Facility: PBU GC I
Operator: BP EXPLORATION (ALASKA)
McMains, Stephen E (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Friday, March 01, 2013 6:57 AM
To: McMains, Stephen E (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GCI OSM; AK,
HSSEE Env Adv West
Subject: Gas flaring events at GC1
To: Steve McMains, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson,
AOGCC
steve.mcmainsoalaska.00v dave.roby(o)alaska.aov
victoria.ferauson aoalaska.gov
From: Travis Rybicki, GPB Production Optimization Team Leader
A flaring event occurred at GC1 starting at 02/05/2013 00:00 and stopping at 02/05/2013 24:00 with a volume of 2760
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/06/2013 00:00 and stopping at 02/06/2013 24:00 with a volume of 960
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GILT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GCI starting at 02/08/2013 00:00 and stopping at 02/08/2013 24:00 with a volume of 3700
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/10/2013 00:00 and stopping at 02/10/2013 24:00 with a volume of 4166
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/11/2013 00:00 and stopping at 02/11/2013 24:00 with a volume of 4970
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/21/2013 00:01 and stopping at 02/21/2013 06:23 with a volume of 6980
(MSCF). The event lasted for 382 minutes. Flaring was due to a failed power supply on the OT -28 (oil transit line) PLC
which caused the shutdown of oil shipping pumps and associated production banks. Flaring continued while the power
supply was replaced, production banks were restarted and flare valves went closed one plant stabilized.
A flaring event occurred at GC1 starting at 02/25/2013 00:00 and stopping at 02/25/2013 24:00 with a volume of 2539
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/26/2013 00:00 and stopping at 02/26/2013 24:00 with a volume of 3386
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/27/2013 00:00 and stopping at 02/27/2013 24:00 with a volume of 4330
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/28/2013 00:00 and stopping at 02/28/2013 24:00 with a volume of 4020
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
akoosocceoctl(a)bo. com
Alternate: Kellie Okonek
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED r2As n1SPnS1T1r)M
1. Facility Number 2. Facility Name
0290000031 PBU GC 1
Disposition
3. Field
PBU - WOA
Volume MCF
4. Operator 5. Month/Year of Disposition
14,pJanua -2013
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
0
Pool Name Pool Code Percent
7. Reinjected
p
PRUDHOE 640150 99,820/
LISBURNE 640144 0.00%
8. Flared or vented l hour or less
4,967
MIDNIGHT SUN 640158 0.18%
PT MCINTYRE 640180 0.00%
9. Flared or vented more than 1 hour (see instr.)
112,292
10. Pilot and Purge
63,342
11. Assist Gas
0
12. Fuel gas used in lease operations.
810,474
13. Other (see instructions)
0
._Official [Use Qnly
Authorization>1 hr:
Safety
MCF
14. TOTAL VOLUME (ITEMS 6.12)
991,075
Lease Use
MCF
15. NGL Gas Equivalent
0
Conservation
MCF
16. Purchased gas
0
Waste:
MCF
17. Transferred from:
U
Commissioner Date
18. Transferred to: (Express as a negative #) CGF
-73,268,977
19. Remarks:
I hereby certify that t foregoing is true and correct to the best of my knowledge.
�/ xes and Ro alNote: All volumes must be corrected
Signature Title Manager Production Talies Alaska to pressure of 14.65 psia and to a
temperature of 600 F. Authority 20
Printed Name Diane ColleyPhone (907) 564-5775 Date AAC25.235.
Form 10-422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE Submit in Duplicate
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
January 2013
jUnplanned Events less than or equal to 1 hour
DATE TIME VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO ELIMINATE CAUSE
1/7/2013 0105-0155 4,557 Not required for unplanned events <= 1 hr Not required for unplanned events <=1 hr
TOTAL 4,557
1/3/2013 0000-2400 4,740 See attachments See attachments
1/5-31/2013 0000-2400 107,552
TOTAL 112,292
Planned Events Less Than or Equal 1 Hour AND <= 5,000 mcf
DATE TIME VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO ELIMINATE CAUSE
1/10/2013 0913-0933 410 See attachments See attachments
TOTAL 410
Planned Events Exceeding 1 Hour OR> 5,000 mcf
See attachments
TOTAL 0
L
See attachments
Page 6
2/13/2013
3:46 PM
TOTAL
Unplanned Events < 1 Hour
4,557
Unplanned Events > 1 Hour
112,292
Planned Events < 1 hour and not
410
exceeding 5,000 MCF
Planned Events> 1 hour or
0
exceeding 5,000 MCF
Pilot Purge
.-`.- 63,342
Assist
0
TOTAL FLARED VOLUME
180,601
L
See attachments
Page 6
2/13/2013
3:46 PM
Flare StartDate 01/012013
1320 min
Yes
No
Flare End Date 01/31/2013
BPIISPRINGG
5670
Determination Cause
GC1 Flare
Report
Total Volume (MSCF)
117259
Report
Numbs System Date Start Time Stop Time
Duration Intermittent
Black Smoke Planned Reported By
Volume
13-2 Flare Relief 01/032013 12:00:00 am 12:00:00 am
1440 min Yes
No No BP7ISPRINGG
4740
Determination Cause sk-494 V-7025 blovi valve leaks by
BPIISPRINGG
3760
Determination Cause
Action Taken W/Oenteredto T/S / repairvalve
13-5 Flare Relief 01/05/2013 12:00:00 am 12:00:00 am
1440 min Yes
No No BPIISPRINGG
5470
Determination Cause sk494 V-7025 blowcese valve leaks by
Action Taken W/O entered to T/S / repairvalve
13-10 Other
13-7 Flare Relief 01/062013 12:00:00 am 12:00:00 am
1440 min Yes
No No BPIISPRINGG
4350
Determination Cause sk-494 V-7025 blowcase valve leaks by
BPIUONESCC
4680
Determination Cause
Action Taken W/O entered to T/S / repair valve
13-8 Flare Relief 01/07/2013 2:00:00 am 12:00:00 am
1320 min
Yes
No
No
BPIISPRINGG
5670
Determination Cause
sk-494 V-7025 blowrase valve leaks by
Action Taken
W/Oenteredto T/S / repairvalve
13-9 Flare Relief
01/08/2013 12:00:00 am 12:00:00 am
1440 min
Yes
No
No
BPIISPRINGG
3760
Determination Cause
sk-494 V-7025 blowcase valve leaks by
Action Taken
W/Oenteredto T/S / repairvalve
13-10 Other
01/09/2013 12:00:00 am 12:0000 am
1440 min
Yes
No
No
BPIUONESCC
4680
Determination Cause
Unknown flaring, source not found.
Action Taken
Look for source of Flaring. Volume based on FOIT-01-7446T.
13-11 Other
01/10/2013 12:00:00 am 12:00:00 am
1440 min
Yes
No
No
BPIUONESCC
4810
Determination Cause
FOIT-01-74467 out of calibration.
Action Taken
Input work requestto calibrate FT-ot-7446.
13-11 Controlled Blovii 01/10/2013 9:13:00 am 9:33:00 am
20 min
No
No
Yes
BPIUONESCC
410
Determination Cause
Lower T -bank pressurefrom HP to LP.
Action Taken
Closed T -bank Rare valve. Volume based on FOR -01-7446T.
13-13 Other 01/11/2013 12:00:00 am 11:59:00 pm 1439 min Yes No No BPIIKIRSCHW 2920
Determination Cause unknown leak K-3300 GLT
Action Taken looking over compressor for faultyReaking equipment
13-15 Other 01/12/2013 12:00:00 am 12:00:00 am 1440 min Yes No No BPIUONESCC 3470
Determination Cause Unfound flare source. Suspect FIT -01-7446T calibration error.
Generated 02/04/2013 3:64:59PM Page 6 of 10
Flare StartDate 01/01/2013
Flare End Date 01/31/2013
Action Taken Reference work order 43305922
13-14 Omer
01/13/2013 12:00:00am 11:59:00 pm
1439 min
No
No
No
BPIUORSCHW
4560
Determination Cause
unidentified leak into Bare header
Action Taken
exhaustive search ongoing for leaking psJs , flare valves etc...
Generated
02/04/2013
3:54:59PM
13-16 Other
01/14/2013 12:00:00 am 12:00:00 am
1440 min
Yes
No
No
BP1\BIFFERDL
6010
Determination Cause
Unidentified soure leaking to Bare.
Action Taken
Ongoing search for leak to flare, checking Bare valves,PSVs act.
13-19 Other
01/15/2013 12:00:00 am 12:00:00 am
1440 min
Yes
No
No
BP1\SPRINGG
5390
Determination Cause
Unidentified source leaking to flare.
Action Taken
Ongoing search for leak to flare, checking flare vaNes,PSVs act.
13-20 Other
01/16/2013 12:00:00 am 1200:008M
1440 min
No
No
No
BP1\HELMIGBJ
4610
Determination Cause
Unidentified source leaking to flare.
Action Taken
Leaking source not identified yet.
13-22 Other
01/17/2013 12:00:00 am 11:59:00 pm
1439 min
Yes
No
No
BPi\HELMIGBJ
3200
Determination Cause
Unidentified source leaking to Bare.
Action Taken
Leaking source not identified yet.
13-24 Other
01/18/2013 12:00:OOam 12:00:OOam
1440 min
Yes
No
No
BP1\HELMIGBJ
2900
Determination Cause
Unidentified leaking source to flare.
Action Taken
Leaking source not identified yet.
13-27 Other
01/19/2013 12:00:00 am 120000 am
1440 min
Yes
No
No
BPI\HELMIGBJ
3500
Determination Cause
Unidentified leaking source to Bare.
Action Taken
Still looking for leak source.
13-29 Other
01/20/2013 12:OO:00am 12:O 00am
1440 min
Yes
No
No
BPIWELMIGBJ
3680
Determination Cause
Unidentified leaking source to flare.
Action Taken
Source not identified yet.
13-36 Other
01/21/2013 12:00:OOam 12:0000am
1440 min
Yes
No
No
BP7\HELMIGBJ
4020
Determination Cause
Unidentified leaking source to flare.
Action Taken
Leaking source not found yet.
13-37 Other
01/22/2013 12:00:00 am 120000 am
1440 min
Yes
No
No
BPI\HELMIGBJ
4010
Determination Cause
Unidentified leaking source to the flare.
Action Taken
Leaking source not identified yet.
13-38
Other
01/23/2013
12:00:OOam
12:00:00 am
1440 min
Yes
No
No
BP1\HELMIGBJ 3620
Generated
02/04/2013
3:54:59PM
Page 7 of 10
Flare StartDate 01/01/2013
Flare End Date 01/31/2013
Determination Cause Unidentified leaking sourceto the flare
Action Taken Leaking source not identified yet.
13-39 Other 01/24/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No BP1\SELFJR 3330
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken TRYING TO DETECT SOURCE
13-41 Other 01/25/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No BPI\SELFJR 5290
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken LEAK NOT DETECTED STILL LOOKING
13-43 Other 01/28/2013 12:00:OOam 12:00:OOam 1440 min Yes
No No BP1\SELFJR 3020
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken Leak trouble shooting in progress
13-45 Flare Relief 01/27/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No BP7\SELFJR 3040
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken LEAK DETECTION ONGOING
13-47 Flare Relief 01/28/2013 12:00:00am 12:00:00 am 1440 min Yes
No No BP1\SELFJR 3130
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken leak detection ongoing
13-48 Flare Relief 01/29/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No BP1\SELFJR 2970
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken leak detection ongoing
13-56 Flare Relief 01/30/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No BP1\SPRINGG 3122
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken leak detection ongoing
13-57 Flare Relief 01/31/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No BP1\SPRINGG 3020
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken leak detection ongoing
Total Volume (MSCF) 117258
Generated 02/04/2013 3:54:59PM Paget) of 10
McMains, Stephen E (DOA)
From: AK, OPS PCC EOC TL (AKOPSPCCEOCTL@bp.com)
Sent: Tuesday, February 05, 2013 10:41 AM
To: McMains, Stephen E (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GCI Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West -n � GC-_ I
Subject: Gas flaring events at GCI �'1
To: Steve McMains, AOGCC
AOGCC
steve.mcmains(o' alaska.00v
victoria. ferouson(Dalaska.00v
CC: Dave Roby, AOGCC
dave. roby(cDalaska. cov
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson,
A flaring event occurred at GC1 starting at 01/30/2013 00:00 and stopping at 01/30/2013 24:00 with a volume of 3122
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/31/2013 00:00 and stopping at 01/31/2013 24:00 with a volume of 3020
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/01/2013 11:00 and stopping at 02/01/2013 14:43 with a volume of 3330
(MSCF). The intermittent event lasted for 223 minutes. Flaring was due to multiple start attempts on GLT T/C 3300.
Operations needed to take the sister unit, T/C 3200 down for maintenance. Flaring continued until T/C 3300 was
successfully started.
A flaring event occurred at GC1 starting at 02/02/2013 00:00 and stopping at 02/02/2013 24:00 with a volume of 3340
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/03/2013 00:00 and stopping at 02/03/2013 24:00 with a volume of 3840
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/04/2013 00:00 and stopping at 02/04/2013 24:00 with a volume of 3540
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GILT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
akoosocceoctl0bo. com
Alternate: Kellie Okonek
McMains, Stephen E (DOA)
From:
AK, OPS PCC EOC TL (AKOPSPCCEOCTL@bp.com]
Sent:
Tuesday, January 08, 2013 11:37 AM
To:
McMains, Stephen E (DOA)
Cc:
Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject:
Gas flaring events at GC1
To: Steve McMains, AOGCC
AOGCC
steve. mcmains(@alaska.gov
victoria. ferg use n(o)alaska.gov
CC: Dave Roby, AOGCC
dave.robv(.alaska.gov
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson,
6 C I
A flaring event occurred at GC1 starting at 01/06/2013 00:00 and stopping at 01/06/2013 24:00 with a volume of 4350
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to a leaking blow case valve. A corrective work
order was written to repair/replace the offending valve. Flaring continued into the following day as operations staff waited
for repair/replacement of offending valve.
A flaring event occurred at GC1 starting at 01/07/2013 02:00 and stopping at 01/07/2013 24:00 with a volume of 5670
(MSCF). The intermittent event lasted for 1320 minutes. Flaring was due to a leaking blow case valve. A corrective work
order was written to repair/replace the offending valve. Flaring continued into the following day as operations staff waited
for repair/replacement of offending valve.
A flaring event occurred at GCI starting at 01/07/2013 01:05 and stopping at 01/07/2013 01:55 with a volume of 4557
(MSCF). The intermittent event lasted for 50 minutes. Flaring was due to the unplanned shutdown of IP Compressor K-
108. Flaring continued from the IP Compressor suction vessel until the K-107 IP Compressor unit was started. Flaring
ended when K-107 was started, loaded and the Flare valves closed.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) ream Lead
Office 907-6594472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
a koos occeoctl (M bo. com
Alternate: Kellie Okonek
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopsocceoctl(oft.com
McMains, Stephen E (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Saturday, February 02, 2013 7:30 PM
To: McMains, Stephen E (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West ^ C I
Subject: Gas flaring events at GC1 (� J=
To: Steve McMains, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson,
AOGCC
Steve. mcmains(aalaska. gov dave. robv(c)alaska. oov
victoria.fercuson &alaska.aov
From: Travis Rybicki, GPB Production Optimization Team Leader
A flaring event occurred at GC1 starting at 01/06/2013 00:00 and stopping at 01/06/2013 24:00 with a volume of 4350
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to a leaking blow case valve. A corrective work
order was written to repair/replace the offending valve. Flaring continued into the following day as operations staff waited
for repair/replacement of offending valve.
A flaring event occurred at GC1 starting at 01/07/2013 02:00 and stopping at 01/07/2013 24:00 with a volume of 5670
(MSCF). The intermittent event lasted for 1320 minutes. Flaring was due to a leaking blow case valve. A corrective work
order was written to repair/replace the offending valve. Flaring continued into the following day as operations staff waited
for repair/replacement of offending valve.
A flaring event occurred at GC1 starting at 01/08/2013 00:00 and stopping at 01/08/2013 24:00 with a volume of 3670
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to a leaking blow case valve. A corrective work
order was written to repair/replace the offending valve. Flaring continued into the following day as operations staff waited
for repair/replacement of offending valve.
A flaring event occurred at GC1 starting at 01/09/2013 00:00 and stopping at 01/09/2013 24:00 with a volume of 4680
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV. Flaring
continued into the following day as operations staff investigated the cause of the flaring event. A crew change occurred
and this event is likely the continuation of the events noted above.
A flaring event occurred at GC1 starting at 01/10/2013 00:00 and stopping at 01/10/2013 24:00 with a volume of 4810
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV. Flaring
continued into the following day as operations staff investigated the cause of the flaring event. A crew change occurred
and this event is likely the continuation of the events noted above. A WO was written to calibrate the flared gas meter to
validate reported volumes.
A flaring event occurred at GC1 starting at 01/11/2013 00:00 and stopping at 01/11/2013 24:00 with a volume of 2920
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GILT system. Flaring continued into the following day as operations staff investigated the cause of the
flaring event.
A flaring event occurred at GC1 starting at 01/12/2013 00:00 and stopping at 01/12/2013 24:00 with a volume of 3470
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GILT system or other unknown source. Flaring continued into the following day as operations staff
investigated the cause of the flaring event. Operations indicated suspect calibration on flared gas meter.
A flaring event occurred at GCI starting at 01/13/2013 00:00 and stopping at 01/13/2013 24:00 with a volume of 4560
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/14/2013 00:00 and stopping at 01/14/2013 24:00 with a volume of 6010
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/15/2013 00:00 and stopping at 01/15/2013 24:00 with a volume of 5390
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/16/2013 00:00 and stopping at 01/16/2013 24:00 with a volume of 4610
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GCI starting at 01/17/2013 00:00 and stopping at 01/17/2013 24:00 with a volume of 3200
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/18/2013 00:00 and stopping at 01/18/2013 24:00 with a volume of 2900
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/19/2013 00:00 and stopping at 01/19/2013 24:00 with a volume of 3500
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/20/2013 00:00 and stopping at 01/20/2013 24:00 with a volume of 3680
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/21/2013 00:00 and stopping at 01/21/2013 24:00 with a volume of 4020
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/22/2013 00:00 and stopping at 01/22/2013 24:00 with a volume of 4010
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/23/2013 00:00 and stopping at 01/23/2013 24:00 with a volume of 3620
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GCI starting at 01/24/2013 00:00 and stopping at 01/24/2013 24:00 with a volume of 3330
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GCI starting at 01/25/2013 00:00 and stopping at 01/25/2013 24:00 with a volume of 5290
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/26/2013 00:00 and stopping at 01/26/2013 24:00 with a volume of 3020
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GILT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/27/2013 00:00 and stopping at 01/27/2013 24:00 with a volume of 3040
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GILT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GCI starting at 01/28/2013 00:00 and stopping at 01/28/2013 24:00 with a volume of 3130
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GILT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/29/2013 00:00 and stopping at 01/29/2013 24:00 with a volume of 2970
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GILT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 7584404
GPB Pager 907-659-5272 # 1890
a ko os o cce octl (c).b o. co m
Alternate: Kellie Okonek
Kellie Okonek (alt. Travis Rybicki)
PCCiEOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctlobp.com
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DiSPORITilnN
1. Facility Number
0290000031
2. Facility Name
PBU GC 1
3. Field
PBU - WOA
4. Operator ... •
BP
5. MonthNear of Disposition
I February -2013
Disposition
Volume MCF
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
0
Pool Name Pool Code Percent
7. Reinjected
U
PRUDHOE 640150 99.30%
LISBURNE 640144 0.00%
8. Flaredorvented l hourorless5481
MIDNIGHT SUN 640158 0.07%
PT MCINTYRE 640180 0.00%
9. Flared or vented more than 1 hour (see instr.)
116,131
10. Pilot and Purge
56,624
11. Assist Gas
U
12. Fuel gas used in lease operations.
767,106
13. Other (see instructions)
U
.Official. Use -Only - `
Authorization >1 hr:
Safety
MCF
14. TOTAL VOLUME (ITEMS 6.12)
945,342
Lease Use
MCF
15. NGL Gas Equivalent
0
Conservation
MCF
16. Purchased gas
p
Waste:
MCF
17. Transferred from:
0
Commissioner Date
18. Transferred to: (Express as a negative #) CGF
-64,753,280
19. Remarks:
I hereby certify that thhe� foregoing istrue and correct to the best of my knowledge.
/ '/�/y%q� /� Note: All volumes must be corrected
Signature M'1LG7 �' l.1/(tP1y / ' Title Manager Production Taxes and Royalties Alaska to pressure of 14.65 psis and to a
da temperature of 60o F. Authority 20
Printed Name Diane Colley Phone (907) 564-5775 Date AAC25.235.
Form 10-422 Rev. 512009 INSTRUCTIONS ON REVERSE SIDE Submit in Duplicate
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
February 2013
2/24/2013
1955-2020
2,500 Not required for unplanned events <= 1 hr
2/25/2013
1600-1645
1,971
2/28/2013
2106-2118
480
0001-0623
TOTAL
4,951
ACTION TAKEN TO ELIMINATE CAUSE
Not required for unplanned events <= 1 hr
Page 6
DATE
TIME
VOLUME DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
2/1-28/13
0000-2400
108,751 See attachments
See attachments
2/21/2013
0001-0623
6,980
TOTAL
115,731
Planned Events Less Than or Equal 1 Hour AND <= 5,000 mcf
DATE
TIME
VOLUME DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
2/6/2013
0205-0223
530 See attachments
See attachments
TOTAL
530
Planned Events Exceeding 1 Hour OR > 5,000 mcf
DATE
TIME
VOLUME DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKENTO ELIMINATE CAUSE
2/1/2013
1100-1443
400 See attachments
See attachments
TOTAL
400
Unplanned Events < 1 Hour
Unplanned Events> 1 Hour
Planned Events < 1 hour and not
exceeding 5,000 MCF
Planned Events > 1 hour or
exceeding 5,000 MCF
Pilot Purge
Assist
TOTAL FLARED VOLUME
TOTAL
4,951
115,731
530
400
56,624
0
178,236
3/13/2013
9:52 AM
Flare Start Date 02/01/2013
No No
BPt\SPRINGG
3340
Flare End Date 02/28/2013
Action Taken leak detection ongoing
GC1 Flare Report
13-61 Flare Relief 02/03/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No
Total Volume (MSCF)
121612
Report
Numbe System Date Start Time
Stop Time Duration Intermittent
Black Smoke Planned Reported By
Volume
13-54 Flare Relief 02/01/2013 12:00:00 am
11:59:00 pm 1439 min Yes
No No BPI\HELMIGBJ
2900
Determination Cause Valve leakage into the Flare system.
Action Taken Valve leakage not identified yet.
13-54 Flare Relief 02/01/2013 11:00:00 am
2:43:00 pm 223 min No
No Yes BP1\BIFFERDL
400
Determination Cause Starting GLT 3300, had to try 3 times to get it going. Took down 3200 and depresured it. Bad seat oil pump motor on 3200.
Action Taken Substained fire achieved. Done with turbine swap.
Action Taken leak detection ongoing
13-58 Flare Relief 02/02/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No
BPt\SPRINGG
3340
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken leak detection ongoing
13-61 Flare Relief 02/03/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No
BP1\SPRINGG
3840
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCE
Action Taken leak detection ongoing
13-62 Flare Relief 02/04/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No
BP1\SPRINGG
3540
Determination Cause GAs LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCES
Action Taken leak detection ongoing
13-64 Flare Relief 02/05/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No
BP1\SPRINGG
2760
Determination Cause GAS LEAKAGE INTO FLARE SYSTEM UNIDENTIFIED SOURCES
Action Taken leak detection ongoing
13-65 Other 02/06/2013 12:00:00 am 12:00:00 am 1440 min No
No No
BP1\KIRSCHW
960
Determination Cause leaking equipment to flare... search still ongoing for cause ... or possible x-mitter calibration wrong
Action Taken search ongoing
13-65 Controlled Blowdown 02/06/2013 2:05:00 am 2:23:00 am 18 min No
No Yes
BPIUONESCC
530
Determination Cause Switched T -bank from HP to LP mode.
Action Taken Achieved LP pressure. Flared volume based on FOI-01-7446T.
13-104 Flare Relief 02/07/2013 12:00:00 am 11:59:00 pm 1439 min Yes No No BPIVIELMIGBJ 3700
Determination Cause Unidentified source leaking to the flare system.
Action Taken Still looking for the leak into the flare.
13-67 Flare Relief 02/08/2013 12:00:00 am 12:00:00 am 1440 min Yes No No BPt\SELFJR 3700
Determination Cause FLARE SYSTEM HAS LEAKING VALVES INTO HEADER
Action Taken OPERATIONS IS LOOKING FOR A SOLUTION TO PROBLEM
13-105 Flare Relief 02/09/2013 12:00:00 am 11:59:00 pm 1439 min Yes No No BP1\HELMIGBJ 4100
Determination Cause Flare system leak not Identified yet
Generated 03/07/2013 3:52:03PM Page 5 of 9
Flare Start Date 02/01/2013
Flare End Date 02/28/2013
Action Taken Ops continue looking for valve leakage.
13-69 Flare Relief 02/10/2013 12:00:00 am 12:00:00 am
1440 min Yes
No
No
BPI\SELFJR
4166
Determination Cause Leakage into fire systme from bad valves
Action Taken operations troubleshooting to Identify problem
13-71 Flare Relief 02/11/2013 12:00:00 am 12:00:00 am
1440 min Yes
No
No
BP1\HELMIGBJ
4970
Determination Cause Unidentified leaking source to the flare.
Action Taken Continue to look for leaking source.
13-106 Flare Relief 02/12/2013 12:00:00 am 11:59:00 pm
1439 min Yes
No
No
No
BPIHELMIGBJ
4900
Determination Cause Unidentified leak into the flare system.
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet.
Action Taken Leaking source not identified yet
13-107 Flare Relief 02/13/2013 12:00:00 am 11:59:00 pm
1439 min Yes
No
No
No
No
BPI\HELMIGBJ
4500
Determination Cause Unidentified leaking source to the flare system.
4800
Determination Cause Unidentified leaking source to the flare system.
Action Taken Source leak not identified yet.
Action Taken Leaking source not identified yet
13-108 Flare Relief 02/14/2013 12:00:00 am 11:59:00 pm
1439 min Yes
No
No
No
BPIHELMIGBJ
4600
Determination Cause Unidentified leaking source to the flare sysstem.
Action Taken Leaking source not identified yet.
13-109 Flare Relief 02/15/2013 12:00:00 am 11:59:00 pm 1439 min Yes
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet.
No No BPI\HELMIGBJ 5100
13-110 Flare Relief 02/16/2013 12:00:00 am 11:59:00 pm
1439 min Yes
No
No
BP1\HELMIGBJ
4900
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet.
13-111 Flare Relief 02/17/2013 12:00:OOam 11:59:OOpm
1439min Yes
No
No
BPI\HELMIGBJ
5400
Determination Cause Unidentified leaking source into the flare system.
Action Taken Leaking source not identified yet.
13-112 Flare Relief 02/18/2013 12:00:00 am 11:59:00 pm
1439 min Yes
No
No
BPI\HELMIGBJ
4700
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet
13-113 Flare Relief 02/19/2013 12:00:00 am 11:59:00 pm
1439 min Yes
No
No
BP1\HELMIGBJ
4800
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet
13-114 Flare Relief 02/20/2013 12:00:00 am 11:59:00 pm
1439 min Yes
No
No
BPIHELMIGBJ
3900
Generated 03/072013 3:52:03PM Page 6 of 9
Flare Start Date 02.101/2013
Flare End Date 02/28/2013
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet.
13-81 Flare Relief 02/21/2013 12:00:00 am 11:59:00 pm 1439 min Yes No No BP1\HELMIGBJ 2900
Determination Cause Leakage to the flare is ongoing.
Action Taken Source not identified yet.
13-81 Flare Relief 02/21/2013 12:01:00 am 6:23:00 am 382 min No No No BP1\MATTRR 6980
Determination Cause Loss of power supply to OT -28 PLC caused SDV-8200 to go shut, shutting down the shipping pumps and associated banks.
Action Taken PAC techs reestablished power to the PLC, then the shut down banks were restarted.
13-115 Flare Relief 02/2211013 12:00:00 am 11:59:00 pm 1439 min Yes
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet.
13.116 Flare Relief 02/23/1013 12:00:00 am 11:59:00 pm 1439 min Yes
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet.
13-84 Flare Relief 02/24/2013 12:00:00 am 11:59:00 pm 1439 min Yes
Determination Cause Unidentified leaking source to the flare system.
Action Taken Leaking source not identified yet.
13-88 Flare Relief 02/25/2013 12:00:00 am 12:00:00 am 1440 min Yes
Determination Cause Flare header leakeage ongoing problem
Action Taken Trouble shoofing options to find leaks
No No BPI\HELMIGBJ 4500
No No BP1\HELMIGBJ 3800
No No BPI\HELMIGBJ 2500
No No BP1\SELFJR 2539
13-91 Flare Relief 02/16/1013 12:00:00 am 12:00:00 am 1440 min Yes No No BP1\FISHERCD 3386
Determination Cause Leakage into flare header
Action Taken Flaring tram B-Slugcatcher bemuse of faulty flare valve positioner. Awaiting installafion of new positioner.
13-96 Flare Relief 02/27/2013 12:00:00 am 12:00:00 am 1440 min Yes No No BPI\SPRINGG 4330
Determination Cause Flare header leakeage ongoing problem
Action Taken Trouble shoofing options to find leaks
13-94 Flare Relief 02/28/2013 12:00:00 am 12:00:00 am 1440 min Yes No No BP1\SPRINGG 4020
Determination Cause Flare header leakeage ongoing problem
Action Taken Trouble shooting options to find leaks
Generated 03/07/2013 3:52:03PM Page 7 of 9
McMains, Stephen E (DOA)
From:
AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent:
Tuesday, February 05, 2013 10:41 AM
To:
McMains, Stephen E (DOA)
Cc:
Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano,
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL;
HSSEE Env Adv West
Subject:
Gas flaring events at GC1
F.�
To: Steve McMains, AOGCC CC: Dave Roby, AOGCC
AOGCC
steve.mcmainsoalaska.gov dave robs alaska.gov
victoria.ferguson (cDalaska.gov
From: Travis Rybicki, GPB Production Optimization Team Leader
Alejandra; Benson, Gary A;
AK, OPS GC1 OSM; AK,
&G -r
CC: Victoria Ferguson,
A flaring event occurred at GC1 starting at 01/30/2013 00:00 and stopping at 01/30/2013 24:00 with a volume of 3122
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 01/31/2013 00:00 and stopping at 01/31/2013 24:00 with a volume of 3020
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/01/2013 11:00 and stopping at 02/01/2013 14:43 with a volume of 3330
(MSCF). The intermittent event lasted for 223 minutes. Flaring was due to multiple start attempts on GLT T/C 3300.
Operations needed to take the sister unit, T/C 3200 down for maintenance. Flaring continued until T/C 3300 was
successfully started.
A flaring event occurred at GC1 starting at 02/02/2013 00:00 and stopping at 02/02/2013 24:00 with a volume of 3340
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/03/2013 00:00 and stopping at 02/03/2013 24:00 with a volume of 3840
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 02/04/2013 00:00 and stopping at 02/04/2013 24:00 with a volume of 3540
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-6594472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
akoosocceoctl cDbo.corn
Alternate: Kellie Okonek
McMains, Stephen E (DOA)
From:
AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent:
Monday, March 04, 2013 7:22 AM
To:
McMains, Stephen E (DOA)
Cc:
Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject:
Gas flaring events at GC1
To: Steve McMains, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson,
AOGCC
steve. mcmains(a)alaska. gov dave. robv(cDalaska.gov
victoria. ferguson0alaska.goy
From: Travis Rybicki, GPB Production Optimization Team Leader
A flaring event occurred at GC1 starting at 03/01/2013 00:00 and stopping at 03/01/2013 24:00 with a volume of 4930
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 03/02/2013 00:00 and stopping at 03/02/2013 24:00 with a volume of 2760
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 03/03/2013 00:00 and stopping at 03/03/2013 24:00 with a volume of 4060
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
akoDsr)cceoctl(OD,bp. Corn
Alternate: Kellie Okonek
McMains, Stephen E (DOA)
From:
AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.comj
Sent:
Friday, March 08, 2013 11:45 AM
To:
McMains, Stephen E (DOA)
Cc:
Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject:
Gas flaring events at GC1
To: Steve McMains, AOGCC
steve.mcmains(@alaska.gov
CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
dave.robvaalaska.gov victoria.ferouson(dalaska.gov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at GC1 starting at 02/01/2013 11:00 and stopping at 02/01/2013 14:43 with a volume of 400
(MSCF). The event lasted for 223 minutes and was due to starting GLT 3300 and shutting GLT 3200 down for
maintenance. Flaring stopped when load transfer complete.
A flaring event occurred at GCI starting at 02/21/2013 00:01 and stopping at 02/21/2013 06:23 with a volume of 6980
(MSCF). The event lasted for 382 minutes and was due to loss of power supply to OT -28 which caused and SDV to close,
with associated s/d of shipping pumps and banks. Flaring stopped when power to the PLC was restored. The event had
a volume greater than 5000 (MSCF).
An intermittent flaring event has been ongoing at GC1 due to valve leakage into the flare system, for which operations
continues to investigate the source of leaks:
starting at 02/01/2013 00:00 and stopping at 02/01/2013 23:59 with a volume of 2900 (MSCF). The event lasted for 1439
minutes.
starting at 02/07/2013 00:00 and stopping at 02/07/2013 23:59 with a volume of 3700 (MSCF). The event lasted for 1439
minutes.
starting at 02/08/2013 00:00 and stopping at 02/09/2013 23:59 with a volume of 3700 (MSCF). The event lasted for 1439
minutes
starting at 02/09/2013 00:00 and stopping at 02/09/2013 23:59 with a volume of 4100 (MSCF). The event lasted for 1439
minutes
starting at 02/10/2013 00:00 and stopping at 02/12/2013 23:59 with a volume of 4166 (MSCF). The event lasted for 1439
minutes
starting at 02/11/2013 00:00 and stopping at 02/12/2013 23:59 with a volume of 4970 (MSCF). The event lasted for 1439
minutes
starting at 02/12/2013 00:00 and stopping at 02/12/2013 23:59 with a volume of 4900 (MSCF). The event lasted for 1439
minutes.
starting at 02/13/2013 00:00 and stopping at 02/13/2013 23:59 with a volume of 4500 (MSCF). The event lasted for 1439
minutes.
starting at 02/14/2013 00:00 and stopping at 02/14/2013 23:59 with a volume of 4600 (MSCF). The event lasted for 1439
minutes
starting at 02/15/2013 00:00 and stopping at 02/15/2013 23:59 with a volume of 5100 (MSCF). The event lasted for 1439
minutes. The event had a volume greater than 5000 (MSCF).
starting at 02/16/2013 00:00 and stopping at 02/16/2013 23:59 with a volume of 4900 (MSCF). The event lasted for 1439
minutes
starting at 02/17/2013 00:00 and stopping at 02/17/2013 23:59 with a volume of 5400 (MSCF). The event lasted for 1439
minutes. The event had a volume greater than 5000 (MSCF).
starting at 02/18/2013 00:00 and stopping at 02/18/2013 23:59 with a volume of 4700 (MSCF). The event lasted for 1439
minutes
starting at 02/19/2013 00:00 and stopping at 02/19/2013 23:59 with a volume of 4800 (MSCF). The event lasted for 1439
minutes.
starting at 02/20/2013 00:00 and stopping at 02/20/2013 23:59 with a volume of 3900 (MSCF). The event lasted for 1439
minutes
starting at 02/21/2013 00:00 and stopping at 02/21/2013 23:59 with a volume of 2900 (MSCF). The event lasted for 1439
minutes
starting at 02/22/2013 00:00 and stopping at 02/22/2013 23:59 with a volume of 4500 (MSCF). The event lasted for 1439
minutes
starting at 02/23/2013 00:00 and stopping at 02/23/2013 23:59 with a volume of 3800 (MSCF). The event lasted for 1439
minutes
starting at 02/24/2013 00:00 and stopping at 02/24/2013 23:59 with a volume of 2500 (MSCF). The event lasted for 1439
minutes
flaring continued daily in the interim, but these reports have been sent
starting at 03/04/2013 00:00 and stopping at 03/05/2013 with a volume of 4410 (MSCF). The event lasted for 1440
minutes.
starting at 03/05/2013 00:00 and stopping at 03/06/2013 with a volume of 5040 (MSCF). The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
starting at 03/06/2013 00:00 and stopping at 03/07/2013 with a volume of 5450 (MSCF). The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
starting at 03/07/2013 00:00 and stopping at 03/08/2013 with a volume of 5316 (MSCF). The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctl(abp.com
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000031
2. Facility Name
PBU GC 1
3. Field
PBU - WOA
4.0perator
BP
5. MonthlYear of Disposition
March -2013
Disposition
Volume MCF
20. For production from nwbipge pools, list contribution ofescb pool as a percent of
Tolat Volume
6. Sold
0
Paul Name I Pool Code Percent
7- Reinjected
0
PRUDHOE 640150 ' 99.74%
LISBURNE 640144 0.00%
8. Flared or vented l hour or less
0
MIDNIGHTSUN 640158 0.26%
PT MCINTYRE 640160 0.00%
9. Flared or vented more Wan / hour (sea irisin)
194,364
10. Plot and Purge
62,326
11. Assist Gas
0
12. Fuel gas used in lease operations.
827,660
13. Other (see instructions)
Q
OIflCW Use /
Authorization hr:
iSafery
i -'
Lease Use
Conservation
MCF
14. TOTAL VOLUME (ITEMS 6-12)
1,084,350
MCF
15. NGL Gas Equivalent
0
MCF
-
18. Purchased gas
0
Waste:
MCF
17. Transferred from
0
18. Transferred to: (Express as a negative a) CGF
-72,235,198
Commissioner Date
19. Remarks:
I hereby certify that the foregoing is true and correct to the best of my knowledge.
Note: All volumes mustcorrected
Signature__ �,/�t �T_t :'t f ' V line Manager Production Taxes brio Royalties Alaska to pressure o/ 14.65 psisia and t0 a
nn temperature of 60o F. Authority 20
Printed Name Diane Colley Phone (907) 564-5775 Date L' ) AAC25.235.
Form 10422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE Submit in Duplicate
DATE
BP EXPLORATION )ALASKA) INC-
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
March 2013
Not required for unplanned events <=1 hr Not required for unplanned events <=1 hr
Unplanned Events greater than 1 hour
DATE TIME VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO ELIMINATE CAUSE
3/1-31/2013 0000-2400 187,827 See attachments See attachments
3/26/2013 1628-1810 6,537
TOTAL 194,364
DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO E
See attachments See attachments
TOTAL
Planned Events Exceeding 1 Hour OR > 5,000 mcf
DATE TIME VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO EUMINATE CAUSE
See attachments See attachments
TOTAL
TOTAL
Unplanned Events < 1 Hour 0
Unplanned Events> 1 Hour 194,364
Planned Events < 1 hour and not
exceeding 5,000 MCF
Planned Events > 1 hour or 0
exceeding 5,000 MCF
Pilot Purge 62,326
Assist n
TOTAL FLARED VOLUME 256,690
Page 6
4/10/2013
1:30 PM
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS
J GC 1 3. Field DISPOSITION
Dispositio
a
6. Sold PBU' WOA B4 Operator
BP 5
T. Reinjected
6. Flared or vented 1 hour or less
9. Flared or vented more than
1 hour (see Instr.)
10. Pilot and Purge
11. Assist Gas
12. Fuel gas used in lease operations
13. Other (see instructions)
14. TOTAL VOLUME (ITEMS 6-12)
15. NGL Gas Equivalent
6. Purchased gas
1. Transferred from:
i. Transferred to: (Express as a
negative k) CGF
Remarks:
Signature
Form 10-422 Rev 512009
MY
0
775,
1,197
-65.941
INSTRUCTIONS ON REVERSE SIDE
Commissioner
Use
rear of Dispos
list contribution o/ea April -2073
Tota/ Volume. Poo/ as a 1
Date
Note: All volumes must be corrected
to pressure of 14.65 Asia and to t
temperature of 601 F. Authority 20
n .---
INS rRUCTIONS
--_
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
April 2013
4/19/2013
VOLUME DESCRIPTIONOF INCIDECAUSE
1000-1100 NT &
1,862 Not required for unplanned events <= 1 hr
TOTAL 862
4/1-30/13 voLUME-DESCRIPR TION N
0000-2400
4/22/2013 0455-0915 350,310 See attachments
10,000
TOTAL
360,310
Not required for unplanned events <= 1 hr
See attachments
Page 8
TOTAL
wee attachments
p �
See attachments
TOTAL ----
Unplanned Events < 1 Hour
TOTAL
Unplanned Events >1,862
1 Hour
Planned Events < 1 hour
360,310
and not
exceeding 5,000 MCF
0
Planned Events> 1 hour or
exceeding 5,000 MCF
0
Pilot Purge
Assist
59,384
TOTAL FLARED VOLUME
0
421,556
See attachments
5/14/2013
10:22 AM
Flare Start Date 04/01/2013
Flare End Date 04/30/2013
Report
GC1 Flare Report
Total Volume (MSCF
Numbe System Date 1 382772
Start Time Stop Time Duration Intermittent Black Smoke Planned Re o
13-153 Flare Relief
04/01/2013 12:00:00 am 12:0000 am 1440 min yes P rted BY Volume
Determination Cause Valves leaking into the flare system No NO BPIISPRINGG 5470
Action Taken
-__ - Ops troublshooting what valves are leaking
13-158 -_—_.. _. ._.__ ._ __._ _
Flare Relief ' - -- --
04/02/2013 12:00:00 am 12:00:00 am 1440 min yes Daily Volume (MSCF) 5470
Determination Cause Valves leaking into the flare system No No BPIISPRINGG i C 2'
Action TakenG
Ops troubleshooting what valves are leaking
—�� --
13-158 Flare Relief 04/032013 Daily Volume (MSCF) l0 Z.f
12:00:00 am 12:00:00 am 1440 min yes TO
Determination Cause Valves leaking into the Flare system No N0BPIISPRINGG
5760
Action Taken
Ops troublshooting what valves are leaking
13-159 Flare Relief04/04/2013 12:00:00 am 4:00:00 am
Daily Volume (MSCF)
5760
240 min Yes No
Determination Cause Valves leaking into the flare
NO BPIISPRINGG
system
Action Taken
2290
_ _Ops troublshooting what valves are leaking
13-159 Flare Relief --------- ____..
04/042013 4:00:00 am
4:00:00 __
pm 720 min Yes
Determination Cause GC2-1HPtie-line S/D NO
------------
N0 BPIISPRINGG
___
0010
Action Taken Brought on GC2-1 HP tie
-line
13-159 Flare Relief--- -----___ __
04/04/2013 4:00:00 pm
12:00:00 am 480 min Yes No
Determination Cause Valves leaking into the
NO BP1tSPRINGG
flare system
1730
Action Taken Ops troublshoofing what
valves are leaking
13-161 Flare Relief�
04/052013 12:00:00 am 12:00:00 am 1440
-------'-------
Daily Volume (MSCF)
14030
min yes
Determination Cause Valves leaking into the flare system No
No BPIISPRINGG
ActionTaken Op__ troubIshoo_— what
4870
_ --S valves are leaking
13-162 Flare Relief04/062013 12:00:00 am 12:00:00
Volume (MSCF)
am 1440 min Yes No
Determination Cause Valves leaking into the flare
NO BPIISPRINGG
4870
system
Action Taken—
4490
Ops troublshooflng what valves are leaking
13-163 Flare Relief04/07/2013 12:00:00 am 12:00:00
Daily Volume (MSCF)
am 1440 min yes No
Determination Cause Valves leaking into the flare
NO BPIISPRINGG
4490
system
Action Taken
4180
Ops troublshootin
---____ 9 what valves are leaking
13-185 Flare Relief 04/062013 12:00:00 am 12:00:00
Daily Volume (MSCF)
am 1440 min yes No
Determination Cause Valves leaking into the flare
NO BPIISPRINGG
4180
system
Action Taken
_
5190
Ops troubishoofin 9 whet valves are leaking
13-186 Flare Relief 04/092013 12:0000 am 12:00:00 am
Daily Volume (MSCF) 5190
1440 min Yes No
Determination Cause Valves leaking into the flare
No BPIISPRINGG
system
5130
Genefated 05/07/2013 9:39:07AM
Page 7 of 12
Flare Start Date 04/01/2013
Flare End Date 04/3012013
Action Taken Ops troublshoohmg what valves are leaking
13-167Flare Relie( 04/10/2013 12:07:00 am 12:00:00 am 1439 min Yes Daily Volume (MSCF) 5130
Determination CaUSe Valves leaking into Flare system No N0 BPi\SPINKAJD 6490
Action Taken Operators are troubleshooting along with Maintenance
13-168Flare Relief 04/11/2013 12:00:00 am 12:00:00 am 1440 min Yes Daily Volume (MSCF) 6490
Determination Cause Valves leaking into the Flareheader No NO BPIVSPINKAJD 6410
Action Taken_ _ Work Order written and troubleshooting for souroe.
13-172 Flare Relief 04/72/2013 72:00:00 am 12:00:00 am 1440 min Yes Daily Volume (MSCF) 6410
Determination Cause Leaking valves into the Flare header
No NO BP715PINKAJD 8420
Action Taken Troubleshooting cause is ongoing.
13-175 Flare Relief 04/13/2073 12:00:00 am 12:00:00 am 1440 min yea
Determination Cause Valves leaking into the Flare header
Daily Volume (MSCF)
No NO BPIISPINKAJD
8420
8830
Action Taken _ Still looking for the source.
13-176 Flare Relief 04/14/2013 12:00:00 amDaily
72:00:00 am 7440 min Yes
Determination Cause Valves leaking into the Flare Heatley
Volume (MSCF)
No No BPIISPINKAJD
8830
6470
Action Taken Still looking for source.
73-178 Flare Relief 04/15/2013 12:00:00 am 12:00:00 am 1440 min Yes
Determination Cause Valves leaking into Flare header.
Daily Volume (MSCF)
No No BP7ISPINKAJD
6470
5520
Action Taken Sall seeking source.
13'176Flare Relief 04/16/2013 12:00:00 am 12:00:00 am 1440 min Yes Daily Volume (MSCF) 5520
No No BP7ISPINKAJD
Determination Cause Valves leaking into the Flare Header. 5750
Action Taken The hunt for the source continues.
13-180 Flare Relief 04/17/2013 12:01:00 am 11:59:00 pm 1438 min No Daily Volume (MSCF) 5750
No No BP7\MATTRR
Determination Cause Valves leaking into e gore heatler. 6288
M
Action Taken _ Searching to find the leaking valves.
13-187 Flare Relief 04/18/2013 12:07:00 am 11:59:00 pm 1438 min No Daily Volume (MSCF) 6268
Determination Cause Valves leaking into the flare system. No NO BP1\MATTRR 8640
Action Taken Continue looking for the leaking valves.
13-184Flare Relief 04/19/2013 12:07:00 am 11:59:001)m 1438 min No Daily Volume (MSCF) 6640
Determination Cause Valves leaking into the flare system. No NO BP1Vu1ATTRR
8446
Action Taken Troubleshooting which valves are leaking into the flare system.
Generated 05/07/2013 9:39:07AM
Page 8 of 12
--• ow wruv2013
Flare End Date 04/30/2013
13-186 Flare Relief 04/20/2013 12:00:00 am
12:00:OOam 1440 min Yes
Determination Cause Unknown valves leaking
No
into gave line.
Action Taken
No BpluwgTTRR
Trouble shooting trying to determine
18250
what valves are leaking bye.
13-790 Flare Relief_- -_--- � -
04/21/2013 12 :OO:OOam
- -
_-_-_-
Cause Unknown 72.00 00 am 1440 min yes
valves
Dail V (MSCF)
Y Volume MSCF) 78250
NoNo
leaking into flare lines.
Action Taken
BP11MgTTRR
Trouble shooting trying to track tl Ives what valves
25577
- are leaking by.
13-194Flare
Flaruselief 04/22/2013 12:00.00am 12:00:00am1440 min
Determination Cause
-----------5577
Volume (MSCF)
Unknown valvesDatly
Yes
leaking into flare lines.
25577
N° No
Action Taken Tracking tlown leaking
BP7IMATTRR 71800
flare valve.
13194
Flare Relief 04/22/2013 4:55:00 am
915:00 am 260 min NO
Determination Cause Flared oggas
No
transit line
Pressure due t° CGF losing Action Taken 9compressors.
5555-- - - Once gas rates were
No BPIIMAT7RR 10000
_ cut and stable fl
_
- _ _ - - arin 9 stoPPed.
3-202 Flare Relief- - --_-
04/23/2013 12:01:00
-- - _ --- -- S _ F -
sm 11:59:00 m
Determination Cause
P 1438 min No
- _ - - -
Daily Volume (USCF)
21600
Valves leaking into the flares No No
Action Taken system and Flaring due to low IP eP71MATTRR 38254
Ops trouble shootinggas rates
- -- -- -- 5 5555 5 what valves
are trying leaking and f f
--�____- ng to stabilize
gas rates
13-205 Flare Relief 04/24/2013
---'--- i to-u�---
12:00:00 am
Determination C 12:00:00 am lggp min
Cause
Daily Volume (MSCF)
Valves leaking into me flare No No
system
39254
and flaringNo
Action Taken due to low IF gas rates
-----..__ trouble shooting
BPIIKIRSCHW 30400
.Ops
what valves are leaking and trying to stabilize
gas rates
13-207 Flare Relief ----------5555__
04/25/2013
12:00:00 am 12:00:00 am
Determination Cause
1440 min No
Daily Volume (MSCF)
N°
Valves leaking into the flare system
30400
No
Action Taken
and flaring due to low, lP gas rates
--__ OPs trouble shooting
BPIIKIRSCHW 40600
- what valves are leaking andtrying
- -�_ to stabilize
gas rates
13-209 -�� --�
Flare Relief O412612013
72:00:00 am 12:00:00 am 1440 min No
Determination Cause
Daily Volume (M$CFj
Valves leaking into me flare No
system
No
and flaring due to low IP as
Action Taken 9 rates
OPs trouble shootin
--�-----_�-_g
BPIIKIRSCHW 74120
-14120
what valves am leaking and trying --___ ry g to stabilize gas rates
- 9
13-211 Flare Relief ----�---
04/27/2013
12:00:00 am12:00:00 am 7440 min
Dafly Volume (MSCF)
No
No
Valves leaking into the flare system
14120
No
and flaring due to low IP gas rates
Action Taken Ops trouble shooting
BPIIKIRSCHW 7830
whatva-- W and trying to stabilize
—ng
-----gas rates
73-215 Flare Relief5555
04/28/2013 12:00:00 am12:00
_
Determination Cause:00 am 7440 min Yes
Valves leaking into No
Daily Volume (MSCF) 7930
the Flares ystem
Action Taken
NO BPIISPRINGG
Ops troubl— sh—= o6ng=t valves are leaking
13580
13.217 Flare Relief 04/29/2013 12:00:00
am 12:00:00 am
Determination C 1440 min Yes
Cause Valves leaking into the No
Daily Volume (MSCF) 13580
flares
system
No BPIISPRINGG
Generated 05/07/2013 9:39:O7gM
12110
Page 9 of 12
McMains, Stephen E (DOA)
From:
AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent:
Saturday, April 06, 2013 8:31 AM
To:
McMains, Stephen E (DOA)
Cc:
Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GCI Facility OTL; AK, OPS GCI OSM; AK,
HSSEE Env Adv West
Subject:
Gas flaring events at GC1
To: Steve McMains, AOGCC
steve. mcmainsc@alaska.gov
CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
dave.robvaaalaska.gov victoria.ferousonnaalaska.gov
From: Kellie Okonek, GPB Production Optimization Team Leader
An intermittent flaring event has been ongoing at GCI due to valve leakage into the flare system, for which operations
continues to investigate the source of leaks:
at GC1 starting at 04/05/2013 00:00 and stopping at 04/06/2013 with a volume of 4870 (MSCF). The event lasted for 1440
minutes.
at GC1 starting at 04/04/2013 16:00 and stopping at 04/05/2013 with a volume of 1730 (MSCF). The event lasted for 480
minutes.
A flaring event occurred at GC1 starting at 04/04/2013 04:00 and stopping at 04/04/2013 16:00 with a volume of 10010
(MSCF). The event lasted for 720 minutes. The event had a volume greater than 5000 (MSCF), and was due to the GC2-
GC1 HP tie -line shutdown. Flaring stopped when the line was returned to service.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCCIEOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akoosocceoctl(@bo.com
McMains, Stephen E (DOA)
From:
AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent:
Thursday, April 11, 2013 12:04 PM
To:
McMains, Stephen E (DOA)
Cc:
Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
The event lasted for 1440
Arthur, Gregory, Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GCI OSM; AK,
HSSEE Env Adv West
Subject:
Gas flaring events at GC1
To: Steve McMains, AOGCC
steve.mcmainsno alaska.gov
CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
dave.robvaalaska.gov victoria.ferguson(c)alaska.gov
From: Kellie Okonek, GPB Production Optimization Team Leader
An intermittent flaring event has been ongoing at GC1 due to valve leakage into the flare system, for which operations
continues to investigate the source of leaks:
at GC1 starting at 04/10/2013 00:01 and stopping at 04/11/2013 with a volume of 6490 (MSCF).
The event lasted for 1439
minutes. The event had a volume greater than 5000 (MSCF).
at GC1 starting at 04/09/2013 00:00 and stopping at 04/10/2013 with a volume of 5130 (MSCF).
The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
at GC1 starting at 04/08/2013 00:00 and stopping at 04/09/2013 with a volume of 5190 (MSCF).
The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
at GC1 starting at 04/07/2013 00:00 and stopping at 04/08/2013 with a volume of 4180 (MSCF).
The event lasted for 1440
minutes.
at GC1 starting at 04/06/2013 00:00 and stopping at 04/07/2013 with a volume of 4490 (MSCF). The event lasted for 1440
minutes.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctiabp.com
McMains, Stephen E (DOA)
From:
AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent:
Tuesday, April 16, 2013 8:31 AM
To:
McMains, Stephen E (DOA)
Cc:
Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
The event lasted for 1440
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject:
Gas flaring events at GC1
To: Steve McMains, AOGCC
steve. mcmains(gbalaska.gov
CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
dave.roby(dalaska.gov victoria.ferguson(oalaska.gov
From: Kellie Okonek, GPB Production Optimization Team Leader
An intermittent flaring event has been ongoing at GC1 due to valve leakage into the flare system, for which operations
continues to investigate the source of leaks:
at GC1 starting at 04/15/2013 00:00 and stopping at 04/16/2013 with a volume of 5520 (MSCF).
The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
at GCI starting at 04/14/2013 00:00 and stopping at 04/15/2013 with a volume of 6470 (MSCF).
The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
at GC1 starting at 04/13/2013 00:00 and stopping at 04/14/2013 with a volume of 8830 (MSCF).
The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
at GC1 starting at 04/12/2013 00:00 and stopping at 04/13/2013 with a volume of 8420 (MSCF).
The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
at GC1 starting at 04/11/2013 00:00 and stopping at 04/12/2013 with a volume of 6410 (MSCF).
The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akoosocceoctl(cabo.com
From: A , TL
Sent: Thursday, April 11, PM
To: 'McMains, Stephen E (DOA)'
Cc: 'victoria.ferguson@alaska.gov';'dave.roby@a '• Casta ; Arthur, Gregory;
Kruger, Dale O; AK, OPS GCS Facility OTL; AK, OP SEE Env Adv West
Subject: Gas flaring events at G
mg event has been ongoing at GC1 due to valve leakage into the flare 'Sy' r which operations
to investigate the source of leaks:
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Tuesday, April 30, 2013 12:37 PM
To: McMains, Stephen E (DOA); Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject: Gas flaring events at GC1
To: Jennifer Hunt, AOGCC
ien n iter. h u nt(gDalaska. qov
CC: Dave Roby, AOGCC
dave. robyCoDalaska. qov
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria.ferguson(dalaska.gov
A flaring event occurred at GC1 starting at 04/17/2013 00:00 and stopping at 04/17/2013 24:00 with a volume of 6288
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 04/18/2013 00:00 and stopping at 04/18/2013 24:00 with a volume of 6640
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 04/19/2013 00:00 and stopping at 04/19/2013 24:00 with a volume of 8446
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 04/19/2013 10:00 and stopping at 04/19/2013 11:00 with a volume of 1862
(MSCF). The intermittent event lasted for 60 minutes. Flaring was due to the shutdown of B Bank on high pressure
Flaring continued while BV Bank was brought back online. Flaring ended when B Bank flare valves closed.
A flaring event occurred at GC1 starting at 04/20/2013 00:00 and stopping at 04/20/2013 24:00 with a volume of 18250
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 04/21/2013 00:00 and stopping at 04/21/2013 24:00 with a volume of 25577
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GCI starting at 04/22/2013 00:00 and stopping at 04/22/2013 24:00 with a volume of 11600
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 04/22/2013 04:55 and stopping at 04/22/2013 09:15 with a volume of 10000
(MSCF). The intermittent event lasted for 260 minutes. Flaring was due to the unplanned shutdown tandem compressors
at CGF resulting in high gas transit line pressure. Flaring continued while rate cuts were made to bring the gas transit line
pressure under control. Flaring ended when flare valves closed and sufficient rate cuts were completed.
A flaring event occurred at GC1 starting at 04/23/2013 00:00 and stopping at 04/23/2013 24:00 with a volume of 39254
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system and low LP/IP rates causing LP/IP system to intermittently flare rate
from associated vessels. Flaring continued into the following day as operations staff investigated the cause of the flaring
event and stabilize gas/oil rates.
A flaring event occurred at GC1 starting at 04/24/2013 00:00 and stopping at 04/24/2013 24:00 with a volume of 30400
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to low LP/IP rates causing LP/IP system to
intermittently flare rate from associated vessels. Flaring continued into the following day as operations staff worked to
stabilize gas/oil rates.
A flaring event occurred at GC1 starting at 04/25/2013 00:00 and stopping at 04/25/2013 24:00 with a volume of 40600
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to low LP/IP rates causing LP/IP system to
intermittently flare rate from associated vessels. Flaring continued into the following day as operations staff worked to
stabilize gas/oil rates.
A flaring event occurred at GC1 starting at 04/26/2013 00:00 and stopping at 04/26/2013 24:00 with a volume of 14120
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to low LP/IP rates causing LP/IP system to
intermittently flare rate from associated vessels. Flaring continued into the following day as operations staff worked to
stabilize gas/oil rates.
A flaring event occurred at GC1 starting at 04/27/2013 00:00 and stopping at 04/27/2013 24:00 with a volume of 7930
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to low LP/IP rates causing LPAP system to
intermittently flare rate from associated vessels. Flaring continued into the following day as operations staff worked to
stabilize gas/oil rates.
A flaring event occurred at GCI starting at 04/28/2013 00:00 and stopping at 04/28/2013 24:00 with a volume of 13580
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
A flaring event occurred at GC1 starting at 04/29/2013 00:00 and stopping at 04/29/2013 24:00 with a volume of 12110
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to suspected leaking flare valve or PSV
associated with the GLT system or other plant system. Flaring continued into the following day as operations staff
investigated the cause of the flaring event.
Please let me know if you have any questions.
Travis M. Rybicki
PCC•EOC (Production Optimization) ream Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
a koosocceoctl Ca) b o. com
Alternate: Kellie Okonek
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRomimm c,nc n1QDnc1T1l
1. Facility Number 2. Facility Name
0290000031 PBU GC 1
Disposition
3. Field
PBU - WOA
Volume MCF
4. Operator 5. MonthNear of Disposition
BP I May -2013
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
0
Pool Code Percent
7. Reinjected
0
640150 99.82/
640144 0.00%
8. Flared or vented 1 hour or less
3,490
SMIDNIGHTSUN640158 0.18%
640180 0.00%
9. Flared or vented more than 1 hour (see instr.)
54,290
10. Pilot and Purge
54,592
11. Assist Gas
0
12. Fuel gas used in lease operations.
729,046
13. Other (see instructions)
Official Use Only
Authorization >t hr:
Safety
-„
[� �t r
MCF
14. TOTAL VOLUME (ITEMS 6-12)
841,418
Lease Use
MCF
15. NGL Gas Equivalent
0
Conservation
MCF
16. Purchased gas
0
Waste:
MCF
17. Transferred from.
0
T� _3 _/ 1
Co missioner Date
18. Transferred to: (Express as a negative #) CGF
-66,222,544
19. Remarks:
I hereby certify that the foregoing is true and correct to the best of my knowledge.
b(Ji{ �I Note: All volumes must be corrected
Signature Title Mana er Production Taxes and R aloes Alaska to pressure of 14.65 psis and to a
temperature of 60o F. Authority 20
Printed Name Diane Colley Phone (907) 564-5775 Dat L3 AAC25.235.
Form 10-422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE Submit in Duplicate
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
May 2013
DATE
TIME
VOLUME
DESCRIPTION OF INCIDENT&CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
5/5/2013
0911-0916
350
Not required for unplanned events <= 1 hr
Not required for unplanned events <= 1 hr
5/6/2013
2350-2400
230
1501-1516
660
5/25/2013
1407-1419
600
Planned Events < 1 hour and not
1,620
5/25/2013
2016-2021
300
Planned Events> 1 hour or
5/26/2013
0937-0948
70
Pilot Purge
5/27/2013
1706-1708
40
0
5/27/2013
2105-2109
280
TOTAL
1,870
Unplanned Events greater than 1 hour
DATE
TIME
VOLUME
DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
5/1-7/13
0000-2400
45,310
See attachments
See attachments
5/22/2013
1645-2400
320
5/23-24-13
0000-2400
500
5/30/2013
0040-0540
2,760
TOTAL
48,890
DATE
TIME
VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO ELIMINATE CAUSE
5/3/2013
1547-1555
360 See attachments See attachments
5/15/2013
2100-2115
490
5/20/2013
0250-0330
110
5/28/2013
1501-1516
660
Unplanned Events> 1 Hour
TOTAL
1,620
5/5/2013
0200-0600
5,080 See attachments
5/16/2013
0300-0800
320
TOTAL
5,400
TOTAL
Unplanned Events < 1 Hour
1,870
Unplanned Events> 1 Hour
48,890
Planned Events < 1 hour and not
1,620
exceeding 5,000 MCF
Planned Events> 1 hour or
5,400
exceeding 5,000 MCF
Pilot Purge
54,592
Assist
0
TOTAL FLARED VOLUME
112,372
ACTION TAKEN TO E
See attachments
Page 8
6/13/2013
2:28 PM
Flare Start Date 05/01/2013
Flare End Date 05/31/2013
GC1 Flare Report
Total Volume (MSCF) 57780
Report
Numbs System Date StartTime Stop Time Duration Intermittent Black Smoke Planned Reported By Volume
13-219 Flare Relief 05/01/2013 12:00:00 am 12:00:00 am 1440 min Yes
Determination Cause Unidentified valves leaking into the flare system.
Action Taken Leaking valves not identified yet.
13-222 Flare Relief 05/02/2013 12:00:00 am 12:00:00 am 1440 min Yes
Determination Cause Valves leaking into the flare system
Action Taken Ops troublshooting what valves are leaking
No No BP1\SPRINGG 7120
No
13-225 Flare Relief 05/03/2013 12:00:00 am 12:00:00 am 1440 min
Yes
No
No BP1\SPRINGG
6040
Determination Cause Valves leaking into the flare system
Action Taken Ops troublshooting what valves are leaking
13-225 Flare Relief 05/03/2013 3:47:00 pm 3:55:00 pm 8 min
No
No
Yes BP1\HELMIGBJ
360
Determination Cause Depressured GILT 3300 to flare. Pressured up for Valve PM's.
Action Taken System depressured and flare valve closed.
13-229 Flare Relief 05/04/2013 12:00:00 am 12:00:00 am 1440 min
Yes
No
No BP1\SPRINGG
6120
Determination Cause Valves leaking Into the flare system
Action Taken Ops troublshooting what valves are leaking
13-230 Flare Relief 05/05/2013 12:00:00 am 12:00:00 am 1440 min
Yes
No
No BP1\SPRINGG
6820
Determination Cause Valves leaking into the flare system
Action Taken Ops troublshooting what valves are leaking
13-230 Flare Relief 05/05/2013 2:00:00 am 6:00:00 am 240 min
No
No
Yes BPI\BIFFERDL
5080
Determination Cause Depresuring E-45 from Pad forwork on line, to test separator.
Action Taken Shut flare valve and E-45 parimiter SID valve after line was down to zero presure so field could do their work.
13-235 Flare Relief 05/06/2013 12:00:00 am 12:00:00 am 1440 min Yes No No BPI\SPRINGG 5500
Determination Cause Valves leaking into the flare system
Action Taken Ops troublshoofing what valves are leaking
13-236 Flare Relief 05/07/2013 12:00:00 am 12:00:00 am 1440 min Yes No No BPI\SPRINGG 9070
Determination Cause Valves leaking into the flare system
Action Taken Ops troublshooting what valves are leaking
Generated 06/10/2013 9:22:50AM Page 10 of 14
Flare Start Date 05/01/2013
Flare End Date 05/31/2013
13-259 Flare Relief 05/15/2013 9:00:00 pm 9:15:00 pm 15 min No No Yes BPI\MATTRR 490
Determination Cause Flared during the Planned shutdown of K-7001.
Action Taken Flaring stopped when K-7001 train was depressured.
13-261 Flare Relief 05/16/2013 3:00:00 am 8:00:00 am 300 min No No Yes
Determination Cause Flared oft K-7001 coppus starting motor for turbine cool down.
Action Taken When turbine was cool, the starter motor was stopped and flaring stopped.
13-266 Flare Relief 05/20P2013 2:50:00 am 3:30:00 am 40 min No No Yes
Determination Cause Depressured"C" slugcatcher for maintaince.
Action Taken Flaring stopped when slugcatcher was depressured.
SP1\MATTRR 320
BP1\MATTRR 110
13-267 Flare Relief 05/22/2013 4:45:00 pm 12:00:00 am 435 min Yes No No BPI\HELMIGBJ 320
Determination Cause Skid 50 valve closure shutdown our shipping pumps. Flared off V-136 to maintain compressor operation.
Action Taken Flow rates re-established to the GC.
13-269 Flare Relief 05/23/2013 12:00:00 am 12:00:00 am 1440 min Yes
Determination Cause Valves leaking into the flare system.
Action Taken Leaking valves not identified yet.
No
Generated 06/10/2013 9:22:50AM Page 11 of 14
Flare Start Date 05/01/2013
Flare End Date 05/312013
13-268 Flare Relief 05/24/2013 12:00:00 am 12:00:00 am 1440 min Yes
Determination Cause Valves leaking into the flare system.
Action Taken z
No No BPI\SPRINGG 250
13-280 Flare Relief 05/28/2013 3:01:00 pm 3:16:00 pm 15 min No No Yes BPI\BIFFERDL 660
Determination Cause IP and LP compressor shut down to re -install breaker for emergency Generator E-103
Action Taken Equipment was restarted at 15:16 as soon as breaker was in. flare assist gas kept smoke down.
13-284 Flare Relief 05/30/2013 12:40:00 am 5:40:00 am 300 min Yes No No BPI\SPRINGG 2760
Determination Cause Using coppus FIG to cool down economizer
Action Taken closed FIG to coppus
Total Volume (MSCF) 57780
Generated 06/102013 9:22:50AM Page 12 of 14
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.comj
Sent: Monday, May 06, 2013 7:59 AM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GCI Facility OTL; AK, OPS GCI OSM; AK,
HSSEE Env Adv West; AK, OPS FS1 Facility OTL; AK, OPS FSI OSM; Burgess, David H;
AK, HSSEE Env Adv East
Subject: Gas flaring events at GC1 and FS1
To: Jennifer Hunt, AOGCC
[ennifer.hunt@alaska.gov
CC: Dave Roby, AOGCC
dave.roby@alaska.eov
From: Kellie Okonek, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria.fereuson@alaska.sov
An intermittent flaring event has been ongoing at GCI due to valve leakage into the flare system, for which
operations continues to investigate the source of leaks:
at GC1 starting at 05/05/2013 00:00 and stopping at 05/05/2013 19:55 with a volume of 6820 (MSCF). The
event lasted for 1195 minutes. The event had a volume greater than 5000 (MSCF).
at GC1 starting at 05/04/2013 00:00 and stopping at 05/05/2013 with a volume of 6120 (MSCF). The event
lasted for 1440 minutes. The event had a volume greater than 5000 (MSCF).
at GCI starting at 05/03/2013 00:00 and stopping at 05/03/2013 23:52 with a volume of 6040 (MSCF). The
event lasted for 1432 minutes. The event had a volume greater than 5000 (MSCF).
A flaring event occurred at GC1 starting at 05/05/2013 02:00 and stopping at 05/05/2013 06:00 with a volume
of 5080 (MSCF). The event lasted for 240 minutes. The event had a volume greater than 5000 (MSCF) and was
due to depressuring E-45 from E -pad for planned maintenance. Flaring stopped when line depressured.
A flaring event occurred at FSI starting at 05/03/2013 17:00 and stopping at 05/03/2013 18:15 with a volume
of 420 (MSCF). The event lasted for 75 minutes and was due to T/C 1801 shutdown due to valve issues.
Flaring stopped when the machine was restarted and loaded.
Please let me know if you have any questions.
Thanks,
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctlt7obp.com
Hunt, Jennifer L (DOA)
From:
AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent:
Friday, May 03, 2013 4:09 PM
To:
Hunt, Jennifer L (DOA)
Cc:
Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale 0; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West; AK, OPS FS1 Facility OTL; AK, OPS FS1 OSM; Burgess, David H;
AK, HSSEE Env Adv East
Subject:
Gas flaring events at GC1 and FS1
To: Jennifer Hunt, AOGCC
Tenn fifer. h untCa)alaska.gov
CC: Dave Roby, AOGCC
dave. robyealaska. gov
From: Kellie Okonek, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria.ferguson o�.alaska.gov
An intermittent flaring event has been ongoing at GC1 due to valve leakage into the flare system, for which operations
continues to investigate the source of leaks:
at GC1 starting at 05/02/2013 00:00 and stopping at 05/03/2013 with a volume of 4640 (MSCF). The event lasted for 1440
minutes.
at GCI starting at 05/01/2013 00:00 and stopping at 05/02/2013 with a volume of 7120 (MSCF). The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF)
at GC1 starting at 04/30/2013 00:00 and stopping at 05/01/2013 with a volume of 8265 (MSCF). The event lasted for 1440
minutes. The event had a volume greater than 5000 (MSCF).
A flaring event occurred at FS1 starting at 05/02/2013 07:40 and stopping at 05/02/2013 10:15 with a volume of 1076
(MSCF). The event lasted for 155 minutes and was due to STV/IP compressor s/d due to a solenoid issue on the IP
discharge. Flaring stopped when the problem was fixed and the compressor started and re -loaded.
Please let me know if you have any questions.
Thanks,
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctl()abp.com
Hunt, Jennifer L (DOA
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Thursday, May 30, 2013 10:39 AM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; AK, OPS FS3 OSM; AK, HSSEE Env Adv East; Burgess, David H; AK, OPS
FS3 Facility OTL; AK, OPS FS1 OSM; AK, OPS FS1 Facility OTL; AK, OPS CGF OTL; AK,
OPS CCP CGF OSM; AK, OPS GC1 OSM; AK, OPS GCI Facility OTL; Kruger, Dale O; AK,
HSSEE Env Adv West
Subject: Gas flaring event at FS1, FS3, CGF,
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
lennifer.huntaalaska.aov dave.roby(d)alaska.aov
victoria Ferguson aaalaska.gov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at GC1 starting at 05/30/2013 00:40 and stopping at 05/30/2013 05:40 with a volume of 2760
(MSCF). The event lasted for 300 minutes and was due to use of the copus F/G to cool down the economizer for
inspection on the LPS compressor.
A flaring event occurred at GC1 starting at 05/25/2013 14:07 and stopping at 05/25/2013 14:19 with a volume of 600
(MSCF). The event was a black smoke event and was due to LP/IP compressor sld for workon the emergency generator
breaker.
A flaring event occurred at GC1 starting at 05/24/2013 00:00 and stopping at 05/25/2013 with a volume of 250 (MSCF).
The event lasted for 1440 minutes and was due to valves leaking into the flare system.
A flaring event occurred at GC1 starting at 05/23/2013 00:00 and stopping at 05/24/2013 with a volume of 250 (MSCF).
The event lasted for 1440 minutes and was due to valves leaking into the flare system.
A flaring event occurred at GC1 starting at 05/22/2013 16:45 and stopping at 05/23/2013 with a volume of 320 (MSCF).
The event lasted for 435 minutes and was due to the skid50 valve closure which shut down the GC1 shipping pumps.
Flaring occurred to maintain compressor operation, and stopped when flow rates were re-established to the GC.
A flaring event occurred at CGF starting at 05/29/2013 15:35 and stopping at 05/29/2013 17:00 with a volume of 16847
(MSCF). The event lasted for 85 minutes. The event had a volume greater than 5000 (MSCF) and was due to shutdown
of 1805 T/C due to PCU glitch.
A flaring event occurred at CGF starting at 05129/2013 08:40 and stopping at 05/29/2013 11:00 with a volume of 16847
(MSCF). The event lasted for 140 minutes. The event had a volume greater than 5000 (MSCF) and was due to a
shutdown of 1855 T/C — flaring occurred while operations/maintenance worked to get the machine back online.
A flaring event occurred at FS3 starting at 05/29/2013 01:45 and stopping at 05/29/2013 03:55 with a volume of 875
(MSCF). The event lasted for 130 minutes and was due to 1806 T/C cooldown for planned maintenance. Flaring stopped
when cooldown was completed.
A flaring event occurred at FS1 starting at 05/26/2013 16:30 and stopping at 05/26/2013 16:31 with a volume of 83
(MSCF). The event was a black smoke event. Another event occurred at FS1 starting at 05/26/2013 16:11 and stopping
at 05/26/2013 16:13 with a volume of 168 (MSCF). The event was a black smoke event. A third event occurred at FS1
starting at 05/26/2013 15:51 and stopping at 05/26/2013 16:00 with a volume of 755 (MSCF). The event was a black
smoke event. These events were all related to the 1803 T/C water wash gas crank sequence, including attempts at the
crank sequence to investigate flare issues.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctlabp.com
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPnRiTinNI
1. Facility Number
0290000031
2. Facility Name
PBU GC 1
3, Field
PBU - WOA
4. Operator •5.
BP
Month/Year of Disposition
I June -2013
Disposition
Volume MCF
20. Forproduction from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
�
Pool Name Pool Code Percent
7. Reinjected
p
PRUDHOE 640150 99.55%
LISBURNE 640144 0.00%
8. Flared or vented 1 hour or less
670
MIDNIGHT SUN 640158 0.45%
PT MCINTYRE 640180 0.00%
9. Flared or vented more than 1 hour (see instr.)
3,130
10. Pilotand Purge
52,751
11. Assist Gas
12. Fuel gas used in lease operations.
693,615
13. Other (see instructions)
Official Use Only
Authorization >1 hr:
Safety
_� J7 v
MCF
14. TOTAL VOLUME (ITEMS 6-12)
750,166
Lease Use
MCF
15. NGL Gas Equivalent
0
Conservation
MCF
16. Purchased gas
0
Waste:
MCF
17. Transferred from:
G
Commissioner Date
18. Transferred to: (Express as a negative #) CGF
-59,792,019
19, Remarks:
I hereby certify that the foregoing is true and correct to the best of my knowledge.
AA—��`�� Note: All volumes must be corrected
Signature J cit Title Manager Production Taxes and Royalties Alaska to pressure of 14.65 psia and to a
a temperature of 60o F. Authority 20
Printed Name Diane Colley Phone (907) 564-5775 Date O AAC25.235.
/Z -F
WI M3
Form 10-422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE Submit in Duplicate
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
June 2013
jOnplanned Events less than or equal to 1 hour
DATE TIME VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO ELIMINATE CAUSE
6/12/2013 0014-0030 70 Not required for unplanned events <= 1 hr Not required for unplanned events <= 1 hr
TOTAL 70
6/8/2013
0000-2400
530 See attachments
See attachments
6/11/2013
0000-2400
40
6/14/2013
1015-1320
2,030
6/22/2013
1325-1647
130
6/28/2013
1630-1815
390
6/29/2013
1757-1910
10
TOTAL
3,130
Planned Events Less Than or Equal 1
Hour AND <= 5,000 mcf
DATE
TIME
VOLUME DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
6/1/2013
1645-1649
340 See attachments
See attachments
6/13/2013
1350-1415
190
6/14/2013
2050-2100
70
TOTAL
600
Planned Events
Exceeding 1 Hour OR
> 5.000 mcf
TOTAL
Unplanned Events < 1 Hour
Unplanned Events > 1 Hour
Planned Events < 1 hour and not
exceeding 5,000 MCF
Planned Events> 1 hour or
exceeding 5,000 MCF
Pilot Purge
Assist
TOTAL FLARED VOLUME
VVLUIVR ut]CKIP I IUN OF INCIDENT&CAUSE
See attachments
0
TOTAL
70
3,130
600
0
52,751
0
56,551
ACTION TAKEN TO I
See attachments
Page 6
7/16/2013
11:26 AM
Flare Start Date 06/01/2013
No
Flare End Date 06/30/2013
BPI\MATTRR
GC1 Flare Report
Total Volume (MSCF) 3800
Report
Numbs System Date Start Time Stop Time Duration Intermittent
Black Smoke Planned Reported By Volume
13-289 Controlled Slowdown 06/01/2013 4:45:00 pm 4:49:00 pm 4 min No
No Yes BPIUONESCC 340
Determination Cause Depressure K-51-3220 case for maintenance.
Action Taken Case @ 0 psig.
13-303 Controlled Slowdown 06/08/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No BP7\SPINKAJD 530
Determination Cause Taps slow, down. Starting to increase rates and we are bumping the flare
Action Taken Increasing rates and stabilizing the plant.
BP11WRINGG
13-313 Controlled Blowdown 06/11/2013 12:00:00 am 12:00:00 am 1440 min Yes
No No BP11SPINKAJD 40
Determination Cause Flaring during GILT startup, bringing on the second machine.
Action Taken Startup complete. Turbine starter exhausts to the flare system.
Action Taken completed testing and put back in service
13-318 Controlled Slowdown 06/13/2013 1:50:00 pm 2:15:00 pm 25 min No No Yes BPI\MATTRR 190
Determination Cause Flared to depressure K-7000 train during/after its planned shutdown.
Action Taken Flaring stopped when the process train was depressured.
13-323 Controlled Blowdown 06/14/2013 10:15:00 am 1:20:00 pm 185 min Yes No No BP1\MATTRR 2030
Determination Cause Flared off of V-136 and the HP first stages due to high transit gas line pressure.
Action Taken Flaring stopped when gas transit line pressure was returned to normal.
13-323 Controlled Blowdown 06/14/2013 8:50:00 pm 9:00:00 pm 10 min No
No
Yes
BPI\MATTRR
70
Determination Cause Flared of test bank first stage to switch to LP mode.
Action Taken Flaring stopped when test bank was at LP pressure.
13-333 Controlled Blowdown 06/22/2013 1:25:00 pm 4:57:00 pm 212 min Yes
No
No
BP11WRINGG
130
Determination Cause testing shutdowns on slugoatchers
Action Taken completed testing and put back in service
13-338 Controlled Blowdown 06/28/2013 4:30:00 pm 6:15:00 pm 105 min Yes
No
No
BP1\SPRINGG
390
Determination Cause V-136 Flaring /Little Alice online; blew -down GLT-3300 after S/D
Action Taken completed blowdown
13-339 Controlled Blowdown 06/29/2013 5:57:00 pm 7:10:00 pm 73 min Yes
No
No
BPI\SPRINGG
10
Determination Cause Start-up test for K-7000 /Spin coppus for cool down
Action Taken test complete -closed flare valve
Total Volume (MSCF)
3800
Generated 07/09/2013 4:10:03PM
Page 8 of 10
Hunt, Jennifer L DOA
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.comj
Sent: Saturday, June 08, 2013 3:17 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; AK, HSSEE Env Adv East; Burgess, David H; AK, OPS CGF OTL; AK, OPS
CCP CGF OSM; AK, OPS GCI Facility OTL; O'Riordan, Colm J; AK, OPS PCC EOC TL; AK,
OPS GC1 OSM; AK, OPS FS2 OSM; AK, OPS FS2 Facility OTL; AK, HSSEE Env Adv West;
AK, HSSEE Env Adv Central; AK, OPS GC3&PCC OSM; AK, OPS GC3 Facility & Field OTL;
AK, OPS FSI OSM; AK, OPS FSI Facility OTL
Subject: Gas flaring events at FS2, CGF, GC3, FS1
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
iennifer hunt(a)alaska.gov dave robv(o)alaska.gov victoria ferguson@alaska gov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at FS2 starting at 06/07/2013 07:00 and stopping at 06/07/2013 12:00 with a volume of 5545
(MSCF). The event lasted for 300 minutes. The event had a volume greater than 5000 (MSCF) and was due to
depressurization of the plant for a planned B -train isolation. Flaring stopped when depressurization was complete.
A flaring event occurred at CGF starting at 06/07/2013 10:52 and stopping at 06/07/2013 14:10 with a volume of 11518
(MSCF). The event lasted for 198 minutes. The event had a volume greater than 5000 (MSCF), and was due to 1855 MI
compressor shutdown. Flaring stopped when troubleshooting was complete and the compressor was re -loaded and
facility operations stabilized.
A flaring event occurred at CGF starting at 06/02/2013 18:32 and stopping at 06/02/2013 20:10 with a volume of 12410
(MSCF). The event lasted for 98 minutes. The event had a volume greater than 5000 (MSCF), and was due to shutdown
of T/C 1805 for planned maintenance to replace a failed vibration card. Flaring stopped when the card was replaced and
the T/C returned to service.
are now
ter
Previousrpessurre indicators showed 0 psighfor�the day and therefore understood
the eforre upport that noe the flaring
incorrect meter. The
ng occurred
flare header p
at GC1 starting at 05/13/2013 00:00 and stopping at 05/14/2013 with a volume of 0 (MSCF). The event lasted for 1440
minutes.
at GC1 starting at 05/12/2013 00:00 and stopping at 05/13/2013 with a volume of 0 (MSCF). The event lasted for 1440
minutes.
at GC1 starting at 05/11/2013 00:00 and stopping at 05/12/2013 with a volume of 0 (MSCF).
The event lasted for 1440
minutes.
at GC1 starting at 05/10/2013 00:00 and stopping at 05/11/2013 with a volume of 0 (MSCF).
The event lasted for 1440
minutes.
at GCI starting at 05/10/2013 00:00 and stopping at 05/11/2013 with a volume of 0 (MSCF).
The event lasted for 1440
minutes.
at GC1 starting at 05/09/2013 00:00 and stopping at 05/10/2013 with a volume of 0 (MSCF).
The event lasted for 1440
minutes.
at GC1 starting at 05/08/2013 00:01 and stopping at 05/09/2013 with a volume of 0 (MSCF). The event lasted for 1439
minutes.
A Flaring event occurred at GC3 starting at 06/07/2013 00:05 and stopping at 06/07/2013 09:00 with a volume of 2000
(MSCF). The event lasted for 535 minutes and was due to depressurization of the plant for planned TAR. Flaring stopped
when depressurization complete.
A flaring event occurred at FS1 starting at 06/01/2013 13:30 and stopping at 06/01/2013 16:00 with a volume of 834
(MSCF). The event lasted for 150 minutes and was due to shutdown of STV/IP 1802 compressor due to fuel gas knockout
drum high level. Flaring stopped when the compressor was re -loaded.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctlta7bp.com
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.comj
Sent: Sunday, June 23, 2013 6:02 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GCI OSM; AK,
HSSEE Env Adv West
Subject: Gas flaring events at GC1
To: Jennifer Hunt, AOGCC
iennifer. hunt(ccDalaska.gov
CC: Dave Roby, AOGCC
dave.robvCa alaska.gov
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria. ferguson (caalaska.gov
A flaring event occurred at GC1 starting at 06/08/2013 00:00 and stopping at 06/08/2013 24:00 with a volume of 530
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due low rates at GC1 during TAPS proration
resulting in intermittent flaring from the LP and IP systems. Flaring ended as rates were increased after proration was
over allowing the LP/IP systems to remain loaded.
A flaring event occurred at GC1 starting at 06/11/2013 00:00 and stopping at 06/11/2013 24:00 with a volume of 40
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due to flaring during startup of a GILT compressor,
starting turbine exhausts to flare system. Flaring ended when GLT startup was complete. Note: Suspect duration is over-
stated — however this is how event was reported.
A flaring event occurred at GC1 starting at 06/14/2013 10:15 and stopping at 06/14/2013 13:20 with a volume of 2030
(MSCF). The intermittent event lasted for 185 minutes. Flaring was due to flaring off of V-136 and HP 1st Stage
Separators due to high gas transit line pressure at GC1 resulting from a compressor shutdown at CGF. Flaring continued
while unit at CGF was restarted and transit gas pressure returned to normal operating range, at which time flare valves
closed.
A flaring event occurred at GC1 starting at 06/22/2013 13:25 and stopping at 06/22/2013 16:57 with a volume of 130
(MSCF). The intermittent event lasted for 212 minutes. Flaring was due to shutdown testing on GC1 Slug Catchers.
Flaring continued during testing. Flaring ended when testing was completed and flare valves closed.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-659-4472 (130C) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
a ko p s p cceo ct I tcD b p. c o m
Alternate: Kellie Okonek
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Sunday, July 07, 2013 6:18 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; AK, HSSEE Env Adv East; Burgess, David H; AK, OPS GC1 Facility OTL;
AK, OPS GC1 OSM; AK, OPS FS2 OSM; AK, OPS FS2 Facility OTL; AK, HSSEE Env Adv
West; AK, OPS GC3&PCC OSM; AK, OPS GC3 Facility & Field OTL; AK, OPS FS1 OSM;
AK, OPS FS1 Facility OTL; Kruger, Dale 0
Subject: Gas flaring events at GC1, GC3, FS1, FS2
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
iennifer.huntd)alaska.00v dave.robvaalaska.gov victoria.ferguson@.alaska.gov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at GC1 starting at 06/28/2013 16:30 and stopping at 06/28/2013 18:15 with a volume of 390
(MSCF). The event lasted for 105 minutes and was due to depressurization of spare GLT compressor when EOA Big AL
was loaded. Flaring stopped when depressurization was complete.
A flaring event occurred at GC1 starting at 06/29/2013 17:57 and stopping at 06/29/2013 19:10 with a volume of 10
(MSCF). The event lasted for 73 minutes and was due to start-up test for K-7000 and spin of coppus for cool down.
A flaring event occurred at GC1 starting at 07/05/2013 00:00 and stopping at 07/06/2013 with a volume of 40 (MSCF).
The event lasted for 1440 minutes and was due to flaring during GLT K3300 startup. Flaring stopped when startup
complete.
A flaring event occurred at GC3 starting at 06/29/2013 19:09 and stopping at 06/29/2013 20:10 with a volume of 551
(MSCF). The event lasted for 61 minutes and was due to LPS compressor s/d due to thermocouple deviations and V4
recycle valve UP failure. Flaring stopped when production was curtailed and compressor re -loaded after repairs complete.
A flaring event occurred at FS1 starting at 06/27/2013 20:35 and stopping at 06/27/2013 23:00 with a volume of 604
(MSCF). The event lasted for 145 minutes and was due to unloading of the 1802 STV/IP compressor due to high ambient
temps. Flaring stopped when the alternate 1801 compressor was loaded.
A flaring event occurred at FS1 starting at 06/28/2013 00:01 and stopping at 06/28/2013 01:26 with a volume of 354
(MSCF). The event lasted for 85 minutes and was due to unloading of the 1801 STV/IP compressor due to high ambient
temps. Flaring stopped when the alternate 1802 compressor was loaded..
A flaring event occurred at FS1 starting at 07/01/2013 16:35 and stopping at 07/01/2013 20:20 with a volume of 851
(MSCF). The event lasted for 225 minutes and was due to depressurization of DS12 for planned maintenance. Flaring
stopped when depressure complete.
A flaring event occurred at FS1 starting at 07/07/2013 09:50 and stopping at 07/07/2013 11:30 with a volume of 851
(MSCF). The event lasted for 100 minutes and was due to depressurization of 12-6 and 12-C commonlines for removal of
pig launcher and receiver.
A flaring event occurred at FS2 starting at 06/30/2013 00:54 and stopping at 06/30/2013 04:03 with a volume of 929
(MSCF). The event lasted for 189 minutes and was due to depressurization of A -HP, B -HP, MP & A -Treater Flash Drum
for A -train turnaround work. Flaring stopped when the HP oil trains were depressured.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (P80C)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akoosocceoctKbbo.com
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000031
2. Facility Name
PBU GC 1
3. Field
PBU - WOA
4. Operator
BP
5. Month/Year of Disposition
July -2013
Disposition
Volume MCF
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume,
6. Sold
0
Pool Name Pool Code Percent
7. Reinjected
U
PRUDHOE 640150 99.85%
LISBURNE 640144 0.00%
8. Flared or vented 1 hour or less
20
MIDNIGHT SUN 640158 0.15%
PT MCINTYRE 640180 0.00%
9. Flared or vented more than 1 hour (see instr.)
200
10. Pilot and Purge
54,974
11, Assist Gas
U
12. Fuel gas used in lease operations.
848,119
13. Other (see instructions)
0
Official Use Only
Authorization >t hr:
Safety
� OD
MCF
14. TOTAL VOLUME (ITEMS 6-12)
903,313
Lease Use
MCF
15. NGL Gas Equivalent
0
Conservation
MCF
16. Purchased gas
0
Waste:
MC F
17. Transferred from:
0
n
1
/ (Q
Commissioner Date
18. Transferred to: (Express as a negative #) CGF
-65,542,254
19. Remarks:
egoing i true to the best of my knowledge.
I hereby certify tGO,
Note: All volumes must be corrected
SignatureTitle Mana er Production Taxes and o 7ties Alaska to pressure of 14.65 psia and to a
// J L temperature of 60o F. Authority 20
7/4/3
Printed Name Diane ColleyPhone (907) 564-5775 Date 0 / 3 AAC25.235.
Form 10-422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE Submit in Duplicate
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
July 2013
Page 7
Unplanned Events less than or equal to 1 hour
DATE TIME VOLUME
DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
7/1/2013 1223-1225
20 Not required for unplanned events <= 1 hr
Not required for unplanned events <= 1 hr
TOTAL
20
Unplanned Events greater than 1 hour
DATE TIME VOLUME
DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
7/5/2013 0000-2400
40 See attachments
See attachments
TOTAL
40
Planned Events Less Than or Equal 1 Hour AND <= 5,000 mcf
DATE TIME VOLUME
DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
See attachments
See attachments
TOTAL 0
Planned Events Exceeding 1 Hour OR > 5,000 mcf
DATE TIME VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO ELIMINATE CAUSE
7/18/2013 0800-1600 160 See attachments See attachments
TOTAL 160
Unplanned Events < 1 Hour
Unplanned Events> 1 Hour
Planned Events < 1 hour and not
exceeding 5,000 MCF
Planned Events> 1 hour or
exceeding 5,000 MCF
Pilot Purge
Assist
TOTAL FLARED VOLUME
TOTAL
20
40
0
160
54,974
0
55,194
8/12/2013
2:34 PM
Flare StartDate 07/01/2013
Flare End Date 07/31/2013
GC1 Flare Report
Total Volume (MSCF) 220
Report
Numbe System Date StartTime Stop Time Duration Intermittent Black Smoke Planned Reported By Volume
13-347 Controlled Blowdown 07/05/2013 12:00:00 am 12:00:00 am 1440 min Yes No No BP7\SPINKAJD 40
Determination Cause Flared during 3300 GLT machine startup.
Action Taken Statup completed.
13-354 Controlled Blowdown 07/18/2013 8:00:00 am 4:00:00 pm 480 min No No Yes BP1\81FFERDL 160
Determination Cause Planned swapping out of LP and IP Compresors in gas Skid 19 for PM's
Action Taken Planned swaps, done as quirk as possible for techs. to do PM's
Total Volume (MSCF) 220
Generated 08/07/2013 11:29:06AM Page 9 of 11
Hunt Jennifer L (DOA)
From: AK, OPS PCC EOC TL (AKOPSPCCEOCTL@bp.com]
Sent: Sunday, July 07, 2013 6:18 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; AK, HSSEE Env Adv East; Burgess, David H; AK, OPS GC1 Facility OTL;
AK, OPS GC1 OSM; AK, OPS FS2 OSM; AK, OPS FS2 Facility OTL; AK, HSSEE Env Adv
West; AK, OPS GC3&PCC OSM; AK, OPS GC3 Facility & Field OTL; AK, OPS FS1 OSM;
AK, OPS FS1 Facility OTL; Kruger, Dale 0
Subject: Gas flaring events at GCI, GC3, FS1, FS2
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
iennifer.huntk@alaska.00v dave.roby(d )alaska.00v victoria ferouson(aa)alaska.gov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at GC1 starting at 06/28/2013 16:30 and stopping at 06/28/2013 18:15 with a volume of 390
(MSCF). The event lasted for 105 minutes and was due to depressurization of spare GLT compressor when EOA Big AL
was loaded. Flaring stopped when depressurization was complete.
A flaring event occurred at GC1 starting at 06/29/2013 17:57 and stopping at 06/29/2013 19:10 with a volume of 10
(MSCF). The event lasted for 73 minutes and was due to start-up test for K-7000 and spin of coppus for cool down.
A flaring event occurred at GC1 starting at 07/05/2013 00:00 and stopping at 07/06/2013 with a volume of 40 (MSCF).
The event lasted for 1440 minutes and was due to flaring during GLT K3300 startup. Flaring stopped when startup
complete.
A flaring event occurred at GC3 starting at 06/29/2013 19:09 and stopping at 06/29/2013 20:10 with a volume of 551
(MSCF). The event lasted for 61 minutes and was due to LPS compressor s/d due to thermocouple deviations and V4
recycle valve I/P failure. Flaring stopped when production was curtailed and compressor re -loaded after repairs complete.
A flaring event occurred at FS1 starting at 06/27/2013 20:35 and stopping at 06/27/2013 23:00 with a volume of 604
(MSCF). The event lasted for 145 minutes and was due to unloading of the 1802 STV/IP compressor due to high ambient
temps. Flaring stopped when the alternate 1801 compressor was loaded.
A flaring event occurred at FS1 starting at 06/28/2013 00:01 and stopping at 06/28/2013 01:26 with a volume of 354
(MSCF). The event lasted for 85 minutes and was due to unloading of the 1801 STV/IP compressor due to high ambient
temps. Flaring stopped when the alternate 1802 compressor was loaded..
A flaring event occurred at FS1 starting at 07/01/2013 16:35 and stopping at 07/01/2013 20:20 with a volume of 851
(MSCF). The event lasted for 225 minutes and was due to depressurization of DS12 for planned maintenance. Flaring
stopped when depressure complete.
A flaring event occurred at FS1 starting at 07/07/2013 09:50 and stopping at 07/07/2013 11:30 with a volume of 851
(MSCF). The event lasted for 100 minutes and was due to depressurization of 12-B and 12-C commonlines for removal of
pig launcher and receiver.
A flaring event occurred at FS2 starting at 06/30/2013 00:54 and stopping at 06/30/2013 04:03 with a volume of 929
(MSCF). The event lasted for 189 minutes and was due to depressurization of A -HP, B -HP, MP & A -Treater Flash Drum
for A -train turnaround work. Flaring stopped when the HP oil trains were depressured.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCCIEOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctl0bp.com
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRMI irFn r_ec niconerrinki
1. Facility Number 2. Facility Name
0290000031 PBU GC 1
Disposition
3. Field
PBU - WOA
Volume MCF
. %Pli I O.J .
4. Operator 5. Month/Year of Disposition
BP Au ust-2013
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
0
Pool Name Pool Code Percent
7. Reinjected
0
PRUDHOE 640150 99.82%
LISBURNE 640144 0.00%
8. Flared or vented hour or less
2,550
MIDNIGHT SUN 640158 0.18%
PT MCINTVRE 640180 0.00%
9. Flared or vented more than 1 hour (see mstr.)
82,231
10. Pilot and Purge
54701
11, Assist Gas
O
12. Fuel gas used in lease operations.
593,655
13. Other (see instructions)
0Official
Use Only
Authorization >1 hr:
Safety
92,7 3 1
/
MCF
14. TOTAL VOLUME (ITEMS 6-12)
733,137
Lease Use
MCF
15. NGL Gas Equivalent
0
Conservation
MCF
16. Purchased gas
Waste:
MCF
17. Transferred from:
O
� � —
Commissioner Date
18. Transferred to: (Express as a negative #) CGF
-54,779,207
19. Remarks:
hereby certify that A (th�e foregoing is true and correct to the best of my knowledge.
C //G1 ' Uq Note: All volumes must be corrected
Signature Title Mana er Production Taxes and Ro. aloes Alaska to pressure of 14.65 psis and to a
Printed Name Diane Colley I i J temperature of 60o F. Authority 20
Phone (907) 564-5775 Date AAC25.235.
VL/—
G/3114
Form 10-422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE
Submit in Duplicate
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT -GC -1
GAS FLARING INCIDENT REPORT
August 2013
8/4/2013
1810-1812
20 Not required for unplanned events <=1 hr Not required for unplanned events <= 1 hr
8/4/2013
2027-2034
45
8/5/2013
0952-0959
45
8/15/2013
2223-2225
10
8/17/2013
1238-1244
110
8/17/2013
1238-1240
60
8/18/2013
1849-1917
650
8/24/2013
1315-1332
300
8/26/2013
0945-0950
40
8/27/2013
0725-0735
280
8/27/2013
2140-2155
320
VOLUME DESCRIPTION OF INCIDENT&CAUSE
TOTAL
1,880
8/6/2013
0111-2359
-----
165 See attachments
n..,,yh,v CWV>L
See..vatt..achmcnents C.......
8/9-14/13
0330.2400
70,700
670
8/16-17/2013
0000-2358
750
1,490
8/23/2013
1945-2400
980
54,701
8/24/2013
0024-2052
7,826
139,482
8/26/2013
1105-1635
320
TOTAL
80,741
Planned Events Less Than or Equal 1
Hour AND <= 5,000 mcf
DATE
8/2/2013
TIME
1654-1704
VOLUME DESCRIPTION OF INCIDENT&CAUSE
ACTION TAKENTO ELIMINATE CAUSE
20 See attachments
See attachments
8/8/2013
0145-0153
70
8/8/2013
0405-0420
280
8/18/2013
0941-0955
300
TOTAL
670
8/8/2013 1050-2400 1,190 See attachments - See attachments
8/11/2013 1930-2035 300
TOTAL 1,490
Page 6
9/12/2013
3:32 PM
TOTAL
Unplanned Events <1 Hour
1,880
Unplanned Events> 1 Hour
80,741
Planned Events< I hour and not
670
exceeding 5,000 MCF
Planned Events > 1 hour or
1,490
exceeding 5,000 MCF
Pilot Purge
54,701
Assist
0
TOTAL FLARED VOLUME
139,482
Page 6
9/12/2013
3:32 PM
Flare StartDate 08/01/2013
Flare End Date 08/31/2013
GCI Flare Report
Total Volume (MSCF) 84781
Report
Numbs System Date Start Time Stop Time Duration Intermittent Black Smoke Planned Reported By Volume
13-381 Other 08/02/2013 4:54:00 pm 5:04:00 pm 10 min No No Yes BPIUONESCC 20
Determination Cause Start-up K-01-7001.
Action Taken Sustained fire achieved.
13-392 Flare Relief 08/06/2013 1:11:00 am 11:59:00 pm 1368 min Yes No No BMJONESCC 165
Determination Cause Low oil rate through Annex due to GC -2 Tie -line / J -pad shutdown & low gas to LP compressors resulting in LP gas flaring for 27 minutes.
Action Taken Oil rates increased through Annex.
13-394 Flare Relief 08/08/2013 1:45:00 am 1:5300 am 8 min
No
No
Yes
BP1\HELMIGBJ
70
Determination Cause Flared from test bank to switch from HP mode to LP mode for
well testing.
Action Taken Test bank pressure at set point for LP testing.
13-394 Flare Relief 08/08/2013 4:05:00 am 4:20:00 am 15 min
No
No
Yes
MP HELMIGBJ
280
Determination Cause Depressumd GLT 3200 to the flare for maintenance repairs.
Action Taken Depressuring complete.
13-394 Flare Relief 08/08/2013 10:50:00 am 12:00:00 am 790 min
No
No
Yes
BP1\HELMIGBJ
1190
Determination Cause Depressured GLT header through B slugcatcher for maintenance
Action Taken Job complete.
13-399 Flare Relief 08/09/2013 3:30:00 am 12:00:00 am 1230 min
No
No
No
BP1\HELMIGBJ
10700
Determination Cause Annex shutdown at 0330 for SSR. Flared off V-136 due to lack
of IP gas.
Action Taken Will continue while the Annex is down.
13-400 Flare Relief 08/10/2013 12:00:00 am 12:00:00 am 1440 min
No
No
No
BP7\HELMIGBJ
12000
Determination Cause Flared off V-136 due to low gas rates while the Annex is down.
Action Taken Annex to remain down for SSR cutover.
13-402 Flare Relief 08/11/2013 12:00:00 am 12:00:00 am 1440 min
No
No
No
BPI\HELMIGBJ
12000
Determination Cause Flared off V-136 due to low gas rates while the Annex is down.
Action Taken Annex remains down for SSR cutover.
Generated 09/04/2013 10:13:15AM
Page 7 of 12
Flare Start Date 08/01/2013
Flare End Date 08/31/2013
13402 Flare Relief 08/11/2013 7:30:00 pm 8:35:00 pm 65 min
No
No
Yes
BP1\HELMIGBJ
300
Determination Cause Depressured C slugcatcher for maintenance.
Action Taken Depressuring complete. Flare valve closed.
13-404 Flare Relief 08/12/2013 12:00:00 am 12:00:00 am 1440 min
No
No
No
BPI\HELMIGBJ
12000
Determination Cause Flared off V-136 due to low gas rates while the Annex is down.
Action Taken Annex remains dawn for SSR cutover work.
13-409 Flare Relief 08/13/2013 120000am 120000am 1440min
No
No
No
BP1\HELMIGBJ
12000
Determination Cause Flared off V-136 due to low gas rates while the Annex is down.
Action Taken Annex is still down.
13-110 Flare Relief 08/14/2013 12:00:00 am 12:00:00 am 1440 min
No
No
No
BPI\SPRINGG
12000
Determination Cause Flared off V-136 due to IoW gas rates while the Annex is down.
Action Taken Annex is still down.
13-417 Flare Relief 08/16/2013 12:00:00 am 1200:00 am 1440 min Yes
Determination Cause V-136 flaring due to swinging oil rates
Action Taken waiting for stable oil rates
13-415 Flare Relief 08/17/2013 12:00:00 am 11:58:00 pm 1438 min Yes
Determination Cause V-136 flaring due to swinging oil rates
Action Taken waiting for stable oil rates
No No BP1\SPRINGG 500
No
13-419 Flare Relief 06/18/2013 9:41:00 am 9:55:00 am 14 min No No Yes BP1\8IFFERDL 300
Determination Cause Flared when eleckican had to installed breaker on AHOA-01,0075 after working on it knocked down the LP and IP Compresors in gas plant
Action Taken Started Compressors back up as soon as breaker was installed.
13-431 Flare Relief 08/23/2013 7:45:00 pm 12:00:00 am 255 min Yes No No BP1\SPRINGG 980
Generated 09/04/2013 10:13:15AM Page 8 of 12
Flare Start Date 08/01/2013
Flare End Date 08131/2013
Determination Cause Flaring due to GT1-3 line lift
Action Taken flaring continuing
13-434 Flare Relief 08/24/2013 12:24:00 am 8:52:00 pm 1228 min Yes No No BP1\SPRINGG 7826
Determination Cause Flaring due to GTI -3 line lift 3n1 stage flare #3 open
Action Taken flaring continued
13-439 Flare Relief 08/26/2013 11:05:00 am 4:35:00 pm 330 min No No No BP1\SPRINGG 320
Determination Cause Swapping GLT machines for 1-12owashes
Action Taken H2o washes complete
Total Volume (MSCF) 84781
Generated 09/04/2013 10:13:16AM Page 9 of 12
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Sunday, August 18, 2013 3:41 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject: Gas flaring events at GC1
To: Jennifer Hunt, AOGCC
ie n niter. h unt(cilalaska. aov
CC: Dave Roby, AOGCC
dave.roby a.alaska.aov
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria.ferg usonoalaska.gov
A flaring event occurred at GCI starting at 08/06/2013 01:11 and stopping at 08/06/2013 23:59 with a volume of 165
(MSCF). The intermittent event lasted for 1368 minutes. Flaring was due low rates at GC1 in the Annex during GC2 plant
outage resulting in intermittent flaring from the LP and IP systems. Flaring ended as rates were increased in the Annex
allowing the LP/IP systems to remain loaded.
A flaring event occurred at GC1 starting at 08/08/2013 10:50 and stopping at 08/08/2013 24:00 with a volume of 1190
(MSCF). The event lasted for 790 minutes. Flaring was due to flaring during the planned depressuring of the WOA GLT
supply line for planned inspection work. Flaring continued while the GLT line was depressured via B Slugcatcher. Flaring
ended when the GLT line was depressured to required state and flare valves closed.
A flaring event occurred at GC1 starting at 08/09/2013 03:30 and stopping at 08/09/2013 24:00 with a volume of 10700
(MSCF). The event lasted for 1230 minutes. Flaring was due to the planned shutdown of the GC1 Annex system for SSR
project work. Flaring from the LP and IP systems occurred intermittently due to low total oil throughput at GC1 with the
Annex down. Flaring continued into the following day.
A flaring event occurred at GC1 starting at 08/10/2013 00:00 and stopping at 08/10/2013 24:00 with a volume of 12000
(MSCF). The event lasted for 1440 minutes. Flaring was due to the planned shutdown of the GC1 Annex system for SSR
project work. Flaring from the LP and IP systems occurred intermittently due to low total oil throughput at GC1 with the
Annex down. Flaring continued into the following day.
A flaring event occurred at GC1 starting at 08/11/2013 00:00 and stopping at 08/11/2013 24:00 with a volume of 12000
(MSCF). The event lasted for 1440 minutes. Flaring was due to the planned shutdown of the GCI Annex system for SSR
project work. Flaring from the LP and IP systems occurred intermittently due to low total oil throughput at GC1 with the
Annex down. Flaring continued into the following day.
A flaring event occurred at GC1 starting at 08/11/2013 19:30 and stopping at 08/11/2013 20:35 with a volume of 300
(MSCF). The event lasted for 65 minutes. Flaring was due to the planned shutdown of the C Slugcatcher for planned
maintenance. Flaring continued while the C Slugcatcher was depressured for the planned work. Flaring ended when the
C Slugcatcher was depressured and the flare valves closed.
A flaring event occurred at GC1 starting at 08/12/2013 00:00 and stopping at 08/12/2013 24:00 with a volume of 12000
(MSCF). The event lasted for 1440 minutes. Flaring was due to the planned shutdown of the GC1 Annex system for SSR
project work. Flaring from the LP and IP systems occurred intermittently due to low total oil throughput at GC1 with the
Annex down. Flaring continued into the following day.
A flaring event occurred at GC1 starting at 08/13/2013 00:00 and stopping at 08/13/2013 24:00 with a volume of 12000
(MSCF). The event lasted for 1440 minutes. Flaring was due to the planned shutdown of the GC1 Annex system for SSR
project work. Flaring from the LP and IP systems occurred intermittently due to low total oil throughput at GC1 with the
Annex down. Flaring continued into the following day.
A flaring event occurred at GC1 starting at 08/14/2013 00:00 and stopping at 08/14/2013 24:00 with a volume of 12000
(MSCF). The event lasted for 1440 minutes. Flaring was due to the planned shutdown of the GC1 Annex system for SSR
project work. Flaring from the LP and IP systems occurred intermittently due to low total oil throughput at GC1 with the
Annex down. Flaring ended when the GC1 Annex was brought back online, rate increased and the flare valves closed.
A flaring event occurred at GCI starting at 08/16/2013 00:00 and stopping at 08/16/2013 24:00 with a volume of 500
(MSCF). The intermittent event lasted for 1440 minutes. Flaring was due low rates at GC1 due to swinging production
rates resulting in intermittent flaring from the LP and IP systems. Flaring continued into the following day.
A flaring event occurred at GC1 starting at 08/17/2013 00:00 and stopping at 08/17/2013 23:58 with a volume of 250
(MSCF). The intermittent event lasted for 1438 minutes. Flaring was due low rates at GCI due to swinging production
rates resulting in intermittent flaring from the LP and IP systems. Flaring ended as rates were increased in the Annex
allowing the LP/IP systems to remain loaded.
Please let me know if you have any questions
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
akops pcceoctl (7 b O. co m
Alternate: Kellie Okonek
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.comj
Sent: Sunday, August 25, 2013 11:06 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GCI Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West; AK, OPS GC2 Facility OTL; AK, OPS GC2 OSM; AK, OPS GC3
Facility & Field OTL; AK, OPS GC3&PCC OSM; AK, OPS FS3 OSM; AK, OPS FS3 Facility
OTL; Burgess, David H; AK, HSSEE Env Adv East
Subject: Gas flaring events at GCI, GC2, GC3, FS3
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson, AOGCC
1ennifer.hunt6dalaska.gov dave.robv(a)alaska.gov victoria.ferguson(g)alaska.gov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at GC2 starting at 08/25/2013 00:00 and stopping at 08/25/2013 13:00 with a volume of 7583
(MSCF). The event lasted for 780 minutes. The event had a volume greater than 5000 (MSCF) and was due to flaring off
the LPS compressors as the transit system pressure came up during startup of gas lifted rate.
A flaring event occurred at GC2 starting at 08/24/2013 13:24 and stopping at 08/25/2013 with a volume of 6448 (MSCF).
The event lasted for 636 minutes. The event had a volume greater than 5000 (MSCF) and was due to flaring off the IP/LP
compressors for operational stability as GILT was ramping back up.
A flaring event occurred at GC1 starting at 08/24/2013 00:24 and stopping at 08/24/2013 20:52 with a volume of 7826
(MSCF). The event lasted for 1228 minutes. The event had a volume greater than 5000 (MSCF) and was due to final
depressurization of the GT -13 for planned inspections.
A flaring event occurred at GC1 starting at 08/23/2013 19:45 and stopping at 08/24/2013 with a volume of 980 (MSCF).
The event lasted for 255 minutes and was due to depressurization of the GT -13 line for planned inspections.
A flaring event occurred at GC3 starting at 08/24/2013 00:00 and stopping at 08/24/2013 15:30 with a volume of 2000
(MSCF). The event lasted for 930 minutes and was due to depressurization of GT -13 for planned inspections. Flaring
stopped when pressure reduced to below 250 psig.
A flaring event occurred at FS3 starting at 08/20/2013 13:00 and stopping at 08/20/2013 14:22 with a volume of 342
(MSCF). The event lasted for 82 minutes and was due to STV/IP compressor 1801 having operational issues. Flaring
stopped when operations switched to 1802.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akogsocceoctiabp.com
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT (IF PPr)ni lrcn rnnc
Form 10-422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE
0/3/1
Submit in Duplicate
9/8/2013
9/10/2013
9/13/2013
9/14/2013
9/15/2013
9/19/2013
9/20/2013
9/23/2013
9/28/2013
9/2/2013
9/6/2013
9/7/2013
9/5/2013
9/5/2013
9/16/2013
9/18/2013
1302-1306
0600-0610
0722-0729
1028-1031
1424-1426
1600-1612
2245-2250
0410-0417
1449-1506
TOTAL
1502-2359
1330-1650
1500-2300
TOTAL
1307-1315
1551-1600
TOTAL
0300-2230
0220-1500
TOTAL
Unplanned Events <1 Hour
Unplanned Events> 1 Hour
Planned Events <1 hour and not
exceeding 5,000 MCF
Planned Events > 1 hour or
exceeding 5,000 MCF
Pilot Purge
Assist
TOTAL FLARED VOLUME
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
September 2013
30 Not required for unplanned events <= 1 hr
240
120
150
40
60
20
290
320
1,270
560 See attachments
160
240
960
110 See attachments
240
350
6,070 See attachments
220
6,290
TOTAL
1,270
960
350
6,290
53,968
0
62,838
Not required for unplanned events <= 1 hr
See attachments
See attachments
See attachments
Page 7
10/11/2013
8:58 AM
Flare StartDate 09/01/2013
Flare End Date 09/30/2013
GCI Flare Report Total Volume (MSCF) 8670
Report
Numbe System Date StartTime Stop Time Duration Intermittent Black Smoke Planned Reported By Volume
13-442 Flare Relief 09/02/2013 3:02:00 pm 11:59:00 pm 537 min Yes No No BP1\MAT rRR 560
Determination Cause Flaring off of the IP compressor due to low IP gas rates from "D" bank.
Action Taken Supplying more IP and LP gas rates from other banks.
13-444 Flare Relief 09/05/2013 1:07:00 on 1:15:00 pm 8 min No No Yes BPI\MATTRR 110
Determination Cause Flaring off the starter motor for K-3300 start-up.
Action Taken Flaring stopped when K-3300 was started.
13-444 Flare Relief 09/05/2013 3:51:00 pm 4:00:00 pm 9 min No No Yes BP1\MATTRR 240
Determination Cause Flaring to depressurize K-3200 after it was shut down.
Action Taken Flaring stopped when K-3200 was depressured.
13-447 Flare Relief 09/06/2013 1:30:00 pm 4:50:00 pm 200 min Yes No No BPITISHERCD 160
Determination Cause Extended Baring event occurred while awaiting GC operator/maintenance evaluation. Flaring from V-136 due to inadequate amount of IP gas
to load compressor K-108
Action Taken No response taken as this was deemed to be of short duration. Piping repairs in Sk-525 ongoing in order load IP gas system
13A48 Flare Relief 09/07/2013 3:00:00 pm 11:00:00 pm 480 min Yes No No BPITUELMO 240
Determination Cause Flaring intermittently off of V-136 because our Annex to "D" bank 2nd stage being out of service do to leak.
Action Taken Get Annex to "D" 2nd stage back in service.
13-465 Flare Relief 09/16/2013 3:00:00 am 10:30:00 pm 1170 min No No Yes BP7\HELMIGBJ 6070
Generated 10/02/2013 9:20:43AM Page 7 of 10
Flare Start Date 09/01/2013
Flare End Date 09/302013
Determination Cause Flared off V-136 and GT -13 to aid in depressudng GT -13 for line lift.
Action Taken Work completed and K-108 back in service.
13-472 Flare Relief 09/182013 2:20:00 am 3:00:00 pm 760 min No No
Determination Cause Schedualed water wash on LPS Compresor K7001
Action Taken Finished planned water wash on K7001
Yes BP10FFERDL 220
Total Volume (MSCF) 8870
Generated 10/022013 9:20:43AM Page 8 of 10
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Sunday, September 01, 2013 2:31 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West; AK, OPS FS3 OSM; AK, OPS FS3 Facility OTL; Burgess, David H;
AK, HSSEE Env Adv East; AK, OPS FS2 Facility OTL; AK, OPS FS2 OSM
Subject: Gas flaring events aWFS2, FS3
To: Jennifer Hunt, AOGCC
iennifer.huntla alaskgM
CC: Dave Roby, AOGCC
dave. robv(ccilalaska. qov
From: Kellie Okonek, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria.fergusona-alaska qov
A flaring event occurred at FS2 starting at 08/31/2013 15:31 and stopping at 08/31/2013 17:50 with a volume of 18
(MSCF). The event lasted for 139 minutes and was due to depressurization of 16D commonline for planned removal of
temporary pigging facilities. Flaring stopped when depressurization complete.
A flaring event occurred at GC1 starting at 08/26/2013 11:05 and stopping at 08/26/2013 16:35 with a volume of 320
(MSCF). The event lasted for 330 minutes and was due to swapping of GLT machines for water washes. Flaring stopped
when water washes complete.
A flaring event occurred at FS3 starting at 08/26/2013 14:50 and stopping at 08/26/2013 15:45 with a volume of 9329
(MSCF). The event was a black smoke event. The event had a volume greater than 5000 (MSCF) and was due to a
power outage that caused loss of T/C's 1801, 1803, & 1806 in addition to the water section, regens shipping pump, etc.
Flaring stopped when the turbine/compressors were started and re -loaded after getting generator power established.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctI(gDbp.com
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Tuesday, September 17, 2013 9:31 AM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject: Gas flaring events atm
To: Jennifer Hunt, AOGCC
4ennifer. h unt(aalaska.gov
CC: Dave Roby, AOGCC
dave. robv(acl�.alaska.gov
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria.ferouson(a)alaska oov
A flaring event occurred at GC1 starting at 09/02/2013 15:02 and stopping at 09/02/2013 24:00 with a volume of 560
(MSCF). The intermittent event lasted for 538 minutes and was due to flaring off the IP Compressor due to low oil rates.
Flaring stopped when sufficient load was available for the IP Compressor.
A flaring event occurred at GC1 starting at 09/06/2013 13:30 and stopping at 09/06/2013 16:50 with a volume of 160
(MSCF). The intermittent event lasted for 200 minutes and was due to flaring off the IP Compressor due to low oil rates
associated with D Bank 2 n Stage vessel unavailability. Flaring stopped when sufficient load was available for the IP
Compressor.
A flaring event occurred at GCI starting at 09/07/2013 15:00 and stopping at 09/07/2013 23:00 with a volume of 240
(MSCF). The intermittent event lasted for 480 minutes and was due to flaring off the IP Compressor due to low oil rates
associated with D Bank 2 n Stage vessel unavailability. Flaring stopped when sufficient load was available for the IP
Compressor.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 * 1890
akoosocceoctl(a)bp.com
Alternate: Kellie Okonek
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akoospcceoctl(abp.com
Hunt, Jennifer L (DOA
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Wednesday, September 25, 2013 10:49 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GCI Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West; AK, OPS GC3 Facility & Field OTL; AK, OPS GC3&PCC OSM; AK,
OPS FS3 OSM; AK, OPS FS3 Facility OTL; Burgess, David H; AK, HSSEE Env Adv East; AK,
OPS PCC EOC TL; AK OPS FS2 OSM; AK, OPS FS2 Facility OTL
Subject: Gas flaring events at*M, GC3, FS2, FS3
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson,
AOGCC
iennifer.hunt( alaska.00v dave.robvaalaska oov
victoria.ferousona-alaska oov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at FS2 starting at 09/24/2013 01:00 and stopping at 09/24/2013 03:00 with a volume of 214
(MSCF). The event lasted for 120 minutes, and was due to depressurization of 9A commonline for repairs. Flaring
stopped when line depressured.
A flaring event occurred at FS2 starting at 09/23/2013 20:30 and stopping at 09/23/2013 23:30 with a volume of 479
(MSCF). The event lasted for 180 minutes, and was due to DS9E commonline coming down to swap blinds.
A flaring event occurred at FS3 starting at 09/22/2013 14:20 and stopping at 09/22/2013 15:40 with a volume of 60
(MSCF). The event lasted for 80 minutes, and was due to depressurization of 6D commonline to install a pig launcher.
Flaring stopped when line depressured.
A flaring event occurred at GC1 starting at 09/18/2013 02:20 and stopping at 09/18/2013 15:00 with a volume of 220
(MSCF). The event lasted for 760 minutes, and was due to scheduled water wash on K7001.
A flaring event occurred at GC3 starting at 09/18/2013 00:01 and stopping at 09/18/2013 02:00 with a volume of 413
(MSCF). The event lasted for 119 minutes, and was due to wet gas compressor shutdown due to control/instrumentation
failure. Flaring stopped when WOA production was decreased.
A flaring event occurred at GC3 starting at 09/17/2013 20:02 and stopping at 09/18/2013 with a volume of 826 (MSCF).
The event lasted for 238 minutes, and was due to wet gas compressor shutdown due to control/instrumentation failure.
Flaring stopped when WOA production was decreased.
A flaring event occurred at FS3 starting at 09/17/2013 14:14 and stopping at 09/17/2013 15:51 with a volume of 74
(MSCF). The event lasted for 97 minutes, and was due to depressurization of 6B for the make-piggable project.
A flaring event occurred at GC1 starting at 09/16/2013 03:00 and stopping at 09/16/2013 22:30 with a volume of 6070
(MSCF). The event lasted for 1170 minutes. The event had a volume greater than 5000 (MSCF) and was due to
depressurization of GT -13 in support of line lifts for inspection.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoct[CWbp.com
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY RFPC)RT nG OOnnl li+rr% ^ A [.
Form 10-422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE
✓L /. ,
,�-/31d`-
Submit in Duplicate
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
October 2013
= Il t VOLUME DESCRIPTION OF INCIDENT &-CAUSE
10/16/2013 1353-1359 40 Not required for unplanned events <= 1 hr
TOTAL 40
10/4-8/2013
2051-2400
41,290 See attachments
10/9/2013
2204-2400
40
10/18-19/2013
1800-1430
3,025
10/23/2013
1015-1515
67,000
exceeding 5,000 MCF
TOTAL
111,355
anned Events Less Than or Equal 1
Hour AND <= 5,000 mcf
DATE
TIME
VOLUME DESCRIPTION OF IN(
10/10/2013
0928-0931
60 See attachments
10/15/2013
0730-0757
370
10/15/2013
1215-1219
270
10/25/2013
1221-1225
140
TOTAL
840
See attachments
TOTAL 0
Not required for unplanned events <= 1 hr
See attachments
See attachments
See attachments
Page 1
11/15/2013
10:49 AM
TOTAL
Unplanned Events < 1 Hour
40
Unplanned Events> 1 Hour
111,355
Planned Events < 1 hour and not
840
exceeding 5,000 MCF
Planned Events> 1 hour or
0
exceeding 5,000 MCF
Pilot Purge
55,340
Assist
0
TOTAL FLARED VOLUME
167,575
Not required for unplanned events <= 1 hr
See attachments
See attachments
See attachments
Page 1
11/15/2013
10:49 AM
Flare Start Date 10/01/2013
Flare End Date 10/31/2013
GCI Flare Report Total Volume (MSCF) 112235
Report
Numbs System Date Start Time Stop Time Duration Intermittent Black Smoke Planned Reported By
Volume
13-510 Flare Relief 10/04/2013 8:51:00 pm 12:00:00 am 189 min Yes No No BPI\FUELMO
1290
Determination Cause
Flaring off of V-136 due to taking the Annex down for SSR work and reduced oil flow though facility.
Action Taken
Flaring will stop when Annex is back in service.
Daily Volume (MSCF)
1290
13-514 Flare Relief
10/05/2013 12:00:00 am 12:00:00 am 1440 min No No No BPt\FUELMO
10000
Determination Cause
Flaring off of V-136 due to taking the Annex down for SSR work and reduced oil flow though facility.
Action Taken
flaring will stop when annex is back up.
Daily Volume (MSCF)
10000
13-515 Flare Relief
10/06/2013 12:00:00 am 12:00:00 am 1440 min No No No BP1\FUELMO
10000
Determination Cause
Flaring off of V-136 due to taking the Annex down for SSR work and reduced oil flow though facility.
Action Taken
flaring will stop when annex is back up.
Daily Volume (MSCF)
10000
13-518 Flare Relief
10/07/2013 12:00:00 am 12:00:00 am 1440 min No No No 8P1\FUELMO
10000
Determination Cause
Flaring off of V-136 due to taking the Annex down for SSR work and reduced oil flow though facility.
Action Taken
Flaring will stop when annex is put back in service. Aprox. 1 day.
Daily Volume (MSCF)
10000
13-520 Flare Relief 10/08/2013 12:00:00 am 12:00:00 am 1440 min Yes No No BP1\FUELMO
10000
Determination Cause
Flaring off of V-136 due to taking the Annex down for SSR work and reduced oil flow though facility.
Action Taken
Flaring will stop when Annex is back up.
Daily Volume (MSCF)
10000
13-526 Flare Relief 10/09/2013 10:04:00 pm 12:00:00 am 116 min Yes No No BP1\SPRINGG
40
Determination Cause
low oil rate
Action Taken
waiting for rate increase
Daily Volume (MSCF)
40
13-525 Flare Relief 10/10/2013 9:28:00 am 9:31:00 am 3 min No No Yes BP1\BIFFERDL
60
Determination Cause
Depresured test separator to put in Low Presure Mode.
Action Taken
Shut flare valve when presure was low enough to open into Low Presure system.
Daily Volume (MSCF)
60
13-532 Flare Relief 10/15/2013 7:30:00 am 7:57:00 am 27 min No No Yes BPI\BIFFERDL
370
Determination Cause
Flaring FA2/43/44 down to 50OPSI to test separator for line lifts.
Action Taken
Stopped flaring when lines were deppresured far enough to do line lifts.
13-532 Flare Relief 10/15/2013 12:15:00 pm 12:19:00 pm 4 min No No Yes BP1\BIFFERDL
270
Determination Cause
Took GLT 3300 down and depresured.
Action Taken
Planned shut down and depmure, closed flare when done.
Daily Volume (MSCF)
640
13-536 Flare Relief 10/18/2013 6:00:00 pm 12:00:00 am 360 min Yes No No BP1\SPRINGG 3
Generated 11/04/2013 3:38:24PM Page 10 of 13
Flare Start Date 10/01/2013
Flare End Date 10/31/2013
Determination Cause low oil rate
Action Taken compressors -waiting for more rate
Daily Volume (MSCF) 3
13-539 Flare Relief 10/19/2013 12:00:00 am 2:30:00 pm 870 min Yes No No BPI\SPRINGG 3022
Determination Cause Low GC1 oil rete.
Action Taken Waited for oil rate increase
13-543 Flare Relief 10/23/2013 10:15:00 am 3:15:00 pm 300 min No Yes
Determination Cause Power failure shut down LPS compressors after the bam doors would not work on them
Action Taken Power re supplied and LPS machines back in service.
13-547 Flare Relief 10/25/2013 12:21:00 pm 12:25:00 pm 4 min No No
Determination Cause Flared off 1st stage test bank to run in LP mode.
Action Taken Test bank 1st stage at operating pressure.
Daily Volume (MSCF) 3022
No BP1\FUELMO 67000
Daily Volume (MSCF) 67000
Yes BPI\HELMIGBJ 140
Daily Volume (MSCF) 140
Total Volume (MSCF) 112235
Generated 11/04/2013 3:38:24PM Page 11 of 13
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Tuesday, October 15, 2013 10:32 AM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject: Gas flaring events a
To: Jennifer Hunt, AOGCC
iennifer. h unt(aa)alaska. gov
CC: Dave Roby, AOGCC
dave. robv(aalaska. gov
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria. fergusonaalaska.gov
A flaring event occurred at GC1 starting at 10/04/2013 20:51 and stopping at 10/04/2013 24:00 with a volume of 1290
(MSCF). The intermittent event lasted for 189 minutes and was due to flaring off the V-136 IP vessel due to low oil rates
associated with the planned shutdown of the GC1 Annex for ongoing Safety System Renewal (SSR) work. Flaring
continued into the following day.
A flaring event occurred at GC1 starting at 10/05/2013 00:00 and stopping at 10/05/2013 24:00 with a volume of 10000
(MSCF). The event lasted for 1440 minutes and was due to flaring off the V-136 IF vessel due to low oil rates associated
with the planned shutdown of the GC1 Annex for ongoing Safety System Renewal (SSR) work. Flaring continued into the
following day.
A flaring event occurred at GC1 starting at 10/06/2013 00:00 and stopping at 10/06/2013 24:00 with a volume of 10000
(MSCF). The event lasted for 1440 minutes and was due to flaring off the V-136 IP vessel due to low oil rates associated
with the planned shutdown of the GC1 Annex for ongoing Safety System Renewal (SSR) work. Flaring continued into the
following day.
A flaring event occurred at GC1 starting at 10/07/2013 00:00 and stopping at 10/07/2013 24:00 with a volume of 10000
(MSCF). The event lasted for 1440 minutes and was due to flaring off the V-136 IP vessel due to low oil rates associated
with the planned shutdown of the GC1 Annex for ongoing Safety System Renewal (SSR) work. Flaring continued into the
following day.
A flaring event occurred at GC1 starting at 10/08/2013 00:00 and stopping at 10/08/2013 24:00 with a volume of 10000
(MSCF). The event lasted for 1440 minutes and was due to flaring off the V-136 IP vessel due to low oil rates associated
with the planned shutdown of the GC1 Annex for ongoing Safety System Renewal (SSR) work. Flaring continued into the
following day.
A Flaring event occurred at GC1 starting at 10/09/2013 22:04 and stopping at 10/09/2013 24:00 with a volume of 40
(MSCF). The intermittent event lasted for 116 minutes and was due to flaring off the V-136 IP vessel due to low oil rates in
the plant. Flaring continued into the following day.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 * 1890
akopspcceoctl (0b b p. co m
Alternate: Kellie Okonek
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctl(c bl).com
Hunt, Jennifer L (DOA
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Saturday, October 26, 2013 6:20 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; AK, OPS PCC EOC TL; AK, OPS CGF OTL; AK, OPS CCP CGF OSM; AK,
OPS GC1 Facility OTL; AK, OPS GC1 OSM; Kruger, Dale O; O'Riordan, Colm J; Burgess,
David H; AK, OPS FS2 OSM; AK, OPS FS2 Facility OTL; AKHSSEEEnvAdvWest@bp.com;
AK, HSSEE Env Adv East; AK, HSSEE Env Adv Central
Subject: Gas flaring events at CG FS2
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson,
AOGCC
jenn ifer. hunt(3alaska.gov dave. robVaalaska.gov
victoria. ferq u son (c.a laska. aov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at FS2 starting at 10/25/2013 00:45 and stopping at 10/25/2013 02:05 with a volume of 410
(MSCF). The event lasted for 80 minutes and was due to shutdown both 1801, 1803, 1804 and depressurization of A HP,
B HP and B S/C to remove blind from C S/C. Flaring stopped when depressurization for their plant shutdown was
complete.
A flaring event occurred at FS2 starting at 10/25/2013 10:30 and stopping at 10/25/2013 10:50 with a volume of 720228
(MSCF). The event had a volume greater than 5000 (MSCF) and was due to extended flaring event occurred while to
support planned acoustic testing of FV -1506.
A flaring event occurred at CGF starting at 10/23/2013 10:21 and stopping at 10/23/2013 14:25 with a volume of 34024
(MSCF). The event lasted for 244 minutes. The event had a volume greater than 5000 (MSCF) and was due to T/C 1855
Shutdown BESD on Low Seal Oil DP. Flaring stopped when offline 1805 T/C was started.
A flaring event occurred at GCI starting at 10/23/2013 10:15 and stopping at 10/23/2013 15:15 with a volume of 67000
(MSCF). The event was a black smoke event. The event lasted for 300 minutes. The event had a volume greater than
5000 (MSCF). Approximately 1/3 of the GC1 facility (LPS, WSW, & PWX) lost all power simultaneously. The loss of
power resulted in the gas compressor cooling fans (gas/utility water), and instrument air going down. Soon after this
occurred the LIPS and GILT compressors were shutdown in a controlled fashion by the board operator. The loss of these
compressors resulted in a flaring event.
A flaring event occurred at GC1 starting at 10/19/2013 00:00 and stopping at 10/19/2013 14:30 with a volume of 3022
(MSCF). The event lasted for 870 minutes and was due to.
A flaring event occurred at GCI starting at 10/18/2013 18:00 and stopping at 10/19/2013 with a volume of 3 (MSCF). The
event lasted for 360 minutes and was due to lowering of rates on the LP/IP compressor KO to prevent black smoke.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akoosocceoctl anbp corn
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODIICFn [;o-qnicpnQ1TinKi
1. Facility Number 2. Facility Name
0290000031 PBU GC 1
Disposition
3. Field
PBU - WOA
Volume MCF
4. Operator 5, Month/Year of Disposition
BP I November -2013
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
6. Sold
G
Pool Name Pool Code Percent
7. Reinjected
0
PRUDHOE 640150 99.83%
LISBURNE640144 0.00%
8. Flared or vented l hour or less
800
MIDNIGHT SUN 640158 017%
PT MCINTYRE 640180 0.00%
9. Flared or vented more than 1 hour (see instr.)
111,914
10. Pilot and Purge
53,971
11. Assist Gas
G
12. Fuel gas used in lease operations.
767,545
13. Other (see instructions)
Official Use Only
Authorization >1 hr:
Safety934,230
7
MCF
14. TOTAL VOLUME (ITEMS 6-12)
Lease Use
MCF
15. NGL Gas Equivalent
U
Conservation
MCF
16. Purchased gas
G
Waste:
MCF
17. Transferred from:
0
Commissioner Date
18. Transferred to: (Express as a negative #) CGF
-69,223,784
19. Remarks:
I hereby certify that the foregoing is true and correct to the best of my knowledge.
=(Who Note: All volumes must corrected
Signature Title Mana er Production Taxes and Ro a ties Alaska to pressure of 14.65 psisia and to a
Printed Name Diane Colleytemperature of 60o F. Authority 20
Phone (907) 564-5775 Date AAC25.235.
vz�F
6 /3// 4J -
Form 10-422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE Submit in Duplicate
11/6/2013 1607-1636
11/26/2013 0330-0415
TOTAL
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT - GC -1
GAS FLARING INCIDENT REPORT
November 2013
250 Not required for unplanned events <=1 hr
340
590
Not required for unplanned events <= 1 hr
11/4/2013
0735-0836
1,020 See attachments
See attachments
11/20/2013
1143-1856
1,856
TOTAL
2,876
Planned Events Less Than or Equal 1 Hour AND <= 5,000 mcf
DATE
TIME
VOLUME DESCRIPTION OF INCIDENT & CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
11/7/2013
1430-1431
10 See attachments
See attachments
11/7/2013
1543-1546
200
TOTAL
210
Planned Events Exceeding 1 Hour OR > 5,000 mcf
DATE
TIME
VOLUME DESCRIPTION OF INCIDENT& CAUSE
ACTION TAKEN TO ELIMINATE CAUSE
11/10-18/13
0730-1200
106,438 See attachments
See attachments
11/19/2013
0000-2400
2,600
TOTAL
109,038
TOTAL
Unplanned Events < 1 Hour
590
Unplanned Events> 1 Hour
2,876
Planned Events < 1 hour and not
210
exceeding 5,000 MCF
Planned Events> 1 hour or
109,038
exceeding 5,000 MCF
Pilot Purge
53,971
Assist
0
TOTAL FLARED VOLUME
166,685
Page 6
12/10/2013
2:51 PM
Flare Start Date 11/01/2013
Flare End Date 11/30/2013
GC1 Flare Report Total Volume (MSCF) 112774
Repoli
Numbs System Date Start Time Stop Time Duration Intermittent Black Smoke Planned Reported By Volume
13-556 Flare Relief 11/04/2013 7:35:00 am 8:36:00 am 61 min Yes No No BP1\FUELM0 1020
Determination Cause Modified stop production caused while instrument techs where trouble shooting old beta panel alarm.
Action Taken Fount problem and brought production back into plant..
13-558 Other 11/07/2013 2:30:00 pm
Determination Cause Start GTRB-51-3204,
Action Taken Sustained fire achieved.
13-558 Controlled Slowdown 11/07/2013 3:43:00 pm
Determination Cause Depmssure K-51-3320.
Action Taken Case pressure <5 psig.
2:31:OOpm 1 min No No Yes BPIUONESCC 10
3:46:00 pm 3 min No No Yes BPIWONESCC 200
13-562 Flare Relief 11/10/2013 7:30:00 am 12:00:00 am 990 min No No Yes BPIISPRINGG 8938
Determination Cause D -bank taken offline for SSR Project Cutover. Although oil rate is ower 60,000 bpd, the LP/IP gas compression system is not designed for
today's gas conditions when only banks A, B & C are online without D -bank.
Action Taken flV-1r 13P flarree setpoint intentionally lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to
13-563 Flare Relief 11/11/2013 12:00:00 am 12:00:00 am 1440 min Yes No Yes BPIISPRINGG 13000
Determination Cause D -bank taken offline for SSR Project Cutover. Although oil rate is over 60,000 bpd, the LP/IP gas compression system is not designed for
today's gas conditions when only banks A, B & C are online without D -bank.
Action Taken V-136 flare setpoint intentionally lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to
_.--erevent hladesmMre
13-564 Flare Relief 11/12/2013 12:00:00 am 12:00:00 am 1440 min Yes No Yes BPIISPRINGG 13000
Determination Cause D -bank taken offline for SSR Project Cutover. Although oil rate is over 60,000 bpd, the LP/IP gas compression system is not designed for
today's gas conditions when only banks A, B & C are online without D -bank.
Action Taken V-136 flare setpoint intentionally lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to
_—oreventMack�
13-565 Flare Relief 11/13/2013 12:00:00 am 12:00:00 am 1440 min No No Yes BPIIKIRSCHW 13000
Determination Cause D -bank taken offline for SSR Project Cutover. Although oil rate is over 60,000 bpd, the LP/IP gas compression system is not designed for
today's gas conditions when only banks A, B & C are online without D -bank.
Action Taken V-136 flare setpoint intentionally lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to
Pr ntblaek-smoke-
13-567 Flare Relief 11/14/2013 12:00:00 am 12:00:00 am 1440 min No No Yes BPIIKIRSCHW 13000
Determination Cause D -bank taken offline for SSR Project Cutover. Although oil rate is over 60,000 bpd, the LP/IP gas compression system is not designed for
today's gas conditions when only banks A, B & C are online without D -bank.
Action Taken V-136 flare Wtpoint intentionally lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to
r - p vent lack s
13-568 Flare Relief 11/15/2013 12:00:00 am 12:00:00 am 1440 min No No
Yes BP111CIRSCHW 13000
Generated 12/02/2013 1:44:10PM Page 5 of 8
Flare Start Date 11/01/2013
Flare End Date 11/30/2013
Determination Cause D -bank taken offline for SSR Project Cutover. Although oil rate is over 60,000 bpd, the LP/IP gas compression system is not designed for
today's gas conditions when only banks A, B & C are online without D -bank.
Action Taken V-136 flare setpoint intentionally lowered to minimize the volume flared by preventing LP Flaring that requires the addition of assist gas to
oreventbladr smnkr- -
13-569 Flare Relief 11/16/2013 12:00:00 am 12:00:00 am 1440 min No No Yes BP1\KIRSCHW 13000
Determination Cause D -bank taken online for SSR Project Cutover. Although oil rate is over 60,000 bpd, the LP/IP gas compression system is not designed for
today's gas conditions when only banks A, B & C are online without D -bank.
Action Taken V-136 flare setpoint intentionally lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to
—prevent black smoke
13-570 Flare Relief 11/17/2013 12:00:00 am 12:00:00 am 1440 min No No Yes BP1\KIRSCHW 13000
Determination Cause D -bank taken offline for SSR Project Cutover. Although oil rate is over 60,000 bpd, the LP/IP gas compression system is not designed for
today's gas conditions when only banks A, B & C are online without D -bank.
Action Taken V-136 flare setport intentionally lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to
-. -.--preventAlack-smoke—
13-571 Flare Relief 11/18/2013 12:00:00 am 12:00:00 pm 720 min No
Determination Cause V-136 flare opened due to D -Bank SSR project.
Action Taken D -Dank BIS
13-573 Flare Relief 11/19/2013 12:00:00 am 12:00:00 am 1440 min Yes
Determination Cause Depressure tat and 2nd stage C -bank for leaking gasket
Action Taken replaced gasket
No Yes 8P1WRSCHW 6500
No Yes BPI\KIRSCHW 2600
13-574 Flare Relief 11/20/2013 11:43:00 am 6:56:00 pm 433 min Yes No No BP1\SELFJR 1856
Determination Cause Odd reboiler shut down causing gas temp to get high and comp lost forward flow
Action Taken V-136 flare setpoint intentionally lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to
__...-t eventblack-smoke-
Total Volume (MSCF) 112714
12/02/2013 1:44:10PM
Page 6 of 8
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Tuesday, November 12, 2013 8:22 AM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GCI Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject: Gas flaring events
To: Jennifer Hunt, AOGCC
ien n fifer. h unt(a2alaska. aov
CC: Dave Roby, AOGCC
dave.robv aaalaska.00v
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victoria.femusonaalaska oov
A flaring event occurred at GC1 starting at 11/04/2013 07:35 and stopping at 11/04/2013 08:36 with a volume of 1020
(MSCF). The intermittent event lasted for 61 minutes and was due to flaring from the GC1 facility associated with an
unplanned modified stop production (shutdown) of GC1 caused while technicians were troubleshooting a panel. Flaring
ended when the problem was resolved and GC1 was restarted.
A flaring event occurred at GC1 starting at 11/10/2013 07:30 and stopping at 11/10/2013 24:00 with a volume of 8938
(MSCF). The event lasted for 990 minutes and was due to flaring off the LP/IP system due to low oil rates associated with
the planned shutdown of the GC1 D Bank separation train for ongoing Safety System Renewal (SSR) work. Flaring
continued into the following day.
A flaring event occurred at GC1 starting at 11/11/2013 00:00 and stopping at 11/11/2013 24:00 with a volume of 13000
(MSCF). The event lasted for 1440 minutes and was due to flaring off the LP/IP system due to low oil rates associated
with the planned shutdown of the GCI D Bank separation train for ongoing Safety System Renewal (SSR) work. Flaring
continued into the following day.
Please let me know if you have any questions.
Travis M. Rybicki
PCC•EOC (Production Optimization) Team Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 758-4404
GPB Pager 907-659-5272 # 1890
akor)spcceoctl(a)bp com
Alternate: Kellie Okonek
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) 15566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopspcceoctl(a)bp.com
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL (AKOPSPCCEOCTL@bp.com]
Sent: Sunday, November 17, 2013 10:11 AM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; AK, OPS PCC EOC TL; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM;
Kruger, Dale O; AK, H SEE Env Adv West
Subject: Gas flaring events a
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson,
AOGCC
iennifer.hunt(@alaska.gov dave. robv(rDalaska. gov
victoria.ferguson(a.alaska qov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at GCI starting at 11/12/2013 00:00 and stopping at 11/13/2013 with a volume of 13000 (MSCF).
The event lasted for 1440 minutes. The event had a volume greater than 5000 (MSCF).
Flaring continued at GCI starting at 11/13/2013 00:00 and stopping at 11/14/2013 with a volume of 13000 (MSCF). The
event lasted for 1440 minutes. The event had a volume greater than 5000 (MSCF).
Flaring continued at GCI starting at 11/14/2013 00:00 and stopping at 11/15/2013 with a volume of 13000 (MSCF). The
event lasted for 1440 minutes. The event had a volume greater than 5000 (MSCF).
Flaring continued at GC1 starting at 11/15/2013 00:00 and stopping at 11/16/2013 with a volume of 13000 (MSCF). The
event lasted for 1440 minutes. The event had a volume greater than 5000 (MSCF).
Flaring continued at GC1 starting at 11/16/2013 00:00 and stopping at 11/17/2013 with a volume of 13000 (MSCF). The
event lasted for 1440 minutes. The event had a volume greater than 5000 (MSCF).
These events are due to D -bank being taken offline for the planned SSR cutover. V-136 flare setpoint intentionally
lowered to minimize the volume flared by preventing LP flaring that requires the addition of assist gas to prevent black
smoke.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akoosocceoctl@bo com
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com)
Sent: Sunday, November 24, 2013 3:12 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; AK, OPS PCC EOC TL; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM;
Kruger, Dale O; AK, HSSEE Env Adv West
Subject: Gas flaring events a
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson,
AOGCC
en niter. h u nt(a)alaska. gov dave. robv(a)alaska.gov
victoria.ferauson(cDalaska.00v
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at GC1 starting at 11/20/2013 11:43 and stopping at 11/20/2013 18:56 with a volume of 1856
(MSCF). The event lasted for 433 minutes and was due to Odd reboiler shut down causing gas temp to get high and
compressor lost forward flow. V-136 flare setpoint was intentionally lowered to minimize the volume flared by preventing
LP flaring that requires the addition of assist gas for prevention of black smoke.
A flaring event occurred at GC1 starting at 11/19/2013 00:00 and stopping at 11/20/2013 with a volume of 2600 (MSCF).
The event lasted for 1440 minutes and was due to depressurization of 1 st and 2nd stage C -bank for a leaking gasket.
Flaring stopped when the gasket was replaced.
A flaring event occurred at GC1 starting at 11/18/2013 00:00 and stopping at 11/18/2013 12:00 with a volume of 6500
(MSCF). The event lasted for 720 minutes. The event had a volume greater than 5000 (MSCF).
A flaring event occurred at GCI starting at 11/17/2013 00:00 and stopping at 11/18/2013 with a volume of 13000 (MSCF).
The event lasted for 1440 minutes. The event had a volume greater than 5000 (MSCF). These events are due to D -bank
being taken offline for the planned SSR cutover. V-136 flare setpoint intentionally lowered to minimize the volume flared
by preventing LP flaring that requires the addition of assist gas to prevent black smoke
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akoosccceoctl(a)by.com
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number
0290000031
2. Facility Name
PBU GC 1
3. Field
PBU - WOA
4. Operator
BP
5. Month/Year of Disposition
I December -2013
Disposition
Volume MCF
20. Forproduction from multiple pools, list contribution or each pool as a percent of
Total Volume.
6. Sold
0
Pool Name Pool Code Percent
7. Reinjected
O
PRUDHOE 640150 99.883/.
LISBURNE 640144 0.00%
8. Flared or vented hour or less
500
MIDNIGHTSUN 640158 0.12%
PT MCINTYRE 640180 0.00%
9. Flared or vented more than 1 hour (see instr.)
2,260
10. Pilot and Purge
56,112
11. Assist Gas
0
12. Fuel gas used in lease operations.
803,221
13. Other (see instructions)
U
Official Use Only
Authorization >l hr
Safety
Z D
MCF
14. TOTAL VOLUME (ITEMS 6-12)
862,093
Lease Use
MCF
15. NGL Gas Equivalent
0
Conservation
MCF
16. Purchased gas
0
Waste:
MCF
17. Transferred from:
0
L Commissioner Date
18. Transferred to: (Express as a negative #) CGF
-75,132,157
19. Remarks:
I hereby certify that thA foregoing is true and correct to the best of my knmledge.
�//�,1 Note: All volumes must be corrected
Signature IDYL' I U Title Mana er Production Taxes and R alties Alaska to pressure of 14.65 psis and to a
temperature of 60o F. Authority 20
Printed Name Diane Colley Phone (907) 564-5775 Date / AAC25.235.
rt, i
f-/7/>¢
Form 10422 Rev. 5/2009 INSTRUCTIONS ON REVERSE SIDE Submit in Duplicate
BP EXPLORATION (ALASKA) INC.
PRUDHOE BAY UNIT -GC -1
GAS FLARING INCIDENT REPORT
December 2013
Unplanned Events less than or equal to 1 hour
DATE TIME VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO ELIMINATE CAUSE
12/3/2013 1620-1649 440 Not required for unplanned events <= 1 hr Not required for unplanned events <= 1 hr
12/15/2013 1325-1335 60
TOTAL 500
DATE
TIME
12/1/2013
0730-0915
12/7/2013
0910-1030
12/11/2013
0803-0945
12/8/2013 1606-1748
TOTAL
1E DESCRIPTION OF INCIDENT &
1,000 See attachments
220
Planned Events Less Than or Equal 1 Hour AND <= 5,000 mcf
See attachments
ACTION TAKEN TO ELIMINATE CAUSE
See attachments
See attachments
TOTAL
0
Planned Events Exceeding 1 Hour OR> 5,000 mcf
DATE TIME
VOLUME DESCRIPTION OF INCIDENT & CAUSE ACTION TAKEN TO ELIMINATE CAUSE
12/8/2013 0810-0947
90 See attachments See attachments
12/8/2013 1606-1748
380
TOTAL
470
TOTAL
Unplanned Events < 1 Hour
500
Unplanned Events> 1 Hour
1,790
Planned Events < 1 hour and not
0
exceeding 5,000 MCF
Planned Events > 1 hour or
470
exceeding 5,000 MCF
Pilot Purge
56,112
Assist
0
TOTAL FLARED VOLUME
58,872
Page 7
1/12/2014
10:27 AM
Flare Start Date 12/01/2013
Flare End Date 12/31/2013
GC1 Flare Report
Total Volume (MSCF)
2760
Report
Numbe System Date StartTime Stop Time Duration Intermittent
Black Smoke
Planned
Reported By
Volume
13-580 Flare Relief 12/01/2013 7:30:00 am 9:15:00 am 105 min Yes
No
No
BPI\FUELMO
1000
Determination Cause High transit gas pressure causing and flaring off of V-136
Action Taken Transit gas pressure returned to normal and flaring was stopped.
.. ............... __. __. _._'___.. _._..._ ................. .....-._-.-.-._.
__._..
_........ ..... ...
.... ...........
....____...........
13-585 Flare Relief 12/07/2013 9:10:00 am 10:30:00 am 80 min Yes
No
No
BP1\SELFJR
220
Determination Cause Y-LDF HAS CRACK ON WELD INSIDE SKID 450 NEED TO DEIVENTORY LINE
Action Taken PIGGING Y-LDF FOR REPAIRS TO CRACK ON LINE IN SKID 450
13-586 Flare Relief 12/08/2013 81000 am 9:47:00 am 97 min No
No
Yes
BPI\BIFFERDL
90
Determination Cause Pigging Y-LDF for line repair.
Action Taken As soon as pigs were in shut off.
__. ........... .. ............... ....... __. _._ ..._
................
._...
__.
13-586 Flare Relief 12/08/2013 4:06:00 pm 5:48:00 pm 102 min No
No
Yes
BP1\BIFFERDL
-...... _.
380
Determination Cause Dropping GLT line presure at Y -Pad while Pad is down for line repairs on LDF crack in pipe skid 450 at GC1
Action Taken Shutoff as soon as presurewas low enough at pad, on GILT line.
13-589 Flare Relief 12/11/2013 8:03:00 am 9:45:00 am 102 min Yes No No BPI\SPRINGG 570
Determination Cause K-107/108 surging up&down
Action Taken Waiting for compressors to settle out
Total Volume (MSCF) 2760
Generated 01/06/2014 9:50:43AM Page 6 of 6
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Tuesday, December 10, 2013 11:45 AM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; Kruger, Dale O; AK, OPS GC1 Facility OTL; AK, OPS GC1 OSM; AK,
HSSEE Env Adv West
Subject: Gas flaring events aSgft
To: Jennifer Hunt, AOGCC
Wenn iter. h untCcDalaska.gov
CC: Dave Roby, AOGCC
dave. robv(cDalaska. gov
From: Travis Rybicki, GPB Production Optimization Team Leader
CC: Victoria Ferguson, AOGCC
victori a. ferg uson (cbalaska.gov
A flaring event occurred at GC1 starting at 12/01/2013 07:30 and stopping at 12/01/2013 09:15 with a volume of 1000
(MSCF). The intermittent event lasted for 105 minutes. Flaring was due to high transit gas pressures resulting in flaring
from the V-136 IP Gas KO Vessel. Flaring continued while transit gas pressures were stabilized. Flaring ended when
trans it gas pressure returned to normal ranges.
A flaring event occurred at GC1 starting at 12/07/2013 09:10 and stopping at 12/07/2013 10:30 with a volume of 220
(MSCF). The event lasted for 80 minutes. Flaring was due to flaring off of C Bank Slug Catcher during the de -inventory
pigging operations on the Y Pad LDF. The LDF was shut down a few days prior due to a crack identified in Skid 450.
Flaring ended when pigging operations were completed for the day.
A flaring event occurred at GC1 starting at 12/08/2013 08:10 and stopping at 12/08/2013 09:47 with a volume of 90
(MSCF). The event lasted for 97 minutes. Flaring was due to flaring off of C Bank Slug Catcher during the de -inventory
pigging operations on the Y Pad LDF. The LDF was shut down a few days prior due to a crack identified in Skid 450.
Flaring ended when pigging operations were completed for the day.
A flaring event occurred at GC1 starting at 12/08/2013 16:06 and stopping at 12/08/2013 17:48 with a volume of 380
(MSCF). The event lasted for 102 minutes. Flaring was due to flaring off of C Bank Slug Catcher during the de -pressuring
of the Y Pad GLT supply line, via the Y Pad LDF. The GLT supply line was de -pressured as a precautionary measure,
while the LDF is down for repairs. Flaring ended when the GLT supply line was sufficiently de -pressured.
Please let me know if you have any questions.
Travis M. Rybicki
PCC-EOC (Production Optimization) Team Lead
Office 907-659-4472 (BOC) 659-5566 (PBOC)
Cell 907-748-2118 Harmony 7584404
GPB Pager 907-659-5272 # 1890
akopspcceocti(a.bp. Com
Alternate: Kellie Okonek
Hunt, Jennifer L (DOA)
From: AK, OPS PCC EOC TL [AKOPSPCCEOCTL@bp.com]
Sent: Monday, December 23, 2013 10:14 PM
To: Hunt, Jennifer L (DOA)
Cc: Ferguson, Victoria L (DOA); Roby, David S (DOA); Castano, Alejandra; Benson, Gary A;
Arthur, Gregory; AK, OPS GCI Facility OTL; AK, OPS GCI OSM; Kruger, Dale O; AK,
HSSEE H&S Adv West GC1 GC3)
Subject: Gas flaring event aNIFIM
To: Jennifer Hunt, AOGCC CC: Dave Roby, AOGCC CC: Victoria Ferguson,
AOGCC
jennifer.hunt(cbalaska.gov dave.roby(a)alaska.00v
victoria. fern usonealaska.4ov
From: Kellie Okonek, GPB Production Optimization Team Leader
A flaring event occurred at GCI starting at 12/11/2013 08:03 and stopping at 12/11/2013 09:45 with a volume of 570
(MSCF). The event lasted for 102 minutes, and was due to K-107/108 surging up and down. Flaring stopped once the
compressors settled out.
Please let me know if you have any questions.
Kellie Okonek (alt. Travis Rybicki)
PCC/EOC Production Optimization TL
external: (907) 659 4472 (BOC) / 5566 (PBOC)
cell: (907) 382 1370 Harmony: 758 4404
Pager 574 (WOA - access # 4236) or 1890 (EOA - access #5100)
e-mail akopsocceoctl(aft corn