Gas Disposition Files
Year: 2014
Facility: SR Swanson River LEX
Operator: HILCORP
1330000002
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
i(e v.
Swanson RiverI Swanson River Unit I HILCORP ALASKA LLC I January 2014
Volume MCF 1 20. For production from multiple pools, list contribution of each pool as a percent
6. Sold
181,369
7. Reinjected
0
8. Flared or vented 1 hour or less
43
9. Flared or vented more than 1 hour (see instr.)
3821
10. Pilot and Purge
1,142
11. Assist Gas
0
12. Fuel gas used in lease operations
53,884
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6-13)
236,819
15. NGL Gas Equivalent
2,216 '
16. Purchased gas - Rental Return Gas
211,176'
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(57,723)
Transferred to: Swanson Storage 57,723
To storage for fuel usage: 0
To storage for injection Is Included In LNre 6 as subject to royalty.
Other: Hemlock Production Sold 110,278
certify that the foregoing is true/ and correct to the best of my knowledge.
Signature A00" Tide
Use
1. F13r,I vel. a� prc �l on ", ,DLnZ l
Note: All volumes must be corrected
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
Date 622/2017 AAC25.235.
I
3. Sold
T. Reinjected
3. Flared or vented 1 hour or less
9. Flared or vented more than 1 hour (see insir.)
10. Pilot and Purge
11. Assist Gas
12. Fuel gas used in lease operations
13. Other (see Ins I )
14. TOTAL VOILL104W6o 3)
r. a
15. NGL Gas Equivalent
16. Purchased gas - Rental Return Gas
17. Transferred from: (Off -lease Gas)
18. Transferred to:
Transferred to:
Other:
certify that the fol
Name
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Swanson
181,369
Pool Ne
0
SWANSON RIVE
SWANSON RIVER, HEM
43
SWANSON RIVER, TY
SWANSON RIVER, 0E
362'
SWANSON RIVER, STE
1,142
0
53,884
Swanson Storage 57,723
To storage for fuel usage:0
To storage for injection a included in Line 6 as subject to royally.
Hemlock Production Sold 110,278
;ORP ALASKA LLC I January 20
multiple pools, list contribution of each pool as a
Total Volume,
392, MCF
Use I
MCF
ote: All volumes must be corrected
to pressure of 14.65 pale and to a
temperature of 60o F. Authority 20
OR FLARING EVENTS GREATER THAN 1 HOUR
'
-
!Lego �T�k�nio Minimize a
RIPIDate
O No
Faclllt No --
Date Elated
Start Time
-Ending Time. -
End Date
Planned>:
MCF - '
Oescrip tlon of Flaring Event
tea"-,"oYum
Excess flaring necessary until
O VOL2014
124250
7330000002
01(01/74
12:30:00 PM
2:00:00 PM
01/01)14
U
12
Excess flaring due to V -S Dump Valve
the Dump Valve Controller
being opened.
could be adjusted.
Excess flaring necessary until K-
07/01/1014
124250
1330000002
01/02/14
11:00:00 AM
1:OD:00 PM
01/02/14
U
20
Excess flaring due to the shutdown of
8 could be started, loaded and
Compressor K-8.
returned back to service.
Excess venting due to the shutdown
of Compressor K-22 becasue of high
Excess venting necessary until
01/01/2014
124250
1330000002
01/02/14
11:00:00 AM
1:00:00 PM
01/02/14
U
4
K-22 could be started, loaded
discharge pressure following the
shutdown of K-8.
and returned back to service.
Excess venting due to the
Excess venting necessary until
01/01/1014
124250
1330000002
01/07/14
8:15:00 AM
5:00:00 PM
01/07/14
U
15
unscheduled shutdown of
line could be depressurized
Compressor K-22 caused by
and deared with
plugged discharge line.
methanol/xylene.
Excess venting necessary until/01/2014
01
724250
1330000002
01/15/14
12:00:00 AM
3:00:00 PM
01/15(14
U
32
Excess venting due to a loss of water
the water pump could be
pump an Compressor K-22.
replaced.
Excess venting due toalost
Excess venting necessaryunIII
01/01/2014
124250
1330000002
01/25/14
3:00:00 AM
1159:00 PM
01/31/14
U
298
Compressor Piston in K-22. Venting
a new piston and as:
will be ongoing into February.
parts are received.
REVISED
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1330000002 I Swanson RiverI Swanson River Unit I HILCORP ALASKA LLC I February 2014
Disposition Volume MCF 1 20. For production from multiple pools, list contribution of each pool as a
6.
Sold
174,321
7.
Reinjected
0
8.
Flared or vented 1 hour or less
14
9.
Flared or vented more than 1 hour (see instr.)
0
10.
Pilot and Purge
1,123
11. Assist Gas
0
12. Fuel gas used in lease operations
50,775
13.
Other (see instructions)
0
14.
TOTAL VOLUME (ITEMS 6.13)
226,233
15.
NGL Gas Equivalent
1,835-
116.
Purchased gas - Rental Return Gas
192,370
17.
Transferred from: (Off -lease Gas)
0
18.
Transferred to:
(214,995)
Transferred to: Swanson Storage 214,995
To storage for fuel usage: 0
To storage for injection is included in line 6 as subject to royally.
Other: Hemlock Production Sold 57,695
SILT1
Use
ai1y9
hereby certify that the foregoing is true and correct to the best of my knowledge.
Note: All volumes must be correcte
Signature Title Production Analyst to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
Printed Name Cnrtnwv Dver Phnne 713-9119-9881 nate 6/22/2017 AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
FacilityNumber 2. Facility Name 3. Field 4. Up ennor s. MonimYearotuls osnlor
Y P
1330000002 Swanson River Swanson River Unit HILCORP ALASKA LLC I February 2014
Disposition I Volume MCF 1 20. For production from multiple pools, list contribution of each pool as a percent
6. Sold
174,321
7. Reinjected
0
8. Flared or vented i hour or less
14
9. Flared or vented more than i hour (see instr.)
0
10. Pilot and Purge
1,123
11. Assist Gas
0
12. Fuel gas used in lease operations
50,775
13. Other (see instructions)
ae
14.
TOTAL VOLUME (ITEMS 6.13)
226,233
15.
NGL Gas Equivalent
1,456
16.
Purchased gas - Rental Return Gas
192,370
17.
Transferred from: (Off -lease Gas)
0
18.
Transferred to:
(214,995)
19. Remarks
Transferred to: Swanson Storage 214,995
To storage for fuel usage:0
To storage for injection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 57,695
the for5ginq is trued correct to the best of my knowledge
Signature
>1 hr:
Date
UNDEFINED
Use
772100
0.00%
to pressure of 14.65 Pala and to a
temperature of 60o F. Authority 20
STATE OF ALASKA REVISED
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
1. Facility Number 2. Facility Name 3. Field 4. Operator 5. MonthNear of Disposition
1330000002 Swanson River Swanson River Unit HILCORP ALASKA LLC March 2014
Disposition Volume MCF 1 20. For production from multiple pools, list contribution of each pool as a percent
6. Sold
195,322
7. Reinjected
0
8. Flared or vented 1 hour or less
17
9. Flared or vented more than 1 hour (see instr.)
3 r
10. Pilot and Purge
661
11. Assist Gas
0
12. Fuel gas used in lease operations
72,408
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6-13)
268,411
15. NGL Gas Equivalent
2,938
16. Purchased gas - Rental Return Gas
188,392
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(585,727)
19. Remarks:
Transferred to: Swanson Storage 585,727
To storage for fuel usage: 0 to Storage for Injection:
585727
To storage for injection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 10
I hereby certify that the foregoing is true and correct to the best of my knowledge.
Signature e—M- 4--f Title Prodw
>1 hr:
Use
\. Fla"" val-ayPro�ee.( 0� or.q
-31111,4-
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Unit
6. Sold
195,322
7. Reinjected
0
8. Flared or vented 1 hour or less
17
9. Flared or vented more than 1 hour (see instr.)
3•
10. Pilotand Purge
661
11. Assist Gas
0
12. Fuel gas used in lease operations
72,408
13. Other (see instructions)
0
14. T L -
15. N ntl ]
268,411
2,332
16. Purchased gas - Rental Return Gas
188,392
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(585.727)
Transferred to: Swanson Storage 585,727
To storage for rust usage: 0 to Storage for Injection:
5&5727
To storage for injection is Included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 10
HILCORP ALASKA LLC I March 201
rom multiple pools, list contribution of each pool as a
Use
Use
772105
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
OR FLARING EVENTS GREATER THAN 1 HOUR
VIEW`
a;"'
n�+v & f
�-�di� m y
�,
� '
q.. 'r -.�
-
+ wa:'r>
r
K
y
...
'M
tl iai
di gr' .
`
Excess venting necessary until
03/01/2014
124250
1330000002
3/23/2014
9:30:00AM
11:00:00 AM
03/23/14
F
3
Scheduled Maintenance.
proper preventative
maintenance was performed
and compressor could be
brought back online.
STATE OF ALASKA y"IV
ALASKA OIL AND GAS CONSERVATION COMMISSION /�� � -p
FACILITY REPORT OF PRODUCED GAS DISPOSITION /
�. Facility Number
1330000002
2. Facility Name
Swanson River
3. Field
Swanson River Unit
4. Operator
HILCORP ALASKA LLC
5. Month/Year of Disposition
March 2014
Disposition
Volume MCF
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
�L
&/
3. Sold
242,786
Pool Name _ PoolCode Percent
r. Reinjected
0
SWANSON RIVER, HEMLOCK 772100 70.99%
SWANSON RIVER, HEM FISTERUNG UNDEF 772105 0.00%
3. Flared or vented 1 hour or less
12
SWANSON RIVER, TYONEK UNDEFINED 772500 1.82%
SWANSON RIVER, BELUGA UNDEFINED 772520 11.80%
3. Flared or vented more than 1 hour (see insir.)
2
SWANSON RIVER, STERLING UNDEFINED 772550 15.39%
10. Pilot and Purge
489
11. Assist Gas
0
12. Fuel gas used in lease operations
53,509
13. Other (see instructions)
0
Official Use Only
Authorization >1 hr.
Safely
Z
MCF
14. TOTAL VOLUME (ITEMS 6.13)
296,798
Lease Use
MCF
15. NGL Gas Equivalent
2,332
Conservation
MCF
16. Purchased gas - Rental Return Gas
222,461
Waste:
JMCF
17. Transferred from: (OH -lease Gas)
0
�T[
Co isswner Date
18. Transferred to:
(312,079)
Transferred to: Swanson Storage 312,079
To storage fa fuel usage: 6912 to Storage for Injection:
242767
To storage for injection is included in Line 6 as subject to royally.
Other: Hemlock Production Sold 14
certify that the foregoing a and correct to the best of my knowledge.
Note: All volumes must be corrected
Signature Title Production Analyst to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
OR FLARING EVENTS GREATER THAN 1 HOUR
Taken to Minimize
R p tDate
O No .
Facill Na - '
Date Flared
Starl I me
- Ending Time.
- . End Date
Planned
MCF
- Description of Flaring Event
_Action
Volume ='
Excess venting necessary until
proper preventative
03/01/2014
124250
1330000002
3/23/2014
9:30:00 AM
11:00:00AM
03/23/14
P
2
Scheduled Maintenance.
maintenance was performed
and compressor could be
brought back online.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
I1. Facility Number 330000002 I2. Facility Name3.
River I3. Field Swanson River Unit I4 Operator
HILCORP ALASKA LLC I5. Month'year 2014 position
Disposition Volume MCF 20. For production from multiple pools, list contribution of each pool as a percent
6. Sold
186,300
7. Reinjected
0
8. Flared or vented 1 hour or less
95.
9. Flared or vented more than 1 hour (see instr.)
161
10. Pilot and Purge
626
11. Assist Gas
0
12. Fuel gas used in lease operations
49,839
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6.13)
236,876
15. NGL Gas Equivalent
2,713
16. Purchased gas - Rental Return Gas
144,325
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(72,414)
Transferred to: Swanson Storage 72,414
To storage for fuel usage: 0 to Storage for Injection:
72414
To storage for injection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 72,828
I the foregoing is true and correct to the best of my knowledge
Signature 2;K" Title
of Total Volume.
Use
1. Fla+ -� vol z,e� a l dV*In A'k .
Note: All volumes must be
corrected to pressure of 14.65 psia
and to a temperature of 600 F.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
1.
Facility Number
1330000002
2. Facility Name
Swanson River
3. Field
Swanson River Unit
4. Operator
HILCORP ALASKA LLC
5. Month/Year of Disposition
2014
Apri1201
Disposition
Volume MCF
20. For production from multiple pools, list contribution
Total Volume.
of each pool as a percent of
6.
Sold
186,300
Pool Name
Pool Code Percent
7.
Reinjected
0
SWANSON RIVER, HEMLOCK
772100 62.06%
SWANSON RIVER, HEM F/STERLING UNDEF
772105 0.00%
8.
Flared or vented 1 hour or less
95
SWANSON RIVER, TVONEK UNDEFINED
772500 2.80%
SWANSON RIVER, BELUGA UNDEFINED
772520 18.08%
9.
Flared or vented more than 1 hour (see instr.)
16 '
SWANSON RIVER, STERLING UNDEFINED
772550 17.06%
10.
Pilot and Purge
626
11. Assist Gas
0
12.
Fuel gas used in lease operations
49,839
13.
Other (see instructions)
0
Official Use Only
Authorization>1 hr:
Safety
MCF
14. TOTAL VOLUME (ITEMS 6.13)
236,876
Lease Use
MCF
15. NGL Gas Equivalent
2,153
Conservation
MCF
16.
Purchased gas- Rental Return Gas
144,325
Waste:
MCF
17.
Transferred from: (Off -lease Gas)
0/'�,/
Colrffiiss`iotfefr
�'�Date/�
18.
Transferred to:
(72,414)
19. Remarks:
Transferred to: Swanson Storage
To storage for fuel usage: 0 to Storage for Injection:
72414
To storage for injection is included in Line 6 as subject to
Other: Hemlock Production Sold
72,414
royalty.
72,828
I hereby certify that the fore ' oq and correct to the best of my knowledge
Signature Title Production Analyst to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
Printed Name Cortnev Dver Phone 713-289-2881 Date 5/20/2014 AAC25.235.
VL,F-
6/z¢/t4-
OR FLARING EVENTS GREATER THAN 1 HOUR
Action Taken to Minimize
R tDate
0 No
Facili No
Date Flared
Start Time
EndingTime
End Date
Planned
MCF
Description of FlaringEvent
Volume
Excess venting due to unscheduled
04/01/2014
124250
1330000002
4/6/2014
12:00:00 AM
2:00:00 PM
04/06/14
U
4
shutdown of Compressor K-22 due to
Unscheduled Maintenance.
the lose of the fn fan cooler belt.
Excess flaring due to unscheduled
04/01/2014
124250
1330000002
04/10/14
10:00:00 PM
11:59:00 PM
04/10/14
U
8
shutdown of the Lex Plant to work on
Unscheduled Maintenance.
the therminol heater.
Excess venting due to scheduled
04/01/2014
124250
1330000002
04/11/14
10:00:00 AM
11:45:00 aM
04/11/14
P
4
maintenance including an oil change
Scheduled Maintenance.
and filter change on the K-22
Compressor.
1330000002
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED OAS DISPOSITION
Swanson River
Swanson River Unit
6. Sold
196,873
7. Reinjected
0
8. Flared or vented 1 hour or less
30
9. Flared or vented more than 1 hour (see instr.)
906 1
10. Pilot and Purge
659
11. Assist Gas
0
12. Fuel gas used in lease operations
50,738
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6-13)
249,206
15. NGL Gas Equivalent
2,540 '
16. Purchased gas - Rental Return Gas
151,792 '
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(86.061) '
Transferred to: Swanson Storage 86,061
To storage for fuel usage: 0 to Storage for injection:
66061
To storage for irqection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 69,940
certify that the foregoing is true and correct to the best of my knowledge.
Signature 6&14W A9PW
Printed
HILCORP ALASKA LLC
Use
1 cv-
May 2014
;h pool as a
bP11
Note: All volumes must be correcte
to pressure of 14.65 pate and to a
temperature of 60o F. Authority 20
7/1 212 0 1 7 AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
6. Sold
196,873
7. Reinjected
0
8. Flared or vented 1 hour or less
30
9. Flared or vented more than 1 hour (see instr.)
906'
10. Pilot and Purge
659
11. Assist Gas
0
12. Fuel gas used in lease operations a�.�, fir-^
50,738
13. Other (see i;; tlpns)
0
14. TOTAL VOLUME (ITEMS 6-13)
249,206 -
15. NGL Gas Equivalent
2,016
16. Purchased gas - Rental Return Gas
151,792
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(86,061)
Transferred to: Swanson Storage 86,061
To storage for ruel usage: 0 In Storage for Injection.
ff1
To storage for injection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 69,940
hereby certify that the foregoing istrue
. aand Cor"re"ct to the best of my knowledge.
Signature CL4.t v y 7G/�//2� Title Prod
Printed Name Cortnev over 61 ii Phone 713:
Corrected
5. MonthNear of Disposition
tP ALASKA LLC May 2014
tiple pools, list contribution of each pool as a percent
Total Volume.
SWANSON RIVER, HEMLOCK
772100
62.66%
SWANSON RIVER, HEM FISTERUNG UNDEF
772105
0.00%
SWANSON RIVER, T'ONEK UNDEFINED
772500
2.69%
SWANSON RIVER, BELUGA UNDEFINED
772520
21.32%
SWANSON RIVER. STERLING UNDEFINED 1
772550
12.90%
Lease Use
Ite: All Volumes must be Corrected
pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
Corrected
OR FLARING EVENTS GREATER THAN 1 HOUR
Action Taken to Minimize
R tDate
O No
FacifilyNo
Date Flared
Start Timer6:30:OO
End Date
Planned
MCF
Description of Flann Event
Volume
Excess venting necessary until
Excess venting due to shutdown of
05/01/2014
124250
1330000002
5/16/2014
8:00:00 AM05/16/14
P
22
Compressor K-22 for Scheduled
the cooler could be cleaned
and the compressor could be
Maintenance to clean the cooler.
brought back online.
Excess venting due to a power
Excess venting necessary until
outage which caused the
power could be restored and
05/01/2014
124250
1330000002
05/31/14
11:15:00 AM
05/31/14
P
25
unavoidable shutdown of
Compressorcould be brought
Compressor K-22.
back online.
Excess flaring necessary until
et a ty
Excess fnca
05/01/2014
124250
1330000002
/3 /
OS 114
11:15:00 AM
11:59:00 PM
05/33/14
P
859
use
power could be restored and
shutdown cause by a power outage.
power outage.
equipment brought back online.
,�eZ)04-
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION 10
Facility Number
1330000002
2. Facility Name
Swanson River
3. Field
Swanson River Unit
4. Operator
HI LCORP ALASKA LLC
5. M/Year of Disposition
May 2014
Disposition
Volume MCF
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
. Sold
203,261
Pool Name Pool Code Percent
. Reinjected
0
SWANSON RIVER, HEMLOCK 772100 59.71%
SWANSON RIVER, HEM F/STERLING UNDEF 772105 0.00%
. Flared or vented 1 hour or less
30
SWANSON RIVER, iYONEK UNDEFINED 772500 2.75%
SWANSON RIVER, BELUGA UNDEFINED 772520 25.29%
. Flared or vented more than 1 hour (see instr.)
811
SWANSON RIVER, STERLING UNDEFINED 772550 12.25%
0. Pilot and Purge
663
1. Assist Gas
0
2. Fuel gas used in lease operations
51,053
3. Other (see instructions)
0
- Official Use Only
Authorization >1 hr:
Safety
�j
MCF
U �F
4. TOTAL VOLUME (ITEMS 6.13)
255,918
Lease Use
MCF
S. NGL Gas Equivalent
2,016
Conservation
MCF
6. Purchased gas -Rental Return Gas
147,620
Waste
JMCF
7. Transferred from: (Off -lease Gas)
0
/w— _
Commissioner—Date
8. Transferred to:
(88,595)
Note: All volumes must be corrected
Analyst to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
Date 6/20/2014 AAC25.235.
9. Remarks:
Transferred to: Swanson Storage 88,595
To storage for fuel usage: 0 to Storage for Injection:
72414
To storage for injection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 68,469
hereby certify that the foregoing is true and correct to the best of my knowledge.
Signature 'w D Title Production
Printed Name Cortnev Over Phone 713-289-2881
OR FLARING EVENTS GREATER THAN 1 HOUR
R tDateO
No
Facif No
Date Flared
Start Time
EndingTime
End Date
Planned
MCF
Descrition of Flaring Event
Action Taken to Minimize Volume
Excess venting necessary until
Excess venting due to shutdown of
the cooler could be cleaned and
05/01/2014
124250
1330000002
5/16/2014
8:00:00 AM
6:30:00 PM
05/16/14
P
22
Compressor K-22 for5cheduled
the compressor could be
Maintenance to clean the cooler.
brought back online.
Excess venting necessary until
Excessventing duetoa poweroutage
power could be restored and
05/07/2014
124250
1330000002
05/31/14
31:15:00 AM
11:59:00 PM
05/31/14
P
25
which caused the unavoidable
Compressor could be brought
shutdown of Compressor K-22.
back online.
Excess flaring necessary until
Excess flaring due to a facility wide
05/01/2014
124250
1330000002
05/31/14
11:15:00 AM
11:59:00 PM
05/31/14
P
863
power could be restored and
shutdown cause by a power outage.
equipment brought back online.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
(111V
1. Facility Number 2. Facility Name 3. Field 4. Operator 5. Month/Year 0t UISpoSltlon
1330000002 Swanson River Swanson River Unit HILCORP ALASKA LLC June 2014
Disposition I Volume MCF 1 20. For production from multiple pools, list contribution of each pool as a percent
6. Sold
173,992
7. Reinjected
0
8. Flared or vented 1 hour or less
357
9. Flared or vented more than 1 hour (see instr.)
1,2671
10. Pilot and Purge
805
11. Assist Gas
0
12. Fuel gas used in lease operations
49,664
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6.13)
226,085
15. NGL Gas Equivalent
4,995
16. Purchased gas - Rental Return Gas
181,205
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(186.052)
Transferred to: Swanson Storage 186,052
To storage for fuel usage: 0 to Storage for Injection:
86061
To storage for injection is included in Line 6 as subled to royaly.
Other: Hemlock Production Sold 7,341
Safety
Use
`•Flan,, vo(tx tii v,, 0.,it"a (
certify that the toregoing is true and correct to the bast or MY knowledge.
Note: All volumes must be
Signature �'0'�"� Ti0e Production Analyst corrected to pressure of 14.65 psia
and to a temperature of 60o F.
and hien,. Cnrfnmr rlvcr Phnne 713-2A0_2AA1 Date 7/12/2017 AuthOI11V 20 AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
I1. Facility Number e I D5
330000002 12. Facility NamSwanson River I3. Field Swanson River Unit I4 Op HILCORP ALASKA LLC Irator5. Month J % 20114position
Disposition I Volume MCF 1 20. For production from multiple pools, list contribution of each pool as a percent of
6. Sold
173,992
7. Reinjected
0
8. Flared or vented 1 hour or less
357
9. Flared or vented more than 1 hour (see instr.)
1,267
10. Pilot and Purge
805
11. Assist Gas
0
12. Fuel gas used in lease operations
49,664
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6.13)
226,085
15. NGL Gas Equivalent
3,964
16. Purchased gas - Rental Return Gas
181,205
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(136,0521
Transferred to: Swanson Storage 186,052
To storage Wr fuel usage: 14044 to Storage for
Injection: 172008
To storage for injection is included in Line 6 as subled to royalty.
Other: Hemlock Production Sold 7,341
certify that the foregoing is true and Correct to the best of my knowledge.
Signature Title Prodi.
ted Name Cndnev over Phone 713-,
HEMLOCK
772500
9.71
1ae1 �x viny
MCF V�
MCF s12$J1�-
Use
Nation MCF
.L..- ' 3MCF
/ Date
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
OR FLARING EVENTS GREATER THAN 1 HOUR
Action Taken to Minimize
R tDater124250
Facili No
Date Flared
Start Time
Ending Time
End Date
Planned
MCF
Description of Flaring Event
Volume
Excess venting necessary until
Excess venting due to a power outage
Power could be restored and
06/01/2014
1330000002
06/01/2014
12:00:00 AM
6:30:00 PM
06/02/14
U
84
which caused the unavoidable
Compressor could be brought
shutdown of Compressor K-22.
back online.
Excess venting necessary until a
Excess venting due to unavoidable
06/01/2014
124250
1330000002
06/03/2014
02:00:00 PM
3:25:00 PM
06/03/14
U
3
shutdown of Compressor K-22 caused
new throttle rod could be
installed and compressor
by a broken throttle rod.
restarted.
Excess venting due to scheduled
Excess venting necessary until
preventative maintenance on
preventative maintenance
06/01/2014
124250
1330000002
06/05/2014
07:30:00 AM
9:15:00 PM
06/05/14
P
4
Compressor K-22 for an ail and filter
could be completed and
change.
compressor restarted.
Excess venting necessary until
Excess venting due to a power outage
power could be restored and
06/01/2014
124250
1330000002
06/16/2014
4:15:00 PM
11:00:00 PM
06/16/14
U
10
which caused the unavoidable
Compressor could be brought
shutdown of Compressor K-22.
back online.
Excess flaring due to unscheduled
Excess flaring necessary until
maintenance on Compressor K-8 farM
06/01/2014
124250
1330000002
06/17/2014
4:00:00 AM
6:45:00 P
06/21/14
U
1111
the dense of the leak could be
repair of a gas leak on the suction
identified and repaired.
scrubber.
Excess venting necessary until
Excess venting due to Compressor K-8
maintenance could be
06/01/2014
124250
1330000002
06/21/2014
12:05:00 AM
6:05:00 PM
06/21/14
U
41
scrubber bottle failure and overload
performed. The scrubber bottle
of Compressor K-22.
on Compressor K-8 was
replaced.
Excess flaring necessary until
Excess flaring due to unavoidable
preould a normalized
06/01/2014
124250
1330000002
06/24/2014
11:15:00 AM
12:45:00 PM
06/24/14
U
14
shutdown of Compressor K-8 due to
ressor
and compressor brought back
and comsurepressor ought
high #350 Flare pressure.
online.
1330000002
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
Swanson River
Swanson River Unit
6. Sold
132,497
7. Reinjected
0
8. Flared or vented 1 hour or less
133
9. Flared or vented more than 1 hour (see instr.)
9 1
10. Pilot and Purge
617
11. Assist Gas
0
12. Fuel gas used in lease operations
51,874
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6-13)
185,130
15. NGL Gas Equivalent
8,464'
16. Purchased gas - Rental Return Gas
143,237
17. Transferred from: (Off -lease Gas)
0
118. Transferred to: 1 (45,800)
Transferred to: Swanson Storage 45,800
To storage for fuel usage: 0 to Storage for Injection:
45800
To storage for injection is induced in Line 6 as subject to royalty.
Other: Hemlock Production Sold 67,498
HILCORP ALASKA LLC
>1
I. Fen �i . -life*
Of
Use
f 6/ -
July
July 2014
:h pool as a
a.1 GrL.na.I
certify that the foregoing is true and correct to the lest of my knowledge.
/� Note: All volumes must be
Signature A%aef Title Production Analyst corrected to pressure of 14.65 psia
and to a temperature of 60o F.
ted Name Cortnev Over Phone 713-289-2881 Date 7112120117 Authority 20 AAC25.235.
RECEIVE®
AUG 2 2 2014
STATE OF ALASKA AOGCC
ALASKA OIL AND GAS CONSERVATION COMMISSION ��//
I. Facility Number
1330000002
2. Facility Name
Swanson River
3. rielo
Swanson River Unit
v. upe�aou ,........
HILCORP ALASKA LLC July 2014
Disposition
Volume MCF
20. For production from multiple pools, list contribution of each pool as a percent of
Total Volume.
3. Sold
132,497
Pool Name Pool Code Percent
7. Reinjected
0
SWANSON RIVER, HEMLOCK 772100 79.94%
SWANSON RIVER, HEM F/STERLING UNDEF 772105 0.00%
3. Flared or vented 1 hour or less133
SWANSON RIVER, TYONEK UNDEFINED 772500 2.55%
SWANSON RIVER, BELUGA UNDEFINED 772520 0.00%
9. Flared or vented more than 1 hour (see Iflsb.)
9-
SWANSON RIVER, STERLING UNDEFINED 772550 17.52%
10. Pilot and Purge
617
11. Assist Gas
0
12. Fuel gas used in lease operations - i+:
51,874
13. Othersee instructions)
(
0
Official Use Only
Authorization >1 hr:
Safety
U
MCF
V LF
/ Lt
14. TOTAL VOLUME (ITEMS 6.13)
185,130
Lease Use
MCF
15. NGL Gas Equivalent
2,821
Conservation
MCF
16. Purchased gas - Rental Return Gas
143.237
Waste:
MCF
17. Transferred from: (Off -lease Gas)
0
C mml Date
18. Transferred to:
(45,800)
Note: All volumes must be corrected
Analyst pressure of 14.65 Asia and to a
temperature of 60o F. Authority 20
Date 8/18/2014 AAC25.235.
19. Remarks:
Transferred to: Swanson Storage 45,800
To storage far fuel usage: 0 w Storage for Injection:
45600
To storage for injection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 67,498
1 hereby certify that the foregoing is true and correct to the best of my knowledge.
%%����
Signature lF'�- L� Title Production
M—r,.n�<,. n„or Phone 713-289-2881
OR FLARING EVENTS GREATER THAN 1 HOUR
Action Taken t0 Minimize
R tDate
O No I
FacilitvNo
Date Flared
Start Time
Ending Time
End Date
Planned
MCF
Description of Flaring Event
Volume
Excess venting necessary until
Excess venting due to a power outage
power could be restored and
06/01/2014
124250
1330000002
06/01/2014
12:00:00 AM
6:30:00 PM
06/02/14
U
84
which caused the unavoidable
Compressor could be brought
shutdown of Compressor K-22.
back online.
Excess venting necessary until a
Excess venting due to unavoidable
new throttle rod could be
06/01/2014
124250
1330000002
06/03/2014
02:00:00 PM
3:25:00 PM
06/03/14
U
3
shutdown of Compressor K-22 caused
installed and compressor
by a broken throttle rod.
restarted.
Excess venting due to scheduled
Excess venting necessary until
preventative maintenance on
preventative maintenance
06/01/2014
124250
1330000002
06/05/2014
07:30:00 AM
9:15:00 PM
06/05/14
P
4
Compressor K-22 for an oil and filter
could be completed and
change.
compressor restarted.
Excess venting necessary until
Excess venting due to a power outage
power could be restored and
06/01/2014
124250
1330000002
06/16/2014
4:15:00 PM
11:00:00 PM
06/16/14
U
10
which caused the unavoidable
Compressor could be brought
shutdown of Compressor K-22.
back online.
Excess flaring due to unscheduled
Excess flaring necessary until
06/01/2014
124250
1330000002
06117/2014
4:00:00 AM
6:45:00 PM
06/21/14
U
1111
maintenance on Compressor K-8 for
the cause of the leak could be
repair of a gas leak on the suction
identified and repaired.
scrubber.
Excess venting necessary until
Excess venting due to Compressor K-8
maintenance could be
06/01/2014
124250
1330000002
06/21/2014
12:05:00 AM
6:05:00 PM
06/21/14
U
41
scrubber bottle failure and overload
performed. The scrubber bottle
of Compressor K-22.
on Compressor K-8 was
replaced.
Excess flaring necessary until
Excess flaring due to unavoidable
pressure could be normalized
06/01/2014
124250
1330000002
06/24/2014
11:15:00 AM
12:45:00 PM
06/24/34
U
14
shutdown of Compressor due to
and compressor brought back
high p350 Flare pressure.
online.
1330000002
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
Swanson River
Swanson River Unit
6. Sold
154,851
7. Reinjected
0
8. Flared or vented 1 hour or less
42
9. Flared or vented more than 1 hour (see instr.)
1951
10. Pilot and Purge
766
11. Assist Gas
0
12. Fuel gas used in lease operations
49,413
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6-13)
205,267
15. NGL Gas Equivalent
2,522'
16. Purchased gas - Rental Return Gas
159,881
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(64,064)
Transferred to: Swanson Storage 64,064
To storage for fuel usage: 0 to Storage for Injedion:
64060
To storage for injection is inducted In Line 6 as subject to royalty.
Other: Hemlock Production Sold 71,224
oertry that the toregomg is true and correct to me nest or my Knovneage.
Signature ' 4W Title
Name
HILCORP ALASKA LLC
Use
GU
August 2014
3ch pool as a percent
I. Flae,. a f fee'.4.IL an Onyt�.%1,.
_ to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
Dale 7/13/2017 AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Swanson River Unit
6.
Sold
154,851
7.
Reinjected
0
8.
Flared or vented 1 hour or less
42
9.
Flared or vented more than 1 hour (see instr.)
195'
10.
Pilot and Purge
766
11. Assist Gas
0
12. Fuel gas used in lease operations
49,413
13.
Other (see instructions)
0
14.
TOTAL VOLUME (ITEMS 6-13)
205,267
15.
NGL Gas Equivalent
2,522
16.
Purchased gas - Rental Return Gas
159,881
17.
Transferred from: (Off -lease Gas)
0
18.
Transferred to:
(64,064)
Transferred to:
Swanson Storage
64,064
Vc--
To storage forfuel usage: 0 to Storage for Injection:
MCF
64064
MCF
To storage for injection is included in Line 6 as subject
to royalty.
Other:
Hemlock Production Sold
71,224
1 hereby certify that the foregoing is true amend c"orre�ct to the best of my knowledge.
Signature trig
2Y -g:.
Title Production Ar
Printed Name Cortnev Dver
Phone 713-289-2881
Date
HILCORP ALASKA LLC
rom multiple pools, list oontri
Total Volume.
RECEIVE®
SEP 19 2014
AOGCC
,t 2014
as a percent
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
g�
MCF
Vc--
Use
MCF
nation
MCF
MCF
-P/ Ir, —Cj_l q
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
' n ?014
OR FLARING EVENTS GREATER THAN 1 HOUR
Action Taken to Minimize
R tDate
O No
FacilityNo
Date Flared
Start Time
Ending Time
End Date
Planned
MCF
Description of Flaring Event
Volume
Excess venting due to unscheduled
Excess venting necessary until
08/01/2014
124250
1330000002
8/2/2014
S:00:00 PM
11:59:00 PM
8/2/2014
N
14.0
shutdown of Compressor K-22
compressor could be restarted
because of low suction.
and brought back online.
Excess venting due to unscheduled
E-22 xcess venting necessary until
08/01/2014
124250
1330000002
8/4/2014
11:00:00 AM
12:30:00 PM
8/4/2014
N
3.0
shutdown of Compressor
compressor could be restarted
i n Tank
because of high tank vapors n Ta
and brought back online.
22.
Excess venting due to high
Excess venting necessary until
08/01/2014
124250
1330000002
8/5/2014
5:30:00 PM
6:45:00 PM
8/5/2014
N
2.5
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting necessary until
Excess venting due to unscheduled
08/01/2014
124250
1330000002
8/7/2014
130:00 PM
11:59:00 PM
8/7/2014
N
21.1
shutdown of Compressor K-22.
the mechanic could address the
work order. Compressor was
Compress or would not stay running.
repaired and restarted.
Excess venting necessary until
Excess venting due to unscheduled
the mechanic could address the
08/01/2014
124250
1330000002
8/8/2014
12:01:00 AM
7:00:00 AM
8/8/2014
N
14.0
shutdown of Compressor K-22.
work order. Compressor was
repaired and restarted.
Excess venting due to unscheduled
Excess venting necessary until
08/01/2014
124250
1330000002
8/17/2014
10:00:00 AM
11:30:00 AM
8/17/2014
N
3.0
shutdown of Compressor K-22
compressor could be loaded
because of high vapors from Tank 22
which overloaded the compressor.
and restarted.
Excess venting due to well liquids
Excess venting necessary until
08/01/2014
124250
1330000002
8/19/2014
11:00:00 AM
3:00:00 PM
8/19/2014
Y
8.0
unloading causing over pressurization
pressure could be relieved and
in the field.
liquids unloaded from wells.
Excess venting due to shutdown of
Excess venting necessary until
08/01/2014
124250
1330000002
8/21/2014
2:00:00 PM
7:15:00 PM
8/21/2014
N
10.5
Compressor K-22 because of high
the compressor cooled and
temperature alarms.
restarted.
RECEIVED
SEP 19 2014
40( cn
OR FLARING EVENTS GREATER THAN 1 HOUR
Action Taken to Minimize
R tOate O No Facili No Date Flared Start Time Ending Time End Date Planned MCF Deacri tion of FlaringEvent Volume
Excess venting due to high
Excess venting necessary until
08/01/2014
124250
1330000002
8/22/2014
12:00:00 PM
4:30:00 PM
8/22/2014
N
9.0
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to high
Excess venting necessary until
08/01/2014
124250
1330000002
8/23/2014
3:00:00 PM
4:30:00 PM
8/23/2014
N
3.0
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to high
Excess venting necessary until
08/01/2014
124250
1330000002
8/24/2014
12:00:00 PM
2:30:00 PM
8/24/2014
N
5.0
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to high
Excess venting necessary until
08/01/2014
124250
1330000002
8/25/2014
12:00:00 PM
4:45:00 PM
8/25/2014
N
9.5
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to unscheduled
Excess venting necessary until
shutdown of Compressor K-22 caused
valve issues could resolved
08/01/2014
124250
1330000002
8/26/2014
6:15:00 AM
11:59:00 PM
8/26/2014
N
35.6
by valve trouble and valve cover
and compressor brought back
replacement.
online.
Excess venting due to high
Excess venting necessary until
08/01/2014
124250
1330000002
8/27/2014
12:00:00 PM
10:00:00 PM
8/27/2014
N
20.1
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to high
Excess venting necessary until
08/01/2014
124250
1330000002
8/28/2014
5:00:00 PM
8:30:00 PM
8/28/2014
N
7.0
temperature and low suction
the compressor cooled and
shutdown of Compressor K-22.
restarted.
Excess venting due to high
Excess venting necessary until
08/01/2014
124250
1330000002
8/29/2014
12:00:00 PM
7:30:00 PM
8/29/2014
N
15.0
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to high
Excess venting necessary until
08/012014
124250
1330000002
8/30/2014
11:15:00 AM
6:30:00 PM
F8/30/2014
N
14.5
temperature shutdown of
the compressor cooled and
I
Compressor K-22.
restarted.
1330000002
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
Swanson River
Swanson River Unit
B.
Sold
218,012
7.
Reinjected
0
8.
Flared or vented 1 hour or less
501
9.
Flared or vented more than 1 hour (see matt.)
8 it
10.
Pilot and Purge
594
11. Assist Gas
0
12. Fuel gas used in lease operations
50,072
13.
Other (see instructions)
0
14.
TOTAL VOLUME (ITEMS 6-13)
269,187
15.
NGL Gas Equivalent
2,238 -
16.
Purchased gas - Rental Return Gas
157,090
17.
Transferred from: (Off -lease Gas)
0
18.
Transferred to:
(81.215)
Transferred to: Swanson Storage 81.215
To storage for fuel usage: 0 to Storage for Injection:
81215
To storage for irlec8on is inducted in Line 6 as subject to royalty.
Other: Hemlock Production Sold 80,330
Signature & ' low
HILCORP ALASKA LLC
Safety
Use
September 2014
each Dooi as a o
I. Ft Wkn d�oQrwco� o.-- e,r .cra l
Note: All volumes must be corrected
to pressure of 14.65 Pete and to a
temperature of 60o F. Authority 20
AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Production
6.
Sold
Other (see instructions)
218,012
7.
Reinjected
NGL Gas Equivalent
0
8.
Flared or vented 1 hour or less
Transferred from: (Off -lease Gas)
501
9.
Flared or vented more than 1 hour (see instr.)
8
10.
Pilot and Purge
594
1. Assist Gas
12. Fuel gas used in lease operations
13.
Other (see instructions)
14.
TOTAL VOLUME (ITEMS 6-13)
15,
NGL Gas Equivalent
16.
Purchased gas - Rental Return Gas
17.
Transferred from: (Off -lease Gas)
18.
Transferred to:
0
50,072
0 n,,r
269,187
2,238
157,090
0
(81,215)
Transferred to: Swanson Storage 81,215
To storage for Mel usage: o to Storage for lnjedion:
81215
To storage for injection is indwled in Line 6 as subject to royalty.
Other: Hemlock Production Sold 80,330
:ertify that the foregoing is ttrruee. and correct to the best of my knowledge.
Signature l�"7�y Title
Use
RECEIVED
OCT 2 1 2014
,AOGC C
as a
MCF ! 12
Note: All volumes must be corrected
pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
RECEIVED
OCT 2 1 2014
OR FLARING EVENTS GREATER THAN 7 HOUR
Action Taken to Minim¢e
R tDate O No FacilityNc, Date Flared Start Time Ending Time End Date Planned MCF DescriptionFlaring Event Volume
Excess venting due to unscheduled
Excess venting necessary until
shutdown of Compressor K-22 caused
compressor rpms could be
09/07/2014
124250
1330000002
9/2/2014
6:45:00 AM
9:30:00 AM
9/2/2014
N
5.3
by increased tank vapors due to wells
increased and compressor
being brought online.
restarted.
Excess venting due to unscheduled
Excess venting necessary until
9/23/2014
2:15:00 PM
3:45:00 PM
9/23/2014
N
2.7
shutdown of Compressor K-22 due to
both Compressor and K-22
09/07/2014
124250
7330000002
high discharge pressure from
ar
could be restarted.
shutdown of Compressor K-6.
,2"3,D)0-4
1330000002
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
Swanson River
Swanson River Unit
6. Sold
222,142
7. Reinjected
0
8. Flared or vented 1 hour or less
508
9. Flared or vented more than 1 hour (see instr.)
3.981 1
10. Pilot and Purge
1,188
11. Assist Gas
0
12. Fuel gas used in lease operations
87,342
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6-13)
315,161
15. NGL Gas Equivalent
2,038
16. Purchased gas - Rental Return Gas
179,832
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(27.111)
Transferred to: Swanson Storage 27,111
To storage for fuel usage: 0 to Storage for Injection:
81215
To storage for igection is included in Line 6 as subjed to royalty.
Other: Hemlock Production Sold 111,286
Signature 6 y'VIW
Printed Name
HILCORP ALASKA LLC
>1
1- nir,n VV
of Total Volume.
Use
L✓
October 2014
:ach pool as a
A.nl ✓0-.K OvI. C11L tX%W-
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITInN
Name
6. Sold
87,342
222,142
7. Reinjected
g
g
8. Flared or vented 1 hour or less
315,161
508
9. Flared or vented more than 1 hour (see instr.)
2,038
3,981-
10. Pilot and Purge
179,832
1,188
11. Assist Gas
0
g
12. Fuel gas used in lease operations
87,342
13.
Other (see instructions)
g
14.
TOTAL VOLUME (ITEMS 6.13)
315,161
15.
NGL Gas Equivalent
2,038
16.
Purchased gas - Rental Return Gas
179,832
17.
Transferred from: (Off -lease Gas)
0
18.
Transferred to:
19.
Remarks:
Transferred to: Swanson Storage 27,111
To storage for fuel usage: 0 to Storage for Injection:
81215
To storage for injection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 111,286
centty trial the toregoing Is true" and correct to the best of my knowledge.
Signature B2rluu,/ TDyg�,
f.A KI.— !`..Mne.. In.—
HILCORP ALASKA LLC ) October 20
rom multiple pools, list contribution of each pool as a
HEM
Use
1-2--Is-
to pressure of 14.65 pails and to a
temperature of 60o F. Authority 20
yTL
14191J4
I
OR FLARING EVENTS GREATER THAN 1 HOUR
I
Action Taken to Minimize
R !Date
O No
FacilitvNo
Date Flared
Start Time
Endina Time
End Date
Planned
MCF
Description of Flaring Event
Volume
10/01/2074
124250
1330000002
10/9/2014
12:01:00 AM
10/9/2014
4:00:00 AM
N
184.3
Excess flaring due to valve on
Excess flaring necessary until
vessel left open and gas sent to flare.
an
open valve could be located
and closed.
Excess venting due to high
Excess venting necessary until
10/01/2014
124250
1330000002
10/10/2014
3:30:00 PM
10/10/2014
4:45:00 PM
N
4.3
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess flaring necessary until
10/01/2014
124250
1330000002
10/11/2014
8:00:00 AM
10/11/2014
4:00:00 PM
N
1720.4
Excess flaring due to a facility wide
power could be restored and
shutdown cause by a power outage,
equipment brought back
online.
Excess flaring necessary until
10/01/2014
124250
1330000002
10/11/2014
8:00:00 AM
10/11/2014
4:00:00 PM
N
69.5
Excess flaring due to a facility wide
power could be restored and
shutdown cause by a power outage.
equipment brought back
online.
Excess flaring necessary until
10/01/2014
124250
1330000002
10/11/2014
8:00:00 AM
10/11/2014
4:00:00 DM
N
144.7
Excess flaring due to a facility wide
power could be restored and
shutdown cause by a power outage.
equipment brought back
online.
Excess venting due a power outage
Excess venting necessary until
70!01/2014
124250
1330000002
10/11/2014
8:00:00 AM
10/11/2014
4:00:00 PM
N
28.0
which caused thee unavoidable
power could be restored and
shutdown of Compressor K-22.
Compressor could be brought
back online.
Excess flaring due to high production
10/01/2014
124250
1330000002
10/14/2014
8:30:00 AM
10/14/2014
10:30:00 PM
N
2,9
which caused an
Excess flaring necessary until
overload/overpressurization of
production slowed down and
compressor able to handle gas.
Compressor K-8.
Excess venting due to high production
10/01/2014
124250
1330000002
10/14/2014
12:00:00 PM
10/14/2014
7:45:00 PM
N
27,1
which caused an
Excess venting necessary until
overload/overpressurization of
production slowed down and
compressor able to handle gas.
Compressor K-22.
16, ' 1
Action Taken to Minimize
R tDate
O No
FacalltyNo
Date Flared
Start Time
Ending Time
End Date
Planned
MCF
Description of Flaring Event
Volume
Excess venting due to high production
Excess venting necessary until
10/01!2014
124250
1330000002
10/15/2014
4:00:00 AM
10/15/2014
10:45:00 AM
N
23.6
which caused an
Production slowed down and
overload/overpressurization of
compressor able to handle gas.
Compressor K-22.
Excess venting due to high
Excess venting necessary until
10/01/2014
124250
1330000002
10/17/2014
1:30:00 AM
10/17/2014
3:00:00 PM
N
5.2
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to high production
Excess venting necessary until
10/01/2014
124250
1330000002
10/19/2014
12:00:00 PM
10/19/2014
2:00:00 PM
N
7.0
which caused an
Production slowed down and
overload/overpressurization and high
compressor able to handle gas.
temperatures on Compressor K-22.
Excess flaring due to unscheduled
maintenance on Compressor K-8
caused by lose If #2 Comp. Cylinder
Excess flaring necessary until
10/01/2014
124250
1330000002
10/22/2014
2:00:00 AM
10/28/2014
1:00:00 PM
N
1708.9
piston liner. Parts are on order and
parts arrive and Compressor K -
are scheduled to arrive on November
8 can be repaired.
3. Until parts arrive, Compressor K-8
will flare continuously.
Excess venting due to unscheduled
10/01/2014
124250
1330000002
10/22/2014
12:00:00 PM
10/22/2014
6:00:00 PM
N
21.0
shutdown of Compressor K-22 due to
Excess venting necessary until
high discharge pressure from
both Compressor K-22 could be
shutdown of Compressor K-8.
restarted.
Excess venting due to high
Excess venting necessary until
10/01/2014
124250
1330000002
10/28/2014
3:30:00 AM
10/28/2014
5:00:00 PM
N
5.2
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to high
Excess venting necessary until
10/01/2014
124250
1330000002
10/29/2014
9:15:00 AM
10/29/2014
11:00:00 AM
N
6.1
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due unscheduled
Excess venting necessary until
10/01/2014
124250
1330000002
10/31/2014
9:15:00 AM
70/31/2014
3:45:00 PM
N
22.8
shutdown of Compressor
or due to
compressor could be loaded
high discharge pressure. .
and restarted, line was swept
and pumped with Methanol.
16, ' 1
1330000002
S. Sold
7. Reinjected
S. Flared or vented 1 hour or less
9. Flared or vented more than 1 hour (see instr.)
10. Pilot and Purge
11. Assist Gas
12. Fuel gas used in lease operations
13. Other (see instructions)
14. TOTAL VOLUME (ITEMS 6-13)
15. NGL Gas Equivalent
16. Purchased gas - Rental Return Gas
17. Transferred from: (Off -lease Gas)
18. Transferred to:
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
Swanson River I Swanson River Unit I HILCORP ALASKA LLC
CY
November 2014
of each 000l as a r
98,423
Pool Name Pool Code
0
SWANSON RIVER, HEMLOCK 772100
SWANSON RIVER, HEM F/STERLING UNDEF 772105
100
SWANSON RIVER, TVONEK UNDEFINED 772500
SWANSON RIVER, BELUGA UNDEFINED 772520
7171
SWANSON RIVER, STERLING UNDEFINED 772550
1,561
0
89,589
0
Oficial Use Only
Authorization>1 hr:
Safety
190,390
Lease Use
1,835 '
Conservation
142,765
Waste:
0
Commissioner
(32,529)
Transferred to: Swanson Storage 32,529
To storage for fuel usage: 0 to Storage for Injection:
32529
To storage for injection is included in Lina 6 as subject to royalty.
Other: Hemlock Production Sold 49,452
Signature 100"
Printed Name
\. fl -a",3 aO for,a �L—L
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
Facility Name
Transferred to: Swanson Storage 32,529
To storage for fuel usage: 0 to Storage for Injection:
32529
To storage for injection is includetl in Line 6 as subject to royalty.
Other: Hemlock Production Sold 49,452
certify that the foregoing is true and correct to the best of my knowledge.
Signature Leo �yyti Title Prodt
ae,f M--- r�rf— n„or Phone 713-2
>1 hr:
pools, list contribution
Total Volume.
Use
RECEIVE®
DEC 22±4 20011x4
A®GCC
ter 2014
as a per
12%
Note: All volumes must be corrects
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
V7—L—
j�8f l5
6. Sold
98,423
7. Reinjected
0
8. Flared or vented 1 hour or less
100
9. Flared or vented more than 1 hour (see instr.)
717 '
10. Pilotand Purge
1,561
11. Assist Gas
0
12. Fuel gas used in lease operations
89,589
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6.13)
190,390
15. NGL Gas Equivalent
1,835
16. Purchased gas - Rental Return Gas
142,765
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(32,529)
19. Remarks:
Transferred to: Swanson Storage 32,529
To storage for fuel usage: 0 to Storage for Injection:
32529
To storage for injection is includetl in Line 6 as subject to royalty.
Other: Hemlock Production Sold 49,452
certify that the foregoing is true and correct to the best of my knowledge.
Signature Leo �yyti Title Prodt
ae,f M--- r�rf— n„or Phone 713-2
>1 hr:
pools, list contribution
Total Volume.
Use
RECEIVE®
DEC 22±4 20011x4
A®GCC
ter 2014
as a per
12%
Note: All volumes must be corrects
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
V7—L—
j�8f l5
OR FLARING EVENTS GREATER THAN 1 HOUR
Action Taken to Minimize
R tDate
O No
Facili No
Date Flared
Start Time
EndingTime
End Date
Planned
MCF
Description of FlaringEvent
Volume
Excess venting necessary until
Excess venting due to plugging of the
a cutting box was set up to
11/01/2014
124250
1330000002
11/1/2014
12:01:00 AM
6:30:00 PM
11/1/2014
U
65.2
discharge line on Compressor K-22
blow the line into and
causing a high pressure shutdown.
compressor brought back
online.
Excess venting due to unscheduled
Excess venting necessary until
11/01/2014
124250
1330000002
11/2/2014
12:30:00 AM
7:00:00 AM
11/2/2014
U
23.4
shutdown of Compressor K-22
Compressor K-22 could be
caused by high discharge. Line was
brought back online.
blown down to cutting box.
Excess venting due to
Excess venting due to unscheduled
unscheduled shutdown of
11/01/2014
124250
1330000002
11/3/2014
8:30:00 AM
9:45:00 AM
11/3/2014
U
4.9
shutdown of Compressor K-22
Compressor K-22 because of
because of high discharge pressure.
high discharge pressure.
Excess venting due to high
Excess venting necessary until
11/0112014
124250
1330000002
11/5/2014
8:15:00 AM
9:30:00 AM
11/5/2014
U
4.4
temperature shutdown of
the compressor cooled and
Compressor K-22.
restarted.
Excess venting due to unscheduled
Excess venting necessary until
11/01/2014
124250
1330000002
11/10/2014
8:30:00 PM
11:30:00 PM
11/10/2014
U
10.7
shutdown of Compressor K-22
because of high vapors from Tank 22
compressor could be loaded
and restarted.
which overloaded the compressor.
Excess venting necessary until
Excess venting due to unscheduled
parts can be ordered and
11/01/2014
124250
1330000002
11/16/2014
5:45:00 AM
6:00:00 PM
11/20/2014
U
381.6
shutdown of Comressor K-22 caused
shipment arrived. Compressor
by lost of the #2 Compressor Cylinder.
is expected to be down for
about 3 more days.
Excess venting due to a power
Excess venting necessary until
outage which caused the
power could be restored and
11/01/2014
124250
1330000002
11/18/2014
12:45:00 PM
8:45:00 PM
11/18/2014
U
200.5
unavoidable shutdown of
Compressor could be brought
Compressor K-8.
back online.
Excess venting necessary until
Excess venting due to scheduled
maintenance could be
11/01/2014
124250
1330000002
11/21/2014
6:00:00 AM
9:00:00 AM
11/21/2014
P
10.7
maintenance on Compressor K-22 to
complete and compressor
replace the valves on Cylinder #1.
brought back online.
Excess venting necessary until
Excess venting due to the 20V3
o the 20V1ng
vent ngair
an indirect heater and steam
11/0112014
124250
1330000002
11/25/2014
6:00:00 AM
10:30:00 AM
11/25/2014
U
15.6
iExcess
lines o
which caused an unscheduled
could be used on the air lines
and line unfrozen. Compressor
shutdown of Compressor K-22.
loaded and restarted.
Z , i
PAI YA
1330000002
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
fGv,
Swanson RiverI Swanson River Unit I HILCORP ALASKA LLC I December 201
Volume MCF 1 20. For production from multiple pools, list contribution of each pool as a
6.
Sold
174,166
7.
Reinjected
0
8.
Flared or vented 1 hour or less
131
9.
Flared or vented more than 1 hour (see instr.)
1,2281
10.
Pilot and Purge
2,244
11.
Assist Gas
0
12. Fuel gas used in lease operations
91,095
13.
Other (see instructions)
0
14.
TOTAL VOLUME (ITEMS 6-13)
268,864
15.
NGL Gas Equivalent
1,069
16.
Purchased gas - Rental Return Gas
146,131
17.
Transferred from: (Off -lease Gas)
0
118. Transferred to: 1 (51650) 1
Transferred to: Swanson Storage 51,650
To storage for fuel usage: 0 to Storage for Injection:
51650
To storage for injection is included in Line 6 as subject to royalty.
Other: Hemlock Production Sold 63,711
cemry mal me toregoing Is true ana correct to me nest or my Knowieage.
Signature �A+y 15?i1l" Title
Use
I. f)0f'ery ayffadej O,
tote: All volumes must be corrects,
to pressure of 14.65 pale and to a
temperature of 60o F. Authority 20
AAC25.235.
STATE OF ALASKA
ALASKA OIL AND GAS CONSERVATION COMMISSION
FACILITY REPORT OF PRODUCED GAS DISPOSITION
Facility Number 12. Facility Name 13. Field 14
20. For production
6. Sold
174,166
7. Reinjected
0
8. Flared or vented 1 hour or less
131
9. Flared or vented more than 1 hour (see instr.)
1,228 '
10. Pilotand Purge
2,244
11. Assist Gas
0
12. Fuel gas used in lease operations
91,095
13. Other (see instructions)
0
14. TOTAL VOLUME (ITEMS 6-13)
268,864
15. NGL Gas Equivalent
1,069
16. Purchased gas- Rental Return Gas
146,131
17. Transferred from: (Off -lease Gas)
0
18. Transferred to:
(51,650)
Transferred to: Swanson Storage 51,650
To storage for fuel usage. 0 to Storage for Injection,
51650
To storage for injection is induced in Line 6 as subjed to royalty.
Other: Hemlock Production Sold 63,711
zrtify that the foregoing Is true and correct to the best of my knowledge.
SignatureyL/ Title Prod
Ipd Namp Codnpv rlvpr Phone 713-
RECEIVE®
JAN 2 1 2015
AOGCC
multiple pools, list contri
Total Volume,
Use
December 2014
ch pool as a per
122-0
to pressure of 14.65 psia and to a
temperature of 60o F. Authority 20
VtL
OR FLARING EVENTS GREATER THAN 1 HOUR
Action Taken to Minimize
R tDater124250
Facili No
Date Flared
Start Time
EndingTime
End Data
Planned
MCF
Desai ion of Rating Event
Volume
Excess venting due to scheduled
Excess venting necessary until
12/0112014
1330000002
12/19/2014
4:00:00 PM
8:00:00 PM
12/19/2014
P
47.0
maintenance to depressurize the back
maintenance could be
side of the ESP.
complete.
Excess venting due to blow down of
12/01/2014
1330000002
12/20/2014
12:00:00 AM
11:59:00 PM
12/22/2014
P
863.4
Well 14B-27 while performing a flow
Excess venting necessary until
test. Venting from the back side
flow testing can be completed.
casing to a Johnson tank.
Excess venting due to scheduled
Excess venting necessary until
12/01/2014
124250
1330000002
12/21/2014
12:00:00 PM
2:45:00 PM
12/21/2014
P
9.6
maintenance on Compressor K-22 to
maintenance could be
change the oil and filters, replace
completed and compressor
spark plugs, and adjuste lube rates.
restarted.
Excess venting necessary until
Excess venting due to unscheduled
12/01/2014
124250
1330000002
12/23/2014
4:15:00 AM
11:59:00 PM
12/26/2014
U
308.0
maintenance on Compressor K-22
spare parts can be ordered and
received by the facility and
due to loss of a cylinder.
repairs could be made.