Alaska Logo
Department of Commerce, Community, and Economic Development
Alaska Oil and Gas Conservation
Commission
Loading...
HomeMy WebLinkAboutUNOCAL - GRANITE POINTState of Alaska Alaska Oil & Gas Conservation Commission 1999 Facility Report Files File Names Gas Disposition ALASKA OIL AND GAS CONSER~TATION COMMISSION FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility Operator Field(s) Month/Year of Disposition Granite Point Platform Unocal Oil and Gas Granite Point Jan 98 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 319 4. Flared or vented greater than 1 hour (Supplemental report required--See 20 AAC 25.235) 927 5. Pilot and Purge 620 6. Used for lease operations 41,295 7. Other 0 TOTAL items 1 - 7 43,156 8. NGL gas equivalent produced 0 9. Purchased gas 51G 10. Transferred from: Granite Point Plt. 0 GPTF-LEX 11. Transferred to: GPTF•GPP 35,272 5,902 Remarks: I hereby certify that the foregoing is true and correct to the best of my knowledge. Signature ~~ /7~l•-ter- Title: Acct. Supervisor Date: 2/16/99 *Lidicate contribution of each pool to total. Pool Name Code Percent Tyonek Lease 18761 280150 79.12% Hemlock Lease 18761 280152 5.48% ,Tyonek Lease 374044 280150 3.57% Tyonek Lease 374045 280150 11.83% Official Use Only -- Flaring Authorization > 1 hr 1. Safety MCF 2. Lease Use MCF 3. Conserv. Purposes MCN' Commissioner Date Note: All volumes must be corrected to pressure of 14.65 psia and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 Fm~m IO~d23 Rev. d/95 ___ ~. ARE SUMMARY oint Platform Jan-99 Date Start Time End Time Event Hrs. Total MCF Source ID No. Equipment Description Category Oper/Safety Reason for Excess (Categorize, if possible) Planned or Unplanned 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0 10 0 11 0 12 0 13 1800 1930 1.5 733 Gas lift compress Operatidnal Other-AC power faiturE Unplanned 14 0000 1230 12.5 194 VRU compressor Operational Other-VRU down during generator repairs Unplanned 15 0 ' 16 0 17 0 18 0 19 0 20 0 21 0 22 0 23 0 24 0 25 0 26 0 27 0 28 0 29 0 30 0 31 0 Total ~ 14.0+ 927 Report ONLY flaring events greater than 1 hour or single events exceeding.5 MMCF. Operational Reasons for Excess Flaring: Safety Reasons for Excess Flaring: Well tests Blow down well Alarm tests Other(describe) Well spikes Other(describe) H2S Purging Scheduled maintenance Unscheduled maintenance Scheduled maintenance Unscheduled maintenance - -~ ALASKA OIL AND GAS CONSERVATION COMMISSION FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility Operator Field(s) Month/Year of Disposition :Granite Point Platform Unocal Oil and Gas Granite Point Feb 99 Disposition Volume MCF* 1. Sold p 2. Reinjected 0 3. Flared or vented leas than 1 hour 207 4. Flared or vented greater than 1 hour (Supplemental report required-•See 20 AAC 25.235) 2,381 5. Pilot and Purge ~ 560 6. Used for lease operations 38,832 7. Other 0 TOTAL items 1 - 7 41,980 8. NGL gas equivalent produced 0 9. Purchased gas 0 10. Transferred from: Granite Point Plt. 0 GPTF-LEX 11. Transferred to: GPTF-GPP 26,840 6,665 Remarks: I hereby certify tha the foregoing is true and correct to the best of my knowledge. Signature ,_- Title: Acct. Supervisor Date: 3/16/99 *Indicate contribution of each pool to total. Pool Name Code Percent Tyonek Lease 18761 280150 79.11% Hemlock Lease 18761 280152 5.41% Tyonek Lease 374044 280150. 3.59% Tyonek Lease 374045 280150 11.89% Official Uae Only -- Flaring Authorization > 1 hr 1. Safety MCF 2. Lease Use MCF 3. Conserv. Purposes MCF Commissioner Date Note: All volumes must be corrected to pressure of 14.65 Asia and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 Form 10~d22 Rev. Jl95 -~.. EXCESS FLARE LOG Granite Point Platform Feb-99 Date Start Time End Time Event Hrs. Total MCF Source ID No. Equipment Description Category (Oper/Safet y) Reason for Excess (Categorize, if possible) Planned or Unplanned 1 0 2 0 t 3 0000 2359 24.0 177. Compressor Operational OSS compressor down Unplanned 4 0000 2359 24.0 321 Compressor Operational OSS Compressor down Unplanned 5 0000 2359 24.0 423 Compressor Operational OSS Compressor down Unplanned 6 0000 2359 24.0 503 Compressor Operational OSS Compressor down Unplanned 7 0000 2359 24.0 588 Compressor Operational OSS Compressor down Unplanned 8 0000 1100 11.0 369 Compressor Operational OSS Compressor down Unplanned 9 0 10 0 ' 11 0 12 ~ 0 13 0 14 0 15 0 16 0 17 0 18 0 19 0 20 p 21 0 22 0 23 0 24 0 25 0 26 0 27 0 28 0 29 0 30 0 31 0 ~ Total 1 131.01 2,381 ~ Report ONLY Flaring events greater than 1 hour or single events exceeding 5 MMCF. Operational Reasons for Excess Flaring: Safety Reasons for Excess Flaring: Well tests Blow down well Alarm tests Other(describe) Well spikes Other(describe) H2S Purging Scheduled maintenance Unscheduled maintenance Scheduled maintenance Unscheduled maintenance ALASKA OIL AND GAS CONSERVATION COMMISSION FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility Operator Field(s) Month/Year of Disposition Granite Point Platform Unocal Oil and Gas Granite Point March 1999 Disposition Volume MCF* 1. Sold p 2. Reinjected p 3. Flared or vented less than 1 hour 161 4. Flared or vented greater than 1 hour (Supplemental report required--See 20 AAC 25.235) 0 5. Pilot and Purge 620 6. Used for lease operations 42,195 7. Other p TOTAL items 1 - 7 42,976 8. NGL gas equivalent produced 0 9. Purchased gas 0 10. Transferred from: Granite Point Plt. 0 GPTF•LEX 11. Transferred to: GPTF-GPP 30,306 8,493 Remarks: I hereby certify that the foregoing is true and correct to the best of my knowledge. Signature/y~~~_ Title: Acct. Supervisor Date: 4/8/99 *Indicate contribution of each pool to total. Pool Name Code Percent Tyonek Lease 18761 280150 77.96% Hemlock Lease 18761 280152 6.81% Tyonek Lease 374044 280150 3.53% Tyonek Lease 374045 280150 11.70% Official Use Only -- Flaring Authorization > 1 hr 1. Safety MCF 2. Lease Use MCF 3. Conserv. Purposes MCF Commissioner Date Note: All volumes must be corrected to pressure of 14.65 psis and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 Form 10-d•22 Rev. U'J5 ALASKA OIL AND. GAS CONSERVATION COMMISSION FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility Operator Field(s) Month/Year of Disposition Granite Point Platform Unocal Oil and Gas Granite Point April 99 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 742 4. Flared or vented greater than 1 hour (Su plemental report required--See 20 AAC 25.235) 23,802 5. Pilot and Purge 600 6. Used for lease operations 20,241 7. Other 0 TOTAL items 1 • 7 •45,385 8. NGL gas equivalent produced 0 wt< 9. Purchased gas 20,416 10. Transferred from: Granite Point Plt. 0 GPTF-LEX 11. Transferred to: GPTF-GPP 18,874 7,384 Romarks: I hereby certify at the foregoin is true and correct to the best of my knowledge. Signature Title: Acct. Supervisor Date: 5/20/99 Form IO~A22 aev. U93 *Indicate contribution of each pool to total. Pool Name Code Percent Tyonek Lease 18761 280150 74.40% Hemlock Lease 18761 280152 10.14% Tyonek Lease 374044 280150 3.59% Tyonek Lease 374045 280150 11.87% Official Use Only -• Flaring Authorization > 1 hr 1. Safety MCF 2. Lease Use MCF 3. Conserv. Purposes MCF Commissioner Date Note: All volumes must be corrected to pressure of 14.65 psia and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 ~~!f:s: s'~ ~: ~i`s`~~ ~i`¢J~1.fi~so ~~Xla4i~is-:56.x_ ~IiBC~iUt'~~~ EXCESS FLARE SUMMARY Granite Point Platform Apr-99 Date Start Time End Time Event Hrs. Total MCF .Source ID No. Equipment Description Category (Oper/Safety) Reason for Excess (Categorize, if possible) Planned or Unplanned 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0 10 0 11 0 12 0 13 0 14 0 15 7.30 2400 16.5 2;013 GP28 Compressor down Operational Compressor down. Purchased lift gas Unplanned 16 0001 1201- 12.0 .6,957 GP28 Compressor down Operational Compressor down. Purchased lift gas Unplanned 17 2030 2300 2.5 2,630 Operational Blow down well unplanned 18 0001 2200 22.0 840 OSS compressor Operational Tankfarm compressor down unable to use our gas unplanned 19 00:00 07:00 7.0 664 OSS compressor Operational Insufficient gas due to chak pipeline and unstable wells on gpp Unplanned 20 05:00 2400 18.0 7,429 GP28 Turbine Compressor Operational Scheduled maintenance! Purchased Lift gas from CIGS Planned 21 00:00 00:00 24.0 1,922 Operational Blow down well planned 22 00;00 00;00 24.0 1,156 Operational Blow down well planned 23 0 24 0 25 0 26 0 27 0 28 0 29 0 30 0600 1800 12.0 191 wire line Operational blowing down wells for wire line work, Some well spikes Planned 31 0 Total ~ 138.0 23,802 Report ONLY Flaring events greater than 1 hour or single events exceeding 5 MMCF. Operational Reasons for Excess Flaring: Safety Reasons for Excess Flaring: Well tests Blow down well Alarm tests Other(describe) Well spikes Other(describe) H2S Purging Scheduled maintenance Unscheduled maintenance Scheduled maintenance Unscheduled maintenance Gpp & GPTF Excess emissions Subject: Gpp & GPTF Excess emissions Date: Wed, 7 Apr 1999 14:09:04 -0700 From: "Bounds, Janet G" <boundsj@unocal.com> To: ""Wendy Mahan' (AOGCC)"' <Wendy_Mahan@admin.state.ak.us> CC: "Isham, Jim R" <ishamj@Orion.Unocal.com>, "Bezilla, Mike G" <bezilmg@Orion.Unocal.com>, "Birchfield, David R" <birchdr@Orion.Unocal.com> Wendy The Granite Point Platform had excess emissions in January and February 1999. On January 13th the voltage regulator on the AC generator malfunctioned. This caused all wells to go down along with the gas lift compressor. As reported on the excess flare log 733 MCF of gas was flared. On January 14th the vapor recovery unit was down during repairs to the generator from the previous days incident. The voltage regulator was replaced. 194 MCF of gas was flared as wells were brought back on line and sufficient gas support was established to run the vapor recovery unit. >From February 3 to February 8 the On Shore Side Compressor (OSS} was down at the Granite Point Tank Farm due to the frozen shipping lines and unusually cold weather. As a result Granite Point Platform could not ship their gas. The loading configuration was altered so that Granite Point Platform could resume shipping. 2,381 MCF of gas was flared from Granite Point Platform and 1,278 MCF was flared at the Granite Point Tank Farm. Please contact me if more information is needed. Thank you, Janet G. Bounds Environmental Scientist Unocal (907) 263-7694 (office) (907) 263-7901 {fax) 1 of 1 4/8/99 8:23 AM '_ 1~.IJASI~A OIL AND GAS CONSERVATION COMMISSION ,~ FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility °".a a n+ p~>jtor Field(s) Month/Year of Disposition (3rauTC2 Pb~i~~}},, ~q~'A' •~ ~ Unocal Oil and Gas Granite Point MAY 99 ~.. E.; 6'b~i~il1 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 1,954 4. Flared ar vented greater than 1 hour (Supplemental re ort required--See 20 AAC 25.235) 800 5. Pilot and Purge 620 6. Used for lease operations 42,985 7. Other 0 TOTAL items 1 - 7 46,359 8. NGL gas equivalent produced 0 9. Purchasedgas 0 10. Transferred from: ~ Granite Point Plt. 0 GPTF-LEX 11. Transferred to: GPTF-GPP 21,984 8,091 Remarks: I hereby certify t the foregoi is u a d correct to the best of my knowledge. Signature ~ Title: Acct. Supervisor Date: 6/22/99 *Indicate contribution of each pool to total. Pool Name Code Percent Tyonek Lease 18761 280150 70.54% Hemlock Lease 18761 280152 14.71% Tyonek Lease 374044 280150 3.42% Tyonek Lease 374045 280150 11.33% Official Use Only -- Flaring Authorization > 1 hr 1. Safety MCF 2. Lease Use MCF 3. Conserv. Purposes MCF Commissioner Date Note: All volumes must be corrected to pressure of 14.65 psis and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 Farm IO~J22 Rev. d/95 EXCESS FLARE SUMMARY Granite Point Platform May-99 Date Start Time End Time Event Hrs. Total MCF Source ID No. Equipment Descr' lion Category Oper/Safety Reason for Excess (Categorize, if possible) Planned or Unplanned 1 0 2400 24.0 240 Well spikes 2 0 2400 24.0 328 Well spikes 3 0 4 0 5 0 6 0 7 0 8 0 9 0 10 0 11 0 12 1300 1700 4.0 165 #820 Valve, Operational Sales. Gas Valve at tank,farm closed (bad solenoid) Unplanned 13 0 14 67 Well spikes 15 0 16 0 17 0 18 0 19 0 20 0 21 0 22 0 23 0 24 0 25 0 26 0 27 0 28 0 29 0 30 0 31 ~ 0 Total ~ ~ 800 Report ONLY flaring events greater than 1 hour orsingle events exceeding 5 MMCF. ALASKA OIL AND GAS CONSERVATION COMMISSION FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility Operator Field(s) Mm~th/Iear of Disposition Granite Point Platform Unocal Oil and Gas Granite Point June 99 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 2,072 4. Flared or vented greater than 1 hour (Sup lemental report required--See 20 AAC 25.235) - 0 5. Pilot and Purge 600 6. Used for lease operations 40,230 7. Other 0 TOTAL items 1 - 7 42,902 8. NGL gae equivalent produced 0 9. Purchased gas 0 10. Transferred from: Granite Point Plt. 0 GPTF-LEX 11. Transferred to: GPTF-GPP 24,146 6,658 Remarks: I hereby certify t at he fore of g is t ue and correct to the best of my knowledge. //t~ Signature ~'` (~ /t./`C' Title: Acct. Supervisor Date: 7/15/99 *Indicate contribution of each pool to total. Pool Name Code Percent Tyonek Lease 18761 280150 72.67% Hemlock Lease 18761 280152 14.08% Tyonek Lease 374044 .280150 3.07% Tyonek Lease 374045 280150 10.18% Official Uae Only •- Flaring Authorization > 1 hr 1. Safety MCF 2. Lease Use MCF 3. Conserv. Purposes MCF Commissioner Date Note: All volumes must be corrected to pressure of 14,65 psia and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 t°~N to-a2a Rer. Il95 ALASKA OIL AND GAS CONSERVATION COMMISSION FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility Operator Field(s) Month/Year of Disposition Granite Point Platform Unocal Oil and Gas Granite Point July 99 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 1,148 4. Flared or vented greater than 1 hour (Supplemental report required••See 20 AAC 25.235) 1,596 5. Pilot and Purge 620 6. Used for lease operations 41,967 7. Other 0 TOTAL items 1 • 7 45,331 8. NGL gas equivalent produced 0 9. Purchased gas 80 10. Transferred from: Granite Point Plt. 0 GPTF-LEX 11. Transferred to: GPTF-GPP 21, 350 7,644 Remarks: I hereby certify tjrr$t t~ foregoin~ tr~~ cy~ rrect to the best of my knowledge. Signature L/L` ~ +~/P Title: Acct. Supervisor Date: 8110/99 *Indicate contribution of each pool to total. Pool Name Code Percent Tyonek Lease 18761 280150 73.13% Hemlock Lease 18761 280152 13.98% Tyonek Lease 374044 280150 2.99% Tyonek Lease 374045 280150 9.90% Official Uae Only -- Flaring Authorization > 1 hr 1. Safety MCF 2. Lease Use MCF 3. Conserv. Purposes MCF Commissioner Date Note: All volumes must be corrected to pressure of 14.65 Asia and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 t°~m io-azz Nev. d/95 EXCESS FLARE SUMMARY Granite Point Platform Jul-99 Date Start Time End Time Event Hrs. Total MCF Source ID No. Equipment Description Category (Oper/Safety) Reason for Excess (Categorize, if possible) Planned or Unplanned 1 0 2 0 3 0 4 0 5 0000 2400 24.0 152 Operational Well spikes /Wireline work Planned 6 0000 2400 24.0 . 334 Operational Well spikes /Wireline work Planned 7 0000 2400 24.0 63 Operational Weli spikes /Wireline work Planned 8 0 9 0 10 0 11 0 12 0 r 13 0 14 0000 2400 287 Operational Well spikes /Wireline work Planned 15 0 16 0000 2400 243 Operational WeII spikes /Wireline work Planned 17 0 18 0 19 0 20 0 21 0 22 0 23 0 24 0 25 0 26 0 27 0 28 0 29 0 30 07:00 09:30 2.5 517 Produced gas Operational Blow down well /Comp. operating w/ Gas line Is Planned 31 0 Total I 74.5 1,596 Report ONLY flaring events greater than 1 hour or single events exceeding 5 MMCF. Operational Reasons for Excess Flaring: Safety Reasons for Excess Flaring: Well tests Blow down well Alarm tests Other(describe) Well spikes Other(describe) H2S Purging Scheduled maintenance Unscheduled maintenance Scheduled maintenance Unscheduled maintenance ALASKA OIL AND GAS CONSERVATION COMMISSION FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility Operator Field(s) MonthlYear of Disposition Granite Point Platform Unocal Oil and Gas Granite Point August 1999 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 2,052 4. Flared or vented greater than 1 hour (Supplemental re ort required--See 20 AAC 25.235) 8,719 5. Pilot and Purge 620 6. Used for lease operations 33,891 7. Other 0 TOTAL items 1 • 7 45,282 8. NGL gas equivalent produced 0 9. Purchased gas 3,815 10. Transferred from: Granite Point Plt. 0 GPTF-LEX 11. Transferred to: GPTF•GPP 9,600 6,739 Remarks: I hereby certi ~t the foreg ~ng is true and correct to the best of my knowledge. ~ U,, ~e Signature ~ f ~~ Title: Acct. Supervisor Date: 9/15/99 *Indicate contribution of each pool to total. Pool Name Code Percent Tyonek Lease 18761 280150 69.81% Hemlock Lease 18761 280152 15.93% Tyonek Lease 374044 280150 3.31% Tyonek Lease 374045 280150 10.95% Official Use Only •• Flaring Authorization > 1 hr 1. Safety MCF 2. Lease Use MCF 3. Conserv. Purposes MCF Commissioner Date Note: All volumes must be corrected to pressure of 14.65 psis and to a temperature of 60 degrees F. Report due by the 20th of the month following the. month of disposition. Authority 20 AAC 25.235 Form 10-d22 x°~. ass ~~~ SEP. 9.1999 1~10PM UNOCAL y ~~ ,~~ '~ >t ^ EXCESS IFt.~tRE StJMNlARY Granite Pant 1~tatfonm _ ~( ~ Stnr9 1 f:nd f;venl TeHn9 Sourc:c RQuipmtati Calegury Raesem felt Frucs:c ax l un~ '1'imc Flrs. MC1= ID No. , Dcscri 'on (O cr/5stcN1 __ (CatC~'txc, if po2~rlbk) .. .. ~~~ _ 2 (t __ ~ • ~ -_.. .__ . z 1 I ~00 24 00 1 z 0 714 G-0194 tins Pipdine (')perotiwutl pi~olUte a1spactiu~n Flmu 4 24U0 24AQ 24.U 1.011 Ci~0194 G~+ Pipeline OPorntionel Pipeline inapeclion • _...___. _ Plant _ S _ 24.00 24.00 ...24.0 _ 1.029 G0194_-_ Chts Pipaiints O~twtiom-1 Pipaliere it~vprxtion-- •-. .. Ptata (~ '!~•UU 24i7t1 24.t1 I.ctt)h (i-0_l'J4 _ (ias I~r~clinc . (~Cratinnal - Pi~elinoir~inn-_- .. Plsm 7 Za:0u 7x:00 24.0 yZ3 G-01~~4 t:lea Pi~clinc,.. - (), denN __. . . Pipcline:in metfon ... Niaru 8 24:00 24:00 24.0 919 _ ._ (3-019d t'rss Apeliae ~~atioeul 1'i~e[!rIe aspeafiam _. ...- - - Plem y 7.d 0(- IM•O(1 i1S.(1 7fi3 - 0119$ _ _ (iar Pipeline (fretalimra! Npeiirrc ingroc.4irnt Ylsrn 0 22.30 00:00 1:5 i,31S 00194 GssPipcline O~csrntiomil P>r-syeCiioat~•-___._ 1'latu ( UU:UU UO:ttU 24.0 1,016 C1.019d 1 - - _ _ Cits t's,~cla-c - - .O~etana~l. welly back on nfisa i't~~mo MSS °~°a( Plmm Z ~ 0 ~ .. ( .q ~' I f Q _. ~~-.__... .._ .._------'- ~ ...._. _._ -..__ .._.__-_..._.-__..... 'I 6 O 17 0 - . i ~ al _ ~_ ... .. .... _._ - ------ _.~_---- ~ .. . . ,y 0 >.0 U 0 ~ t3 ~ 0 1 ~(~ Q .. ~.. _....... . _ ~~ 0 1 ! 1 ~e I fl _ ._ .. _1 .__... iy i ~ i - - - 0 __ _.... ,.. ..~ _..... -. .. ~~----..-._. ~ t0 0 ~ _ ~ r _. .- _ _ .. -_- sI o _ _~_~. I ~ 't'nt11 17b~5 tt,719 Rupcnt ONi.l' tl>ai~ cva2a ~' {hrn i how ar xirrgio Cv.tre 5 [ufivlCF. IIl)rernticx~l kes»cma ('as E~ceas Flat'ing_y. .~Ssse~ Reaxona ibr E~tess {well lasts 4ilow down well ~ Alarm tads I`wcI1.:Mkcs tltltei(d~vccibc) H'~11'irtgtng l~cl~edulcd uuuul~-rutce - --- -- -- =__ _- _ Uahoheduled mrtintennnce N0.538 P.1i1 lvin~--.-.-.._---• .__. (Jthc~r(dsycaihc) Aug-99 ~~-E'lemtcr! or iin lRtmCd ~oJ ocl cA ,ed ~ccf Kd iecl jai red .~~~ i ~.. Unocal Alaska Resources Unocal Corporation 909 West 9th Avenue, P.O. Box 196247 Anchorage, Alaska 99519-6247 Telephone (907) 263-7809 Facsimile 263-7634 uNOCa~~b August 26, 1999 ~;~ Martin T. Morel) Oil and Gas Operations Manager CERTIFIED MAIL P 438 292 673 Return Receipt Requested Dear Ms. Mahan: ~. , `... Wendy Mahan Natural Resource Manager Alaska Oil and Gas Conservation Commission 3001 Porcupine Drive Anchorage, AK 99501-3192 Response to AOGCC Email 7/22/99 Granite Point Platform & Granite Point Tank Farm In your email of July 22, 1999 you requested information regarding the excess flare events at the Granite Point Platform (GPP) on April 15-16, and 18-20. The email also requested information regarding events at Granite Point Tank Farm (GPTF) on April 15 -18, 22 - 23, and 30, 1999. Since some of these events are related to each other this response will address both facilities. On April 15, 1999 an upset occurred on the Granite Point Platform when the Motor Control Center panel which distributes electrical power failed. This resulted in a platform shutdown. Generator #2 and the compressor were also shutdown. New cables and breakers were ordered from the beach and installed on April 16, 1999. In order to maintain oil production during this time, Granite Point Platform purchased lift gas from the high pressure CIGGS pipeline. Since the compressor was down the lift gas could not be recompressed; therefore, gas was flared. Under normal operating conditions the GPTF receives gas from Granite Point, the Anna and Bruce Platforms. When the compressor is down on the Granite Point Platform gas cannot be transported to the Granite Point Tank Farm (GPTF). At this same time the frozen GP-1 line resulted in the gas line being used to ship oil to the GPTF which in turn prevented gas shipments to the GPTF from Bruce and Anna Platforms. On April 15 and 16, 1999 the GPTF did not have sufficient gas support to run the Vapor Recovery Unit, the compressor or the generator. The GPTF flared the residual gas it could not compress. On April 17, 1999 the GP-1 line was still frozen and GPP was blowing down well 11-13. This resulted in insufficient gas support to the compressor and Vapor Recovery Unit at the GPTF. Gas was not available from the Bruce or Anna Platforms because the GP1 line was still frozen. On April 18 to April 19, 1999 the wells on GPP continued to be unstable after the shutdown on April 16, 1999. After a shutdown it takes a few days for the wells to level out and produce sufficient amounts of gas that can be compressed and shipped. During this time there was insufficient gas support coming from GPP to run the vapor recovery unit at GPTF. Gas was still not available from Bruce or Anna Platforms. L:\environ\air\facility\99AOGCC_GPP_GPTF_apr_may99. doc f On April 20, 1999 an 8,000 hour scheduled inspection occurred on the GPP turbine compressor On April 22 and 23, 1999 the excess flaring at GPTF was due to purging as part of the process of returning the GP-2 line back to gas service. The event on April 30, 1999 at the GPTF continued until May 3, 1999. During this time there was trouble shooting on several components of the vapor recovery system. On May 3, 1999 the loading and unloading valves were repaired and the system was returned to normal operating conditions. Should you have further questions please direct them to Janet Bounds at 263-7694. Sincerely, `~ ~ ~ t~.. Martin T. Morell cc: John T. Beitia/File Janet G. Bounds Chris Myers Dave Cole Jon Cronk Mike Dimmick /Anna Allen Dorman /Bruce Dusty Rhodes /GPP David Birchfield /GPTF Anna /Air file Bruce /Air file GPP /Air file GPTF /Air file FW: increased flare at Granite Point, Grayling, GPTF and TBPF Subject: FW: increased flare at Granite Point, Grayling, GPTF and TBPF Date: Thu, 5 Aug 1999 11:56:45 -0700 From: "Bounds, Janet G" <boundsj@unocal.com> To: ""Wendy Mahan' (AOGCC)"' <Wendy_Mahan@admin.state.ak.us> CC: "Santiago, Johnny T" <santiagoj@Orion.Unocal.com>, "Helton, Carl D (Doc)" <heltonc@Orion.Unocal.com>, "Rhodes, Dustin J" <rhodedj@Orion.Unocal.com>, "Cronk, Jon A" <jcronk@Orion.Unocal.com>, "Johnson, Regina -Contract" <johnsonr@Orion.Unocal.com>, "Geeslin, James W (Tray)" <geeslinj@Orion.Unocal.com>, "Bezilla, Mike G" <bezilmg@Orion.Unocal.com>, "Birchfield, David R" <birchdr@Orion.Unocal.com>, "Dimmick, Mike W" <dimmick@Orion.Unocal.com>, "Dorman, Allen" <DormanA@Orion.Unocal.com>, "Beitia, John T" <beitiaj@Orion.Unocal.com>, "Myers, Chris S" <myersc@Orion.Unocal.com>, "Johnson, Dwight E" <johnsond@Orion.Unocal.com>, "Geisert, C. Dean" <geisecd@Orion.Unocal.com> > AOGCC > Wendy Mahan: > As promised on your voice mail August 3, 1999 this email documents > anticipated increase in flare volumes related to riser inspections at > Granite Point, Grayling and Monopod Platforms. Since these inspections > require a blowdown of the pipelines there will also be increased flare > volumes at Granite Point Tank Farm (GPTF), Trading Bay Production Facility > (TBPF) . > These inspections are a vital part of maintaining safe operations. > The purpose of the inspections is to determine if the risers have > experienced corrosion so that Unocal can take proper action to mediate > before there is an environmental or safety issue. We have increased the > crew by bringing on five additional employees/contractors for this > project, plus two inspectors to the platforms. Additional personnel will > also be on hand at the onshore facilities. We are completing > modifications to the pipeline risers prior to the inspections to limit the > amount of downtime. > Grayling Platform and TBPF > On July 31, 1999 and August 1, 1999 flanges were installed on the > gas riser in order to seal off the pipeline. During the modification > flare volumes increased by approximately 700 MCFD at the platform and 288 > MCFD at TBPF. On August 2, 1999 the construction crew began working on > installing a new oil spool, flanges, brackets, bracing and hatch access > for the construction process to the oil line. Construction is scheduled > to be completed prior to August 9, 1999. In order to continue shipping > oil Unocal is using the gas line for shipping oil. During these > modifications we anticipate 700 MCFD to be flared at the platform and 290 > MCFD at TBPF. A similar amount will be flared during the inspections > scheduled for August 10 or 11. > Granite Point, Bruce, Anna and GPTF > Between August 3 and 9, 1999 flanges will be installed on the oil > and gas risers. Riser inspection is scheduled for August S and 9, 1999. > Flare volumes will increase by an estimated 1 NIMCFD at the platform and 1 > MMCFD at the Tank Farm during the pipeline modifications and inspections. 8/5/99 11:17 AM 1 of 2 FW: increased flare at Granite Point, Grayling, GPTF and TBPF > During the blowdown of the gas pipeline we have not been able to bleed the > line down to 0 psi. In order to determine if this is being caused by > leaking valves or condensate in the line we shut in the GPTF on August 4, > 1999. If it is determined that the cause is condensate in the line we > will push water through line in order to complete the inspection. Also, > blinds will be installed at GPTF as soon as the line is bled down. At the > same time we are installing a jumper line at the Platform to allow us to > pig the line from Granite Point Platform to the Tank Farm without shutting > down the platform. This step is separate from the riser inspections and > is being done at this time to take advantage of the line being down. > Shutting in the GPTF results in lack of gas support to the Uapor > Recovery Unit and increased flaring at Anna and Bruce Platforms. Bruce > has shut in their gas well in order to minimize the amount of flare. Anna > does not have a gas well, all of its gas production is associated with the > oil. > Monopod and TBPF > Flanges will be installed on the gas riser on August I1. Riser > inspections are scheduled for August 11 and will require a complete > platform shutdown. Therefore, Unocal does not anticipate an increase in > flare volumes at the platform. A blowdown of the line between the Monopod > and TBPF will be required. This will result in an increase of > approximately 280 MCF at TBPF. > I apologize for not getting this to you earlier. I nearly had an > email typed when the power went out, and the message went goof. > If you have questions or need more information please ask. > Thank you, > Janet G. Bounds > Environmental Scientist > Unocal > (907) 263-7694 (office) > (907) 263-7901 (fax) 8/5/99 11:17 AM 2 of 2 4~ Y ~L/ ~~T ~~ ~99~ ALASKA OIL AND GAS CONSERVATION COMMISSION ~IasKaOii&Ga~Gons.CommisSiorl FACILITY REPORT OF PRODUCED GAS DISPOSITION Facility " "--°" Operator Field(s) Month/Year of Disposition GRANITE POINT PLATFORM UNOCAL ALASKA RESOURCES GRANITE POINT FIELD SEPTEMBER1999 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 853 4. Flared or vented greater than 1 hour (Supplemental report required -See 20 AAC 25135) 105,865 5. Pilot and Purge 600 6. Used for lease operations 23,545 7. Other 0 TOTAL items 1 - 7 130,863 8. NGL gas equivalent produced 0 9. Purchased gas 101,346 10. Transferred from: 0 11. Transferred to: 12,844 Remarks: I hereby certify that the foregoing is true and correct to the best of my knowledge. Signature ~~(~~~~~~1/~~ Title ACCOUNTING SUPERVISOR Date 10/12/1999 Form 10-422 Rev. 4/95 *Indicate contribution of each pool to total. Pool Name Code Percent MIDDLE KENAI 280150 81.43 HEMLOCK UNDEFINED 280152 18.57 Note: All volumes must be corrected to pressure of 14.65 psis and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 ARE SUMMARY oint Platform Date Start Time End Time Event Hrs. Total MCF Source ID No. Equipment Description Category OpedSafety Reason for Excess (Categorize, if possible) Planned or Unplanned 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0 10 0 11 0 12 0 13 0 14 0 15 0400 2400 20.0 96 Flare tip Operational platform shut in for flare tip change out Planned 16 00:00 2400 24.0 7,440 Centaur comer perational Compressor rebuild, buying gas to lift wells Unplanned 17 00:00 2400 24.0 9,006 Centaur compress Operational Compressor rebuild, buying gas to lift wells Unplanned 18 00:00 2400 24.0 8,562 Centaur compress Operational Compressor rebuild, buying gas to lift wells Unplanned 19 00:00 2400 24.0 9,541 Centaur compress Operational compressor being replaced flaring produced ga Unplanned 20 00:00 2400 24.0 10,426 Centaur Compress perational Compressor being replaced flaring produced g Unplanned 21 00:00 2400 24.0 10,288 Centaur Compress perational Compressor being replaced flaring oroduced g Unplanned 22 00:00 2400 24.0 10,023 Centaur Compress perational Compressor being replaced flaring produced g Unplanned 23 00:00 2400 24.0 10,623 Gas Compresso Operational Compressor being replaced flaring produced g Unplanned 24 00:00 2400 24.0 10,855 Gas Compresso Compressor being replaced flaring produced g Unplanned 25 00:00 2400 24.0 10,819 Gas Compresso Operational Compressor being replaced flaring produced g Unplanned 26 00:00 2400 24.0 6,029 Gas Compresso Operational Compressor being replaced flaring produced g Unplanned 27 00:00 11:30 11.5 1,187 Gas Compresso Operational Blow down well Unplanned 28 00:00 24:00 24.0 310 VRU Operational VRU down due to control problems Unplanned 29 00:00 24:00 24.0 427 VRU Operational VRU down due to control problems Unplanned 30 00:00 24:00 453 VRU Operational VRU down due to control problems Unplanned 31 0 Total ~ 343.5 106,085 Report ONLY flaring events greater than 1 hour or single events exceeding 5 MMCF. Operational Reasons for Excess Flaring: Safety Reasons for Excess Flaring: Well tests Blow down well Alarm tests Other(describe) Well spikes Other(describe) H2S Purging Scheduled maintenance Unscheduled maintenance Scheduled maintenance Unscheduled maintenance .- . ~- ~~ ALASKA OIL AND GAS CONSERVATION COMMISSION . ~ w.' "[ ~' ~~c~r FACILITY REPORT OF PRODUCED GAS DISPOSITION ~l~ska ~!~ ~ ~~~ ~~~~. C~rr~mssju ty Operator Field(s) onth/Year of Disposition ~ ~~ GRANITE POINT PLATFORM UNOCAL ALASKA RESOURCES GRANITE POINT FIELD OCTOBER 1999 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 1,064 4. Flared or vented greater than 1 hour (Supplemental report required -See 20 AAC 25.235) 15,600 5. Pilot and Purge 620 6. Used for lease operations 40,147 7.Other 0 TOTAL items 1 - 7 57,431 8. NGL gas equivalent produced 0 9. Purchased gas 15,461 10. Transferred from: 0 11. Transferred to: 13,409 Remarks: I hereby certif that the f reg/oi~~ng~is true and correct to the best of my knowledge. Signature '£ - ~ °<'^"' ~~ Title ACCOUNTING SUPERVISOR Date 11/09/1999 *Indicate contribution of each pool to total. Pool Name Code Percent MIDDLE KENAI 280150 92.00 HEMLOCK UNDEFINED 280152 8.00 Note: All volumes must be corrected to pressure of 14.65 psis and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 Form 10-422 Rev. 4195 EXCESS FLARE SUMMARY Granite Point Platform Oct-99 Date Start Time End Time Event Hrs. Total MCF Source ID No. Equipment Description Category (O er/Safety) Reason for Excess (Categorize, if ossible) Planned or Un lanned 1 00:00 24:00 24.0 514 VRU erational VRU down due to make-u gas roblems Un lanned 2 00:00 08:00 8.0 498 Well GP-11-13rd Operational Blow down well Un lanned 3 00:00 24:00 24.0 542 O erational Wells ikes Un lanned 4 00:00 00:00 3.5 450 11-13 31-23 O erational Wells ikes Un lanned 5 00:00 2400 5.0 579 11-13 O erational Scheduled maintenance Un lanned 6 0930 1530 6.0 3,132 entaur Com resso Operational Scheduled maintenance Planned 7 00:00 24:00 24.0 703 Wells O erational Wells ikes Un lanned 8 00:00 2400 24.0 193 31-23 Operational Wells ikes Un lanned 9 0 10 0 11 0000 1700 17.0 264 erational OSS com ressor maintenance un lanned 12 0 13 0 14 0 15 0 16 0 17 0 18 0 19 0 20 0 21 0 22 0 23 0 24 0 25 0 26 0 27 1030 2400 13.5 4,845 GT-1270 entaur Com resso Operational Scheduled maintenance lanned 28 0000 2000 20.0 3,880 GT-1270 entaur Compresso Operational Scheduled maintenance lanned 29 0 30 0 31 0 Total ~ 169.0 ~ 15,600 Report ONLY flaring events greater than 1 hour or single events exceeding 5 MMCF. O erafional Reasons for Excess Flaring: Safety Reasons for Excess Flarin Well tests Blow down well Alarm tests Other(describe) Well spikes Other(describe) H2S Purging Scheduled maintenance Unscheduled maintenance Scheduled maintenance Unscheduled maintenance ~V ~ ~, ~ ..~ ~~ ~.1~sk3 0i1 ~? ~'--0aJ it C4 ~rctroe ~~ ~°rnmissip,~ -* _.. ~ECEIVEQ DEG 22 ~gg~LASKA OIL AND GAS CONSERVATION COMMISSION FACILITY REPORT OF PRODUCED GAS DISPOSITION Fa ~ChOta$8 Operator Field(s) onth/Year of Disposition GRANITE POINT PLATFORM UNOCAL ALASKA RESOURCES GRANITE POINT FIELD NOVEMBER 1999 Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 1,173 4. Flared or vented greater than 1 hour (Supplemental report required -See 20 AAC 25.235) 1,469 5. Pilot and Purge 600 6. Used for lease operations 42.292 7.Other 0 TOTAL items 1 - 7 45,534 8. NGL gas equivalent produced 0 9. Purchased gas 62 10. Transferred from: 0 11. Transferred to: 13,491 Remarks: I hereby certify that the foregoing ist~rue and correct to the best of my knowledge. Signature C~~~~Z~_ ;~.~~~~J Title ACCT. SUPERVISOR Date 12/15/1999 Form 10-422 Rev. 4/95 *Indicate contribution of each pool to total. Pool Name Code Percent MIDDLE KENAI 280150 94.49 HEMLOCK UNDEFINED 280152 5.51 Note: All volumes must be corrected to pressure of 14.65 psis and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 ARE SUMMARY oint Platform Nov-99 Date Start Time End Time Event Hrs. Total MCF Source 1D No. Equipment Description Category Oper/Safety Reason for Excess (Categorize, if possible) Planned or Unplanned 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 10:00 24:00 14.0 226 Vapor Recovery Operational Vapor Recovery unit down for inspection Unplanned 10 00:00 24:00 24.0 346 Vapor Recovery Operational V.R.U. down due to mechanical problems Unplanned 11 00.00 24:00 24.0 356 Vapor Recovery Operational VRU down for valve spring replacement Unplanned 12 00:00 24:00 24.0 329 Vapor Recovery Operational VRU down for valve spring replacement Unplanned 13 00:00 13:00 13.0 212 Vapor Recovery Operational VRU down for valve spring replacement Unplanned 14 0 15 p 16 0 17 0 18 0 19 0 20 p 21 p 22 0 23 0 24 0 25 0 26 p 27 0 28 0 29 p 30 0 31 0 I Oral l 99.U 1 1,469 I Report ONLY flaring events greater than 1 hour or single events exceeding 5 MMCF. Operational Reasons for Excess Flaring: Safety Reasons for Excess Flaring: Well tests Blow down well Alarm tests Other(describe) Well spikes Other(describe) H2S Purging Scheduled maintenance Unscheduled maintenance Scheduled maintenance Unscheduled maintenance FW: GPP VRU down Subject: FW: GPP VRU down Date: Mon, 15 Nov 1999 08:55:31 -0800 From: "Bounds, Janet G" <boundsj@unocal.com> To: ""Wendy Mahan' (AOGCC)"' <Wendy_Mahan@admin.state.ak.us> CC: "Beitia, John T" <beitiaj@Orion.Unocal.com> Wendy The VRU was back on line at 1:OOpm Saturday, November 13, 1999. Janet G. Bounds Environmental Scientist Unocal (907) 263-7694 (office) (907) 263-7901 (fax) > From: Bounds, Janet G > Sent: Thursday, November 11, 1999 4:58 PM > To: ' 'Wendy Mahan ' (AOGCC) ' > Cc: Myers, Chris S; Rhodes, Dustin J; Medley, Ted J; Beitia, > Subject: GPP VRU down > Wendy Mahan > AOGCC > At 10:00 am on Tuesday, November 9 Granite Point Platform shut > vapor recovery unit in order to investigate noises coming from > Ualve springs and gaskets have been ordered and are scheduled > Friday. We should be back to normal operating conditions late > Saturday. Increased flare volumes are estimated at 350 mcfd. > will be recorded as required on the excess flare log. > Please contact me if you have questions. > Thank you, > Janet G. Bounds > Environmental Scientist > Unocal > (907) 263-7694 (office) > (907) 263-7901 (fax) John T down the the VRU. to arrive on Friday or This event 1 of 1 11/22/99 8:39 AM ~~ x t ~ ,. , ~.` ALASKA OIL AND GAS CONSERVATION COMMISSION ' ~ - ~ FACILITY REPORT OF PRODUCED GAS DISPOSITION r aciuty ,-,- - vperawr r ieiu~~~ GRANITE POINT PLATFORM UNOCAL ALASKA RESOURCES GRANITE POINT FIELD Disposition Volume MCF* 1. Sold 0 2. Reinjected 0 3. Flared or vented less than 1 hour 922 4. Flared or vented greater than 1 hour (Supplemental report required -See 20 AAC 25.235) 902 5. Pilot and Purge 620 6. Used for lease operations 45.075 7. Other 0 TOTAL items 1 - 7 47,519 8. NGL gas equivalent produced 0 9. Purchased gas 170 10. Transferred from: 0 11. Transferred to: 11,826 Remarks: I hereby certify that the foregoing is true and correct to the best of my knowledge. Signature ~~.(~~ ~.~~i ~~.~J Title ACCT. SUPERVISOR Date 01/13/2000 Form 10-422 Rev. 4/95 'ear of Disposition DECEMBER 1999 *Indicate contribution of each pool to total. Pool Name Code Percent MIDDLE KENAI 280150 92.94 HEMLOCK UNDEFINED 280152 7.06 Note: All volumes must be corrected to pressure of 14.65 psis and to a temperature of 60 degrees F. Report due by the 20th of the month following the month of disposition. Authority 20 AAC 25.235 _ARE SUMMARY Point Platform Dec-99 Date Start Time End Time Event Hrs. Total MCF Source ID No. Equipment Descri lion Category (O er/Safe Reason for Excess (Cate orize, if ossible) Planned or Un lanned 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0 10 0 11 0 12 12:00 00:00 12.0 322 well 11-13 erational Well 11-13 as lift roblems un lanned 13 00:00 16:00 4.0 247 11-13 erational Wells ikes lanned 14 0 15 0 16 00:00 00:00 2.0 333 Wells O erational Wells ikes Unplanned 17 0 18 0 19 0 20 0 21 0 22 0 23 0 24 0 25 0 26 0 27 0 28 0 29 0 30 0 31 0 Total ~ 18.0 902 Report ONLY flaring events greater than 1 hour or single events exceeding 5 MMCF. O erational Reasons for Excess Flaring: Safet Reasons for Excess Flarin Well tests Blow down well Alarm tests Other(describe) Well spikes Other(describe) H2S Purging Scheduled maintenance Unscheduled maintenance Scheduled maintenance Unscheduled maintenance