Started the HP B compressor. Equipment Outage HP1
6/24/04 9:53 AM 6/24/04 10:22 AM 29 130 Normal purge during initiation of HP B restart. Allowed to follow normal purge sequence. Equipment Outage HP1
6/27/04 9:44 AM 6/27/04 9:54 AM 10 38 Normal purge prior to HP A restart. Attempted to start the HP A Compressor. Equipment Outage HP1
6/26/04 10:49 PM 6/26/04 10:52 PM 3 5 Purge Gas. Started the HPA Compressor. HPA Start Gas LP
6/26/04 10:08 PM 6/26/04 10:13 PM 5 13 purge of HP A prior to restart. Attempted to start the Compressor. Equipment Outage HP1
6/23104 8:59 PM 6/23/04 9:03 PM 4 3 Purge prior to restart of HP A. Attempt to start HP A Compressor. HPA Start Gas LP
6/26/04 6:10PM 6/26/04 6:14 PM 4 4 restart attempt. Troubleshoot failure to start. HPA Start Gas LP
617104 1 :46 AM 617104 1 :50 AM 4 5 Start up of compressor after stack repair and turbine water Normal start sequence. HPB Start Gas LP
wash.
6/26/04 9:02 PM 6/26/04 9:05 PM 3 5 Start was unsuccessful. HP A Start Gas LP
6/26/04 10:05 PM 6/26/04 10:09 PM 4 5 Start was unsuccessful. Troubleshoot failure to start. HPA Start Gas LP
6/15/04 3:23 AM 6/15/04 3:27 AM 4 9 Unloading new production well NS-21 Into Test Separator. None. Normal well startup. Commissioning HP1
Had to lower pressure in the Test Separator in order to flow
well.
2 of 4
"
Start DatelTime End DateITlme Minutes MCF IncldenVCause Description Remediation Taken Event Type Flare
6/15/04 3:39 AM 6/15/04 3:45 AM 6 20 Unloading new production well NS-21 Into Test Separator. None. Normal well startup. Commissioning HP1
Had to lower pressure In the Test Separator in order to flow
well.
6/15/04 3:44 AM 6/15/04 3:46 AM 2 Unloading new production well NS-21 Into Test Separator. None. Normal well startup. Commissioning LP
Had to lower pressure in the Test Separator In order to flow
well.
6/15/04 6:09 AM 6/15/04 6:19 AM 10 31 Unloading new production well NS-21 into Test Separator. None. Normal well startup. Commissioning HP1
Had to lower pressure In the Test Separator In order to flow
well.
6/15/04 6:25 AM 6/15/04 6:27 AM 2 3 Unloading new production well NS-21 into Test Separator. None. Normal well startup. Commissioning HP1
Had to lower pressure in the Test Separator In order to flow
well.
6/26/04 5:29 PM 6/26/04 5:33 PM 4 4 Unsuccessful start. Troubleshoot problem. HPA Start Gas LP
Group Total: 1,304
Planned GreaterThan1 Hour
6/17104 8:25 PM 6/17/04 10:11 PM 106 169 Bringing in 011 rate to start LP Compressor Started LP comperssor as soon as we had enough Plant Startup HP1
gas
6/26/04 7:01 PM 6/26/04 8:19 PM 78 220 Resumption of production prior to LP compressor restart. Attempt another LP start. Upset LP
6/15/04 6:30 AM 6/15/04 8:31 AM 121 462 Unloading new production well NS-21 into Test Separator. None. Normal well startup. Commissioning HP1
Had to lower pressure in the Test Separator in order to flow
well.
Group Total: 851
Unplanned LessThan1 Hour
Group Total: 3,797
Unplanned GreaterThan1 Hour
6/23104 8:43 PM 6/24/04 12:05 AM 202 1,302 flaring during production restart following Plant OSD. Initiated start sequence. Upset HP1
6/26/04 5:19 PM 6/26/04 6:23 PM 64 395 HP A partial vented shutdown. Troubleshoot cause of shutdown. Equipment Outage HP1
6/17/04 1:19 PM 6/17/04 2:53 PM 94 667 HP-A shut down none Equipment Outage HP1
6/17104 1:20 PM 6/17/04 2:26 PM 66 391 Plant BESD due to fire alarm shut plant down Equipment Outage LP
30f4
O
..
, .
Start DatelTime End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
6/17/04 8:15 PM 6/17/04 9:58 PM 103 243 plant bleeding down at low pressure after BESD none Upset LP
6/23104 9:37 PM 6/23104 11:56 PM 139 225 Production restart following Plant OSD. Start HP A compressor. Upset LP
6/9/04 1 :42 PM 6/9104 9:18 PM 456 2,388 Tech doing PM on fire system caused LP to shutdown. Make sure system bypasses are on before doing Equipment Outage LP
PM.
6/9/04 2:18 PM 6/9/04 9:24 PM 426 1,403 Tech doing PM on fire system caused LP to shutdown. Make sure system bypasses are on before doing Equipment Outage HP1
PM.
6/26/04 6:26 PM 6/26/04 9:38 PM 192 1,805 Test separator PCV-1011 failed to fully seat. MTT Isolated and cleared obstruction from seat. Equipment Outage HP1
6/10/04 1:00 AM 6/10/04 2:04 AM 64 444 Upset from HPB start up. Also C Solar flameout. Normal equipment blowdown Equipment Outage HP1
Group Total: 9,262
Report
4of4
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Facility Name
N1
3. Field
Northstar
Volume MCF
Disposition
6. Sold
o
7. Reinjected
10,301,947
8. Fiared or vented 1 hour or less
4,296
9. Flared or vented more than 1 hour (see instL)
11,636
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see instructions)
o
13. TOTAL VOLUME (ITEMS 6-12)
10,317,879
14. NGL Gas Equivalent
15. Purchased gas
1,907,249
16. Transferred from:
17. Transferred to: (Express as a negative #)
4. Operator
5. Month/Year of Disposition
BP Jul -2004
20. For production from muitiple pools, list contribution of each pool as a percent of
Total Volume.
Pool Name
Pool Code
Percent
100%
Northstar
590100
~ß--
MCF
MCF
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (Le. no purchased gas). Gas purchased from PBU was used as foil
563,692, pilot purge 2759, injection 1,340,798
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 20 AAC25.235.
Printed Name
Robert A. Re nolds
Titre Mana er, State Taxes and Royalty
Signature
Phone (907)564-5028 Date
Form 10-422 Rev. 1/2004
Submit in Duplicate
Start DatelTime End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
7/11/04 10:31 AM 7/11/04 10:34 AM 3 2 Normal flaring due to plant start up Started Compressor Plant Startup LP
7/11/04 12:05 PM 7/11/04 12:10 PM 5 6 Normal flaring due to plant start up Started compressor Plant Startup HP1
7/11/04 12:35 PM 7/11/04 12:37 PM 2 Normal flaring due to plant start up Started compressor Plant Startup LP
7/11/04 1 :09 PM 7/11/04 1 :13 PM 4 2 Normal flaring due to plant start up Started compressor Plant Startup LP
7/11/04 6:10 PM 7/11/04 7:00 PM 50 805 Normal flaring due to plant start up Started compressor Plant Startup HP1
7/11/04 6:11 PM 7/11/04 6:13 PM 2 Normal flaring due to plant start up Started compressor Plant Startup LP
7/11/04 6:26 PM 7/11/04 6:30 PM 4 6 Normal flaring due to plant start up Started compressor Plant Startup LP
7/11/04 10:24 PM 7/11/04 10:26 PM 2 35 Normal flaring due to plant start up Started compressor Plant Startup HP1
7/11/04 10:30 PM 7/11/04 10:42 PM 12 16 Normal flaring due to plant start up Started compressor Plant Startup LP
7/11/04 11 :03 PM 7/11/04 11:46 PM 43 158 Normal flaring due to plant start up Started compressor Plant Startup LP
7/12104 1:14 AM 7/12104 1 :22 AM 8 15 Normal flaring due to plant start-up following TAPS Started the compressors Piant Startup LP
shutdown.
7/10/04 12:15 AM 7/10/04 12:40 AM 25 108 SID for Taps Slow down Shut In all wells Equipment Safe Out HP1
7/10/04 12:39 AM 7/10104 1 :09 AM 30 10 SID for Taps Slow down Shut in all wells Equipment Safe Out HP2
7/10/04 12:52 AM 7/10/04 1 :02 AM 10 5 SID for Taps Slow down Shut In all wells Equipment Safe Out LP
7/10/04 1:01 AM 7/10/04 1 :05 AM 4 4 SID for Taps Slow down Shut In all wells Equipment Safe Out HP1
7/10/04 1:12 AM 7/10/04 1 :33 AM 21 32 SID for Taps Slow down Shut In all wells Equipment Safe Out HP1
7/10/04 1:18 AM 7/10104 1:24 AM 6 2 SID for Taps Slow down Shut In all wells Equipment Safe Out LP
7/10104 1 :29 AM 7/10/04 1 :34 AM 5 6 SID for Taps Slow down Shut In all wells Equipment Safe Out LP
7/10104 3:21 AM 7/10/04 3:23 AM 2 2 SID for Taps Slow down Shut In all wells Equipment Safe Out LP
Group Total: 1,215
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned GreaterThan1 Hour
7/11/04 12:50 PM 7/11/04 4:14 PM 204 ./ 1,740 Normal flaring due to plant start up Started compressor Plant Startup HP1
7/11/04 1 :15 PM 7/11/04 3:46 PM 151 ./ 570 Normal flaring due to plant start up Started compressor Plant Startup LP
7/11/04 10:50 PM 7/12104 1:11 AM 141 ./ 1,381 Normal flaring due to plant start-up following TAPS Started the compressors Plant Startup HP1
shutdown.
Group Total: 3,692
Unplanned LessThan1 Hour
Group Total: 3,081
Unplanned GreaterThan1 Hour
7/5/04 10:38 AM 7/5/04 1 :07 PM 149 / 916 LP SID and Solars flamed out. started plant back up. Equipment Outage HP1
7/5/04 11 :20 AM 7/5/04 12:52 PM 92 ./ 331 LP SID and Solars flamed out. started plant back up. Equipment Outage LP
716104 4:05 PM 7/6/04 5:16 PM 71 ./ 162 LP SID do to high seal vent pressure Restarted plant Equipment Outage LP
7/6/04 4:06 PM 716104 5:37 PM 91 934 LP SID do to high seal vent pressure Restarted plant Equipment Outage HP1
716104 6:04 PM 716104 7:24 PM 80 ,/ 1,547 LP SID do to high seai vent pressure Restarted plant Equipment Outage HP1
7/25/04 3:39 PM 7/25/04 4:48 PM 69 ¡/ 127 PLC Fault PLC Plant Upgrades Upset LP
7/25/04 5:41 PM 7/25/04 6:47 PM 66 v 109 PLC Fault PLC Plant Upgrades Upset LP
/
7/4/04 9:32 PM 7/5/04 2:12 AM 280 2,501 Solar Flame out restarted the plant back up Equipment Outage HP1
./
714104 9:48 PM 7/5/04 1 :04 AM 196 920 Solar Flame out restarted the plant back up Equipment Outage LP
7/5/04 2:01 AM 7/5/04 3:09 AM 68 / 51 Solar Flame out restarted the plant back up Equipment Outage LP
7/5/04 7:36 AM 7/5/04 9:07 AM 91 / 178 Solar Flame out restarted the plant back up Equipment Outage LP
/
7/5/04 7:42 AM 7/5/04 9:19 AM 97 169 Solar Flame out restarted the plant back up Equipment Outage HP1
Group Total: 7,944 ¡/ II( b 3><,.. ~ (>\~)
,.
STATE OF ALASKA
ALASKA Oil AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
Disposition
3. Field
Northstar
Volume MCF
4. Operator
5. MonthlYear of Disposition
1. Facility Number
0290000025
2. Facility Name
N1
BP Au -2004
20. For production from multiple pools, list contribution of each pooi as a percent of
Total Voiume.
6. Sold
o
Pool Name
Pooi Code
Percent
100%
7. Reinjected
6,303,849
Northstar
590100
8. Flared or vented 1 hour or less
13,843
9. Flared or vented more than 1 hour (see instr.)
31,643
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see instructions)
o
13. TOTAL VOLUME (ITEMS 6-12)
6,349,335
14. NGL Gas Equival.ent
MCF
15. Purchased gas
2,395,181
Waste:
MCF
16. Transferred from:
17. Transferred to: (Express as a negative #)
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (i.e. no purchased gas). Gas purchased from P
432,206, pilot purge 2759, injection 1,960,216
Titie Manager, State Taxes and Royalty
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 20 AAC 5.235.
Printed Name
Robert A. Re no Ids
Phone (907)564-5028 Date
Form 10-422 Rev. 1/2004
Submit in Duplicate
Start DatelTime
End DatelTime
Planned
LessThan1 Hour
8/20/04 8:44 PM
8/20/04 8:48 PM
8/16/04 7:22 AM
8/16/04 7:37 AM
8/16/04 7:22 AM
8/16/04 7:26 AM
8/16/04 7:22 AM
8/16/04 8:00 AM
8/16/04 7:36 AM 8/16/04 7:59 AM
8/16/04 8:33 AM 8/16/04 8:33 AM
8/16/04 11 :11 AM 8/16/04 11 :58 AM
8/19/04 10:00 AM 8/19/04 10:37 AM
9112104 9:49 PM 8/12104 9:53 PM
8/12104 10:06 PM 8/12104 10:13 PM
8/12104 10:16 PM 8/12104 10:19 PM
9112/04 10:26 PM 8/12104 10:29 PM
8/12/04 10:32 PM 9112/04 10:36 PM
8/12104 10:42 PM 8/12/04 10:50 PM
8/15/04 3:31 AM 8/15/04 4:01 AM
8/6/04 7:09 AM
8/6/04 7:19 AM
8/16/04 1 :07 AM
8/16/04 1:13 AM
8/16/04 1:15 AM
8/16/04 1 :20 AM
NSTR Flare report 08-04 FINAL.xls
Minutes
I 4
MCF
4
15
21
4
38
61
23
80
o
47
63
37
108
7
3
3
4
12
8
25
30
271
10
51
6
13
5
22
;¿q ~
Incident/Cause Description
5
Attempt to start HP-A
BESD test.
6
BESD test.
\ '2 7 MIt\W<-~
Bfç,. ~ ~+s
BESD test.
"Z '3\ Me-F-
BESD test.
o
BESD test.
BESD test.
Bled NS-31 for wirellne work.
5
Bled off gas from test separator to gel NS-20 to flow after
Acid Treatment.
8
Bled off gas from test separator to get NS-20 to flow after
Acid Treatment.
4
Bled off gas from test separator to get NS-20 to flow after
Acid Treatment.
4
Bled off gas from test separator to get NS-20 to flow after
Acid Treatment.
Bled off gas from test separator to get NS-20 to flow after
Acid Treatment.
Bled off gas from test separator to get NS-20 to flow after
Acid Treatment.
Depressure HP-B prior to Maint.
Remediation Taken
Start HP-A
Test successfully completed.
Test completed successfully.
Test successfully completed.
Test successfully completed.
Test successfully completed.
Test successfully completed.
Finished bleed.
Stopped flaring once well started flowing.
Stopped flaring once well started flowing.
Stopped flaring once well started flowing.
Stopped flaring once well started flowing.
Stopped flaring once well started flowing.
Stopped flaring once well started flowing.
Blowdown and depressure HP-B.
Depressured the test separator so wlrellne could blow down separator at 0 psi
lubricator
Depressurring plant for shutdown.
Depressurrlng plant for shutdown.
Allow system to depressure.
Allow system to depressure.
Event Type
Flare
HP A Start Gas
LP
Plant Integrity
HP2
Plant Integrity
HP1
Plant Integrity
LP
Plant Integrity
HP1
Plant Integrity
HP1
Plant Integrity
HP1
Equipment Safe Out
HP1
Well Outage
HP1
Well Outage
HP1
Well Outage
HP1
Well Outage
HP1
Well Outage
HP1
Well Outage
HP1
Equipment Outage
HP1
Well Outage
HP1
Plant Integrity
HP1
Plant Integrity
HP1
~ NS-jO 01'1. ~~ ~ 'T~ <M,,::¿F
Start DatelTime End DateITl me Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
8/14104 2:12 PM 8/14104 2:20 PM 8 12 Gas flared while starting HP-A. Started HP-A. HP A Start Gas LP
8/11/04 2:25 AM 8/11/04 2:33 AM 8 12 HPA Start. None, normal start sequence. HP A Start Gas LP
8/11/04 7:00 AM 8/11/04 7:06 AM 6 25 HPA Start. None, normal start sequence. HPA Start Gas LP
8/20/04 9:11 PM 8/20/04 9:19 PM 8 22 HP-A suction Pressure High, Venting from contactor Load up HP-A Plant Startup HP1
8/20/04 9:23 PM 8/20/04 9:31 PM 8 49 HP-A suction Pressure High, Venting from contactor Load up HP-A Plant Startup HP1
8/22104 2:42 PM 8/22104 2:45 PM 3 5 HP-B purging prior to start up. Started HP-B Upset HP1
8/20/04 6:08 PM 9120/04 6:16 PM 8 17 Normal flaring during HP start. Aborted start up due to valve sequence problems. Plant Startup HP1
8/20/04 6:21 PM 9120/04 6:24 PM 3 2 Normal flaring during HP start. Aborted start up due to valve sequence problems. HPA Start Gas LP
8/20/04 6:39 PM 8/20/04 6:55 PM 16 88 Normal flaring during HP start. Aborted start up due to valve sequence problems. Plant Startup HP1
8/20/04 7:38 PM 8/20/04 7:45 PM 7 31 Normal flaring during HP start. Aborted start up due to valve sequence problems. Plant Startup HP1
8/20104 7:48 PM 9120/04 7:54 PM 6 8 Normal flaring during HP start. Aborted start up due to valve sequence problems. HPA Start Gas LP
8/20/04 8:10PM 8/20/04 8:27 PM 17 119 Normal flaring during HP start. Aborted start up due to valve sequence problems. Plant Startup HP1
8/21/04 11 :43 AM 8/21/04 11 :47 AM 4 11 Performance testing of HP-A causing high suction pressure, Completed performance testing Upset HP1
flared from contactor
8/21/04 12:37 PM 8/21/04 12:42 PM 5 18 Performance testing of HP-A causing high suction pressure, Completed performance testing Upset HP1
flared from contactor
8/21/04 5:09 PM 8/21/04 5:14 PM 5 10 Performance testing of HP-A causing high suction pressure, Completed performance testing Upset HP1
flared from contactor
8/21/04 5:16 PM 8/21/04 5:21 PM 5 59 Performance testing of HP-A causing high suction pressure, Completed performance testing Upset HP1
flared from contactor
9120/04 8:51 PM 8/20/04 9:05 PM 80 Purge gas for HP-A prior to start Start HP-A Plant Startup HP1
8/20/04 10:59 PM 8/20/04 11 :05 PM 4 Purge gas for LP compressor prior to st rt. Purged LP compressor Plant Startup LP
,þ t1fA ~¥~
~ .-.-,
NSTR Flare report 08-04 FINAL.xls ~ fjfJ n?G~ 2 of 6
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
8/20/04 11 :20 PM 9120104 11 :27 PM 7 7 Purge gas for LP compressor prior to start. Purged LP compressor Plant Startup HP1
8/20/04 11 :32 PM 8/20104 11 :37 PM 5 5 Purge gas for LP compressor prior to start. Purged LP compressor Plant Startup HP1
8/20/04 11 :33 PM 8/20/04 11 :39 PM 6 5 Purge gas for LP compressor prior to start. Purged LP compressor Plant Startup LP
8/21/04 7:22 AM 8/21/04 7:32 AM 10 45 Purge HP-B prior to start Start HP-B Plant Startup HP1
8/14/04 1 :49 PM 8/14/04 2: 12 PM 23 250 Purge LP Compressor prior to start. Start LP Compressor. Upset HP1
8/28/04 1: 1 0 AM 8/28/04 1 :25 AM 15 147 Restart after acoustic failure. None. Normal start. HPB Start Gas HP1
8/28/04 1: 17 AM 8/28/04 1 :21 AM 4 5 Restart after acoustic failure. None. Normal start. HPB Start Gas LP
8/28/04 1 :29 AM 8/28/04 1 :34 AM 5 16 Restart compressor purge after acoustic failure. None. Normal start. HPB Start Gas HP1
8/28/04 1:47AM 8/28/04 1 :49 AM 2 2 Restart compressor purge after acoustic failure. None. Normal start. HPB Start Gas HP1
8/29104 2:54 AM 8/28/04 2:58 AM 4 8 Restart compressor purge after acoustic failure. None. Normal start. HPB Start Gas HP1
8/15/04 9:44 PM 8/15/04 10:07 PM 23 76 Shut down LP Compressor and began depressuring plant for Depressure Plant for turnaround. Equipment Safe Out HP1
turnaround.
8/15/04 1 :41 AM 8/15/04 1 :48 AM 7 67 Shutdown HP-B for repair of exhaust stack. Shut down Hp·B. Equipment Outage HP1
8/21/04 7:32 AM 8/21/04 7:36 AM 4 5 Start gas to flare from HP-B Started HP-B HPB Start Gas LP
8/22104 2:44 PM 9122104 2:52 PM 8 12 Start HP-B after unplanned shutdown Start HP-B HPB Start Gas LP
8/22104 4:39 PM 8/22104 4:47 PM 8 12 Start HP-B after unplanned shutdown Start HP-B HPB Start Gas LP
8/22104 8:00 PM 8/22104 8:08 PM 8 12 Start HP-B after unplanned shutdown Start HP-B HPB Start Gas LP
8/25/04 7:39 AM 8/25/04 7:49 AM 10 43 Start up after flow control valve repair. None. Normal start sequence. HPB Start Gas HP1
8/25/04 7:49 AM 8/25/04 7:53 AM 4 5 Start up after flow control valve repair. None. Normal start sequence. HPB Start Gas LP
8/8/04 8:10 AM 8/8/04 8:12 AM r 2( Start up after LP repairs Start up of plant Plant Startup LP
8/8/04 8:17 AM 8/8/04 8:22 AM 5 6 Start up after LP repairs Start up of plant Plant Startup HP1
NSTR Flare report 08-04 FINAL.xls 3 of 6
Start DatelTime End DatelTime Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
8/8/04 1 :49 PM 8/8/04 2:23 PM 34 83 Start up after LP repairs Start up of plant Plant Startup HP1
8/8/04 1 :50 PM 8/8/04 2:24 PM 34 154 Start up after LP repal Lf> <&\~- ~~ Start up of plant Plant Startup LP
8/8/04 2:32 PM 8/8/04 2:35 PM 3 2 Start up after LP repal Start up of plant Plant Startup LP
~\ ~'1A1A - t51,,,,
919104 2:37 PM 8/8/04 2:39 PM 2 2 Start up after LP repai Start up of plant Plant Startup LP
~
8/8/04 2:43 PM 918/04 2:53 PM 10 39 Start up after LP repail II ~L\p ~ Start up of plant Plant Startup HP1
8/8/04 2:53 PM 8/8/04 2:57 PM 4 4 Start up after LP repair LP r~'r- .... Start up of plant Plant Startup LP
8/8/04 3:04 PM 8/8/04 3:08 PM 4 4 Start up after LP repairs -~ p~ Start up of plant Plant Startup LP
8/8/04 3:23 PM 8/8/04 3:26 PM 3 5J Start up after LP repairs Start up of plant Plant Startup LP
8/10/04 6:27 AM 8/10/04 6:31 AM t 4 5 7 Started HP A from sid NIA HPA Start Gas LP
8/15/04 6:38 PM 8/15/04 6:41 PM 3 3 Starting HP-A. Started HP-A HPA Start Gas LP
8/16/04 1:54 AM 8/16/04 1 :58 AM 4 5 Used start to roll HP-A turbine for cool down after we shut it Shut off start gas when done. HPA Start Gas LP
down.
8/15/04 2:34 AM 8/15/04 2:39 AM 5 6 Used start to roll HP-B turbine for cool down after we shut It Shut off start gas when done. HPB Start Gas LP
down.
8/15/04 2:46 AM 8/15/04 2:50 AM 4 4 Used start to roll HP-B turbine for cool down after we shut It Shut off start gas when done. HPB Start Gas LP
down.
8/15/04 2:55 AM 8/15/04 3:00 AM 5 6 Used start to roll HP-B turbine for cool down after we shut It Shut off start gas when done. HPB Start Gas LP
down.
8/15/04 3:27 AM 8/15/04 3:32 AM Used start to roll HP-B turbine for cool down after we shut It Shut off start gas when done. HPB Start Gas LP
down.
8/8/04 6:23 AM 8/8/04 6:27 AM 4 4 Wire line blowing down lubarcator through the test separator done Well Outage HP1
a~ . I 35 t)?(/F
Group Total: 2,390 ~
Planned GreaterThan 1 Hour
8/20/04 11 :46 PM 8/21104 2:21 AM 155 504 Brought In 011 rate until we had enough gas to start the LP Started LP compressor Plant Startup LP
compressor
8/20/04 11 :46 PM 9121/04 4:18 AM 272 675 Brought In oil rate until we had enough gas to start the LP Started LP compressor Plant Startup HP1
NSTR Flare report 08-04 FINAL.xls 4 of 6
Start DatelTime End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
compressor
8/21/04 2:25 AM 8/21/04 4:10AM 105 470 Brought In 011 rate until we had enough gas to start the LP Started LP compressor Plant Startup LP
compressor
8/15/04 10:20 PM 8/15/04 11:41 PM 81 88 Depressurlng plant for turnaround. Depressured plant for turnaround. Plant Integrity HP1
8/16/04 2:23 AM 8/16/04 7:05 AM 282 866 Depressuring the plant. Allowed systems to depressure. Equipment Outage HP1
9115/04 4:04 PM 8/15/04 5:36 PM 92 248 Flared produced gas prior to starting LP Compressor. Started LP compressor. Equipment Outage LP
8/9104 8:50 AM 8/8/04 10:37 AM 107 573 Start up after LP repairs Start up of plant Plant Startup LP
8/8/04 8:53 AM 8/8/04 10:34 AM 101 243 Start up after LP repairs £e. ~4 Start up of plant Plant Startup HP1
8/8/04 10:36 AM 8/8/04 1 :47 PM 191 417 Start up after LP repairs Start up of plant Plant Startup HP1
8/8/04 10:38 AM 8/8/04 1 :49 PM 191 937 Start up after LP repairs g~ - Il11f" Start up of plant Plant Startup LP
LP
Group Total: 5,021 btf/ 0-
Unplanned LessThan1 Hour 0') 3A.\- I ~1f1'\
Group Total: 11,453
Unplanned GreaterThan1 Hour
8/10/04 5:40 AM 8/10/04 6:53 AM 73 754 HP A step to Idle and then SID Restarted HP A Equipment Outage HP1
9110/04 9:07 PM 8/10/04 10:18 PM 71 1,219 HP A step to Idle and then SID. Purge and restart compressor. Equipment Outage HP1
8/10/04 10:29 PM 8/10/04 11 :49 PM 80 2,347 HP A step to Idle and then SID. Purge and restart compressor. Equipment Outage HP1
8/11/04 1 :55 AM 9111/04 3:02 AM 67 892 HP A step to Idle and then SID. Restarted HP A Equipment Outage HP1
8/27/04 11:55 PM 8/28/04 1 :06 AM 71 541 HP B compressor shutdown due to acoustic failure. Allowed to blowdown for restart. Equipment Outage HP1
9115/04 4:03 PM 9115/04 5:42 PM 99 1,577 HP-A SID on fuel control valve malfunction. Re-started HP-A. Equipment Outage HP1
8/14/04 12:38 PM 8/14104 1 :41 PM 63 486 HP-A shutdown due to a glitch while programming with a lap Re-Started HP-A. Upset HP1
top computer.
8/1/04 2:50 PM 8/1/04 4:57 PM 127 959 HPB Compressor Start Gas, attempted start. Checking call1bration on 5th stg. recycle FCY- HPB Start Gas HP1
2360.
NSTR Flare report 08-04 FINAL.xls 5 of 6
Start DateITlme End DatelTime Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
911/04 2:52 PM 911/04 4:13 PM 81 245 HPB Compressor Start Gas, attempted start. Checking callibration on 5th stg. recycle FCY- HPB Start Gas LP
2360.
8/28/04 3:37 PM 8/28/04 5:46 PM 129 378 LP Compressor down because of DGV ( Diffuser Guldev Shut-In Wells to mitigate flaring. Equipment Outage LP
Vane) problems.
8/28/04 8:18 PM 8/29/04 12:15 PM 957 4,678 LP Compressor down because of DGV (Diffuser Guide Vane) Shut-in wells to mitigate flaring. Equipment Outage HP1
problems.
lOt b'3( ~
8/28/04 8:22 PM 8/29104 12:27 AM 245 1,504 LP Compressor down because of DGV (Diffuser Guide Vane) Shut-In wells to mitigate flaring. Equipment Outage LP
problems.
9129/04 12:28 AM 8/29/04 12:08 PM 700 4,071 LP Compressor down because of DGV (Diffuser Guide Vane) Shut-In wells to mitigate flaring. Equipment Outage LP
problems.
8/5/04 10:36 AM 8/5/04 8:48 PM 612 2,438 Shutdown the LP compressor on re-start attempt due to hi None necessary. Equipment Outage HP1
seal pressure. LP blew down to LP flare.
8/5104 10:47 AM 8/5104 8:50 PM 603 3,062 Shutdown the LP compressor on re-start attempt due to hi None necessary. Equipment Outage LP
seal pressure. LP blew down to LP flare.
9110/04 7:14 PM 8/10/04 8:39 PM 85 1,472 Started HPA from sid. Restarted HP A. Plant Startup HP1
8/18/04 1 :34 PM 8/18/04 2:43 PM 69 0 While commissioning the new PLC, a valve opened, Closed Valve. Commissioning LP
releasing residual gas to flare.
Group Total: 26,622
Report
NSTR Flare report 08-04 FINAL.xls
6 of 6
RE: August Gas Disposition
1) Milne Point installed a new, vertical flare in late August_ This flare uses
air for assist gas instead of fuel gas so you'll see the assist gas go to zero in
the Sept report_ Pilot purge IS slightly higher with the new flare and I'm
tracking down the technical reason for that_
2) I talked with the Operations Lead Tech at Endicott regarding this flaring. He
said they were depressuring and deinventorying the facility over the 14th and 15th.
The volumes shown were flared volumes, not assist gas. The comment refers to the
need to use some assist gas to prevent black smoke during this time.
3) I've requested this programming change for the Northstar report.
Let me know if you need more information.
Anne Fiedler
Volume Accounting
BP Exploration (Alaska) Inc.
907/564-5826
907/564-4094 (fax)
fiedleam@bp.com
-----Original Message-----
From: Stephen Mcmains [mailto:steve mcmains@admin.state.ak_us]
Sent: Monday, October 11, 2004 3:17 PM
To: Fiedler, Anne M
Subject: August Gas Disposition
Ann,
I need some question answered for Jim Regg from August reports.
*Milne pt Unit *- Why the big increase in pilot-purge gas volume for the
month, 633 mcf and other months average 350-360 mcf?
*Endicott* - The > 1 hour flared events for the August report had
"Assist gas to bleed down NGL separator Plant SD". Jim Regg wants to
know is 100% of this assist gas, 1285 mcf?
*Northstar *- Something has to be corrected for this facility reports.
They are still the most confusing reports to review_ All future reports
must be sorted by date and time. It might take some revisions to your
reports, how they sort or how they are automated. Too much time is
spent trying to follow what is going on. The events greater than 1 hour
must be listed by *date and time*. They must include duration of event,
mcf gas flared, incident description and remediation.
Steve
1 of 1
10/14/20042:54 PM
Northstar Flaring - August Reports
August 2004 gas disposition report showed a volume increase in > lhr events; it
appears from summary pages attached to the report that a significant part was
attributed to the LP compressor being down "because of diffuser guide vane
problems" .
I'd appreciate a brief explanation of the DGV and the specific problems
encountered. Thanks.
Jim Regg
AOGCC
I of!
.
10/15/2004 10:44 AM
[Fwd: RE: Northstar Flaring - August Reports}
Put copy of this with Augsut 2004 disposition report for Northstar. Thanks
Jim
--------
Original Message --------
RE: Northstar Flaring - August Reports
Sat, 16 Oct 2004 10:56:18 -0800
PBU, Nstar Ops Team Leader <PBUNstarOpsTeamLeader@BP.com>
James Regg <jim reg_~@ad~in_~~tate.ak.u~2
Subject:
Date:
From:
To:
Hi Jim,
The DGVs (diffuser guild vanes) are in the gas flow path on each of the
6 stages of our LP compressor. The DGVs provide head balancing between
the stages of the compressor_ If one fails, we get vibration shutdowns
as the stages become unevenly balanced_ In this instance, one of the DGV
positioners, the device used to move
the DGVs, failed with the DGV in the closed position. This is the normal
start position so that on subsequent start tries, the failure went
unnoticed with only
A high vibration shutdown alarm taking the unit down. The repeated start
attempts are what gave us the extended flare events. When we figured out
the problem, we replaced the positioner, added deviation alarms between
DGV demand and actual position and the machine was returned to service.
Give me a call if you need more detail_
Thanks
Steve Carboy
Northstar OTL
670-3601
-----Original Message-----
From: James Regg [mailto:jim regg@admin.state.ak.us] Sent: Friday, October 15, 2004
10:44 AM
To: PBU, Nstar Ops Team Leader
Subject: Northstar Flaring - August Reports
August 2004 gas disposition report showed a volume increase in > Ihr events; it
appears from summary pages attached to the report that a significant part was
attributed to the LP compressor being down "because
of diffuser guide vane problems"_
I'd appreciate a brief explanation of the DGV and the specific problems
encountered. Thanks.
Jim Regg
AOGCC
lof2
10/19/20047:52 AM
STATE OF ALASKA
ALASKA Oil AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Facility Name
N1
3. Field
Northstar
Volume MCF
Disposition
6. Sold
o
7. Reinjected
10,319,833
8. Flared or vented 1 hour or less
5,427
9. Flared or vented more than 1 hour (see instr.)
7,004
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see instructions)
o
13. TOTAL VOLUME (ITEMS 6-12)
10,332,264
14. NGL Gas Equivalent
15. Purchased gas
3,316,768
16. Transferred from:
17. Transferred to: (Express as a negative #)
4. Operator
5. Month/Year of Disposition
BP Se -2004
20. For production from multiple pools. list contribution of each pool as a percent of
Total Volume.
Pool Name
Pool Code
Percent
100%
Northstar
590100
SfIL
MCF
,
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (i.e. no purchased gas). Gas purchased from PBU was used as follows (all in mscf): fuel gas
589,278, pilot purge 2670, injection 2,724,820
Signature
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 20 AAC25.235.
Printed Name
Robert A. Re nolds
Title Manager, State Taxes and Royalty
Phone (907)564-5028 Date
Form 10-422 Rev. 1/2004
Submit in Duplicate
...
Start DatelTime End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
9/9/04 3:34 PM 9/9/04 3:38 PM 4 16 HP A purge Attempted to start HP A compressor. Equipment Outage HP1
9/9/04 3:22 PM 9/9104 3:26 PM 4 7 HP A start gas. Started HP A compressor. Equipment Outage LP
9/9/04 3:50 PM 9/9/04 4:48 PM 58 304 HP A start gas. Started HP A compressor. Equipment Outage HP1
9/9/04 4:04 PM 9/9/04 4:10PM 6 4 HP A start gas. Started HP A compressor. Equipment Outage LP
9/10/04 3:07 PM 9/10/04 3:11 PM 4 5 HP A start gas. Started HP A compressor. Equipment Outage LP
9/9104 1 :50 PM 9/9/04 2:13 PM 23 646 HP B purge Started compressor Equipment Outage HP1
9/10/04 2:57 PM 9/10/04 3:05 PM 8 39 HP B Purge Started HP B compressor. Equipment Outage HP1
9/9/04 1 :59 PM 9/9/04 2:23 PM 24 44 Normal flare activity for HP B start Started the compressor. HPB Start Gas LP
9/14104 10:41 AM 9/14104 10:45 AM 4 5 Normal flaring during start sequence of HP compressor. Started the compressor. HPB Start Gas LP
9/14104 10:31 AM 9/14/04 10:38 AM 7 39 Purge and pressure prior to start. Started the compressor. Upset HP1
9/14/04 10:06 AM 9/14/04 10:12 AM 6 14 Purge LP Compressor prior to start. Started LP Compressor. Upset LP
9/14104 4:36 PM 9/14104 4:43 PM 7 33 restart HPA start compressor HPA Start Gas HP1
9/14104 4:47 PM 9/14104 4:51 PM 4 7 restart HPA start compressor HP A Start Gas LP
9/8104 3:18 PM 9/9104 3:22 PM 4 6 Start gas provided for HP A start. Started the HP A Compressor. HPA Start Gas LP
Group Total: 1,168
Planned GreaterThan1 Hour
9/9/04 2:16 PM 9/9/04 3:19 PM 63 697 HP A purge Attempted to start compressor. Equipment Outage HP1
9/14104 8:42 AM 9/14/04 10:05 AM 83 239 Start gas for LP Compressor. Started LP Compressor Upset LP
Group Total: 936
NSTR Flare Report 09-2004.xls
1 of 2
...
,"
Start DateITlme End DatelTime Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Unplanned LessThan1 Hour
Group Total: 4,259
Unplanned GreaterThan1 Hour
9/9/04 5:26 PM 9/9/04 8:27 PM 181 648 Bringing on wells for LP restart Start LP Gas compressor Equipment Outage LP
9/9/04 5:31 PM 9/9/04 8:32 PM 181 485 Bringing on wells for LP restart Start LP Gas compressor Equipment Outage HP1
9/14/04 8:28 AM 9/14104 10:22 AM 114 246 Flaring due to excess pressure resulting form shutdown. Cut Import gas and shut In wells. Upset HP1
9/30/04 3:02 PM 9/30/04 5:22 PM 140 636 High High Pressure on the LP Heater shell Restarted plant Plant Integrity HP1
9/30/04 3:08 PM 9/30104 5:07 PM 119 509 High High Pressure on the LP Heater shell Restarted plant Plant Integrity LP
918104 9:16 PM 9/9104 10:43 PM 87 349 LP compressor had discharge transmitter go bad resulting in calibrated transmitter anad restarted LP Upset LP
LP shutdown
9/8104 9:31 PM 9/9104 10:49 PM 78 302 LP compressor had discharge transmitter go bad resulting In calibrated transmitter anad restarted LP Upset HP1
LP shutdown
9/14104 7:21 AM 9/14/04 8:28 AM 67 84 NGL system overpressured. Shut In wells. Upset LP
9/8104 12:12 PM 9/8104 2:19 PM 127 394 NGL System upset caused LP compressor to shutdown, Started the plant back up. Upset LP
ultimately resulting In a level 3A shutdown.
9/8104 12:26 PM 9/8104 2:24 PM 118 364 NGL System upset caused LP compressor to shutdown, Started the plant back up. Upset HP1
ultimately resulting In a level 3A shutdown.
911/04 7:03 PM 9/1/04 9:01 PM 118 1,868 Plant shutdown due to suspected psv release off of HP-B Wells shut In. Upset HP1
causing high pressure In HP-flare scrubber.
9/1/04 7:40 PM 9/1/04 8:43 PM 63 183 Plant shutdown due to suspected psv release off of HP-B Wells shut in. Upset LP
causing high pressure In HP-flare scrubber.
Group Total: 6,068 '-I JlCl~
Report (
NSTR Flare Report 09-2004.xls
2 of 2
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Facility Name
N1
Disposition
3. Field
Northstar
Volume MCF
4. Operator 5. MonthlYear of Disposition
BP Oct-2004
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
o
Pool Name
Pool Code
Percent
100%
7. Reinjected
10,238,746
Northstar
590100
8. Flared or vented 1 hour or less
11 ,466
9. Flared or vented more than 1 hour (see instr.)
3,280
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
MCF
12. Other (see instructions)
o
13. TOTAL VOLUME <ITEMS 6-12)
10,253,492
14. NGL Gas Equivalent
MCF
15. Purchased gas
3,210,603
Waste:
16. Transferred from:
17. Transferred to: (Express as a negative #)
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (Le. no purchased gas). Gas purchased from
610,254, pilot purge 2759, injection 2,597,590
Date
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 2 AAC25.235.
Signature
Title Manager, Production Taxes and Royalties Aiaska
Printed Name
Phone (907)564-5028
---ä Y
Form 10-422 Rev. 1/2004
Submit in Duplicate
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
Group Total: 1,229
Planned GreaterThan1 Hour
/ 10/12104 6:21 PM 10/12104 7:50 PM ~ 89 77 Normal flare for LP compressor and plant start up. Plant Startup HP1
10/12104 7:57 PM 10/12104 9:14 PM '" 77 214 Production for LP compressor start. Plant Startup LP
~ 10/12/04 8:08 PM 10/12/04 9:14 PM '\, 66 36 Production for LP compressor start. Plant Startup HP1
Group Total: 327
Unplanned LessThan1 Hour
Group Total: 10,237
Unplanned GreaterThan1 Hour
10/9/04 10:08 PM 10/9/04 11:10 PM 62 472 . HP A shutdown. Equipment Outage HP1
I 10/11/04 9:56 PM 10/12104 12:30 AM 154 441 . Production restart and HP A shutting down Plant Startup LP
':;.. 10/11/04 10:02 PM 10/12104 12:42 AM 160 294 . Plant startup and LP Compressor shutdown. Plant Startup HP1
10/12/04 6:58 AM , 10/12104 9:09 AM 131 353 HP A & B logic problems. Diagnosing fuel control logic. Upset LP
If 10/12104 7:14 AM _ 10/12104 8:43 AM 89 417 HP B vented shutdown. Diagnosing HP fuel control logic. Upset HP1
10/12104 12:05 PM 10/12104 1 :21 PM 76 262 HP B trouble shooting, step to Idle. Diagnosing fuel control problem. Upset HP1
10/12/04 2:16 PM 10/12104 3:30 PM 74 ( 123 HP A & B logic problems. Diagnosing fuel control problem. Upset LP
"'. 10/12/04 9:15 PM 10/12104 10:42 PM 87 (24 LP Compressor shutdown. Restart LP. Equipment Outage HP1
10/12104 9:16 PM 10/12104 10:31 PM 75 17' LP Compressor shutdown. Restart LP. Equipment Outage LP
10/21/04 12:09 AM 10/21/04 1:12 AM 63 15 HPB stepped to idle due to a "hardwlred fuel control" Shut In 5 of the High GOR wells Immediately to Equipment Outage HP1
problem. This backed up pressure in the LP compressor and control flaring.
shut it down on high Interstage pressure.
NSTR Flare Report 10-04 FINAL.xls
1 of 2
Start DateITlme
End DateITlme
10/26/04 3:14 PM
10/26/04 4:16 PM
10/27/04 8:57 AM
10/27/04 10:25 AM
Group Total:
Report
NSTR Flare Report 10-04 FINAL.xls
Minutes
Incident/Cause Description
Remediation Taken
MCF
62
Solar A SID and trip the LP compressor off line
shut In well to minimize flaring and started up
plant
30
88
LP SID on high high level 1 st stage suction scrubber
cleared shut down and restarted plant
205
2,953
Event Type
Equipment Outage
Upset
Flare
HP1
HP1
2 of 2
~
.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Facility Name
N1
3. Field
Northstar
Volume MCF
Disposition
6. Sold
o
7. Reinjected
10,955,425
8. Flared or vented 1 hour or less
3,316
9. Flared or vented more than 1 hour (see instr.)
3,356
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see instructions)
o
13. TOTAL VOLUME <ITEMS 6-12)
10,962,097
14. NGL Gas Equivalent
15. Purchased gas
3,451,009
16. Transferred from:
17. Transferred to: (Express as a negative #)
4. Operator 5. Month/Year of Disposition
BP Nov-2004
20. For production from multiple pools. list contribution of each pool as a percent of
Totai Volume.
Pool Name
Pool Code
Percent
100%
Northstar
590100
Jr-~
MCF
MCF
MCF
/-//-
Date
18. Remarks: Blocks 6 -13 include only produced gas from Northstar (i.e. no purchased gas). Gas purchased from PBU was used as follows (all in mscf): fuel gas
624,202, pilot purge 2670, injection 2,824,137
Title Manager, Production Taxes and Royalties Aiaska
Signature
I hereby certify that the foregoing is tr
/I
rect to the best of my knowledge.
/7
Printed Name
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 20 AAC25.235.
Form 10-422 Rev. 1/2004
Phone (907)564-5028 Date
Submit in Duplicate
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Unplanned LessThan1 Hour
Group Total: 3,316
Unplanned GreaterThan1 Hour
11/1/04 12:32 PM 11/1/04 2:13 PM 101 1,103 Lp Compressor shutdown due to high level in 1st stage Cut rate. Stopped production to repair 5th stage Upset HP1
suction scrubber. seal.
11/3104 12:31 AM 11/3104 1:40 AM 69 98 LP camp. 5th stg. seal repair. New generation seal upgrade. Plant Startup LP
11/3104 1 :44 AM 11/3104 4:57 AM 193 1,334 LP camp. 5th stg. seal repair. New generation seal upgrade. Plant Startup HP1
11/3104 1 :53 AM 11/3104 4:34 AM 161 822 LP camp. 5th stg. seal repair. New generation seal upgrade. Plant Startup LP
Group Total: 3,356
NSTR Flare Report 11-04 FINAL.xls
1 of 1
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000025
2. Facility Name
N1
3. Field
Northstar
Volume MCF
Disposition
6. Sold
o
7. Reinjected
11,981,166
8. Flared or vented 1 hour or less
4,143
9. Flared or vented more than 1 hour (see instr.)
5,047
10. Pilot and Purge
o
11. Used for lease operations (specify in Remarks)
o
12. Other (see instructions)
o
13. TOTAL VOLUME (ITEMS 6-12)
11,990,356
14. NGL Gas Equivalent
15. Purchased gas
3,044,199
16. Transferred from:
17. Transferred to: (Express as a negative #)
4. Operator 5. MonthlYear of Disposition
BP Dec-2004
20. For production from multiple poois, list contribution of each pool as a percent of
Total Volume.
Pool Name
Pool Code
Percent
100%
Northstar
590100
:flt'.--
MCF
MCF
18. Remarks: Blocks 6 - 13 include only produced gas from Northstar (i.e. no purchased gas). Gas purchased from PBU was used as follows (all in mscf): fuel gas
648,816, pilot purge 2759, injection 2,392,624
I hereby certify that t.,~..e foregoing iSïJtr#.;( rre ct. to the best of my knowledge.
?L, ,i. r?
Signature /;r-c~, <)
'( / 1,/ /
Printed Name Bernard W. Ha"n
Phone (907)564-5028
Title Manager, Production Taxes and Royalties Alaska
Date
} .- Ös-
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
Authorit 20 AAC25.23 .
Form 10-422 Rev. 1/2004
Submit in Duplicate
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
Planned LessThan1 Hour
1217104 4:26 PM 1217104 4:40 PM 14 15 Bleeding down test seperator so we can bleed NS-DS IA to O. NIA Other HP1
12/8104 5:23 PM 1218104 5:27 PM 4 6 HPB Start Gas LP
12/8104 5:46 PM 1218104 6:15 PM 29 220 HPB Purge Gas HP1
12/8104 6:17 PM 12/8/04 6:25 PM 8 13 HPB Start Gas LP
12/17/04 11:26 AM 12/17/04 11:32 AM 6 10 Restarted plant after shutdown. None: Normal startup. HPB Start Gas HP1
12/21/04 2:50 PM 12/21/04 2:55 PM 5 6 Restarting HPA after SID none HPA Start Gas LP
12/21/04 6:49 PM 12/21/04 6:53 PM 4 6 Restarting HPA after SID none HPA Start Gas LP
12/21/04 7:25 PM 12/21104 7:29 PM 4 6 Restarting HPA after SID none HPA Start Gas LP
12/21/04 7:59 PM 12/21/04 8:03 PM 4 6 Restarting HPA after SID none HPA Start Gas LP
12/21/04 8:03 PM 12/21104 8:31 PM 28 45 Restarting HPA after SID none HPA Purge Gas HP1
12/21/04 9:56 PM 12/21/04 10:00 PM 4 6 Restarting HPA after SID none HPA Start Gas LP
12/21/04 10:16 PM 12/21/04 10:18 PM 2 2 Restarting HPA after SID none HPA Purge Gas HP1
12/22/04 1 :32 PM 12/22/04 1 :40 PM S 30 trying to start HPA none HPA Purge Gas HP1
12/22/04 1 :44 PM 12/22104 1 :46 PM 2 2 trying to start H P A none HPA Purge Gas HP1
12122/04 1 :46 PM 12/22/04 1:51 PM 5 6 trying to start HPA none HPA Start Gas LP
12/22104 3:34 PM 12/22104 3:52 PM 18 105 trying to start HPA none HPA Purge Gas HP1
12/22/04 4:04 PM 12/22/04 4:11 PM 7 30 trying to start HPA none HPA Purge Gas HP1
12122/04 4:13 PM 12/22104 4:18 PM 5 6 trying to start HPA none HPA Start Gas LP
12/23104 9:09 AM 12/23/04 9:16 AM 7 29 Starting HPA none HPA Purge Gas HP1
12/23/04 9:20 AM 12/23/04 9:22 AM 2 3 Starting HPA none HPA Purge Gas HP1
Northstar Flare Report 12-04 FINAL.xls 1 of 2
Start DateITlme End DateITlme Minutes MCF Incident/Cause Description Remediation Taken Event Type Flare
12/23104 9:22 AM 12/23104 9:26 AM 4 6 Starting HPA none HPA Start Gas LP
12/23/04 10:14 AM 12123104 10:22 AM 8 13 Starting HPA none HPA Start Gas LP
12/23104 11 :23 AM 12/23104 11 :28 AM 5 25 Starting HPA none HPA Purge Gas HP1
Group Total: 595
Planned GreaterThan 1 Hour
1217/04 2:45 PM 1217/04 3:47 PM 62 "., 113 Bleeding down test seperator so we can bleed NS-D8 IA to O. NIA Other HP1
-
12/21/04 2:57 PM 12/21/04 6:13 PM 196 ' 704 Restarting HPA after SID none HPA Purge Gas HP1
Group Total: 817
Unplanned LessThan1 Hour
Group Total: 3,548
Unplanned GreaterThan1 Hour
/ 1218104 12:59 PM 1218104 5:21 PM 262 .'...J 2,064 Plant restart from PSLL 2270 shutdown. Equipment Outage HP1
~
1218104 1 :43 PM 1218104 4:10 PM 147 '" 362 Plant restart from earlier shutdown. Equipment Outage LP
12117/04 1 :16 AM 12117/04 2:21 AM 65 .... 47 Plant shutdown due to faulty level transmitter on Crude None: Normal plant shutdown. Upset LP
J Stabilizer.
/
( 12117104 2:51 AM 12117/04 4:45 AM 114 ' 90 Plant shutdown due to faulty level transmitter on Crude None: Normal plant shutdown. Upset LP
~. Stabilizer.
\
12117/04 4:48 AM 12117/04 5:55 AM 67 J 56 Plant shutdown due to faulty level transmitter on Crude None: Normal plant shutdown. Upset LP
Stabilizer.
/12/21/0411:28AM 12/21/04 1:13 PM 105 '- 429 Incidental set point change caused plant to shutdown. Normal plant shutdown. All wells shut-In. Upset LP
I 12121/04 11:29 AM 12121/04 1 :07 PM 98 '-.. 698 Incidental set point change caused plant to shutdown. Normal plant shutdown. All wells shut-In. Upset HP1
\
'') 12121/04 1:28 PM 12/21104 2:55 PM 87 " 309 Incidental set point change caused plant to shutdown. Normal plant shutdown. All wells shut-In. Upset HP1
12122104 4:32 PM 12/22104 6:05 PM 93 174 HPA blow down failed to start none Equipment Outage HP1
Group Total: 4,230